No Description PCT’s Responsibilities

Design, manufacturing, supply, erection and


1 Cooling towers above cold water basin
commissioning
1.      GA drawings & load data to enable Purchaser
design and construct the CW basin
2 Cooling tower basins and cold water channels 2.     Vetting of sizing of CW basin and channel
3.      Design and supply of ½” and 10 mesh screens in
cold water channel

3 Cooling water sumps and CW pump house including EOT crane --

4 Circulating water pumps including drives and accessories --

1.       Design, engineering, procurement, supply,


Pressure sand filters (side stream filters) including allied piping erection, testing & commissioning
5
and instrumentation 2.      Design of Civil foundation

1.      Design, engineering, procurement, supply,


Circulating water treatment and chemical dosing system (ClO2 erection, testing & commissioning
dosing system, polymeric dispersant dosing, biocide dosing, 2.      Engaging a specialist sub-vendor to design,
6 H2SO4 storage and dosing system) plus supplying all chemicals monitor, run and maintain chemical dosing system for 6
for initial fill, commissioning, trial run for 30 days and 6 months of months of operation after commissioning
operation after commissioning 3.     Design of Foundation for Dosing packages

Piping, valves and fittings (including interconnecting pipes


Design, procurement, fabrication, erection, installation,
7 between CWTP skids) within the battery limit as per Scope
testing and commissioning
Drawing and P&I diagram

8 Chemical treatment plant building Vetting of GA/Architectural drawing

9 Shed for chemical storage Sizing and preparation of GA drawings


Design, engineering, procurement, supply, erection,
10 Fire Water Spray System
testing & commissioning
Complete electrical work (including motors, lighting system and Design, engineering, procurement, supply &
11
equipment earthing system) as per specification commissioning within battery limit
1.           Design, engineering, procurement, supply,
erection, commissioning & testing of:
(i)         chlorine detector
(ii)     local PLC for ClO2 dosing
system
(iii)       Instruments, analysers etc. required in
various chemical
12 Instrumentation and controls as per specification and P&ID
dosing system
(iv)      Loop-powered Vibration transmitters
2.           Design, engineering, procurement, supply and
Installation of cable trays for cabling included by us
within our battery limit
3.          Design and engineering of all ISBL cabling up to
junction box at battery limit and cable trench within our
battery limit
13 Fire Alarm / Plant Communication / Telephone System --
Design and engineering / documentation as per
14 3D modelling
specification
15 Approach roads, ERC / IRC, box culvert for approach road --

16 Pavements within battery limit --


Owner’s Responsibilities

Supply, erection & testing of all hot water piping external to cooling tower including risers, riser isolation valves, etc.
1.  Sizing, Hydraulic design, CFD analysis, structural design, Construction (including supply of all civil work materials),
erection, construction supervision, testing, etc.
2.   Design, supply, erection and commissioning of sluice gates

3.  Erection and commissioning of screens in cold water channel


1. Design, engineering, supply of all material, preparation of AFC drawings, construction (including supply of all civil work
materials), erection, construction supervision, testing, etc.
2. Pump foundation and pump house flooring
Design, engineering,
procurement, supply, civil work, erection, testing and commissioning

1.     Civil work towards SSF foundation

2.     All allied civil work

1. Civil work towards foundation

2. All allied civil work

3. Procurement, supply, erection, testing and commissioning of corrosion probe/coupon

Allied civil work (if any)

GA / Architectural Drawing, structural design, supply of all material, preparation of AFC drawings, construction (including
supply of all civil work materials), Air condition system, erection, construction supervision, testing, etc.
Structural Design, supply of all material, preparation of AFC drawings, construction (including supply of all civil work
materials), erection, construction supervision, testing, etc.
--
Erection, installation, allied civil work (if any), testing and commissioning of balance electrical items viz. switchgears,
transformers, all power & control cables, cable trays & supports, cable trench, etc.
1.      Design, engineering, procurement, supply, erection / construction, testing & commissioning of balance instruments,
analysers, DCS system, etc.
2.      Supply, installation, all associated civil work & testing / commissioning of cable trench (within battery limit) designed
by Paharpur
Design, engineering, procurement, supply, erection, testing & commissioning

--
Design, engineering, supply of all material, preparation of AFC drawings, construction (including supply of all civil work
materials), erection, construction supervision, testing, etc.
Design, engineering, supply of all material, preparation of AFC drawings, construction (including supply of all civil work
materials), erection, construction supervision, testing, etc.
Task Name
INPUTS FROM CLIENT
Handing over of Site
Area for Office & Store
Laydown Area
Area for Labor colony
Handing over of Basin duly Tested
CW Return up to B/L
CW Sump
CWTP Building
Civil foundation for SSF
Civil foundation for Naclo2 and HCL Tank
Availability of Power & Water for
Commissioning cell 1-8
Completion of Inputs