LINDE - ARKEMA - SMR#2 - PRELIMINARY SCHEDULE

ID Task Task Name Duration Start Finish


Mode 15 Jan '18 05 Feb '18
15 Jan '18 05 Feb '18
F S S M T W T F S S M T W T F S S M T W T F S S M
1 TECHNIP - HOARDING CONSTRUCTION AT ARKEMA KERTEH 2 60 days Mon 29-01-18 Sat 31-03-18
2 PROJECT AWARD 1 day Mon 29-01-18 Mon 29-01-18 29-01
3 Purchase Order Receive 1 day Mon 29-01-18 Mon 29-01-18
4 Kick off Meeting 1 day Mon 29-01-18 Mon 29-01-18
5 DOCUMENTATION SUBMISSION AND APPROVAL 7 days Mon 29-01-18 Mon 05-02-18
6 Job safety analysis 7 days Mon 29-01-18 Mon 05-02-18
7 Job method statement 7 days Mon 29-01-18 Mon 05-02-18
8 Project execution plan 7 days Mon 29-01-18 Mon 05-02-18
9 Temporary facility submission and approval 4 days Mon 29-01-18 Sat 03-02-18
10 PROCUREMENT 7 days Tue 06-02-18 Mon 12-02-18 12-02
11 Tempoary facilities 6 days Tue 06-02-18 Mon 12-02-18
12 Others 10 days Tue 06-02-18 Thu 15-02-18
13 WORKSHOP ACTIVITY 30 days Tue 06-02-18 Sun 11-03-18
14 Mobilization Machinerie, Toolbox and Material 7 days Tue 06-02-18 Mon 12-02-18
15 Setup Pre Fabrication Area 1 day Tue 13-02-18 Tue 13-02-18
16 Fabrication Work 19 days Wed 14-02-18 Wed 07-03-18
17 Others 6 days Mon 12-02-18 Tue 20-02-18
18 SITE CONSTRUCTION 38 days Wed 21-02-18 Sat 31-03-18
19 Scan Underground Electromagnetic Scan Work 3 days Wed 21-02-18 Fri 23-02-18
20 Site Working and Excavation For Fence and Gate Post 7 days Sat 24-02-18 Fri 02-03-18
21 Installation Fence Works 29 days Sat 03-03-18 Sat 31-03-18
22 * Levelling Work
23 * Concrete Foundation and Fence Gate Post
24 * Backfill and Compaction

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: Proposed Schedule Ark
Milestone Inactive Summary Start-only Baseline Slippage
Date: Thu 01-02-18
Summary Manual Task Finish-only Baseline Milestone

Project Summary Duration-only External Tasks Baseline Summary

1 /2 LINDE - ARKEMA SMR #2 - PRELIMINARY SCHEDULE


LINDE - ARKEMA - SMR#2 - PRELIMINARY SCHEDULE

26 Feb '18 19 Mar '18


26 Feb '18 19 Mar '18
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

11-03

31-03

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: Proposed Schedule Ark
Milestone Inactive Summary Start-only Baseline Slippage
Date: Thu 01-02-18
Summary Manual Task Finish-only Baseline Milestone

Project Summary Duration-only External Tasks Baseline Summary

2 /2 LINDE - ARKEMA SMR #2 - PRELIMINARY SCHEDULE