INDIRECT COST

COST DURATION UNIT


JOBSITE OVERHEAD
Warehouse 20,000.00 1 project
Power Consumption 3,000.00 4 months
Fuel 5,000.00 4 months
Temporary Water Connection 15,000.00 1 project
Representation 10,000.00 1 project
Small Tools 10,000.00 1 project

SUPERVISION
Project Engineer 20,000.00 4 months
Foreman 15,000.00 4 months
Warehouse/ Checker 12,000.00 4 months

TOTAL INDIRECT COST


AMOUNT
20000.00
12000.00
20000.00
15000.00
10000.00
10000.00

80000.00
60000.00
48000.00

Php 275,000.00