Vous êtes sur la page 1sur 124

GOVERNMENT OF RAJASTHAN

PUBLIC WORKS DEPARTMENT

DETAIL PROJECT
REPORT
FOR

Upgradation of Existing Road under PMGSY II

NAME OF WORK : Upgradation of Anjana Pardi Jagdish


Road Km 0/00 to 11/500

NAME OF VILLAGE & : Anjana (1010) , Saliyo ka Khera ( 612 ),


POPULATION Anoppura ( 494 ) & Kundwa (791)

LENGTH : 11.500 Km.

ESTIMATED COST : Rs. 384.07 Lacs

COST PER KM : Rs. 33.40 Lacs

Name of District : Rajsamand

Name of Block : Deogarh

Name of Circle : P.W.D. Circle Rajsamand

Name of Division : P. W. D. Division BHIM

Name of Sub Division : P. W. D. Sub Division DEOGARH


P
TECHNICAL REPORT
1. Name of Work :- Upgradation of B/T Road from Anjana Pardi Jagdish Road km ( T 04 )
Km 0/00 To 11/500 under PMGSY II
2. Adm. Sanction :-

3. Preliminary Details :
The construction of new village road having following details in proposed to be constructed confirming to
the norms of PMGSY :-

Name of Dhani /
Amount Estima Ref. of
Habitation to be Length
Name of Road approved ted PMGSY Core
connected with (in Km.)
by STA Cost Network
Population (2001)

U /G of Anjana Anjana,
Pardi Jagdish Saliyo ka
1010, 612,
Road Km 0/00 Khera, Total 11.50 Km. 384.07 T-04
494, 791
to 11/500 ( T04 Anoppura,
) Kundwa

B.T. 10.40 Km.


C.C. 1.10 Km.

The off - take point of this road is SH-61 Km 276 & Presently badly damaged due to heavy traffic
Upgradation of road would good facility & the opportunities for the nearby habitations connect to bhilwara
distt.& avail the facilities available in the nearby important village/town. The socio-economic status of
the villages exist on this road would increase many folds. The people would have access to
market centre Deogarh and also would have access to SDO headquarter DEOGARH and district
Headquarter Rajsamand in lesser time and that to throughout the year.

4. Right of way
Sufficient right of way having width 10.0 Mtr. Is available as Govt. land in entire length.
5. Road Design and Specification :
The carriage way width of the road has been kept as 3.75 m. while the formation width is 7.50 m
The structural Overlay of pavement has been done as per Rural Road Manual IRC-SP-72. The
soaked CBR of soil has been found as 6.00% Considering the traffic intensity & CBR of the
existing soil, crust requirement comes to 425 mm, for which following specifications have been
adopted.
6. Scope of Work
A. B.T. Road
One Layer of 150 mm thick GSB. To be proposed in existing damaged portion in streches where required

Two Layer of 75 mm thick WBM to be proposed in damaged or raising portion as per requirement
Primer Coat of low porosity.
Tack Coat (RS-1) 0.25 to 0.30 kg. per sqm on the prepared Granular Surface treated with primer
40 mm thick bitumenous Macadam to be proposed as Overlay on existing B. T. Road
20mm thick PMC and premix seal coat by paver finisher.

B. CC Pavement :
One layer 150 mm thick GSB on entire width as per Clause 401.4 & 408.

100 mm thick C. Conc Inter Locking Block provided as C. C. pavement in village portion
7. Road Furnishing :
RCC M15 grade Kilometer Stones & 200 Mtr Stones of standard design as per IRC : 8 shall be provided as
per MoRD Specifications Clause 1703.
Providing and fixing of semi reflective cautionary, mandatory and informatory sign board as per IRC :67
made of 1.5 mm thick MS Sheet as per MoRD Specifications Clause 1701.
Direction and place identification of semi reflective sign boards as per IRC-67 made of 2mm thick M.S.
Sheet as per MoRD Specification Clause 1701.
Typical PMGSY Informatory sign board as per MoRD specifications and drawing shall be provided at
starting point.& PMGSY Logo board on every 2 kms
Typical Citizen’s Information Board as per MoRD specifications and drawing shall be provided at starting of
BT Road work and every stretch of more than 50 mtr. length of CC Pavement Road work.

8. Syphons & HPC


150mm thick PCC M-10 Grade Nominal mix 1:3:6 as per Clause 802, 803, 1202 & 1203

Random Rubble Stone masonry in cement mortar 1:4 as per Clause 702, 704, 1202 & 1203

RC NP-4 Pipes as per Clause 1106

Cement Pointing in CM 1:3 as per Clause 613.3 & 1208.4


PCC M-20 coping 50 mm thick as per Clause 615, 710 & 1204.3.11

No. of Syphon provided :- 6 Nos


9. Protection works
150mm thick PCC M-10 Grade Nominal mix 1:3:6 as per Clause 802, 803, 1202 & 1203
Random Rubble stone masonry in cement mortar 1:4 as per Clause 702, 704, 1202 & 1203
Cement Pointing in CM 1:3 as per Clause 613.3 & 1208.4
PCC M-20 coping 50 mm thick as per Clause 615, 710 & 1204.3.11

10. Details of C.D. Works :

The details of C.D. works included in this estimate are as under :-

S.No. Location No. of C.D. Details of Proposed C.D. Work Length


0/100, 1 Row 1000 mm dia HPC ( Replacement of
1/625,
1 4 Nos 7.50 m
8/025,
10/575 existing Stone slab culvert )
3/600, 2 Row 1000 mm dia HPC ( Replacement of
2 2 Nos 7.50 m
9/200 existing Stone slab culvert )

11. Material, Labour and Equipments :


The suitable material required for road construction is available in approved quarries as per R-1. The
crusher broken ballast and grit is available at the crusher at approved Quarry. The skilled / unskilled labour
is also available in the nearby area.

12. Construction Programme :


The likely period of the execution would be approximately 9 months after the awarding of Contract.

13. Rates : The cost of above project comes out 384.07 Lacs based on PWD UNIFIED BSR 2017 of
Rajasthan w. e. f. 1-07-2017
Assiatant Engineer
P. W. D. Sub Dn. DEOGARH
PERFORMA -C
PRADHAN MANTRI GRAM SADAK YOJANA ( PMGSY )
CHECK LIST FOR P.I.U. & S.T.A.
( For individual Road works )

To be filled by P.I.U.
1 Location :- State :- Rajasthan District :- Rajsamand Block :-Deogarh
2 Package :- RJ-26
3 Name of the Road :- UPGRADATION OF ANJANA PARDI JAGDISH ROAD ( T04 ) km 0/00 to 11/500
4 Length ( Km ) 11.500 Km. In built up area : 1.100 Km In Open area : 10.400 Km
Length Not to be Treated : 0.000 Km
Net Effected Length. 11.500 Km
5 Estimated Cost : 384.07 Average Cost Per Km : 33.40
Item Total Cost in Lacs Cost per Km in Lacs
Flexible Pavement 228.95 19.91
Rigid Pavement 73.37 6.38
Other 81.74 7.11
Total 384.07 33.40
6 Type of Proposal : - New Connectivity / Up Gradation Up Gradation
( i ) If the proposed road is a New Connectivity
- Is the road a part of core network N/A
- If Yes, Through / Link Route Number N/A
- Name of the unconnected Habitation (s) ( To be cross checked with CN-6 ) N/A
- List of Habitations connected enroute
- Populaion sub served by the proposed road N/A
- Does the proposed Road lead up to the habitation for which it is proposed -
to provide connectivity ( In other words are you sure that the road is not N/A
being made partially ? )
- Does the proposed Road connect the unconnected habitation to
( a ) Another Habitation having All weather road. N/A
( b ) Directly to an all weather road.
If (b), indicate the nature of road to which the proposed road leads. RR MDR SH NH
( ii ) If the Proposal is for upgradation
- Is the road a part of core network YES
- Is it associated through route or not T04
- PCI Value 2
- Age of the road 46 Years
- Is it certified that there are no other unconnected Habitation in the district N/A
7 ( a ) Whether the proposed road has the desired carriageway width.
Yes
Roadway width and Road land width ( RLW )
( b ) Indicate the actual widths of this following for the proposed road. In the built In the open
up area (m.) area ( m.)
( a ) Carriageway width 3.75 3.75
( b ) Roadway width 6.00 7.50
( c ) Road Land width 6.00 8.0-10.0
Lenear Chart
Anjana Anoppura Kundwa

SH-61
0.00 11.50
8 Base Year Traffic volume
Month & Year of Traffic Volume February, 2017
Motorised Traffic Non - Motorised Traffic
Agricultural Tractor Animal Drawn
car,jeep, Motorised Light Trucks Buses
Days Trailors Cycle Vehicle
vans,three Two Commercial Cycle
Rickshaw Num
wheelers Wheelers Vehicle SWC
L U OL L U OL L U OL Typed
Day 1
04.02.2017 160 360 54 10 8 17 7 5 21 10 0 0 30 0 0 0
Day 2
05.02.2017 162 435 38 13 13 25 10 7 16 13 0 0 35 0 0 0
Day 3
06.02.2017 140 232 42 12 10 20 8 7 17 12 0 0 56 0 0 0
Average 154 342 45 12 10 21 8 14 18 12 0 0 40 0 0 0
ADT in year of Traffic Count = 668 Base year Traffic AADT ( T ) = 883
Growth rate adopted ( % ) = 6%
Design Life = 10 Years
Number of Harvesting Seasons = 2 Nos.
No. of Days in Each Harvesting Season ( t ) = 75 Days
Value of ( n ) assumed = 1 Years Cumulative ESAL = 1362330
Traffic Category = up to 1 msa
9 Subgrade CBR ( for Different Sections ) = 6.00 to 7.00 %
CBR Adopted
Chainage Km 0/00 TO 11/500
( Average )
Design CBR ( % ) Av. CBR 6.00 % 6.00%
10 Cost Details Cost Cost / Km
A General Costs
Cost of Preparation of DPR, Inaugration 13000.00 1130.43
B Pavement Components.

Description of the Layer Thickness in mm Qty. Cost Cost / Km

Cleaning & Grubbing - 2.75 34070.00 2962.61

HSMB ( for Net filling ) - 2396.72 301987.00 26259.74

HSMB ( From Cutting ) - 37.50 1313.00 114.17

Compaction ( for soil cutting ) - 884.08 30059.00 2613.83

Ordinary rock - 75.00 4125.00 358.70

Hard Rocks - 637.50 112200.00 9756.52

GSB - 1822.50 816480.00 70998.26

Earthen Shoulders 150 4500.00 571500.00 49695.65

WMM 150 1687.50 1984500.00 172565.22


-
C Bituminous Layers
Prime Coat - 11250.00 315000.00 27391.30

Tack Coat - 40251.00 603765.00 52501.30

BM / DBM - 1631.64 10390284.00 903502.96

Surface Dressing / 20 mm PMC 20 mm 40251.00 5152128.00 448011.13

Seal Coat 40251.00 1932048.00 168004.17

D Cement Concrete Road


Cement Concrete Road ( Interlocking Block ) 100 mm 1100 m 7337481.00 638041.83
E CD Works
No. of Existing CD Works 27
Do They Require any improvement - specify the nature of improvement proposed
If Yes , their Number and Cost of improvement
Location - Chainage ( Similar Type of Type of CD & Their Total Length of
Cost in Rs.
CD'S may be ground together ) Nos. Bridge / Culvert

HPC 1 ROW 4 - 581204.00


HPC 2 ROW 2 - 604064.00

Total Cost of Proposed CD Work Nos ( 1x1000 mm HPC ) & 0.00 0.00
6 Nos (1x 300 mm Syphons) 136857.00 11900.61
Cost Rs. Cost/Km (Rs.)

E Protection Works 450 M ( 1.50 Ht ) Length 450.00 Mtr. 3627329.00 315419.91


G Pucca Side Drains ( if Provided ) Length 1100.00 Mtr. 2794397.00 242991.04
H Road Logo , other Road Furniture 315536.00 27437.91
I Any other Provisions ( Please Specify ) Setting Out & Plantation 645783.00 56155.04

Total Cost of Project ( Rs. ) 38407110.00 3339748.70

J Five Year Routine maintenance : Year Cost in Lacs % of Const. Cost Cost / Km

I 430159.63 1.12 37405.19


II 549221.67 1.43 47758.41
III 702850.11 1.83 61117.40
IV 825752.87 2.15 71804.60
V 948655.62 2.47 82491.79
Total Maintenance Cost 3456639.900 9.00 300577.38
11 Whether the road has Geometrics as per Rural Roads Manual RRM/Latest Circulars of NRRDA YES

12 Wheather CD works / Protection works are Provided as per RRM/Latest Circulars of NRRDA/Respective codes Yes

13 Weather the the Cost estimate are as per standard data analysis and S.S.R. Yes

14 Sources and the Lead distance of Materials are as under :


Material Source Lead Distance Material Source Lead Distance
Earth Locally 1.00 km Cement Deogarh 6.0 Km
Murrum Locally 3.00 km BT Vadodra 350.0 km
Aggregate Kakrod / Kitela 28.0 km Steel Kankroli 53.0 km
Sand khari River 18.0 km Emulsion Vadodra 350.0 km

Certified that information provided is true


Prepared By Checked By Scrutinized By

( R. N. Sharma ) ( P. M. Chawla ) ( A. K. Sharma )


Assistant Engineer Executive Engineer Superintending Engineer
P. W. D. Sub Dn. Deogarh P. W. D. Dn. Bhim P. W. D. Circle Rajsamand
To be filled by State Technical Agency
Name of The STA : MBM ENGINEERING COLLEGE, JODHPUR ( Rajasthan )

Name of The Road : UPGRADATION OF ANJANA PARDI JAGDISH ROAD ( T-04 ) Km 0/00 to 11/500
15 Is the Proposed Road Entered on the OMMS:
Yes / No
( Data entries to be verified by STA before Checking the Proposal )
16 If the proposal is new connectivity

Have you satisfied yourself that proposed road is a part of Core Network Yes / No

Is the unconnected habitation (s) part of list of unconnected Habitations as per CN - 6 Yes / No

Does the Proposal ensure full connectivity to Target Habitation

a ) If No. the name of Unconnected Habitation up to which it is connected Yes / No

b) If such unconnected Habitation Eligible Under PMGSY Yes / No

17 Are you satisfied with the following :

Engineering Surveys ( L - Section, X - Section must be verified ) Yes / No

Soil / Material investigation (CBR, Density, LL, Pl, Gradation to be verified ) Yes / No

Traffic Surveys / Estimation Yes / No

Hydraulic Studies Yes / No

( Catchment for structures with more than 2 Vents to be verified from topo sheet location and

requirement of all CD structures to be verified from L section)

18 In case, Traffic is projected beyond TA Category are you satisfied with the reason given by PIU Yes / No

19 In case, sub grade CBR is less than 3, has Soil Stabilisation etc, been proposed Yes / No

( If not, specific Reasons Given by PIU )

20 Is the Design of the following elements as per Rural Roads manual / Circulars of NRRDA

Alignment & Geometrics Yes / No

Location and type of CD works and Yes / No

Side drains Yes / No

Integration for cross and longitudinal Drainage Yes / No

Protection Works Yes / No

21 Is the Design of Flexible pavement as per IRC:SP:72-2007 and design of Rigid Pavement as per Yes / No

IRC SP 62-2004

22 Does the Estimation Confirm to standard Rate Analysis and SSR Generated for the current Yes / No

Phase

23 Does the proposal have provisions for PMGSY Logo Sign Boards and information Board

Km / Hm Stones Yes / No
Guard Stones ( Where necessary ) Yes / No

Traffic Sign Boards ( as Necessary ) Yes / No

24 Specific Remarks, if any, by, STA

(Specific remarks of STA about the overall project are necessary on each DPR )

Certified that the Design and Estimate for the Proposed Road work are based on the data and SSR
provided by PIU Engineers. The Proposal after final correction is entered on the OMMS. The Proposal may be
considered for clearance.

Technical Scruitiny at STA done by : Co - ordinator STA :

Signature Signature

Name Name

Date Date
}u
Annexure-I

iz/kkuea=h xzke
lM+d ;kstuk
CERTIFICATE FOR APPLICATION OF ESMF FOR PROJECTS

This is to certify that relevant provisions for the Environmental and Social Management Framework
have been applied during the preparation of Detailed Project Report for the road from
UPGRADATION OF ANJANA PARDI JAGDISH ROAD ( T04 ) Km 0/00 to 11/500
(name of habitations being connected) in District Rajsamand of Rajasthan.

The Provisions of the following ECOPs are applicable to the sub-


project

1.0 PROJECT PLANNING & DESIGN : YES NO


Are provisions made for enhancements

2.0 SITE PREPARATION : YES NO

3.0 CONSTRUCTION CAMPS


Are likely locations identified in the DPR : YES NO NR

4.0 ALTERNATE MATERIALS FOR CONSTRUCTION : YES NO NR


Specify Material: Not Available within 100Km lead

5.0 BORROW AREAS : YES NO

6.0 TOPSOIL SALVAGE,STORAGE AND REPLACEMENT


Is provision made in the BoQ : YES NO NR

7.0 QUARRY MANAGEMENT : YES NO NR

8.0 WATER FOR CONSTRUCTION :


Are water sources identified in case of water scarce areas YES NO NR

9.0 SLOPE STABILITY AND EROSION CONTROL : YES NO

10.0 WASTE MANAGEMENT : YES NO

Are locations for waste disposal identified YES NO

11.0 WATER BODIES : YES NO NR


Specify Material: NIL

12.0 DRAINAGE : YES NO NR

13.0 CONSTRUCTION PLANTS & EQUIPMENT MANAGEMENT : YES NO NR


Contd……2
iz/kkuea=h xzke
lM+d ;kstuk
14.0 PUBLIC AND WORKER'S HEALTH AND SAFETY : YES NO NR

15.0 CULTURAL PROPERTIES : YES NO NR


Specify Material: NIL

16.0 TREE PLANTATION : YES NO NR


Is road side tree plantation plan attached

17.0 MANAGING INDUCED DEVELOPMENT : YES NO


Is location map for area identified for induced development been attached

18.0 ENVIRONMENTAL AUDIT : YES NO


Is Checklist-1 for DPR Preparation attacted

19.0 NATURAL HABITATS : YES NO NR


Specify Location:__________________________

20.0 CONSULTATIONS FOR ENVIRONMENTAL ASPECTS : YES NO

21.0 PAP'S IDENTIFIED : YES NO NR

22.0 ADDITIONAL LAND REQUIRED : YES NO

23.0 PAP'S COMPENSATED AND ASSISTANCE PROVIDED


ACCORDING TO ESME : YES NO NR

24.0 DOCUMENTATION FOR VOLUNTARY LAND DONATION : YES NO NR


COMPLETED

25.0 IS THE ASSISTANCE UNDER RD/LIVELIHOOD PROGR- : YES NO NR


AMS TO THE ELIGIBLE PAP'S BEING DELIVERED.

26.0 ARE THERE ANY OUTSTANDING ISSUE OR GRIEYANC- : YES NO


ES IN REGARD TO LOSSES AND PROPOSED MEASURES

Exeuctive Engineer Superintending Engineer


PWD.,Division-Bhim PWD.,Circle, Rajsamand

Verified:

Date: iz/kkuea=h xzke


(STA/Technical Examiner,Rajasthan State)
Place:

lM+d ;kstuk
iz/kkuea=h xzke
lM+d ;kstuk
=h xzke
d ;kstuk

=h xzke
d ;kstuk
=h xzke
d ;kstuk
PRADHAN MANTRI GRAM SADAK YOJANA
( Ministry of Rural Development, Govt. of India )
Format -B

SUMMARY SHEET
Name of Road : - UPGRADATION OF ANJANA PARDI JAGDISH ROAD ( T04 ) Km 0/00 to 11/500
Length of Road : - 11.500 Km Package : Rj - 26

BLOCK :- Deogarh District : Rajsamand

S No. Name Of Name of Road Type of Estimate Cost of Nos of C. Cost of C. Total Estimated ( Cost in Average Cost per Km
Block Proposed d Cost Pavement D. Works D. Works ( Lacs )
Road N in Lacs ( Nos ) In Lacs )
/U

From To Const. Maint. Const. Maint.


1 2 3 4 5 6 7 8 9 10 11 12 13

1 DEOGARH ANJANA KUNDWA U 384.07 306.63 6 77.44 384.07 5.83 33.40 0.51

TOTAL COST 384.07 5.83 33.40 0.51

Prepared by: Signature


Name ( R. N. Sharma )
Designation Assist. Engineer Technical Scruitiny Signature
Done by Name

Prepared by: Signature


Name ( P. M. Chawla )
Designation Exe. Engineer
Co-Ordinator Signature
Name
Prepared by: Signature
Name ( A. K. Sharma )
Designation Supdt. Engineer
PRADHAN MANTRI GRAM SADAK YOJANA ( PMGSY )
ROAD WISE SUMMARY OF ESTIMATE
FORMAT - 7

BLOCK DEOGARH DISTRICT : RAJSAMAND PACKAGE NO. RJ - 26 -

Name of Road : UPGRADATION OF ANJANA PARDI JAGDISH ROAD ( T04 ) km 0/00 to 11/500
Upgradation / New Construction UPGRADATION
Length of the Road ( In Kms ) : 11.500 Kms
CBR Value of Soil 6.00%

Existing Thickness
Design Thickness 40 mm BM & 20 mm PMC with Seal Coat

S.N Particulars Unit Quantity Rate( Rs ) Amount ( Rs )


1.a Cleaning & Grubbing Hactare 2.75 12389.00 34069.75
b. Stripping of Top Soil Cum 0.00 97.00 0.00
c. Turfing with Sods Sqm 0.00 35.00 0.00 34069.75
2 Earth work Cutting filling
a. Earth Work ( for net filling ) Cum 2396.72 126.00 301986.97
b. Earth Work ( from cutting ) Cum 37.50 35.00 1312.50
c. Embankment from cutting Cum 884.08 34.00 30058.65
d Ordinary rocks Cutting Cum 75.00 55.00 4125.00
e Hard Rocks cutting Cum 637.50 176.00 112200.00
f Phylite Rocks Cum 0.00 0.00 0.00 449683.12
3 Gravelling
a. Carriage way Cum 1822.50 448.00 816480.00 816480.00
b. Earthen Shoulders Cum 4500.00 127.00 571500.00 571500.00
4 W.M.M. WORK Cum 1687.50 1176.00 1984500.00 1984500.00
5 Primer Coat Sqm 11250.00 42.00 315000.00 315000.00
6 Tack Coat Sqm 40251.00 15.00 603765.00 603765.00
7 Bitumenous Macadam Sqm 1631.64 6368.00 10390283.52 10390283.52
8 20mm PMC Sqm 40251.00 128.00 5152128.00 5152128.00
9 Premix seal Coat Sqm 40251.00 48.00 1932048.00 1932048.00
10 Road Furniture - - 315536.00 315536.00
11 Interlocking c. Conc. Block Pavement Mtr 1100.00 7337481.00 7337481.00
12 Misc. Work ( Setting Out, etc. ) Mtr 11.50 56155.00 645782.50 645782.50
Total 30548256.89 30064504.02
12 CD & Protection Work
a. 1 Row x 1000 mm dia HPC Nos 4 145301.00 581204.00 581204.00
b. 2 Row x 1000 mm dia HPC Nos 2 302032.00 604064.00 604064.00
c. Syphons Nos 6 136857.00 136857.00 136857.00
d. Protection wall M 450.0 - 3627329.00 3627329.00
e.Toe wall M 0 - 0.00 0.00
f. Side Drain M 1100m - 2794397.00 2794397.00
13 Cost of DPR Km 11.50 10000.00 115000.00 115000.00
7858851.00 7858851.00
TOTAL Cost 38407107.89 38407107.89

ASSISTANT ENGINEER EXECUTIVE ENGINEER


P.W.D. SUB DN. Deogarh P.W.D. DN BHIM
PRADHAN MANTRI GRAM SADAK YOJANA
( Ministry of Rural Development, Govt. of India ) Format -2

Name of Road : - UPGRADATION OF ANJANA PARDI JAGDISH ROAD ( T04 ) Km 0/00 to 11/500
Length of Road : - 11.500 Km Package : Rj - 26
District : Rajsamand
BLOCK :- Deogarh

Facillities
Road
S. Road Accessed
Name of Road Connecting Traffic per day Existing Road Details
No. Length ( Use
to
A/B/C/D)

Total Land Road


Total Embankment (
Truck/T CBR width width WBM Layer Bituminous Layer
Motorised formation )
ractor (m) (m)
Height Width Width Thickness Type Width Thickness
(m) (m) (m) (mm) (m) (mm)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Anjana,
Anjana Pardi saliyo ka 0.60
8.0 to PMC
1 Jagdish Road 11.50 khera, C 687 172 6.00% 7.50 -0.90 7.5 m 3.75 150 mm 3.75 20 mm
Anoppura, 10.0 m + SC
( T 04 ) m
Kundwa

ASSISTANT ENGINEER EXECUTIVE ENGINEER


P.W.D. SUB DN. Deogarh P.W.D. DN BHIM
PRADHAN MANTRI GRAM SADAK YOJANA
( Ministry of Rural Development, Govt. of India )
Format -2A
SUMMARY SHEET

Name of Road : - UPGRADATION OF ANJANA PARDI JAGDISH ROAD ( T04 ) Km 0/00 to 11/500
Length of Road : - 11.500 Km Package : Rj - 26
District : Rajsamand
BLOCK DEOGARH
New Construction ( N )

Upgradation ( U )

A/B/C/D )

Road length ( Km )
Name of Places /
Villages connected Facility accessed ( use Details of thickness & cost for Pavement layers
by Road
S.No.

Earth Work
Existing Details C.Conc.

Cleaning &
Grubbing

Subgrade
preparation

Prime coat

Road Furnish
Misc BM + Total cost

Tack Coat
Surface Pavement PMC of

WBM
Type + SC pavement
Sum of
( 10 to 19
From To )

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1 Anjana Kundwa U C 11.50 A.W. TH 200 - 600 125 150 - - - - 20

Cost 73.37 0.34 4.497 13.88 19.85 3.15 3.155 6.04 7.61 174.7 306.63

ASSISTANT ENGINEER EXECUTIVE ENGINEER


P.W.D. SUB DN. Deogarh P.W.D. DN BHIM
PRADHAN MANTRI GRAM SADAK YOJANA
( Ministry of Rural Development, Govt. of India )
Format -2B
SUMMARY SHEET

Name of Road : - UPGRADATION OF ANJANA PARDI JAGDISH ROAD ( T04 ) Km 0/00 to 11/500
Length of Road : - 11.500 Km Package : Rj - 26
District : Rajsamand
BLOCK :- Deogarh
S.No.

Name of Road New Road Existing CD Structure by type Details of Proposed CD structure by
Constructi length type
on / Hume pipe RCC Minor Details Hume pipe Drain, Toe Protection Total cost Total cost Total cost
Upgradatio culverts Slab / Bridge culverts Wall wall of of of road
n Stone pavement
proposed
Slab CD from
Structures
format -F- ( 18 + 19 )
No. Dia. No. Len No. Len No. Dia. No. Length Ht. Len 2A
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
UPGRADATION
OF ANJANA
PARDI JAGDISH
ROAD ( T04 ) Km
1 0/00 to 11/500 U 11.50 1.50 30

13.22 27.94 36.27 77.44 306.63 384.07

ASSISTANT ENGINEER EXECUTIVE ENGINEER


P.W.D. SUB DN.Deogarh P.W.D. DN BHIM
MASTER DATA
A & F Sanction No :
Block DEOGARH District Rajsamand Package No. RJ-26

Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road km 0/00 to 11/500

Road From Anjana


From
Length of the Road : 11.50 Km. Length :
Package No. : Length :
1 Core Net Link Route No. T-03
2 Population (2001) of Village 260
3 CBR 6.00%
4 Total Crust of Road 325 mm
5 Formation Width 7.50 Mtr.
6 Traffic (CVPD) 21
7 Earth work from Calculation Sheet 2115.92 Diff. in Cost (Estimate -
8 Sanction Amount (STA)
9 Habitation connected incidentally
Name
Population(2001)
10 C.C. Pavement Chainage
Length of C.C. Pavement 1100 Mtr. 0/000 to 0/300 & 1/100 to 1/300

11 C.D. Works
(i) Hume Pipe Culverts
HPC Single Row 4 Nos.
HPC Double Row 2 Nos.
Slab Culvert 0 Nos.
(ii) Causeways
Total Length CC Pavement Numbers Chainage Straight Length
FCW 0 Mtr. 0 Mtr. 0 Nos. 0 Mtr.
FCW 0 Mtr. 0 Mtr. 0 Nos. 0 Mtr.
FCW 0 Mtr. 0 Mtr. 0 Nos. 0 Mtr.
Vented Causeway 0 Mtr. 0 Mtr. 0 Nos. 0 Mtr.
(iii) Syphones 6 Nos.
12 Protection Work
Length of Toe Wall & Pitching 0.00 Mtr. Lateral Height of Pitching
0/600-0/630,
Length of Protection Wall 600.00 Mtr. Section of Toe Wall
Top Width
13 Drain Bottom Width
Length of Drain 1000.00 Mtr. Height
14 Road Geometrics C.C. BT Section of Protection Wall
Junction 0 Nos. 0 Nos. Top Width
Ramp 0 Nos. Bottom Width
Bus Bay 0 Nos. 0 Nos. Height
CC Ramp 0 Nos.
Material Stacking 0 Nos.
Extra Widening
0 Nos. 0 Nos.
of Curve
15 Road Furniture CBR Value
(i) Ordinary Kilometer Stone 13 Nos. Km. 1
(ii) 200m Stone (Precast) 44 Nos. Km. 2
(iii) Semi Reflective Board 96 Nos. Km. 3
(iv) Place Identification Board 10 Nos. Km. 4
(v) Citizen's Information Board 4 Nos. Km. 5
Km. 6
(vi) PMGSY Informatory Sign Board 2 Nos. Km. 7
(vii) PMGSY Logo Board 6 Nos. Km. 8
(vii) Painting 4800 Nos. Km. 9
Km. 10
Km. 11
Earth Local 1000 M
GSB / Murrum Nearby Area 3 Km
Aggregate Kitela 28
Sand Khari River 18
Cement Deogarh 6
Emulsion Badodra 345 km
Bitumen Badodra 345 km
Dated :
Circle P.W.D. Circle Rajsamand
Division P.W.D. Division BHIM
Sub Dn. P.W.D. Sub Dn. Deogarh

To Kundwa
To
11.500 Km.
5.500 Km.(For Earth Work)
Cost Analysis
Estimated Cost (in Lacs.) 384.07
Av. Cost per Km (Lacs) 33.40
Estimated Cost Rs. 384.07
"G" Schedule Amount Rs. 0.00
Misc. Amount Rs. 0.00
Diff. in Cost (Estimate - "G"-Schedule) Rs. 0.00
% on STA Amount

Width
Width of C.C. 3.75 Mtr.
Pavement

Raising Face Walls Guide Post


Each Side 0 Mtr. 0 Nos.
Each Side 0 Mtr. 0 Nos.
Each Side 0 Mtr. 0 Nos.
Each Side 0 Mtr. 0 Nos.

Width/Height
al Height of Pitching 0 Mtr.
on of Toe Wall 0 Mtr.

on of Protection Wall
0.50 Mtr.
1.25 Mtr.
2.25 Mtr.
Av Value
6.00%
6.00%
6.00%
6.00%
6.00%
6.00%
6.00%
6.00%
6.00%
6.00%
6.00%
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
LINEAR CHART
Block :- DEOGARH
A. Existing Road

Anjana Saliyo ka khera Anoppura Kundwa Pardi

SH-61

0/0 3/00 6/00 9/00 12/00 15/00

B. Proposed Road

Anjana Saliyo ka khera Anoppura Kundwa Pardi

200 m 300 m 200 m 400 m


SH-61
c.c Pav. c.c Pav. c.c Pav. c.c Pav.

0/0 3/00 6/00 9/00 11/00 15/00

Earth Work C.C. Road

GSB Assistant Engineer


CD Work P.W.D. Sub Dn. Deogarh
BT Road
18/00

18/00
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

Mtr 7.50
12.00
Mtr 3.75
m0
3% 3%
4% % % 4%
% %

2:1

Preserved Soil
Earthen shoulder Proposed 40 mm BM & 20mm
Existing 150 mm WBM Gr-III PMC with Seal Coat type B with
Existing 150 mm thick GSB Bitumen VG-30

TYPICAL CROSS SECTION OF PROPOSED BT ROAD

Assistant Engineer
P.W.D. Sub Dn. Deogarh
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

1.00 1.00
Mtr Mtr 3.75 Mtr

75mm Thick Coping 0.30

2%
0.60m

150 mm Thick (M-10)


0.60m L-Shape Drain

Proposed 100 mm Th
Inter locking Block
Proposed 150 mm thick GSB

TYPICAL X- SECTION OF INTER LOCKING BLOCK PAVEMENT WITH


DRAIN IN VILLAGE PORTION

Assistant Engineer
P.W.D. Sub Dn. Deogarh
DISTRICT MAP

Assistant Engineer
P.W.D. Sub Dn. Deogarh

Assistant Engineer
P.W.D. Sub Dn. Deogarh
GENERAL ABSTRACT
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road km 0/00 to 11/500
UNDER PMGSY II
Package No. RJ-26-
Length of the Road :-11.50 Km.

S. No. Particulars Amount


1 PART- A : EARTH WORK 1129537.00
2 PART - 'B' : W.B.M. & HARD SHOULDER WORK 3372480.00
3 PART - C : B.T. WORK 18393225.00
4 PART- D : ROAD FURNISHING 315536.00
5 PART- E : C.C. PAVEMENT 7337481.00
6 0 2794397.00
7 PART- G : SYPHON 136857.00
8 PART- H (i) : HP CULVERT - 1000MM DIA SINGLE ROW 581204.00
9 PART- H (ii) : HP CULVERT - 1000MM DIA DOUBLE ROW 604064.00
10 PART - I - RCC Slab Culvert 0.00
11 PART- J : PROTECTION WORK 3627329.00
12 Add for DPR Rs. 10000/- Per Km. 115000.00
Total :- 38407110.00

Say 384.07 Lacs

Assistant Engineer
P.W.D. Sub Dn. Deogarh
COST ESTIMATE FOR ROAD CONSTRUCTION
NAME OF ROAD :- Anjana Pardi Jagdish Road ( T 04 ) km 0/00 to 11/500
District :-

Sl. Rate
Description of Item Measurement Qty. Unit
No. (Rs)
1 2 3 4 5 6
PART- A : EARTH WORK
1 Clearing and Grubbing Road land - Cleaning and grubbing road land
including uprooting wild vegetation grass,bushes, shrubs, saplings and
trees of girth upto 300mm, removal of stumps of such trees earlier and
disposal of unserviceable materials and stacking of serviceable material to
be used or auctioned upto a lead of 1000 m including removal and disposal
of top organic soil not exceeding 150mm in thickness as per MoRD
specification Clause 201, By mechanical means in area of non-thorny
jungle.
2 x 5500.00 x 2.50 2.750 12389.00 P.Hect.
2 Excavation in Soil using Hydraulic Excavator and tippers with disposal upto
1000 m. Excavation for road work in soil with hydraulic excavator of 0.9
cum bucket capacity including cutting and loading in tippers, trimming
bottom and side slopes, in accordance with requirements of lines, grades
and cross-sections, and transporting to the embankment location with a lift
upto 1.5m and lead upto 1000 in as per MoRD specification Clause 302.3
As per Sheet enclosed 37.50 35.00 P.Cum.
3 Excavation in Ordinary Rock using Hydraulic Excavator and Tippers with
disposal upto 1000m. Excavation for roadway in ordinary rock with
hydraulic excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site with lift upto 1.5m and
lead upto 1000m, trimming bottom and side slopes in accordance with
requirements of lines, grades and cross - sections as per MoRD
specification Clause-302.3.5
As per Sheet enclosed 75.00 55.00 P.Cum
4 Excavation in hard rock ( requiring blasting) with disposal upto 1000m.
Excavation for roadway in Hard rock(requiring blasting) by drilling, blasting
and breaking, trimming of bottom and side slopes in accordance with
requirement of lines, grades and cross-sections, loading and disposal of
cut rock with a lift upto 1.5m and leads upto 1000m as per MoRD
specification Clause 302.3.5
As per Sheet enclosed 637.50 176.00 P.Cum
5 Construction of Embankment with material obtained from Roadway cutting.
Construction of embankment with approved materials deposited at site
from roadway cutting and excavation from drain and foundation of other
structures graded and compacted to meet requirement of Tables 300.1 and
300.2 as per MoRD specification Clause 301.5
As per Sheet enclosed 884.08 34.00 P.Cum
6 Construction of Embankment with Material from Borrow Pits.
Construction of embankment with approved material obtained from borrow
pits with a lift upto 1.5m, transporting to site, spreading, grading to required
slope and compaction to meet requirement of Table 300.1 and 300.2 with a
lead upto 1000m by mechanical means as per MoRD specification Clause
301.5.

file:///conversion/tmp/scratch/378102405.xlsx
NAME OF ROAD :- Anjana Pardi Jagdish Road ( T 04 ) km 0/00 to 11/500
District :-

Sl. Rate
Description of Item Measurement Qty. Unit
No. (Rs)
1 2 3 4 5 6
As per Sheet enclosed 2115.92
0.000 1.500
For Junction 2 4 30.00 0.60 108.00
2
For Junction 2 15.00 1.500 0.60 27.00
1.500 15.00
For Junction 2 1 13.50 0.60 145.80
2
2396.72 126.00 P.Cum
7 Excavation for roadway in Phylite rock by drilling , blasting and breaking ,
trimming of bottom and side slopes in accordance with requirements of
lines , grades an cross sections loading and disposal of cut rock with a lift
upto 1.5 m and leads upto 1000 m as per MoRD Specification Clause
302.3.5
As per Sheet enclosed 0.00 0.00 P.Cum
8 Stripping, Storing and Relaying Top Soil from Right-of-Way (R.O.W)
Stripping, storing and preservation of top soil from borrow areas located in
agriculture fields, storing at suitable place, spreading and relaying after
taking the borrow earth to maintain fertility of the agricultural field, finishing
it to the required levels to the satisfaction of the farmer/land owner as per
MoRD specification clause 302.3.2
0 700 1.13 0 0.00 97.00 P.Cum
9 Setting Out. Construction of reference bench mark , working bench mark
( 4 Nos ) and near all drainage structures and bridges (as per direction of
Engineer-in-charge ) reference pillar/ burgees @ 50m interval on both side
of formation width including marking of centre line, setting out curves,
recording of levels, white washing and lettering etc. complete as per MoRD
specifications cl. 108.
1 11.500 11.500 56155.00 P.Km.
TOTAL OF PART - A

Assistant Engineer
P.W.D.Sub Dn. Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
Rajsamand

Amount
(Rs)
7

34070.00

1313.00

4125.00

112200.00

30059.00

file:///conversion/tmp/scratch/378102405.xlsx
Rajsamand

Amount
(Rs)
7

301987.00

0.00

0.00

645783.00
1129537.00

Assistant Engineer
P.W.D.Sub Dn. Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR ROAD CONSTRUCTION

Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Block :- DEOGARH District :Rajsamand

Sl. Description of Rate Amount


Measurement Qty. Unit
No. Item (Rs) (Rs)
1 2 3 4 5 6 7
PART - 'B' : W.B.M. & HARD SHOULDER WORK
1 Construction of granular sub-base by providing well graded material,
spreading in uniform layers with tractor mount grader on prepared
surface, mixing by mix in place method with rotavator at OMC, and
compacting with smooth wheel roller to achieve the desired density,
complete as per MoRD Specification Clause 401. For Grading III
Material.
For Raising of
Various 1 3000.00 0.15 1822.50
Reaches
Total 1822.50 448.00 P.Cum 816480.00
2 Wet Mix Macadam (Providing, laying, spreading and compacting
graded stone aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix plant
carriage of mixed Material by tipper to site, laying in uniform layers with
paver in sub- base / base course on well prepared surface and
compacting with vibratory roller to achieve the desired density.)
For Raising of
Various 1 3000.00 0.075 843.75
Reaches
Total 843.75 1176.00 P.Cum 992250.00
3 Wet Mix Macadam (Providing, laying, spreading and compacting
graded stone aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix plant
carriage of mixed Material by tipper to site, laying in uniform layers with
paver in sub- base / base course on well prepared surface and
compacting with vibratory roller to achieve the desired density.)
For Raising of
Various 1 3000.00 0.075 843.75
Reaches
Total 843.75 1176.00 P.Cum 992250.00
4 Construction of subgrade and earthen shoulders with approved
material obtained from borrow pits with all lifts and leads, transporting
to site,spreading, grading to required slope and compacted to meet
requirement of table 300.2 with lead up to 1000 m as per Technical
Specification Clause 303.1
For Berms 2 10000.00 1.500 0.15 4500.00
Filling

Total 4500.00 127.00 P.Cum 571500.00


TOTAL OF 3372480.00
PART - B

file:///conversion/tmp/scratch/378102405.xlsx
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Block :- DEOGARH District :Rajsamand

Sl. Description of Rate Amount


Measurement Qty. Unit
No. Item (Rs) (Rs)
1 2 3 4 5 6 7
Assistant Engineer
P.W.D.Sub Dn. Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR ROAD CONSTRUCTION

Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Existing C.C. (7.50 Mtr. Width) 0 Mtr.

District Rajsamand
Existing FCW (not to be taken) 0 Mtr.
Sl. Description of Rate Amount
Measurement Qty. Unit
No. Item (Rs) (Rs)
1 2 3 4 5 6 7
PART - C : B.T. WORK
1 PRIMER COAT Providing and applying primer coat with bitumen
emulsion (SS-1) on prepared surface of granular base including
cleaning of road surface and spraying primer at the rate of 0.70-1.0
kg/Sqm using mechanical means as per Technical Specification
Clause 503 ( Low Porosity )
For Carrigeway
of raising 1 3000.00 3.75 11250.00
reaches
11250.00 42.00 P.Sqm 315000.00
2 Providing and applying tack coat with Bitumen emulsion (RS-1)
using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm
on the prepared granular surfaces treated with primer & cleaned
with Hydraulic broom as per MoRD Specification Clause 503.
For Carrigeway 1 10400.00 3.75 39000.00
For Jucction 8 30.00 0.75 180.00
For Jucction 8 15.00 1.50 180.00
For Junction 8 13.50 8.25 891.00
40251.00 15.00 P.Sqm 603765.00
3 Providing and laying bituminous macadam with hot mix plant using
crushed aggregates of grading as per Table 500.4 premixed with
bituminous binder, transported to site with all leads laid over a
previously prepared surface with paver finisher to the required
grade, level and alignment and rolled to achieve the desired
compaction as per MoRD Specification Clause 504. Bitumen ( VG-
30 )
1 10400 3.75 0.04 1560.00
0.00 1.50 28.80
For Junction 8 30.00 0.04
2
For Junction 8 15.00 1.50 0.04 7.20
1.50 15.00
For Junction 8 13.50 0.04 35.64
2
Total 1631.64 6368.00 P.Cum 10390284.00

file:///conversion/tmp/scratch/378102405.xlsx
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Existing C.C. (7.50 Mtr. Width) 0 Mtr.

District Rajsamand
Existing FCW (not to be taken) 0 Mtr.
Sl. Description of Rate Amount
Measurement Qty. Unit
No. Item (Rs) (Rs)
1 2 3 4 5 6 7
4 Providing, laying and rolling of open-graded premix carpet of 20
mm thickness composed of 13.2 mm to 5.6 mm aggregates either
using penetration grade bitumen or emulsion to required line,
grade and level to serve as wearing course on a previously
prepared base, including mixing in a suitable plant, laying and
rolling with a three wheel 80-100 kN static roller capacity, finished
to required level and grades to be followed by seal coat of either
Type A or Type B or Type C as per MoRD Specification Clause 508
( excluding cost of seal coat ) Case - II By Mechanical Means
Bitumen VG-30
Area as per item No. 1 40251.00 128.00 P.Sqm 5152128.00
5 Providing and laying seal coat sealing the voids in a bituminous
surface laid to the specified levels, grade and cross fall using Type
A, Type B and Type C as per MoRD Specification Clause 510 By
Mechanical Means Case - III : Type C Bitumen VG-30
Area as per item No. 1 40251.00 48.00 P.Sqm 1932048.00
TOTAL OF PART - C 18393225.00

9 Assistant Engineer
P.W.D.Sub Dn.Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
p

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR ROAD FURNITURE

Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Langth of the Road : 11.500 Km. District :- Rajsamand

Sl. Quantit Rate Amount


Description of Item Measurement Unit
No. y (Rs) (Rs)
1 2 3 4 5 6 7
PART- D : ROAD FURNISHING
1 Reinforced cement concrete M15 grade kilometre stone / Local stone of
standard design as per IRC:8 fixing in position including painting and
printing, etc as per drawing and MoRD Specification Clause 1703
(i) Ordinary Kilometer Stone (Precast) Nos. 13 1589.00 20657.00
(ii) 200 m stone (precast) Nos. 44 364.00 16016.00
2 Providing and fixing of semi reflective cautionary, mandatory and informatory
sign board as per IRC:67 made of 1.5 mm thick MS Sheet duly stove white
colour in front and gray colour on back with red reflective border of 65 mm
width and required letters and figures with reflective tape engineering grade
as per Clause 1701.3.9 of MORD for Rural Roads of required shade and
colour supported and welded on 47mm x 47 mm x 12 SWG sheet tube firmly
fixed to the ground by mean of properly designed foundations with M-15
grade cement concrete 450x450x600 mm, 600 mm below ground level as
per approved drawing Clause 1701.2.2 600 mm equilateral triangle. Nos. 96 1668.00 160128.00
3 Providing and erecting direction and place identification of semi reflective
sign boards as per IRC-67 made of 2 mm thick M.S. Sheet duly stove
enameled paint white colour in front and grey colour on back with reflective
border of 70 mm width and required message, letters, figures with reflective
tape of engineering grade as per MORD specifications of required shade
and colour. Supported and welded on two nos. 47 mm x 47 mm of 12 SWG
square tube of 3050 mm height duly strengthened by 25 mm x 5 mm MS flat
iron on edges on back firmly fixed to the ground by means of properly
designed foundations with M-15 grade cement concrete 450 mm x 450 mm
x 600 mm, 600 mm below ground level as per approved drawing and MoRD
Specification Clause 1701 with size more than 0.9 sqm size board Sqm 14.40 3082.00 44381.00
4 P& F of typical PMGSY informatory sign board with logo as per MORD
specification and drawing. Three M.S. plates of 1.6 mm thick, top and middle
plate duly welded with M.S. flat iron 25mm x 5mm size on back on edges.
The lower plate will be welded with MS angle iron frame of 25mm x 25mm x
5mm. The angle iron frame of the lower most plate and flat iron frame of
middle plate will be welded to 2 nos. 75mm x 75mm of 12 SWG sheet tubes
posts duly embedded in cement concrete M-15 grade blocks of 450mm x
450mm x 600mm, 600mm below ground level. The top most diamond plate
will be welded to middle plate by 47mm x 47mm of SWG steel plate tube. All
M.S. will be stove enamelled on both sides. Lettering and printing arrows,
border etc. will be painted with ready mixed synthetic enamel paint of
superior quality in required shade and colour. All sections of framed posts
and steel tube will be painted with primer and two coats of epoxy paint as
per drawing Clause 1701 and Annexure 1700.1 Nos. 2 10822.00 21644.00

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR ROAD FURNITURE

Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Langth of the Road : 11.500 Km. District :- Rajsamand

Sl. Quantit Rate Amount


Description of Item Measurement Unit
No. y (Rs) (Rs)
1 2 3 4 5 6 7
5 Supply and fixing of PMGSY logo with definition plate (as per MORD
design/drawing) 2mm thick MS plate framed to angle Iron 40x40x5 mm on
MS post of angle Iron of size 65x65x6mm, 3m long stove enameled paint
with hold fast including orange luminous colour paint on logo, size of
diamand plate 600x600mm definition plate 900x250mm fixed to the ground
by means of properly designed foundation with M-15 grade cement concrete
450x450x600mm, 600mm below ground level as per approved drawing and
MoRD specification Clause 1701 Nos. 6 2977.00 17862.00
6 Providing and Erecting typical Citizen's information Board as per approved
drawing & specification of MoRD made of two MS sheet of 1.6 mm thick
each of size 900mm x 750mm stiffened by angle iron 25mmx25mm x 3mm
all around the plate & plates fixed on frame of 75mm dia pipe of 12 SWG
sheet (vertical post 3050 mm with angle holdfasts and horizontal member
900mm) to be joined by 5mm thick MS plate at 12 places ( 65mm x 50mm )
duly embedded in cement concrete M-15 grade of block of 600mmx 600mm
x 750 mm size below ground level as per enclosed drawings & as directed
by Engineering incharge. All MS will be stove enameled on both side
lettering. Figuring and border will be with ready mixed synthetic enamel
paint of superior quality in required shade and colour etc complete in all
respect. All sections of framed post and steel tube will be painted with primer
and two coat of epoxy paint as per drawing and as per MoRD Specification. Nos. 4 8712.00 34848.00
Total Rs 315536.00

Assistant Engineer
P.W.D.Sub Dn. Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR INTERLOCKING C. C. BLOCK PAVEMENT IN VILLAGE PORTION

IN VILLAGE PORTION
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

Block :- DEOGARH District :- Rajsamand

Chainage : Anjana, Saliyo ka Khera, Anoppura & Kundwa village ( Total Length 1100 m )

Sl. Rate Amount


Description of Item Measurement Unit Quantity
No. (Rs) (Rs)
1 2 3 4 5 6 7
PART- E : C.C. PAVEMENT 1100.00 Mtr.

1 Construction of granular sub-base by providing well


graded material, spreading in uniform layers with
tractor mount grader on prepared surface, mixing by
mix in place method with rotavator at OMC, and
compacting with smooth wheel roller to achieve the
desired density, complete as per MoRD Specification
Clause 401. For Grading III Material.
1 x 1100.00 x 5.50 x 0.150 907.50
Total :- P.Cum 907.50 448.00 406560.00
Providing, laying, spreading and compacting
graded stone aggregate to wet mix macadam
specification including premixing the material with
water at OMC in mechanical mixer (Pug Mill),
carriage of mixed material by tipper to site, laying
in uniform layers in sub-base/base course on a
well prepared sub-base and compacting with
smooth wheel roller of 80 to 100kN weight to
achieve the desired density including lighting,
barricading and maintenance of diversion, etc as
per Tables 400.11 & 400.12 and MoRD
Specification Clause 406. By Mech Means

1 x 1100.00 x 5.50 x 0.075 453.75


Total :- P.Cum 453.75 1115.00 505931.00
2 Providing and Laying of Interlocking M-30 grade
Concrete Block Pavements having thickness 100
mm as per drawings and MoRD Specification Clause
1504with M-30 Grade 0.30x0.30x0.15 mtr Edge
Blocks.Cat B Dentated only two sides like I, Z, T
shape as per IRC: SP:63-2004
1 x 1100.00 x 5.50 6050.00
Total :- P.Sqm 6050.00 1055.00 6382750.00

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR INTERLOCKING C. C. BLOCK PAVEMENT IN VILLAGE PORTION

IN VILLAGE PORTION
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

Block :- DEOGARH District :- Rajsamand

Chainage : Anjana, Saliyo ka Khera, Anoppura & Kundwa village ( Total Length 1100 m )

Sl. Rate Amount


Description of Item Measurement Unit Quantity
No. (Rs) (Rs)
1 2 3 4 5 6 7
3 Providing and laying reinforced cement concrete
pipe NP3 for culverts on first class bedding of
granular material in single row including fixing collar
with cement mortar 1:2 but excluding excavation,
protection works, backfilling, concrete and masonry
works in head walls and parapets Clause 1106. 300
mm dia
For Services 8 x 7.50 P.Rmt. 60.00 704.00 42240.00
Total Part-"E" CC Pavement Rs. 7337481.00

Assistant Engineer
P.W.D.Sub Dn.Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR ROAD CONSTRUCTION
DRAIN WORK
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

Anjana ( 200 m ), Saliyo ka khera (250 m ),Anoppura ( 250 m ), Kundwa ( 400 m )

Sl. Rate Amount


Description of Item Measurement Unit Qty.
No. Rs Rs
1 2 3 4 5 6 7
1100.00 Mtr.
1 Earthwork in excavation for structures as
per drawing and MoRD specifications
Clause 305.1 including setting out,
construction of shoring and bracing,
removal of stumps and other deleterious
material and disposal upto a lead of 50
m, dressing of sides and bottom and
backfilling in trenches with excavated
suitable material Ordinary soil Upto 3 m
depth.
1 x 1100.00 x 1.30 x 0.45 P.Cum 643.50 178.00 114543.00
2 Providing concrete for plain/reinforced
concrete in open foundations complete as
per drawings and MoRD specifications
Clause 802, 803, 1202 & 1203 P.C.C
grade M 10 Nominal mix 1:3:6
1 x 1100.00 x 1.30 x 0.15 P.Cum 214.50 3529.00 756971.00
3 Providing concrete for plain/reinforced
concrete in open foundations complete as
per drawings and MoRD specifications
Clause 802, 803, 1202 & 1203 P.C.C.
grade M 20 Nominal mix (1:2:4)
1 x 1100.00 x 0.50 x 0.05 P.Cum 27.50
Total P.Cum 27.50 4031.00 110853.00
4 Stone masonry work in cement mortar in
foundation complete as per drawing and
MoRD specifications Clauses 702, 704,
1202 & 1203. Random Rubble Masonry
In cement mortar 1:4
0.40 + 0.30 0.60
2 x 1100.00 x x P.Cum 462.00 3115.00 1439130.00
2
5 Providing PCC M-20 architectural coping
on the top of wing wall, return wall etc.
complete as per drawing and MoRD
specification Clauses 615, 710 and
1204.3.11 50 mm thick
2 x 1100.00 x 0.30 x P.Sqm 660.00 237.00 156420.00

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR ROAD CONSTRUCTION
DRAIN WORK
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

Anjana ( 200 m ), Saliyo ka khera (250 m ),Anoppura ( 250 m ), Kundwa ( 400 m )

Sl. Rate Amount


Description of Item Measurement Unit Qty.
No. Rs Rs
1 2 3 4 5 6 7
6 Plastering with cement mortar 1:4,
20mm thick on stone work
Inner Side 2 x 1100.00 x 0.60 x P.Sqm 1320.00 164.000 216480.00
Total Part "F" Drain Work Rs. 2794397.00

Assistant Engineer
P.W.D. Sub Dn. Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF WATER COURSES
( SYPHON )
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Block :- Deogarh District :-Rajsamand
Shypon For Farmers 6 Nos.

Sl. Rate Amount


Description of Item Unit Qty.
No. Rs Rs
1 2 3 4 5 6 7
PART- G : SYPHON
1 Earthwork in excavation for structures as per drawing
and MoRD specifications Clause 305.1 including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious material and
disposal upto a lead of 50 m, dressing of sides and
bottom and backfilling in trenches with excavated
suitable material Ordinary soil Upto 3 m depth.
Face P.Cum 9.00
6 x 2 x 1.25 x 1.00 x 0.60
walls
Syphon 6 x 1 x 10.50 x 0.60 x 1.10 P.Cum 41.58
Pipe Total P.Cum 50.58 178.00 9003.00
:
2 Providing concrete for plain/reinforced concrete in
open foundations complete as per drawings and MoRD
specifications Clause 802, 803, 1202 & 1203 P.C.C
grade M 10Nominal mix 1:3:6.
Face 2.25
6 x 2 x 1.25 x 1.00 x 0.15 P.Cum
walls
Total P.Cum 2.25 3529.00 7940.00
:
3 Providing concrete for plain/reinforced concrete in
open foundations complete as per drawings and MoRD
specifications Clause 802, 803, 1202 & 1203 P.C.C.
grade M 20 Nominal mix (1:2:4)
Syphon 6 x 1 x 6.05 x 0.60 x 0.15 P.Cum 3.27
Pipe
Bedding
Syphon 6 x 1 x 6.25 x 0.60 x 0.25 P.Cum 5.63
Pipe 8.90
Haunche
Deduction
s for Pipe 6 x 1/2 x 3.14 x 0.45 x 0.45 x 6.25 P.Cum -2.98
4
P.Cum 14.82 4031.00 59739.00

4 Providing and laying reinforced cement concrete pipe


NP3 for culverts on first class bedding of granular
material in single row including fixing collar with
cement mortar 1:2 but excluding excavation, protection
works, backfilling, concrete and masonry works in head
walls and parapets Clause 1106. 300 mm dia
6 x 1 x 7.50 P.Rmt 45.00 704.00 31680.00

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF WATER COURSES
( SYPHON )
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Block :- Deogarh District :-Rajsamand
Shypon For Farmers 6 Nos.

Sl. Rate Amount


Description of Item Unit Qty.
No. Rs Rs
1 2 3 4 5 6 7
5 Stone masonry work in cement mortar in foundation
complete as per drawing and MoRD specifications
Clauses 702, 704, 1202 & 1203. Random Rubble
Masonry In cement mortar 1:4
(0.30 + 0.85)
6 x 2 x 1.25 x x 1.35 P.Cum 9.62
2
Deduction
3.14 (0.70 + 0.55)
6 x 2 x x 0.45 x 0.45 x P.Cum -0.85
for Pipe 4 2
P.Cum 8.77 3115.00 27319.00
6 Providing PCC M-20 architectural coping on the top of
wing wall, return wall etc. complete as per drawing and
MoRD specification Clauses 615, 710 and 1204.3.11
50 mm thick
2 x 2 x 1.25 x 0.30 P.Sqm 1.50 237.00 356.00
7 Plastering with cement mortar 1:4, 20mm thick on

stone work
2 x 2 x 1.25 x 1.00 P.Sqm 5.00 164.000 820.00

Total Part-"G" 136857.00


COST OF 6 No's.Syphon 136857.00

Assistant Engineer
P.W.D. Sub Dn Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

District :- Rajsamand

CH: 0/100, 1/625, 8/025, 10/575 4 Nos

PART- H (i) : HP CULVERT - 1000MM DIA SINGLE ROW


Sl. Quantit Rate Amount
Description of Item Measurement Unit
No. y Rs Rs
1 2 3 4 5 6 7
1 Earthwork in excavation for structures as per drawing and MoRD
specifications Clause 305.1 including setting out, construction of
shoring and bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50 m, dressing of sides and
bottom and backfilling in trenches with excavated suitable
material Ordinary soil Upto 3 m depth.
As per IRC:SP:20-2002 Plate No. 7.01 61.46

Total : 61.46 P.Cum 178.00 10940.00


2 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and MoRD specifications
Clause 802, 803, 1202 & 1203 P.C.C grade M 10Nominal mix
1:3:6.
As per IRC:SP:20-2002 Plate No. 7.01 2.71

Total : 2.71 P.Cum 3529.00 9564.00


3 Stone masonry work in cement mortar in foundation complete as
per drawing and MoRD specifications Clauses 702, 704, 1202 &
1203. Random Rubble Masonry In cement mortar 1:4
As per IRC:SP:20-2002 Plate No. 7.01 24.48

Total : 24.48 P.Cum 3115.00 76255.00


4 Construction of granular sub-base by providing well graded
material, spreading in uniform layers with tractor mount grader on
prepared surface, mixing by mix in place method with rotavator at
OMC, and compacting with smooth wheel roller to achieve the
desired density, complete as per MoRD Specification Clause 401.
For Grading III Material.
As per IRC:SP:20-2002 Plate No. 7.01 6.26 P.Cum 448.00 2804.00
5 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 kg laid dry complete as per
drawing and MoRD specifications Clause 1301
As per IRC:SP:20-2002 Plate No. 7.01 10.08 P.Cum 747.00 7530.00

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

District :- Rajsamand

CH: 0/100, 1/625, 8/025, 10/575 4 Nos

PART- H (i) : HP CULVERT - 1000MM DIA SINGLE ROW


Sl. Quantit Rate Amount
Description of Item Measurement Unit
No. y Rs Rs
1 2 3 4 5 6 7
6 Providing and laying reinforced cement concrete pipe NP4 for
culverts on first class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets Clause 1106 1000 mm dia
As per IRC:SP:20-2002 Plate No. 7.01 7.50 P.Rmt 4389.00 32918.00
7 Plastering with cement mortar 1:4, 20mm thick on stone work

2x 6.15 x 1.80 22.14


Deduction for Pipes 2 x3.14/4x(1.23)2 = 2.375 -2.38
Net Qty. 19.76

Total : 19.76 P.Sqm 164.00 3241.00


8 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with 100
mm dia AC pipe extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face complete as per
drawing and MoRD specification Clauses 614, 709, 1204.3.7.
1 x 8.00 8.00 P. Rm 92.00 736.00
9 Providing PCC M-20 architectural coping on the top of wing wall,
return wall etc. complete as per drawing and MoRD specification
Clauses 615, 710 and 1204.3.11 50 mm thick
2x 6.15 x 0.45 5.54

Total : 5.54 P.Sqm 237.00 1313.00


Total : Part-"H" (i) 145301.00
COST OF 4 No's.CULVERT 581204.00

Assistant Engineer
P.W.D. Sub Dn Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE W

Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/0

Block:- DEOGARH

CH: 3/600, 9/200 2 Nos.

PART- H (ii) : HP CULVERT - 1000MM DIA DOUBLE ROW


Sl.
Description of Item Measurement Quantity Unit
No.
1 2 3 4 5
1 Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious material and disposal upto a lead of 50 m,
dressing of sides and bottom and backfilling in trenches with
excavated suitable material Ordinary soil Upto 3 m depth.
As per IRC:SP:20-2002 Plate No. 7.01 98.04

Total : 98.04 P.Cum


2 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 P.C.C grade M
10Nominal mix 1:3:6.
As per IRC:SP:20-2002 Plate No. 7.01 4.01

Total : 4.01 P.Cum


3 Stone masonry work in cement mortar in foundation
complete as per drawing and technical specifications Clauses
702, 704, 1202 & 1203. Random Rubble Masonry In cement
mortar 1:4
As per IRC:SP:20-2002 Plate No. 7.01 39.72

Total : 39.72 P.Cum

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE W

Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/0

Block:- DEOGARH

CH: 3/600, 9/200 2 Nos.

PART- H (ii) : HP CULVERT - 1000MM DIA DOUBLE ROW


Sl.
Description of Item Measurement Quantity Unit
No.
1 2 3 4 5
4 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 P.C.C. grade M
20 Nominal mix (1:2:4)
As per IRC:SP:20-2002 Plate No. 7.01 14.54 P.Cum
5 Providing and laying boulder apron for bed protection with
stone boulders of minimum size and weight as per Table
1300.1, no fragment weighing less than 25 kg laid dry
complete as per drawing and technical specifications Clause
1301
As per IRC:SP:20-2002 Plate No. 7.01 16.30 P.Cum

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE W

Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/0

Block:- DEOGARH

CH: 3/600, 9/200 2 Nos.

PART- H (ii) : HP CULVERT - 1000MM DIA DOUBLE ROW


Sl.
Description of Item Measurement Quantity Unit
No.
1 2 3 4 5
6 Providing and laying reinforced cement concrete pipe NP4
for culverts on first class bedding of granular material in
double row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete
and masonry works in head walls and parapets as per
Clause 1106.( Excluding cost of first class bedding ) 1000
mm dia.
As per IRC:SP:20-2002 Plate No. 7.01 7.5 P.Rmt
7 Plastering with cement mortar 1:4, 20mm thick on stone work
on stone work in substructure as per technical specification
Clauses 613.4 & 1205
2 x 7.88 x 1.80 28.37
Deduction for Pipes
4 x3.14/4x(1.23)2 = 4.75 4.75
Net Qty. 23.62

Total : 23.62 P.Sqm


8 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall
with 100 mm dia AC pipe extending through the full width of
the structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7.
1 x 10.00 10.00 P Rm

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE W

Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/0

Block:- DEOGARH

CH: 3/600, 9/200 2 Nos.

PART- H (ii) : HP CULVERT - 1000MM DIA DOUBLE ROW


Sl.
Description of Item Measurement Quantity Unit
No.
1 2 3 4 5
9 Providing PCC M-20 architectural coping in 50 mm thick on
the top of wing wall, return wall etc. complete as per drawing

and technical specification Clauses 615, 710 and 1204.3.11


2 x 7.88 x 0.45 7.09

Total : 7.09 P.Sqm


Total : Part-"H"
COST OF 2 No's.CULVE

Assistant Engineer
P.W.D. Sub Dn Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
RAINAGE WORKS

T04 ) km 0/00 to 11/500

District :- Rajsamand

Amount
Rate Rs
Rs
6 7

178.00 17451.00

3529.00 14151.00

3115.00 123728.00

file:///conversion/tmp/scratch/378102405.xlsx
RAINAGE WORKS

T04 ) km 0/00 to 11/500

District :- Rajsamand

Amount
Rate Rs
Rs
6 7

4264.00 61999.00

747.00 12176.00

file:///conversion/tmp/scratch/378102405.xlsx
RAINAGE WORKS

T04 ) km 0/00 to 11/500

District :- Rajsamand

Amount
Rate Rs
Rs
6 7

8807.00 66053.00

164.00 3874.00

92.00 920.00

file:///conversion/tmp/scratch/378102405.xlsx
RAINAGE WORKS

T04 ) km 0/00 to 11/500

District :- Rajsamand

Amount
Rate Rs
Rs
6 7

237.00 1680.00
Total : Part-"H" (ii) 302032.00
F 2 No's.CULVERT 604064.00

ant Engineer
ub Dn Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF CD WORKS
3.0 Metre Span RCC Slab Culvert
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Langth of the Road : 0.000 Km. Block:-DEOGARH District :- Rajsamand
CH: 0 0 Nos.
L
D
Sl. B Rate Amount
Description of Item No. Unit Quantity
No. m Rs Rs
m
m
1 2 3 4 5 6 7 8 9 10
PART - I - RCC Slab Culvert
1 Gravel/Soil Aggregate Base/Sub-base Nominal Maximum size
Grading 80 mm (Table 2.3 of IRC SP 77-2008)
Construction of Gravel / Soil Aggregate Sub-base/Base by
providing well graded material of nominal maximum size
grading 80 mm as per Table 2.3 of IRC SP 77-2008, spreading
in uniform layers with tractor mount appropriate grading
arrangements on prepared surface, mixing by mix in place
method at OMC with tractor mount appropriate rotavator
attachment and compaction with three wheel 80-100 KN Static
Roller capacity to achieve the desired density complete as per
specifications contained in Para 2.2, 3.6 and 3.7 of IRC SP 77-
2008
Service Road 1 100.00 3.75 0.15 P.Cum 56.25
Total P.Cum 56.25
For 0 Nos. P.Cum 0.00 470.00 0.00
2 Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious material and disposal upto a lead of 50 m,
dressing of sides and bottom and backfilling in trenches with
excavated suitable material. Ordinary soil upto 3 m depth.
Abutment 2 8.10 2.14 2.50 P.Cum 86.67
Return Wall 4 2.76 2.00 2.50 P.Cum 55.20

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF CD WORKS
2 3.0 Metre Span RCC Slab Culvert
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Langth of the Road : 0.000 Km. Block:-DEOGARH District :- Rajsamand
CH: 0 0 Nos.
L
D
Sl. B Rate Amount
Description of Item No. Unit Quantity
No. m Rs Rs
m
m
Cut off Wall 2 1.40 1.20 1.60 P.Cum 5.38
Total P.Cum 147.25
For 0 Nos. P.Cum 0.00 84.00 0.00
3 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and MoRD
specifications Clause 802, 803, 1202 & 1203. PCC grade M-10
Nominal mix 1:3:6.
Abutment 2 8.10 2.14 0.20 P.Cum 6.93
Return Wall 4 2.76 2.00 0.20 P.Cum 4.42
Cut off Wall 2 1.40 1.20 0.20 P.Cum 0.67
Flooring 1 6.00 2.80 0.20 P.Cum 3.36
Total P.Cum 15.38
For 0 Nos. P.Cum 0.00 1985.00 0.00
4 Stone masonry work in cement mortar in foundation complete
as per drawing & technical specification Clauses 702, 704,
1202 and 1203. Random rubble masonry In 1:4 cement mortar.

Abutment 2 7.90 1.94 0.20 P.Cum 6.13


2 7.70 1.84 0.20 P.Cum 5.67
2 7.50 1.74 0.20 P.Cum 5.22
2 7.30 1.64 0.20 P.Cum 4.79
2 7.10 1.54 0.20 P.Cum 4.37
2 6.90 1.44 0.20 P.Cum 3.97
2 6.70 1.34 0.20 P.Cum 3.59
Return Wall 4 2.76 1.80 0.20 P.Cum 3.97
4 2.76 1.70 0.20 P.Cum 3.75

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF CD WORKS
3.0 Metre Span RCC Slab Culvert
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Langth of the Road : 0.000 Km. Block:-DEOGARH District :- Rajsamand
CH: 0 0 Nos.
L
D
Sl. B Rate Amount
Description of Item No. Unit Quantity
No. m Rs Rs
m
m
4 2.76 1.60 0.20 P.Cum 3.53
4 2.76 1.50 0.20 P.Cum 3.31
4 2.76 1.40 0.20 P.Cum 3.09
4 2.76 1.30 0.20 P.Cum 2.87
4 2.76 1.20 0.20 P.Cum 2.65
Cut off Wall 2 1.60 1.00 0.20 P.Cum 0.64
2 1.80 0.90 0.20 P.Cum 0.65
2 2.00 0.80 0.20 P.Cum 0.64
2 2.20 0.70 0.20 P.Cum 0.62
2 2.40 0.60 0.20 P.Cum 0.58
2 2.60 0.50 0.20 P.Cum 0.52
2 2.80 0.40 0.20 P.Cum 0.45
Total P.Cum 61.01
For 0 Nos. P.Cum 0.00 1460.00 0.00
5 Stone masonry in cement mortar for substructure complete as
per drawing & MoRD specifications Clauses 702, 704, 1202 and
1204 Random rubble masonry In 1:4 cement mortar
Abutment 2 6.50 1.140.70/2 1.32 P.Cum 15.79
Return Wall 4 3.08 1.00+0.57/2 1.32 P.Cum 12.77
4 3.30 0.57+0.40/2 0.50 P.Cum 3.20
Parapet Wall 2 9.60 0.40 0.60 P.Cum 4.61
Total P.Cum 36.37
For 0 Nos. P.Cum 0.00 1530.00 0.00

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF CD WORKS
3.0 Metre Span RCC Slab Culvert
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Langth of the Road : 0.000 Km. Block:-DEOGARH District :- Rajsamand
CH: 0 0 Nos.
L
D
Sl. B Rate Amount
Description of Item No. Unit Quantity
No. m Rs Rs
m
m
6 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7.

Abutment 12 Nos 12
Return Wall 9 Nos 9
Total Nos 21
For 0 Nos. Nos 0 38.00 0.00

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF CD WORKS
3.0 Metre Span RCC Slab Culvert
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Langth of the Road : 0.000 Km. Block:-DEOGARH District :- Rajsamand
CH: 0 0 Nos.
L
D
Sl. B Rate Amount
Description of Item No. Unit Quantity
No. m Rs Rs
m
m
7 Backfilling behind abutment , wingwall and return wall complete
as per drawing & technical specification Clause 1204.3.8
Granular material
2 3.11 5.10 1.50 Cum 47.58
Total P.Cum 47.58
For 0 Nos. P.Cum 0.00 225.00 0.00
8 Plain / Reinforced cement concrete in substructure complete as
per drawings and technical specifications Clause 802, 804,
805,807,1202 & 1204 For height up to 5.00 Mtr R.C.C. grade
M25
Bed Plate 2 6.50 0.70 0.20 P.Cum 1.82
2 6.50 0.40 0.30 P.Cum 1.56
Total P.Cum 3.38
For 0 Nos. P.Cum 0.00 2885.00 0.00
9 Supplying,fitting and placing tmt bar reinforcement (Fe 415 ) in
subsrructure complete as per drawings and technical
specification Clauses1002,1005,1010 &1202

Bed Plate
10 mm Tor 2x13 6.45 0.617 Kg 103.47
8 mm Tor 2x61 1.70 0.395 Kg 81.92
8 mm Tor 2x61 1.70 0.395 Kg 81.92
Total Kg 267.31
Tonne 0.27
For 0 Nos. Tonne 0.00 42080.00 0.00
10 Providing and laying Reinforced cement concrete in
superstructure as per drawing and technical specifications
Clauses 800,1205.4 and 1205.5 R.C.C. Grade M 30

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF CD WORKS
3.0 Metre Span RCC Slab Culvert
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Langth of the Road : 0.000 Km. Block:-DEOGARH District :- Rajsamand
CH: 0 0 Nos.
10 L
D
Sl. B Rate Amount
Description of Item No. Unit Quantity
No. m Rs Rs
m
m
Deck slab 1 3.60 6.50 0.30 P.Cum 7.02
Total P.Cum 7.02
For 0 Nos. P.Cum 0.00 3620.00 0.00

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF CD WORKS
3.0 Metre Span RCC Slab Culvert
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Langth of the Road : 0.000 Km. Block:-DEOGARH District :- Rajsamand
CH: 0 0 Nos.
L
D
Sl. B Rate Amount
Description of Item No. Unit Quantity
No. m Rs Rs
m
m
11 Supplying,fitting and placing TMT bar reinforcement in
supersrructure complete as per drawings and technical
specifications Clauses1002,1010 &1202

Bottom 16 Tor @ 125 C/C 73 4.10 1.578 Kg 472.30


Bottom 10 Tor @ 175 C/C 21 6.80 0.617 Kg 88.11
Top 10 Tor @ 300 C/C 31 3.50 0.617 Kg 66.94
Top 10 Tor @ 300 C/C 13 6.80 0.617 Kg 54.54
Side 10 Tor 2 6.45 0.617 Kg 7.96
Total Kg 689.85
Tonne 0.69
For 0 Nos. Tonne 0.00 42460.00 0.00
12 Providing and laying cement concrete wearing course M 30
grade including reinforcement complete as per drawing and
MoRD specifications Clauses 800 and 1206.3

1 3.60 6.50 0.075 P.Cum 1.76


Total P.Cum 1.76
For 0 Nos. P.Cum 0.00 6405.00 0.00
13 Providing and fixing 20 mm thick compressible fibre board in
expansion joint complete as per drawing and technical
specifications

Rmt per cm
2 6.50 30.00 depth
390.00

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF CD WORKS
3.0 Metre Span RCC Slab Culvert
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Langth of the Road : 0.000 Km. Block:-DEOGARH District :- Rajsamand
13
CH: 0 0 Nos.
L
D
Sl. B Rate Amount
Description of Item No. Unit Quantity
No. m Rs Rs
m
m
Rmt per cm
Total depth
390.00
Rmt per cm
For 0 Nos. depth 0.00 7.00 0.00
14 Pointing with cement mortar (1:3) on stone work
Abutment 2 6.50 1.32 Sqm 17.16
Return wall 4 3.08 1.80 Sqm 22.18
4 3.30 1.80 Sqm 23.76
Parapet 2 9.60 0.60 Sqm 11.52
2 9.60 0.52 Sqm 9.98
Total Sqm 84.60
For 0 Nos. P Sqm 0.00 45.00 0.00
15 Plaster with cement mortar 1:4, 20mm thick on stone work
Parapet walls 4 0.40 0.60 Sqm 0.96
Total Sqm 0.96
For 0 Nos. P Sqm 0.00 80.00 0.00
16 Providing PCC M-20 architectural coping on the top of
wing wall, return wall etc. complete as per drawing and
technical specification Clauses 615, 710 and 1204.3.11
75 mm thick.
Parapet walls 2 9.60 0.40 Sqm 7.68
Total Sqm 7.68
For 0 Nos. Sqm 0.00 200.00 0.00
COST OF 0 No's.CULVERT Rs 0.00

Assistant Engineer

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
COST ESTIMATE FOR CONSTRUCTION OF CD WORKS
3.0 Metre Span RCC Slab Culvert
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Langth of the Road : 0.000 Km. Block:-DEOGARH District :- Rajsamand
CH: 0 0 Nos.
L
D
Sl. B Rate Amount
Description of Item No. Unit Quantity
No. m Rs Rs
m
m
P.W.D. Sub Dn Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR CONSTRUCTION OF PROTECTION WALL
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Block :- DEOGARH District :- Rajsamand
Length of Wall 450.00 Mtr.

Sl. Description of Rate Amount


Unit Qty.
No. Item Rs Rs
1 2 4 5 6 7
PART- J : PROTECTION WALL
1 Earthwork in excavation for structures as per
drawing and MoRD specifications Clause
305.1 including setting out, construction of
shoring and bracing, removal of stumps and
other deleterious material and disposal upto a
lead of 50 m, dressing of sides and bottom
and backfilling in trenches with excavated
suitable material Ordinary soil Upto 3 m
depth.
1 x 450.00 x 1.40 x 0.90 P.Cum 567.00
Total P.Cum 567.00 178.00 100926.00
:
2 Providing concrete for plain/reinforced
concrete in open foundations complete as per
drawings and MoRD specifications Clause
802, 803, 1202 & 1203 P.C.C grade M
10Nominal mix 1:3:6.
1 x 450.00 x 1.40 x 0.20 P.Cum 126.00
Total : P.Cum 126.00 3529.00 444654.00
3 Stone masonry work in cement mortar in
foundation complete as per drawing and
MoRD specifications Clauses 702, 704, 1202
& 1203. Random Rubble Masonry In cement
mortar 1:4
(0.50 + 1.25) 2.25
1 x 450.00 x x P.Cum 885.94
2
Total : P.Cum 885.94 3115.00 2759695.00
4 Providing PCC M-20 architectural coping on
the top of wing wall, return wall etc. complete
as per drawing and MoRD specification
Clauses 615, 710 and 1204.3.11 50 mm
thick.
P. Sqm 225.00 53325.00
1 x 450.00 x 0.50 237.00
5 Pointing with cement mortar (1:3) on
stone work as per drawing and MoRD
specification Clauses 613.3 and 1204 Flush &
Rulled
P. Sqm
1 x 450.00 x 1.50 675.00 45.00 30375.00

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR CONSTRUCTION OF PROTECTION WALL
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Block :- DEOGARH District :- Rajsamand
Length of Wall 450.00 Mtr.

Sl. Description of Rate Amount


Unit Qty.
No. Item Rs Rs
1 2 4 5 6 7
6 Providing weepholes in brick masonry/stone
masonry, plain/reinforced concrete abutment,
wing wall, return wall with 100 mm dia AC
pipe extending through the full width of the
structures with slope of 1(V):20(H) towards
drawing face complete as per drawing and
MoRD specification Clauses 614, 709,
1204.3.7
1 x 297.00 x 0.80 P.RMT 237.60 92.00 21859.00
7 Backfilling behind abutment, wing wall and
return wall complete as per drawing &
technical specification Clause 1204.3.8
Granular Material 450.00 (1.00 x 0.70) 1.00
1 x x x P.Cum 382.50
2
Total : P.Cum 382.50 566.00 216495.00
TOTAL -PART- J : PROTECTION WALL 3627329.00

Assistant Engineer
P.W.D. Sub Dn Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Block :- DEOGARH District :-
CH: 0 0.00 Mtr.
Sl. Rate
Description of Item Measurement Unit Qty.
No. Rs
1 2 3 4 5 6
PART- K : Retaining Wall with Side Drain
1 Earthwork in excavation for structures as per
drawing and technical specifications Clause 305.1
including setting out, construction of shoring and
bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50 m, dressing
of sides and bottom and backfilling in trenches with
excavated suitable material Ordinary soil Upto 3 m
depth.
1 x 0.00 x 1.90 x 1.50 P.Cum 0.00
Total : P.Cum 0.00 109.35
2 Providing concrete for plain/reinforced concrete in
open foundations complete as per drawings and
technical specifications Clause 802, 803, 1202 &
1203 P.C.C grade M 10Nominal mix 1:3:6.
1 x 0.00 x 1.90 x 0.20 P.Cum 0.00
Total : P.Cum 0.00 2234.25
3 Stone masonry work in cement mortar in foundation
complete as per drawing and technical
specifications Clauses 702, 704, 1202 & 1203.
Random Rubble Masonry In cement mortar 1:4
(0.50 + 1.80)
1 x 0.00 x x 3.80 P.Cum 0.00
2
P.Cum 0.00 1794.15

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Block :- DEOGARH District :-
CH: 0 0.00 Mtr.
Sl. Rate
Description of Item Measurement Unit Qty.
No. Rs
1 2 3 4 5 6
4 Providing PCC M-20 architectural coping on the top
of wing wall, return wall etc. complete as per
drawing and technical specification Clauses 615,
710 and 1204.3.11 75 mm thick.
1 x 0.00 x 0.50 P.Sqm. 0.00

file:///conversion/tmp/scratch/378102405.xlsx
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Block :- DEOGARH District :-
CH: 0 0.00 Mtr.
Sl. Rate
Description of Item Measurement Unit Qty.
No. Rs
1 2 3 4 5 6
P.Sqm. 0.00 214.50
5 Providing concrete for plain/reinforced concrete in
open foundations complete as per drawings and
technical specifications Clause 802, 803, 1202 &
1203 P.C.C. grade M 20 Nominal mix (1:2:4)
1 x 0.00 x 0.50 x 0.05 P.Cum 0.00
Total : P.Cum 0.00 2635.10
6 Plaster with cement mortar 1:4, 20mm thick on
stone work
1 x 0 x 2.40 0.00
P.Sqm 0.00 84.105
7 Backfilling behind abutment, wing wall and return
wall complete as per drawing & technical
specification Clause 1204.3.8
Granular Material (2.00 x 1.50) 2.40 P.Cum
1 x 0.00 x x 0.00
2
Total : P.Cum 0.00 237.90
TOTAL-PART- K : TOE WALL AND PITCHING

0 Assistant Engineer
0 P.W.D. Sub Dn Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
KS

Rajsamand

Amount
Rs
7

0.00

0.00

0.00

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
KS

Rajsamand

Amount
Rs
7

file:///conversion/tmp/scratch/378102405.xlsx
Format-F7
KS

Rajsamand

Amount
Rs
7
0.00

0.00

0.00

0.00
0.00

file:///conversion/tmp/scratch/378102405.xlsx
EARTH WORK CALCULATION SHEET

NAME OF ROAD :- Anjana Pardi Jagdish Road ( T 04 ) km 0/00 to 11/500

As per Detail sheet of E/Work


1
Calculation

2 Quantity of Filling of Earth = F 3000.00 Cum

3 Quantity of Cutting of Earth =C 750.00 Cum 1

4 Quantity of Various Type of Soil

% of
Useful Qty. of Earth
Type of Soil Cutting Qty.
Available for filling
Qty.
% Qty.
(a) Earth work in cutting - H.S.M.B. 5% 37.50 100% 37.50
(b) Ordinary rock 10% 75.00 70% 52.50

( c) HRB 85% 637.50 50% 318.75

( d) Phylite rock 0% 0.00 0% 0.00

100% 750 Total 408.75

Const. Of Sub grade & Earthern


Shoulders

5 Qty. of Earth reqd. for Berms 2 900.00 0.00 = 0.00


(1.575+1.125)/2
1.35

5 Total Qty. of Net filling reqd.


FR=Filling -Sum of available Earth
( 3000.00 - 475.33 - 408.75 ) = 2115.92
from Cutting
Cum
Quantity of Earth received from C.D. Structure

A 1 Row 61.46
B R.Wall 3 Mtr 567.00
C Syphon 50.58
679.04 x 70% = 475.33

Const. of Embankment from


6 408.75 + 475.33 = 884.08
roadway Cutting

Assistant Engineer
P. W. D. Sub. Dn. DEOGARH
0 Assistant Engineer
0 P. W. D. Sub. Dn. DEOGARH
Design of Flexible Pavement
(As per IRC : SP : 72-2007)
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

1 Design Datas :
(a) Average Daily Traffic as per last count in the month of July, 2016
(Peak Harvesting Season)
(i) Car, Jeep, Vans, Three Wheelers = 154 Nos.
(ii) Motorised Two Wheelers = 342 Nos.
(iii) Light Commercial Vehicle = 45 Nos.
(iv) Heavy Commercial Vehicle
(A) Trucks
Loaded = 12 Nos.
Unloaded = 10 Nos.
Overloaded = 21 Nos.
(B) Buses
Loaded = 12 Nos.
Unloaded = 0 Nos.
Overloaded = 0 Nos.
(v) Agricultural Tractor Trailors
Loaded = 8 Nos.
Unloaded = 6 Nos.
Overloaded = 18 Nos.
(vi) Cycle = 40 Nos.
(vii) Cycle Rickshaw = 0 Nos.
(viii) Animal Drawn Vehicle = 0 Nos.
Total :- = 668 Nos.
(b) CBR Values of the Sub Grade as under :- = 6.00%
(c) Annual Growth rate of Commercial Traffic (r) = 6.00%
(d) Design life in Years (x) = 10 Years
Number of years between the last count and the year of computation of
(e) = 1 Years
construction (n)

2 Design of Flexible Pavement as per IRC : SP : 72-2007 :-


(a) Computation of the Design Traffic :
(i) Harvesting Seasons in the area = 2 Nos.
(ii) Duration of each Harvesting Season (t) = 75 Days
(iii) Average Daily Traffic during in the Harvesting Season (T) = 668 Nos.
(iv) Average Daily Traffic during in the Non-Harvesting Season (T) = 0 Nos.
(iv) Annual Average Daily Traffic (AADT) =

1.2 x T x t
AADT = T +

[95 of 124]
365

1.2 x 668 x 75
AADT = 668 + = 833
365

(v) AAPT before opening of road to traffic = 833 (1.06)1 883


(vi) Proportions of Heavy Commercial Vehicles (HCV)
(A) Laden
883
HCV = x 24 = 31.72

668

(B) Unladen
883
HCV = x 10 = 13.22

668

(C) Overloaded
883
HCV = x 21 = 27.76

668
(vii) Proportions of Medium Heavy Commercial Vehicles (MCV)
(A) Laden
883
MCV = x 8 = 10.57

668
(B) Unladen
883
MCV = x 6 = 7.93

668
(C) Overloaded
883
MCV = x 18 = 23.79
668
(viii) Animal drawn carts being pneumatic tyres, have not been considered for design purpose

(ix)
T0 for HCV = 31.72 x 2.58 + 13.22 x 0.31 + 28 x 2.86 = 165.33

[96 of 124]
T0 for MCV = 10.57 x 0.31 + 7.93 x 0.019 + 24 x 0.344 = 11.61
Total = 176.94

(x) Commulative ESAL application (N) over the design life (10 years) @ 6.0% growth rate:-
N= T0 x 4811 x L

176.94 x 4811 x 1 = 851261


= 0.851 MSA
(b) Evaluation of Subgrade Strength :-
Since the GWT is too to deep to influence the sungrade moisture

(c) Design Pavement Thickness :-


For above cumulative ESAL application, as per Fig. 4 (Pavement Design Catalogues), for traffic
category range 600,000 to1000,000 ESAL application, the design crust as under :-

Crust thickness
Km CBR Value of the Subgrade
required as per IRC : SP-72-2007
Km 6.00% 425

3 Pavement Composition Proposed as under :-


EXISTING CRUST
(a) Granular Sub-base = 200 mm
WBM Grade-II = 100 mm
WBM Grade-III = 75 mm
Total :- = 375 mm
PROPOSED CRUST
(b) Surfacing :-
40 mm Bitumenous Macadam & 20 mm PMC with Seal Coat Type '"B"using Bitumen
VG-30 on whole width of road as overlay of crust

Assistant Engineer
P. W. D. Sub. Dn. DEOGARH

[97 of 124]
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

Design of Cement Concrete Pavement


(As per IRC:SP:62-2004)
1 Design Parameters
(a) Location of Pavement : Rajasthan
(b) Design Period : 20 Years
(c) Design wheel load : 51 kN
(d) Soaked CBR value of existing soil of : 6.00%
Subgrade
(e) Modulus of Subgrade reaction (k) : 30.80 x 10-3 N/mm 2 /mm
(From Table No. 1 for CBR 13.90%)

(f) Effective k over 150 mm thick Sub : 1.20 x 30.80 x 10-3 N/mm 2 /mm
base
= 36.96 x 10 -3 N/mm 2 /mm
(g) Grade of CC Pavement : M 30 Grade Controlled Concrete

(h) Flexural strength (f f ) for 28 days : 0.70 fc


0.7 30
3.834 Mpa
(i) Flexural strength (f f ) for 90 days : 1.20x3.834=4.60 Mpa
(j) Modulus of elasticity for concrete (E) : 3.0x10 4 MPa

(k) Poisson's ratio (µ) : 0.15

2 Joint Spacing & Lane width


(a) Slab length, or spacing between : 3.75 Mtr.
consecutive contraction joints (L)
(b) Slab width, or spacing between : 2.75 Mtr.
longitudional joints (W)

3 Thickness of pavement
(A) Tacking 150 mm Trial thickness

(a) Edge Load Stress : From Fig. 4 of IRC :SP : 62-2004 Edge Load Stress for
k = 0.037 N / mm 3
= 4.50 Mpa

(b) Temperature Stress : (1) Temperature differential for Rajasthan for 150mm
slab is 12.5OC

(2) Radius of relative stiffness ( l ) '=


Eh 3
4
12(1-µ 2 )k

= 3x10 4 x 150 3 x 10 3
4
12(1-0.15 2 ) 36.96

= 695.17 mm
(3) L / l = 3750 / 695.17
= 5.39
(4) Bradbury's coefficient ( C ) = 0.798

file:///conversion/tmp/scratch/378102405.xlsx
(5) Temperature Stress (ste) = 1.60Mpa

(C) Total Stress = Edge load stress + Temperature stress


= 4.50 + 1.60 = 6.10 Mpa
This is greater than the allowable flexural strength of
concrete (4.60 Mpa)
So the thickness of 200mm assumed is inadequate

(B) Tacking 200 mm Trial thickness in


view of Table 4 of IRC:SP:62-2004

(a) Edge Load Stress : From Fig. 4 of IRC :SP : 62-2004 Edge Load Stress for
k = 0.037N / mm 3
= 2.70 Mpa

(b) Temperature Stress : (1)Temperature differential for Rajasthan for 200mm


slab is 13.10oC

(2) Radius of relative stiffness ( l ) '=


Eh 3
4
12(1-µ 2 )k

= 3x10 4 x 200 3 x 10 3
4
12 (1-0.15 2 ) 36.96

= 862.57 mm
(3) L / l = 3750 / 862.57
= 4.34
(4) Bradbury's coefficient ( C ) = 0.535
(5) Temperature Stress (ste) = 1.00 Mpa

(C) Total Stress = Edge load stress + Temperature stress


= 2.70 + 1.00 = 3.70Mpa
The total stress is less than 4.60 Mpa and hence
assumed thickness of 200mm is Ok

(D) Corner Stress = From Fig. 5, Corner load stress for


wheel load = 51 kN,
K= 0.037 N / mm 3
Slab thickness = 200mm
Corner stress (slc) = 3.10 Mpa

The corner stress is less than 4.6 MPa and hence the
thickness of 200mm assumed is safe.

Hence provide 200mm thick cement concrete slab of


M-30 grade as per section 1401 (9) (iii) of MORD
specification.

Assistant Engineer
P.W.D. Sub Dn. Deogarh

file:///conversion/tmp/scratch/378102405.xlsx
HYDRAULIC DESIGN FOR CONSTRUCTION OF H.P. CULVERT
Name of Road :- SH-61 Km 276 to KITO KA BADIYA

Length of the Road :- 1.30 Km Block :- DEOGARH District :- Rajsamand

CH: 0/600
AS There is no defined channel in D/S as well as U/S. Only rain water from U/S side cultivated
land / top to foot of hill crosses one side to another side of the road.
Catchment Area A = 450 x 225

0.101 Sq Km
By Dicken Formula Discharge Q = C x M3/4
12 x (0.101)3/4 Where C=12 as per IRC
Paper 13 page 13
2.15 cumecs
Discharge which can pass through 1000 mm dia pipes flowing full operating head = 0.50 M
Q = Y x 2gh
A AS per IRC paper 13
Where Y = = 0.686
1+ Kp + Kc Plate 16

Where A = 3.142/4 x 1.00 x 1.00 = 0.7855 m 2


Kc = 0.10 for bevelled Entry

Kp = 0.00394 / R12 X L
where R =Hydraulic mean Radius = 1.00/4 = 0.25
0.00394
Kp = X 7.50
0.18946
Hence Discharge through 1000 mm pipe for operating h = 0.50 m
or Q= 0.686 X 2 X 9.80 X 0.50

Q= 2.148 CUMECS

2.15
Hence No. of pipe Required = = 1.0009310987
2.148

Hence Provide 1000 mm Dia 1 Row H. P. Culvert

Assistant Engineer
P.W.D. Sub Dn. Deogarh

Systek/378102405.xlsx/Design HPC single (1) 104 of 124


0

Systek/378102405.xlsx/Design HPC single (1) 105 of 124


HYDRAULIC DESIGN FOR CONSTRUCTION OF H.P. CULVERT
Name of Road :- NH-8 Km 140 to HAWALA

Length of the Road 2.30 Km Block :- DEOGARH District :- Rajsamand

CH: 0/775
AS There is no defined channel in D/S as well as U/S. Only rain water from U/S side cultivated
land / top to foot of hill crosses one side to another side of the road.
Catchment Area A = 360 x 270

0.097 Sq Km
By Dicken Formula Discharge Q = C x M3/4
12 x (0.097)3/4 Where C=12 as per IRC
Paper 13 page 13
2.085 cumecs
Discharge which can pass through 1000 mm dia pipes flowing with operating head = 0.50 M
Q = Y x 2gh
A AS per IRC paper 13
Where Y = = 0.686
1+ Kp + Kc Plate 16

Where A = 3.142/4 x 1.00 x 1.00 = 0.7855 m 2


Kc = 0.10 for bevelled Entry

Kp = 0.00394 / R12 X L
where R =Hydraulic mean Radius = 1.00/4 = 0.25
0.00394
Kp = X 7.50
0.18946
Hence Discharge through 1000 mm pipe for operating h = 0.50 m
or Q= 0.686 X 2 X 9.80 X 0.50

Q= 2.148 CUMECS

2.085
Hence No. of pipe Required = = 0.9706703911
2.148

Hence Provide 1000 mm Dia 1 Row H. P. Culvert

Assistant Engineer
P.W.D. Sub Dn. Deogarh

Systek/378102405.xlsx/Design HPC single (2) 106 of 124


0

Systek/378102405.xlsx/Design HPC single (2) 107 of 124


Annexure 5.3 (b)
FIELD DATA SHEET FOR TRAFFIC CENSUS
Name of Road : Upgradation of BT Road Anjana Pardi Jagdish Road km 0/00 to 11/500
Location of Road : Km. 0/100
District : Rajsamand
State : Rajasthan
Motorised Traffic Non Motorised Traffic

Buses Trucks Agriculture Tractors Trailler


Days Car, Jeep, Motorised Solid Cycle Total
LCV/ Other
Vans,Three two Wheeled Rickshaw Cycles
wheeler Tempo wheelers Cart
L U OL L U OL L U OL Cart a

6/7/2016 1 1 0 2 2 0 8 4 3 6 3 71 2 0 0 30 133
6/7/2016 1 1 0 2 2 0 8 4 3 6 3 71 2 0 0 30 133
6/7/2016 1 1 0 2 2 0 8 4 3 6 3 71 2 0 0 30 133
6/7/2016 1 1 0 2 2 0 8 4 3 6 3 71 2 0 0 30 133
6/7/2016 1 1 0 2 2 0 8 4 3 6 3 71 2 0 0 30 133
7/7/2016 1 1 0 2 3 0 3 1 0 9 6 89 3 0 0 35 153
8/7/2016 2 2 0 1 1 0 5 5 2 9 7 56 5 0 0 32 127
Total 8 8 0 13 14 0 48 26 17 48 28 500 18 0 0 217 945
Average Traffic 1 1 0 2 2 0 5 3 2 8 5 72 3 0 0 32 136

PCU Factor 3 3 3 3 3 3 3 3 3 1 1.5 0.5 6 6 2 0.5


Average Daily
3 3 0 6 6 0 15 9 6 8 8 36 18 0 0 16 134
Traffic PCU
Total CVPD 2 4 10 8 5 72 3 0 0 32 21

Assistant Engineer
P.W.D. Sub Dn. Deogarh
TEST RESULT OF MATERIAL (SOIL)
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

S. Material Location Source of material Gradation OMC MDD Soaked Atterberg Limits
No. (IS Sieve % passing) CBR %

4.75mm 425 Mic 75 Mic LL PL PI

1 2 3 4 5 6 7 8 9 10 11 12 13
1 Soil Km. 1 On SH-275 100 97 24 9.50 2.1 5.50% 28.00 18.00 10.00

Assistant Eng
P.W.D. Sub Dn. D
Soil Group Remark

14 15
CL

Assistant Engineer
P.W.D. Sub Dn. Deogarh
Area Calculation of Junction
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500
Length of the Road : 11.50 Km. District :- Rajsamand
S.
Particular Area Quantity Unit
No.
= 2 x 10 x 0 + 1.875 / 2 = 18.75 Sqm.

= 2 x 10 x 1.875 = 37.5 Sqm.


1 Junction
= 2 x 10 x 10 - 3.14 x 10 x 10 / 4 = 43.00 Sqm.

Total = 99.25 Sqm.

2 Ramp for Lateral Traffic / Cattle Crossing = 1 x 10 x 7.50 + 3.75 / 2 = 56.25 Sqm.

3 Bus Bay = 1 x 20 x 3.00 + 2.00 / 2 = 50.00 Sqm.

Assistant Engineer
P.W.D. Sub Dn. Deogarh

Systek04/378102405.xlsx
Name of Road :- Upgradation of BT Road Anjana Pardi Jagdish Road ( T04 ) km 0/00 to 11/500

Coping 75mm thick 050m


R.L. of Top

m 1.50 Weep hole


R.R. Stone Masonary C.M. 1:4
.G.L
2.25
R.L.of Bed

0.75 m
m 1.25 R. L. of F
1:3:6 Mix 200 mm thick (M-10 Gr. C.C.)
m 140

CROSS SECTION OF PROPOSED PROTECTION WALL

Assistant Engineer
P.W.D. Sub Dn. Deogarh
0
CH: 0/600
7.50 m
m 0.40 m 0.40
75mm thick C.C. M-20 Coping

0.45 m 0.45 m
R.L. of Top

mm R.C.C. Hume Pipe 1000

3.00 m 3.00 m

R.R.M. in CM 1:4 R.R.M. in CM 1:4

200mm thick GSB Bedding

1.40 m 150mm thick P.C.C. M-10 1.40 m

R. L. of Foundation
1.60 m 1.60 m

TYPICAL X - SECTION OF R.C.C. HUME PIPE CULVERT

Assistant Engineer
P.W.D. Sub Dn. Deogarh
Name of Road : - NH-8 Km 139 To HAWALA
CH: 0/775
7.50 m
m 0.40 m 0.40
75mm thick C.C. M-20 Coping

0.45 m 0.45 m
R.L. of Top

mm R.C.C. Hume Pipe 1000

3.00 m 3.00 m

R.R.M. in CM 1:4 R.R.M. in CM 1:4

200mm thick GSB Bedding

1.40 m 150mm thick P.C.C. M-10 1.40 m

R. L. of Foundation
1.60 m 1.60 m

TYPICAL X - SECTION OF R.C.C. HUME PIPE CULVERT

Assistant Engineer
P.W.D. Sub Dn. Deogarh
CERTIFICATE FOR CORRECTNESS OF ESTIMATE

Name of Road : - SH-61 Km-276 To KITO KA BADIYA

Certified that I have checked estimate for PMGSY the estimate has been
framed on current BSR -2014 for PMGSY Roads of PWD Rajasthan The quantities
rates & nomenclature has been found correct.

Assistant Engineer Executive Engineer


P.W.D Sub Dn. Deogarh P.W.D Dn. Bhim

Ceritied that :
Road from SH-61 Km 276 to KITO KA BADIYA is not funded by other Agencies / Schemes
The proposals fails under other disrict road & village road only.
road only

Assistant Engineer Executive Engineer


P.W.D Sub Dn. Deogarh P.W.D Dn. Bhim
CERTIFICATE

Name of Road : - SH-61 Km-276 To KITO KA BADIYA

Certified that GSB is available as per gradation and as per requirement on


near by approved quarries and soil classification has been taken as per
actual site condition such a HSMB ( 70.0 % ), O.R. ( 10.0 % ), HRB. ( 20.0% ) ,

Assistant Engineer Executive Engineer


P.W.D Sub Dn.Deogarh P.W.D Dn. Bhim
CERTIFICATE

Name of Road : - SH-61 Km-276 To KITO KA BADIYA

Certified that : -
1 The population of the habitation under consideration has been
checked & found more than 250 as per census 2001.
2 The proposed Road work is not funded by any other Agency /
Scheme
3 The Road proposed in this package falls under ODR / VR.
4 The rates, nomenclature and quantities of the various item of the
work has been checked and found correct.
5 I have checked estimate as per present BSR 2014 for PMGSY
Roads of PWD Rajasthan
6 No. land acquisition is required.

Assistant Engineer Executive Engineer


P.W.D Sub Dn. Deogarh P.W.D Dn. Bhim
QUARRY CERTIFICATE

Name of Road : - SH-61 Km-276 To KITO KA BADIYA

This certified that I have inspected the Local Quarries Road stone ballast
and gravel quarries . The quarries have large deposits of material confirm to the
specification laid for sub base / base course and bituminous work respectively .
It is further collected in past under famine relief operations of any other scheme
with in economical leads have been accommodated in the estimate.

Assistant Engineer Executive Engineer


P.W.D Sub Dn.Deogarh P.W.D Dn. Bhim
ENVIRONMENT CERTIFICATE

Name of Road : - SH-61 Km 276 To KITO KA BADIYA

This certified that the road is proposed under rural road connectivity by
world Bank Assistance Shheme. The proposed road from SH-61 Km 276 To
KITO KA BADIYA does not have any environment issue. So this road does not
require any clearance from Rajasthan Pollution Control Board.

Executive Engineer Superintending Engineer


P.W.D Dn.BHIM P.W.D Circle Rajsamand
ncies / Schemes
ement on

B. ( 20.0% ) ,
DETAIL OF EXISTING C. D. WORKS
NAME OF ROAD :- Anjana Pardi Jagdish Road ( T04 ) Km 0/00 to 11/500

S No. CHAINAGE SPAN TYPE OF C.D. WORK REMARKS

1 0/075 1 X 1.20 m Stone slab Culvert

2 0/100 1 X 1.20 m Stone slab Culvert Proposed 1 X 1000 mm HPC

3 0/325 1 X 600 mm H.P. Culvert

4 0/750 1 X 600 mm H.P. Culvert

5 1/125 1 X 600 mm H.P. Culvert

6 1/225 1 X 600 mm H.P. Culvert

7 1/300 1 X 600 mm H.P. Culvert

8 1/625 1 X 600 mm H.P. Culvert Proposed 1 X 1000 mm HPC

9 2/050 1 X 600 mm H.P. Culvert

10 2/325 1 X 600 mm H.P. Culvert

11 2/725 50.0 m Flush Cause Way

12 2/850 50.0 m Flush Cause Way

13 3/075 30.0 m Flush Cause Way

14 3/600 2 X 1.00 m Stone slab Culvert Proposed 2 X 1000 mm HPC

15 4/475 2 X 1000 mm H.P. Culvert

16 5/750 1 X 600 mm H.P. Culvert

17 7/000 30.0 m Flush Cause Way

18 8/025 1 X 600 mm H.P. Culvert Proposed 1 X 1000 mm HPC

19 8/250 1 X 600 mm H.P. Culvert

20 8/500 1 X 600 mm H.P. Culvert

21 8/725 3 X 1000 mm H.P. Culvert

22 8/875 1 X 600 mm H.P. Culvert

23 9/200 2 X 1.00 m Stone slab Culvert Proposed 2 X 1000 mm HPC

24 9/950 1 X 600 mm H.P. Culvert

25 10/050 1 X 600 mm H.P. Culvert

26 10/575 1 X 1.00 m Stone slab Culvert Proposed 1 X 1000 mm HPC

Assistant Engineer
P.W.D. Sub Dn. DEOGARH
DETAIL OF STRETCHES BADLY DAMAGED & SETTELED

NAME OF ROAD :- Anjana Pardi Jagdish Road ( T04 ) Km 0/00 to 11/500

S No. Kms. CHAINAGE Length

From To

1 Km1 0/200 0/450 250 m

2 0/700 0/825 125 m

3 Km 2 1/360 1/540 180 m

4 1/840 1/960 120 m

5 Km 3 2/350 2/500 150 m

6 2/750 2/900 150 m

7 Km 4 3/240 3/390 150 m

8 Km 5 4/180 4/350 170 m

9 4/600 4/780 180 m

10 Km 6 5/050 5/110 60 m

11 5/450 5/600 150 m

12 Km 7 6/270 6/400 130 m

13 6/810 6/900 90 m

14 Km 8 7/225 7/300 75 m

15 7/480 7/600 120 m

16 Km 9 8/270 8/400 130 m

17 8/700 8/850 150 m

18 Km 10 9/200 9/500 300 m

19 9/840 9/900 60 m

20 Km 11 10/050 10/150 100 m

21 10/550 10/700 150 m

TOTAL DAMAGED LENGTH 2990 m

Say 3.000 Km

Assistant Engineer
P.W.D. Sub Dn. DEOGARH