Académique Documents
Professionnel Documents
Culture Documents
1
The primary focus of the assessment, as it forms the key part Nuclear Safety and Nuclear Safety-Related Applications
of the programmable element of the VSD Control System, is (referred to as ‘PES Guidelines’) [5]. The second element
the core software. focussed on the EDF Energy Project and its associated
arrangements for safety assurance of the final operational
3 Functional Safety and Safety Requirements systems and addressed both requirements of the EDF Energy
PES Guidelines and applicable requirements of Part 1
COTS equipment is not commonly developed to comply with (General Requirements) of the international functional safety
the requirements of recognised safety assurance standards and standard for programmable electronic systems, IEC 61508
as a result, evidence of safety assurance (e.g. equipment [6].
safety case report, test evidence) is not routinely available.
Initial assessment activities confirmed that evidence of full The VSD selected for the EDF Energy application had
compliance to the process requirements of IEC 61508 was not evolved over a number of design generations and limited
available for the VSD. design and development information specific to the
equipment was available. The evidence for ‘Production
The EDF Energy Engineering Advice Note (EAN) entitled Excellence’ of the VSD was identified during a series of
Justification of Smart Instruments [7], in line with the ONR audits of the drive manufacturer and considered both the
requirements for safety systems and safety-related generic (core) elements of the Controller and the specific
instrumentation, in particular ESS.27 Engineering principles: application of the Controller to the Heysham 2 and Torness
safety systems – Computer based safety systems, required a application. Assessment was made against guidance for both
demonstration of ‘production excellence’ and ‘independent the 10-2 and 10-3 integrity targets, to establish a margin of
confidence building’ for product hardware and software. confidence above the 10-2 level.
The existing safety case for Torness & Heysham 2 requires 5 Independent Confidence Building Measures
that a failure of a VFC to operate on demand occurs at a rate
(ICBM) Methodology
of no more than 10-2 failures per demand. The VSD are
controlled by software executed on a microprocessor. It was The ‘confidence building’ leg is described by the ONR in
therefore necessary to assess the integrity of this (T/AST/046) as an “independent and thorough, reasonably
programmable element of the VSD against the requirement practicable, assessment of the safety systems”. The activity
for a likelihood of failure to operate on demand better than should be completed, by an independent individual or team,
10-2. on the final product and assesses the realisation of the product
against the design specification, development methods and
The ‘production excellence’ and ‘independent confidence applicable standards. The task also includes independent
building’ assessment paths were conducted over a period assessment of the test programme.
involving two assessment phases, aligned with the two EDF
Energy project phases of ‘Design for Manufacture’ (Phase 1) Implementation of the following set of ICBM was considered,
and ‘Testing’ (Phase 2). Phase 1 was started in mid-2009 and based on the minimum requirements specified in Section 6 of
completed with a Preliminary Assessment Report [4] in April the Smart Instrument Justification EAN [7] for a 10-2
2010. Phase 2 started in the autumn of 2010 and completed probability of failure claim:
with the issue of an Engineering Assessment Report in April Type Test
2013.
EMIT Arrangements
Commissioning Tests
4 Production Excellence Methodology
Prior Use Data Analysis
The intention of the ‘production excellence’ leg of the Hardware FMEA
argument is demonstration of high quality from initial Manufacturer’s Pedigree.
specification through to a commissioned system, e.g.
evidence of application of software development in
compliance with accepted standards. Evidence to support this 6 Assessment Results
argument is expected to be generated through detailed
Assessment of the drive against the PES Guidelines identified
examination of the processes and procedures implemented
that the development of the equipment did not meet all the
during equipment development supported by evidence of
requirements in the areas of the system development process
implementation of these measures through audit of design
and verification for a 10-2 integrity target. This result was not
documentation.
unexpected, given that the system was not developed
specifically for safety applications, and the rigorous processes
The ‘Production Excellence’ assessment was addressed
defined for safety-related systems were not therefore used.
within two distinct elements. The first element focussed
primarily on the activities of the equipment supplier and
Non-compliances identified in undertaking the ‘production
addressed exclusively the requirements of the EDF Energy
excellence’ assessment were presented within a formal report
Guidelines for Using Programmable Electronic Systems in
2
and, where appropriate, compensating measures were code that could adversely affect the required behaviour of the
developed as mitigation. PTCS application is very low.
3
documents, such as Validation and Verification Plans and the
EMIT arrangement Functional Safety Audit Plan.
The finalisation of the Examination, Maintenance, Inspection
and Testing procedures was identified as a condition of final 8 Conclusions
acceptance for use of the VSD Controller as part of the
Heysham 2 and Torness PTCS application. An Engineering Assessment Report was developed in
accordance with an EDF Energy Engineering Advice Note
Commissioning tests (EAN) entitled Justification of Smart Instruments [7] and
The finalisation of the Commissioning test procedures was requirements provided by EDF Energy in progress review
identified as a condition of final acceptance for use of the meetings.
VSD Controller as part of the Heysham 2 and Torness PTCS Subject to a specific set of acceptance conditions being
application. fulfilled, the conclusion of the assessment was that the VSD
Controller, configured with its application specific operating
Hardware FMEA program, fulfils the safety requirements specified for its
As part of the design of the VSD drive for the EDF Energy application as part of the Heysham 2 and Torness Post Trip
PTCS application, the VSD manufacturer commissioned a Cooling System. The acceptance conditions included a need
full Failure Modes, Effect and Criticality Analysis (FMECA) for the VSD manufacturer and EDF Energy to address a set of
and associated Probabilistic Risk Assessment (PRA) of the minor residual concerns associated with the VSD Controller
drive. EDF Energy engineering staff conducted an design and documentation, and complete the outstanding, but
independent review of the VSD manufacturer FMECA/PRA. planned, on-site system validation activities and finalisation
In addition to assessing the VSD manufacturer FMECA/PRA of operation and maintenance support documentation.
from the point of view of specific recommendations arising The assessment comprised two main assessment paths. The
from the initial Production Excellence assessment, ERA results of the first assessment path, ‘Production Excellence’,
Technology conducted a more general independent of the VSD Controller as supplied by the VSD manufacturer,
assessment of the FMECA/PRA and on the manufacturer confirmed that the VSD Controller and its development and
Human Factors Evaluation Report. It was concluded that the assurance processes were compliant with the EDF Energy
FMECA provided a comprehensive analysis of the VSD in PES Guideline requirements for a safety integrity of 1 x 10 -2
accordance with BS EN 60812:2006 and a PRA incorporating probability of failure on demand or, where a compliance
the requirements of BS EN 61025:2007. The FMECA and shortfall was identified as a result of the initial assessment,
PRA evaluated hardware failure only. Software and human adequate compensating measures were implemented.
performance errors were not evaluated as part of this analysis. The results of the second assessment path, ‘Independent
The FMECA included evaluation of the probability of Confidence Building Measures’, confirmed that a set of
detection value for each of the 566 failure modes considered. ICBMs, compliant with the minimum requirements of the
The results of the analysis showed that 98% of all failure EDF Energy EAN [7] for a safety integrity of 1 x 10-2
modes were identified by use of continuous monitoring probability of failure on demand were implemented
supplemented with regular proof testing. successfully.
4
Replacement Project - Preliminary Independent
Functional Safety Assessment, ERA Technology Report
2010-0210”, (April 2010).
[5] British Energy. “Guidelines for Using Programmable
Electronic Systems in Nuclear Safety and Nuclear Safety-
Related Applications, EPS/GEN/REP/0277/97 Revision
2”, (May 2002).
[6] European Standard IEC 61508. “Functional safety of
electrical/electronic/programmable electronic safety-
related systems – Part 1: General requirements”, (2010).
[7] British Energy. “Engineering Advice Note, Justification
of Smart Instruments, E/EAN/BPFB/0047/GEN/05,
Revision 001”, (31 March 2010).