Vous êtes sur la page 1sur 487

Applicable NERC Reliability

Standards
Ryan D. Quint, NERC
Power Plant Model Verification and Testing Workshop
September 2016
Disclaimer

ͻ The material presented here is not intended as compliance


guidance. Its sole purpose is to describe the technical aspects of
related reliability standards to power plant modeling and
verification.
ͻ For questions related to compliance, please contact NERC
Compliance Department directly.

2 RELIABILITY | ACCOUNTABILITY
MOD Standards Framework

NERC MOD Standards


Modeling, Data, and Analysis

MOD-032
Data for Power System Modeling and Analysis

System Modeling Plant Modeling


- Load Forecasts - MOD-025-2 – Generator Capability
- System Components - MOD-026-1 – Volt/Var Control
- Reactive Devices - MOD-027-1 – Power/Frequency Control
- Transfers

MOD-033
Steady-State and Dynamic System Model Validation

3 RELIABILITY | ACCOUNTABILITY
Applicability of MOD Standards

Standard Applicability Effective


MOD-025-2 Generator Owners (and Transmission Owners) 7/1/2016
• Generators and synchronous condensers – 20 MVA
• Aggregate plant/Facility – 75 MVA

MOD-026-1 Generator Owners and Transmission Planners 7/1/14


and EI or QI: Individual or Aggregate > 100 MVA (R1,3,4,5,6)
MOD-027 WI: Individual or Aggregate > 75 MVA
7/1/2018
ERCOT: Individual > 50 or Aggregate > 75 MVA (R2)
MOD-032-1 Balancing Authorities Generator Owners 7/1/2015
Planning Coordinators Resource Planners (R1)
Transmission Planners Transmission Owners
7/1/2016
Transmission Service Providers LSE (R2,3,4)

MOD-033-1 Planning Coordinators, Reliability Coordinators, and 7/1/2017


Transmission Operators
*Directly connected to the Bulk Electric System (BES) with gross nameplate rating

4 RELIABILITY | ACCOUNTABILITY
Implementation Plans

Standard Implementation
Order approving standard on 3/20/2014
Effective Date (all requirements) – 7/1/2016
Implementation Plan:
MOD-025-2 • 40% after 2 years
• 60% after 3 years
• 80% after 4 years
• 100% after 5 years
Order approving standard on 3/20/2014
Effective Dates:
• R1, R3, R4, R5 – 7/1/14
MOD-026-1
• R2 – 7/1/18
&
Implementation Plan:
MOD-027-1
• 30% after 4 years
• 50% after 6 years
• 100% after 10 years

5 RELIABILITY | ACCOUNTABILITY
MOD-025-2:
Verification and Data Reporting of Generator Real
and Reactive Power Capability and Synchronous
Condenser Reactive Power Capability

6 RELIABILITY | ACCOUNTABILITY
MOD-025-2
Requirements

ͻ Ensure accurate information available for planning models


ƒ Generator gross and net Real (P) and Reactive (Q) Power capability
ƒ Synchronous condenser Q capability
ͻ Implementation:
ƒ FERC approved 3/20/14; Order effective 7/1/16
ƒ 40% after 2 yrs, 60% after 3 yrs, 80% after 4 yrs, 100% after 5 yrs
ͻ Requirements:
ƒ R1: GO provides its TP with verification of P capability
ƒ R2: GO provides its TP with verification of Q capability
ƒ R3: TO provides its TP with verification of Q capability
ƒ Verify in accordance with Attachment 1
ƒ Submit completed Attachment 2

7 RELIABILITY | ACCOUNTABILITY
MOD-025-2
Attachment 1

ͻ Verification Specifications:
ƒ First verification for each unit must be a staged test
ƒ If operational data for different points recorded on different days,
designate earliest as verification date
ƒ Periodicity:
o At least every 5 years; or within 12 months of discovery of change affecting
P or Q capability > 10% and expected to last > 6 months
ƒ New units must be verified within 12 months of commercial ops date
o Applies to existing units that have been in long-term shut down
ƒ P capability and full load Q capability testing should be performed at
same time; however, separate testing is allowed.
ƒ Q capability testing should be scheduled for time advantageous for unit
being verified to demonstrate its Q capabilities
o While TOP takes measures to maintain plant’s system bus voltage at
scheduled value within tolerance
8 RELIABILITY | ACCOUNTABILITY
MOD-025-2
Attachment 1

ͻ Verification Specifications
ƒ Units < 20 MVA at plant > 75 MVA aggregate - individual or aggregate
ƒ Units > 20 MVA must be verified individually
ƒ Check auxiliary equipment in-serve for expected normal operation
ƒ AVR in-service for Q capability verification
ƒ Operational data within 2 years prior to verification date acceptable as
long as meets criteria and 90% of previous staged test
o Previous test must have demonstrated at least 50% of D-curve Q capability
o If previously test was unduly restricted, then another staged test required

9 RELIABILITY | ACCOUNTABILITY
MOD-025-2
Attachment 1

Pmax 2.1. P and Q capability


over-excited at normal
Qmax expected maximum P
output:
ͻ Synchronous condenser:
Pmax, Qmax for minimum
of 1 hour
ͻ Variable generating units:
Qmax at time of
verification; should have
at least 90% units online

10 RELIABILITY | ACCOUNTABILITY
MOD-025-2
Attachment 1
Pmin
Pmax 2.2. Q capability* max
Qmax over- and under-excited
Qmax for:
ͻ Normal Pmin, as soon as
limit is reached (nuclear
exempt)
ͻ Normal Pmax, as soon as
limit is reached

Qmin Qmin * Other than wind & solar PV

11 RELIABILITY | ACCOUNTABILITY
MOD-025-2
Attachment 1

Recorded data for verification:


1. Gross P and Q capabilities
2 2. Scheduled voltage provided by TOP, if applicable
3 3. Voltage at high- and low-side of GSU and/or
6,7 interconnection transformer(s)
4. Ambient conditions at end of verification period
3
that GO requires for corrections to P output for
1 different ambient conditions
5. Date and time of verification period (start and
end times)
6. GSU and/or system interconnection transformer
voltage ratio and tap settings
7. GSU losses (P and Q) if measurements taken at
high side
8. Whether staged test or operational data

12 RELIABILITY | ACCOUNTABILITY
MOD-025-2
Attachment 1

ͻ Considerations:
ƒ Verify at normal operating hydrogen pressure for hydrogen-cooled units.
ƒ Calculate GSU losses if measurements taken at high-side
o GSU losses may be estimated based on GSU impedance.
ƒ Simplified one-line diagram must show sources of auxiliary P and Q and
associated connections for each unit verified.
o Include GSU and/or system interconnection and auxiliary transformers.
o Show Q flow with directional arrows.
o If metering does not exist, provide engineering estimate.
ƒ If adjustment requested by TP, develop relationships between test
conditions and unit output so that the amount of P that can be expected
can be determined at different conditions, such as summer peak
conditions.

13 RELIABILITY | ACCOUNTABILITY
MOD-025-2
Attachment 2

ͻ One-line diagram
ͻ Table and summary of
verification information
ͻ Current and past test data
14 RELIABILITY | ACCOUNTABILITY
MOD-026-1:
Verification of Models and Data for Generator
Excitation Control System or Plant Volt/Var Control
Functions

MOD-027-1:
Verification of Models and Data for
Turbine/Governor and Load Control or Active
Power/Frequency Control Functions

15 RELIABILITY | ACCOUNTABILITY
MOD-026-1/MOD-027-1
Terminology

Resource Excitation control system or Turbine/governor and load


plant volt/var control control or active
function power/frequency control
Synchronous Includes generator, exciter, Includes turbine/governor and
Machine voltage regulator, impedance load control
compensation, and power
system stabilizer
Aggregate Includes voltage regulator & Includes active power/frequency
Generating reactive power control system control
Plant controlling and coordinating
plant voltage and associated
reactive capable resources

16 RELIABILITY | ACCOUNTABILITY
MOD-026-1/MOD-027-1
Requirements

R1: Each TP provides information to the GO upon request:


ƒ List of models acceptable to TP
ƒ Block diagrams and/or data sheets for acceptable models
ƒ Model data for GO’s existing units
R2: GO provides verified generator dynamic model(s) for each unit
ƒ Model verified by GO using one or more models acceptable to TP
ƒ Each verification includes the following:
o Unit’s model response matches recorded response (next page)
o Manufacturer, model number (if available), and type of system
– e.g., digital vs. analog, static vs. rotating exciter, plant controls
– e.g., turbine type, boiler type, fuel type, manufacturer and controls
o Model structure and data
– e.g., block diagram, time constants, gains, limits, generator data
o Outer loop controls – blocked or nonfunctioning controls or modes of
operation that limit response
17 RELIABILITY | ACCOUNTABILITY
MOD-026-1/MOD-027-1
System Events and Tests

Standard MOD-026-1 MOD-027-1


System “Voltage excursion from a Frequency excursion event, with
Event measured system disturbance” unit operating in frequency
– size not specified, should responsive mode:
have noticeable perturbation to • EI: ǻf •+]
terminal voltage • TI: ǻf •+]
• WI: ǻf •+]
• QI: ǻf •+]
Staged “Voltage excursion from a • Speed governor reference
Test staged test” – for example, change with unit on-line
voltage reference step test* • Partial load rejection test**
with unit online and PSS on/off
* PSS Off tests verify excitation system models while PSS ON tests verify PSS models.
** Differences in control modes between testing and final simulation model need to be identified. Most
controls change gains or have a set point runback which takes effect when the breaker opens. This can
skew results of load rejection tests if not properly accounted for and understood.

18 RELIABILITY | ACCOUNTABILITY
MOD-026-1/MOD-027-1
Requirements

R3: GO provides written response to TP after receiving from TP:


ƒ Notification that model is not usable
ƒ Comments identifying technical concerns with verification documents
ƒ Comments and supporting evidence indicating modeled response does
not approximate recorded response for three or more events
ƒ Response will include either technical basis for maintaining model,
model changes, or plan to perform verification
R4: GO provides revised model or plans to perform PPMV within
180 days of making changes to controls or equipment that alters
response characteristic.

19 RELIABILITY | ACCOUNTABILITY
MOD-026-1/MOD-027-1
Requirements

MOD-026-1:
R5: GO provides response to TP within 90 days following receipt of
technically justified* request to perform model review, including:
ƒ Details of plans to verify model
ƒ Corrected model data including source of revision
* TP demonstrates simulated vs. measured response does not match
MOD-027-1 / MOD-026-1:
R5/R6: TP provides written response to GO within 90 days of
receiving verified model that model is usable or not usable,
including:
ƒ Initializes without error
ƒ No-disturbance simulation results in negligible transients
ƒ Exhibit positive damping
20 RELIABILITY | ACCOUNTABILITY
21 RELIABILITY | ACCOUNTABILITY
09/21/2016 | ATLANTA, GA

ISO-NE System Operations


Perspective on Power Plant
Model Verification

Bilgehan Donmez
SENIOR ENGINEER | REAL-TIME STUDIES
ISO New England Is Part of a Larger Electric
Power System
NERC
North American Electric Reliability Corporation
• Eastern Interconnection spans Québec Interconnection
from Rocky Mountains to East NPCC
Northeast
Coast and Canadian Maritimes Power
Coordinating
Council
– Primarily alternating-current
(AC) transmission
– New England linked to rest of
Eastern Interconnection via
transmission ties to New York
and New Brunswick

• Tied to Québec only through


direct-current (DC) transmission
Eastern
• 2003 Blackout ushered in wide- Interconnection
area monitoring and mandatory Western
Interconnection
reliability standards ERCOT
Interconnection

2
System Details

• 7.1 million retail electricity customers drive


the demand for electricity in New England
(14.7 million population)
• Region’s all-time summer peak demand set
on August 2, 2006 at 28,130 MW
• Region’s all-time winter peak demand set
on January 15, 2004 at 22,818 MW
• Energy efficiency and behind-the-meter solar
slow the growth in summer peak demand to
0.3% annually and reverse the growth in
overall electricity demand to -0.2% annually

Note: Without energy efficiency and solar, the region’s peak demand is forecasted to grow 1.1% annually and the region’s overall electricity demand
is forecasted to grow 1.0% annually. Summer peak demand is based on the “90/10” forecast for extreme summer weather.

3
A Range of Generation and Demand Resources Are
Used to Meet New England’s Energy Needs
Existing and Future Resources
• 350 generators in the region (MW)
35,000
• 31,000 MW of generating capacity 31,000
30,000
• 11,500 MW of proposed
generation in the ISO Queue 25,000
– Mostly natural gas and wind
20,000
• 4,200 MW of generation has
retired or will retire in the next 15,000
11,500
five years
10,000

• 600 MW of active demand


5,000
response and 1,900 MW of energy 2,500

efficiency with capacity supply 0


obligations Existing Existing Demand Proposed
Generation Resources Generation

4
New England Has Significant Wind Potential

• Population and electric demand are


concentrated along the coast in central
and southern New England
• Most of the new wind farms (current and
upcoming in the interconnection queue)
are coming to the northern part of the
New England system where we have
limited short circuit strength.
• 12,000 MW of onshore and offshore wind
potential
– Preliminary screening eliminated wind
sites near urban areas and sensitive
geographic locations Electricity Demand
(e.g., Appalachian Trail)
• Transmission will be required to connect
potential wind resources to load centers Wind zones
in New England

5
New England’s Transmission Grid Is the Interstate
Highway System for Electricity

• 8,600 miles of high-voltage transmission


lines (115 kV and above)
New
• 13 transmission interconnections Hydro
Brunswick

to power systems in New York and Québec


Eastern Canada
• 16% of region’s energy needs met
by imports in 2015
• $7.88 billion invested to strengthen
transmission system reliability since
2002; $4.18 billion planned New
York
• Developers have proposed multiple
transmission projects to access
non-carbon-emitting resources

6
Ensuring Reliable Power System Operations Is a
Major Responsibility

• Maintain minute-to-minute
reliable operation of
region’s generation and
transmission system
• Perform centralized
dispatch of the lowest-
priced resources
• Coordinate and schedule
maintenance outages
• Coordinate operations with
neighboring power systems

7
Operational Limits

• ISO-NE Operation Support Services perform thermal, voltage and


stability studies to come up with operating limits for the control
room.
• Being at the tail end of the Eastern Interconnection, north to south
transfers in the northern part of our system is transient stability
limited. In New England, we have a few dozen stability based
SOLs/IROLs respected in real time.
• With our stability limits, modeling plays a key role. If we have
models that, we believe, do not do an adequate job of capturing
facility performance, we can keep a new plant from coming on-line
or limit its output.
• We can also limit an existing plant’s output to the point of keeping
it offline, and these could be indefinitely, because using these
models puts us in an “undefined system condition”.
8
Why is it important to have accurate models?

• To ensure our transient stability simulations provide accurate


system representation
• To prevent restricting units due to poor plant models

9
Operational Use of PMUs

• Real-time Oscillation Alarm --> Email


– Operation support engineers
• Write real-time operating procedures
• Communicate with the plant

• Post Event Analysis


– Data: PMU, SCADA, DFR
– TSAT simulations
– PhasorAnalytics
• Frequency Response Monitoring
– System
– Individual generator
– In-house developed Excel tool
– Evaluating PNNL’s Frequency Response Tool

10
How do we use PMUs? Examples…

• Event detection: Oscillation monitoring


– Example 1: Forced oscillations detected by PMUs
• Post-event analysis and power plant model validation
– Example 2: Sustained oscillations detected by PMU due to high gain
settings of the exciter system

11
12
Example 2: Event Details

• Normally cleared single phase to ground fault on a nearby 345


kV line followed by a 5 second automatic reclosing
• Poor damping at the plant was detected by the PMU
oscillation detection logic
• High speed (5 second) reclosing exacerbated the plant
oscillations

13
Unit Details

• Combined cycle plant:


2 gas turbines and 1
steam turbine
• ~550 MW total output
• PMU available at POI

14
PMU Data: Line Flow and Total Plant Output

15
Example 2 is a Success Story in using PMU data
to correct Plant Models
• We worked with the generator owner to analyze the results.
• The generator owner hired a consultant to check the
parameters of the dynamic model and updated the exciter
model parameters to better represent the plant behavior.
• The generator owner also decided to install a power system
stabilizer, which is scheduled to go in-service by the end of
September.

16
What is next?

• MOD 26 and 27
• MOD 33
• Online Transient Stability Analysis

17
Power Plant Model Validation
(MOD-26 & MOD-27)
• Batch Model Validation – 19 generators/plants with 1 click
– A MATLAB tool calls TSAT playback function

PMU & TSAT Real Power (MW) at POI


-1200

-1210
(MV )
Real Power (MW)

-1220
P

PMU Curve
ti

-1230
TSAT Volt-Theta Curve
R

TSAT Volt-Freq Curve

-1240
0 5 10 15 20 25 30 35
Time (s)

PMU & TSAT Reactive Power (MVar) at POI


130

120

110
Reactive Power (MVar)

100

90
PMU Curve
TSAT Volt-Theta Curve
80
TSAT Volt-Freq Curve

70
0 5 10 15 20 25 30 35
Time (s)

18
System Wide Model Validation (MOD-33)

• In-house developed bridging tool – Java


– Carries over real-time SE statuses to the planning case
– Compare power flow and simulation results with SE/PMU data
– Identify mismatches and investigate model accuracy

SE Case

NX-9 Bridging Modified


Mapping Tool Planning Case
Planning
Case

19
Pilot On-line Transient Stability Assessment

• Real-Time security
assessment Fixed data (updated periodically)

Network Dynamic
Generator
model in data in
mapping
planning planning
table
• Post event analysis Updated in real time
case case

– Good match with PMU EMS Snapshot Data Preparation Tool (DPT)
Dynamic
equivalent for
external area

data for the events Updated in real time


Fixed data (updated periodically) (optional)

tested Auxiliary files (e.g.,


interface file, contigency DSA Manager
file, transfer file, etc.)
– Event recreation
– Perform what-if analysis
TSAT Server 1 TSAT Server 2 TSAT Server n

20
21
Power Plant Model Validation
and Performance Monitoring
presented by Dmitry Kosterev
Bonneville Power Administration

NERC Power Plant Model Validation Workshop


September 2016
Power System Models
• Accurate power system models are required for
reliable and economic power grid operations

• Two large-scale power outages in August 10, 1996


the West on July 2 and August 10
1996
• Observed generator responses
were different from what was
expected
• Loss of confidence in abilities to
establish safe operating limits
• Interties were de-rated temporarily :
– California-Oregon AC from 4,800 to Failure of the power system model to
3,200 MW
reproduce what happened
– Pacific HVDC from 3,100 to 2,000 MW
Benefits of Generator Testing in WECC
WSCC required all generators >20 MVA be tested for
model validation

Benefits of WECC generator testing program are


indisputable:
• Great majority of dynamic models needed data revisions
• Structural model errors were detected – e.g. static exciters
represented with models used for rotating dc exciters
• Errors in control settings were identified and corrected, e.g.
error in PSS wiring

Need to sustain model validation efforts was evident


Governor Response Modeling
Generator testing program alone was not enough …

Validation studies done for August 10 1996 outage


showed optimistic frequency response
• WSCC implemented an interim measure – block governors
on all thermal units loaded above 90% of their capacity

In early 2000s, WECC was developing a frequency


response criteria
• System tests were done to validate governor response
across the West (May 2001 – all AGC systems were
suspended, planned dropping Grand Coulee and Hoover
generation)
• Validation studies showed the frequency response was still
optimistic
An effort was launched
in 2002 to classify
power plant operating
practices:

Frequency - Responsive

Under Load Control

Frequency Non-
responsive, or
Baseloaded
June 14 2004 Westwing Event
Malin Frequency, June 14 2004 West Wing event

60.1

Frequency response
60
representation improved
59.9 greatly
Frequency [Hz]

Actual
59.8
Malin Freq

59.7

59.6
COI Power, June 14 2004 West Wing Disturbance

6000
59.5
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
Time [sec] 5500

5000

4500
Power [MW]

Actual
4000
COI

3500

Reasonable correspondence 3000

between actual and simulate 2500

power pick-up
2000
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
Time [sec]
Frequency
response is not just
about system
frequency

Distribution of
frequency response
also affects post-
contingency path
loading and voltage
stability.

It is an issues in
WECC because of
unbalanced
frequency response
distribution
2006 WECC Generating Unit Model
Validation Policy
• WECC formalized its model validation requirements in
Generating Unit Model Validation Policy
• Data Requirements
– Data must be provided using grid simulator models
• Baseline model development
– Required for new plants, when equipment changes are
made, or when a model is found to be in error
• Periodic model verification
– Done every 5 years to make sure that models are up to date
• Reactive limit testing
NERC Reliability Standards
2007 – NERC started the development of model verification
standards

2013 – NERC approved:


– NERC MOD-025 – active and reactive power capabilities
verification
– NERC MOD-026 – generator and excitation control model
verification
– NERC MOD-027 – generator turbine control model
verification

2014 – NERC approved MOD-033 requiring plant operator


to provide accurate power plant model data
Baseline Model Development 10
Baseline Model Development vs. Periodic
Model Validation

• Baseline model development


• Needed to establish the correct model structure
• Needed to create initial model data set

• Periodic model verification


• Done to ensure that the models stay accurate and up-to-
date AFTER a good model baseline is developed
• Should not be a substitute for baseline model
development
Baseline Model Development
Equipment Model
Speed Reference

ZREF uop Gmax

Z 1 1 1
6 1 + s Tf
6 Tp s

ucl Gmin
Damping PILOT
SERVOMOTOR

s Tr
Rt 1 + s Tr

Rp

• Needed to establish the correct model structure


• Inspection of equipment and control settings
• Some staged tests are required
• Disturbance monitoring can complement model development
12
Baseline Model Development
Mechanical Digital

Many modern digital controls map directly to models


13
Baseline Model Development
Thermal Hydro

Practical limitations usually exist in large thermal plants


14
Baseline Model Development
Baseline model development is an essential first step to
establish correct model structure and to develop an
initial model data set that includes:
• Inspection of equipment and control settings
• Some staged tests may need to be done
• Disturbance monitoring can be used to complement
baseline model development
Disturbance Monitoring 16
Disturbance Monitoring
POI Plant
POI Generator
Substation
DDR DDR
EFD
V I V I
IFD

17
Disturbance Monitoring

Plant Disturbance Monitoring


• Plant disturbance monitoring can complement baseline
model development
• Several mature applications are available
• EPRI PPPD is used widely by GOs in North America

POI Disturbance Monitoring


• POI disturbance monitoring can be used for periodic
model verification per MOD-026 and 027 once a good
baseline model is developed
• POI monitoring provides Transmission Planner an
independent way to validate model and generator
performance during disturbances
Using Disturbance Recordings for MOD
• Disturbance recordings can be used for compliance
with MOD-026 and 027 Standards
• All major grid simulators (PSS®E, PSLF, PowerWorld)
have disturbance play in capabilities
• Model verification must be done over multiple
disturbances
• Applications for data and model management are
available and mature
Using POI Disturbance Recordings
MODEL
Power Plant
Voltage and Frequency

MWs and MVARs


G
Controllable
Voltage and
Frequency

Voltage and frequency are played in as inputs


Active and reactive power are used as “measure” of success”
20
Using POI Disturbance Recordings
Using POI Disturbance Recordings
Successful model verification

Voltage and frequency are inputs


Active and reactive power are “measures of success”

Blue line = actual recording


22
Red line = model
Using POI Disturbance Recordings
Un-successful model verification

Voltage and frequency are inputs


Active and reactive power are “measures of success”

Blue line = actual recording


23
Red line = model
When Model and Actual Disturbance Data
Do Not Match
• Check powerflow model (and specifically transformer
impedances and taps)
• Check dynamic data record against test report (and
specifically decimal points)
• Beware of model data conversion and minus signs
• Most common model issues:
– Power System Stabilizer models
– Turbine control mode of operation / governor models
– Operating head in hydro turbines
– Generator inertia
– Deficiencies in model structure
• Things we do not normally model:
– Automatic Generation Controls, secondary controls, UEL
24
Transmission Planners
• MOD Standards require Transmission Planners to check
usability of the GO-provided models, but not model
accuracy
- Sets of automated tools are developed to stress-test
model usability, including voltage and speed reference
step responses, fault simulations, and by playing in
various disturbances

• It is a good practice for Transmission Planners to


– Perform independent model verification
– Transmission planners need to understand models and
associated data and how it affects
Transmission Planners:
Going Beyond the Standard
BPA approach has been “Trust but Verify”
• Systematic deployment of DDRs at power plants following 1996
outages
• Developed and deployed Power Plant Model Validation (PPMV)
application for model validation
• Helped many BPA customers with MOD compliance
• About 60% of models did not match disturbance recordings
even after baseline tests were performed
• Helped to drive model verification efforts, resulting in
significant model improvements
• Disturbance-based model verification studies are performed
following each large disturbance – I know how my generating
fleet performed within minutes after a system event!
DDR Deployment at BPA
BPA has PMU disturbance monitoring:
- Conventional –
- 13 plants, 133 generators, 21,645 MW of capacity
- Wind –
- 12 plants, 1,200 MW of generation

Data is streamed continuously to BPA control centers

Engineering and real-time applications developed and


implemented
27
Success Stories – Plant A

BEFORE AFTER

Blue = Actual, Red = Model

28
Success Stories – Plant B
BEFORE-2014 AFTER-2015

180 180

175 175
Active Power [MW]

Active Power [MW]


170 170

165 165

160 160
0 10 20 30 40 50 60 70 80 0 10 20 30 40 50 60 70 80
Time Time

20 20

10 10
Reactive Power [MVAR]

Reactive Power [MVAR]

0 0

-10 -10

-20 -20

-30 -30

-40 -40
0 10 20 30 40 50 60 70 80 0 10 20 30 40 50 60 70 80
Time Time
29
Success Stories – Plant C
BEFORE-2014 AFTER-2015

240 238

238 236

Active Power [MW]


Active Power [MW]

236
234
234
232
232
230
230

228 228

226 226
0 10 20 30 40 50 60 70 80 0 10 20 30 40 50 60 70 80
Time Time

10 10

5 5
Reactive Power [MVAR]

Reactive Power [MVAR]

0 0
-5 -5
-10 -10
-15 -15
-20 -20
-25 -25
-30 -30
0 10 20 30 40 50 60 70 80 0 10 20 30 40 50 60 70 80
Time Time 30
Detecting Control Abnormalities
After baseline is established, performance data can be used to detect
generator control abnormalities
Power
700
Unexpected action from
680

660 Stabilizer failure plant MW controller


640
Power
Active Power [MW]

550
620

600 540

580
530
560

Active Power [MW]


540 Observed 520
Expected
520
510
500
2 3 4 5 6 7 8 9 10
Time (sec) 500
50 Observed
490 Expected
Reactive Power (MVAR)

480
0 10 20 30 40 50 60 70 80 90 100
0 Time (sec)

-50
Abnormal runback in
reactive power
-100
0 5 10 15 20 25 30 35 40 45 50
Time (sec)
31
Wind Power Plant Model Verification
32
Wind Power Plant Model Verification
Wind power plant dynamic models are complex and not
well understood by utilities or plant operators
– 7 models, more than 130 parameters

Phased approach is adopted in WECC:


• First, develop, validate and stress-test “typical” data
sets for various wind generator make and models

• Second, plant-specific data is updated with actual


settings and validated against tests and disturbances

33
Wind Power Plant Model Validation Example

Input:
POI Voltage

Measure of success:
POI Reactive Power

Measure of success:
34.5-kV substation
voltage
Summary
Accurate models are required for reliable and economic power
system operations

Baseline model development is needed to establish the model


structure and initial data sets

Using disturbance data is an effective method of model


verification, disturbance play-in functions are available in all grid
simulators, tools for model and data management are mature and
available

Transmission planners are encouraged to use disturbance


monitoring for independent model verification and performance
monitoring – tools are available

Collaboration between TPs, GOs and OEMs is encouraged on


model verification and performance/disturbance monitoring 35
Thank You
Power Pla nt Model Verifica tion a nd Testing Workshop

“Ba seline” Testing


• Synchronous Genera tors
– OC Sa tura tion Tests
– Inertia Tests
– Impeda nces a nd Time Consta nts Verifica tion Tests
• Excita tions Systems (a nd PSS)
– Va r Rejection Tests
– OC or On-Line AVR Step Tests
– Frequency Response Tests
• Turbine Controls
– Speed Reference Step Tests

September 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

Gas Turbine and Steam


Turbine Modeling a nd Testing
Power Pla nt Model Verifica tion a nd Testing Workshop

September 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

September 2016
Governor Test via Load Reference Step
Load Reference Step Test Sequence
0.5
+0.4
0.4

0.3
TNR Change (%)

0.2

0.1 0.0
0.0 0.0 0.0
0.0

-0.1 -0.2
-0.2

-0.3 -0.4
-0.4

-0.5
00:00

01:00

02:00

03:00

04:00

05:00

06:00

07:00

08:00

09:00

10:00

11:00

12:00

13:00

14:00

15:00

16:00

17:00

18:00

19:00

20:00
Time (mm:ss)

September 2016
6

Februa ry 22013
013
Governor Test via Load Reference Step
CTG Governor Test via Loa d Reference Step

September 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

Sept. 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

Sept. 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

10

Sept. 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

Practicalities of
Genera tor a nd Excita tion
Testing
Power Pla nt Model Verifica tion a nd Testing Workshop

Examples of Unexpected Events


• Don’t ha ve signa ls you need
• Didn’t get the signa ls you expected
• Ca n’t opera te a s you would like

12

September 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

Don’t have the signals you need – only Ib

13

September 2016
Power Pla nt Model Verifica tion a nd Testing Workshop
Didn’t get the signals you expected

14

September 2016
Power Pla nt Model Verifica tion a nd Testing Workshop
Can’t operate as you would like

15

September 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

Before You Do The Test


Power Pla nt Model Verifica tion a nd Testing Workshop

Two Often-Overlooked Test Prepa ra tion Exa mples


• Rea ctive Ca pa bility Curve with limits a nd protection
• CT Pha se Ca libra tion

17

September 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

18

September 2016
Power Pla nt Model Verifica tion a nd Testing Workshop
CT Phase Errors
• P = f (cos) Q = f (sin)
• Therefore, Q more sensitive to CT pha se errors when
opera ting a t typica l power fa ctors.
Actual Measured Measurement Error
V (kV) I (kA) I Phase (deg) P (MW) Q(MVAR) pf CT Phase Error (deg) P (MW) Q(MVAR) P (MW) Q(MVAR)
18.000 5.556 0.0 100.00 0.00 1.00 2.4 99.91 4.19 -0.09 4.19
18.000 5.556 2.0 99.94 3.49 1.00 2.4 99.71 7.67 -0.23 4.18
18.000 5.556 4.0 99.76 6.98 1.00 2.4 99.38 11.15 -0.38 4.17
18.000 5.556 6.0 99.45 10.45 0.99 2.4 98.93 14.61 -0.52 4.16
18.000 5.556 8.0 99.03 13.92 0.99 2.4 98.36 18.05 -0.67 4.13
18.000 5.556 10.0 98.48 17.36 0.98 2.4 97.67 21.47 -0.81 4.11
18.000 5.556 12.0 97.81 20.79 0.98 2.4 96.86 24.87 -0.96 4.08
18.000 5.556 14.0 97.03 24.19 0.97 2.4 95.93 28.23 -1.10 4.04
18.000 5.556 16.0 96.13 27.56 0.96 2.4 94.89 31.56 -1.24 4.00
18.000 5.556 18.0 95.11 30.90 0.95 2.4 93.73 34.86 -1.38 3.96
18.000 5.556 20.0 93.97 34.20 0.94 2.4 92.45 38.11 -1.51 3.91
18.000 5.556 22.0 92.72 37.46 0.93 2.4 91.07 41.31 -1.65 3.85
18.000 5.556 24.0 91.35 40.67 0.91 2.4 89.57 44.46 -1.78 3.79
18.000 5.556 26.0 89.88 43.84 0.90 2.4 87.96 47.56 -1.91 3.73
18.000 5.556 28.0 88.29 46.95 0.88 2.4 86.25 50..6
50 60
50.60 -2
2.0
04
-2.04 3.66
66
66
3.66
18.000 5.556 30.0 86.60 50.00 0.87 2.4 84.43 53
5 3.58
58
53.58 -2
2.17
17
-2.17 3.58
58
3.58

19

Sept. 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

Online Voltage Reference Step Test


CTs with 0.8 degree pha se error

20

September 2016
Power Plant Model Verification and Testing Workshop

Experience in Testing –
A Consulta nts Perspective
Power Pla nt Model Verifica tion a nd Testing Workshop

Additional Requirements for Consultants


• Knowledge of ma ny different equipment types
• Efficient Project Execution
• Longevity

22
July 2013
Power Pla nt Model Verifica tion a nd Testing Workshop

23

September 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

24

September 2016
Power Pla nt Model Verifica tion a nd Testing Workshop

25

September 2016
Thank You!

Dan Leonard
GE Energy Consulting
daniel1.leonard@ge.com
518-385-0165
Power Plants
Overview
John Undrill

NERC Workshop
September 2016
Does the plant type (hydro/thermal) matter?

If the issue is grid voltage control -


Not very much

The voltage control capability and behavior of


a low speed hydro generator is very similar to
that of a 3600rpm generator

Excitation systems are different in detail but


similar and equivalent in function

Generator protection differs in detail but


not in function
Does the plant type (hydro/thermal) matter?

If the issue is frequency control -


Very much

Gas turbines can change real power output


very quickly initially but must be rate limited
outside a responsive band

Steam turbine plants can change real power


by a small amount very quickly but then must
be rate limited

Most hydro plants are somewhat slower off


the mark but can maneuver over a wide range
much more quickly than thermal plants
Does the plant type (wind) matter ?

If the issue is voltage control


Yes - of course
Generator types are evolving - some can exert
practical reactive power control - some cannot

Interconnection conditions typically require


primary control at the point of interconnection

The point of interconnection is typically more


remote from the generator than in hydro/thermal
plants

Reactive power control effort may be exerted


by device (eg Statcom) separate from the
turbine-generators
Does the plant type (wind) matter ?

If the issue is frequency control


Yes - of course
Generator types are evolving - some can exert
practical real power control - some cannot

Unlike hydro/thermal plants maneuvering


domain is variable due to uncontrollable
natural causes (mother nature)

Nevertheless - control of real power at


practically useful rates of change is
possible

Temperature change issues should be minimal

Other issues - perhaps aerodynamic stability - could turn out to be


significant as experience builds up
Does the plant type (photovoltaic) matter ?

If the issue is voltage control


Yes - of course

If the issue is frequency control


Yes - of course

Converter types are evolving - some can exert


practical real/reactive power control - some cannot

Operational issues associated with providing


primary and secondary control are largely
unknown at present - may arise on much
faster time scales than those of interest in
electromechanical plants
Why should we be deeply concerned about the modeling
of ‘old-tech’ hydro and thermal plants when the
new incoming plants are wind and solar ?

The sun does not shine at night


Even mariners do not fully understand how mother nature
programs the wind

When nature does not provide sun, wind, water -


we will have to burn fuel

Even with ‘rapid’ growth and penetration forecasts -

The control of the power system will depend on and be


strongly influenced by hydro and thermal machines for
most of the way to our present planning horizons
Synchronous Generators

(Ef d − vt )
Ii =
Xd
Ef d Vt sinδ
Pe =
Xd
Vt (Ef d − vt )
Qe =
Xd
Real three phase Idealized d-q axis
machine machine
Generator
characteristics

Magnetization curve

The open circuit


magnetization curve
sets the base for the
per unit representation
of the machine -
if it is wrong -
everything is wrong
Generator
characteristics

Capability curve
Generator
characteristics

Vee curve
Generator
model

Steady state
operation

Sets up initial
conditions for
dynamic
simulations
Generator
model

Dynamics

Standard
Maxwellian

Simple principle
Devilish details

Used in derived
form (via Park
transformation) in
simulations

Basis of genrou/
gentpj
Generator model

T(s) torque applied at coupling


w(s) rotational speed
Efd(s) voltage applied at field winding terminals
ifd(s) current at field winding terminals
v(s) voltage at stator winding terminals
i(s) current at stator winding terminals
Z(s) operational impedance
Power Plant Modeling Basics

Mark W. Baldwin PPMVT Workshop 09-20-2016


PPM Basics – Dominion Perspective
2

'RPLQLRQ¶V)RVVLODQG+\GUR)OHHW§JHQHUDWRUV

Fleet Resides in 3 NERC Regions:


1) SERC
2) RFC
3) NPCC

Operated by 2 RTO’s
1) PJM
2) ISO-NE
Presentation Summary
3

¾ Stability Planners – The Significance of


Stability Studies

¾ Instabilities Associated with Power Plants

¾ Power Plant Modeling Basics – Generating


Unit Natural Response
Transmission Stability Planners
4

¾ Run Studies to Identify System Instabilities –


disturbance tests

¾ Apply Corrective Action in Real Time


Operations

¾ Order Transmission System Upgrades


(Element Additions, Modifications) Years or
Decades Ahead Operations
Generating Unit Instabilities
5

A case of Voltage
Instability –
inadequate leading Adjacent
MVAR capability Bus Cold
Line Loads

230kV

UT SST

Generator
with UEL G
Adjacent Plant Loads
Generating Unit Instabilities
6

A case of Voltage
Instability –
inadequate leading
MVAR capability

UEL attempts to
drive MVARs
NORTH by
increasing field
current
Generating Unit Instabilities
7

Adjacent Bus
Cold Loads
MW’s
A case of Speed Unknown
Instability –
inadequate MW
capability 230kV

UT SST

12 MW
GTG
G
Adjacent Plant Loads
PPM Basics - Overview
8

Natural Response of Generating


Unit Must Be Captured in Order to
Analyze Stability

Energy Storage Media Must be


Modeled to Capture Generating
Unit Natural Response

Energy Storage Media is primarily


a) Flux
b) Rotating Mass
PPM Basics – Synchronous Machine
9

A synchronous machine
model captures effects of
both flux and kinetic energy

Flux effects are captured


in a suite of inductances
and field winding
characteristics

Kinetic effects are


captured in machine
speed and inertia But both the flux and speed drivers must be modeled:
a) Voltage regulator / exciter
b) Governor / turbine
Voltage Regulator / Exciter Models
10

Voltage Regulator DC Commutator Exciter


Feedback Signal

Operator Input Exciter Output


DC Exciter Signal Flow Diagram
Turbine/Governor Models
11

Feedback signal

governor
Fuel valve Turbine
Operator characteristic characteristic
input

Turbine/Governor Signal Flow Diagram


Turbine/Governor Models (cont’)
12

Load-based
temperature Exhaust
limit temperature

Turbine/Governor Signal Flow Diagram


Turbine/Governor Models (cont’)
13

Turbine
damping

Turbine/Governor Signal Flow Diagram


PPM Basics Summary
14
Current Modeling Practices
15

¾ Compensator (voltage) and PSS Models always


available but compensators are not included in one
RTO’s Approved Models List (AML)
¾ UEL and other limiter models are sometimes
available but no limiters are included in RTO AML
¾ Governor deadbands very frequently not modeled on
STG’s. One RTO has 11 approved T/G model types –
only one of the 11 features db.
¾ Fast-valve schemes, FB load controllers never
modeled (though PSS/E does have T/G model types
that feature fast-valve)
Reference Material
16

¾ IEEE Technical Report, PES-TR1, “Dynamic Models


for Turbine-Governors in Power System Studies,”
Power System Dynamic Performance Committee, et
al. January 2013
¾ IEEE Std 1110 IEEE-2002 (R2007), Guide for
Synchronous Generator Modeling Practices and
Applications in Power System Stability Analyses
¾ IEEE Std 421.5-2016, IEEE Recommended Practice
for Excitation System Models for Power System
Stability Studies
¾ PSS/E 33.3 Model Library (and associated manuals),
Siemens PTI, September 2012
PPM Basics
17

Questions
Modeling Improvements
Initiative Update
Mohamed Osman, NERC
Power Plant Model Verification and Testing Workshop
September 2016
Advanced Analytics

Goals:
ͻ Improve interconnection-wide models
ͻ Address modeling gaps
ͻ Develop modeling guidance
ͻ Understand changing grid characteristics
ͻ Increase industry awareness and expertise
ͻ Collaborate with entire utility industry
ͻ Engage with other industry groups

2 RELIABILITY | ACCOUNTABILITY
Case Quality Metrics Assessments

ͻ Case Quality: Reasonableness of the data for individual Element


models that comprise the powerflow and dynamics cases.
ƒ Powerflow Metrics: assessment of quality of powerflow base case as
developed by interconnection-wide case creation entities
ƒ Dynamics Metrics: assessment of quality of associated dynamics case –
component models
ͻ Assessments
ƒ Phase 1 (2015): Initial development of criteria and testing; main focus on
powerflow case
ƒ Phase 2 (2016): Re-assessment of Phase 1 metrics; additional metrics, focus
on dynamics
ƒ Phase 3 (2017): At a minimum, assessment of Phase 1 and 2 metrics on new
cases (trending); possible new metrics

3 RELIABILITY | ACCOUNTABILITY
Dynamics Metrics
Phases 1 and 2

Phase Dynamics
Phase 1 • Generator netting
(2015) • Generator classical model representation
• Consistence reactance values
Phase 2 • Generator inertia and time constants
(2016) • Saturation factors and “severe” factors
• Generator speed damping coefficient
• Turbine-governor time constants
• Turbine power development fractions
• GAST models
• DC exciter self-excitation parameters
• WT3E electrical wind speeds
4 RELIABILITY | ACCOUNTABILITY
Phase 2 Metrics Assessment
Observations

ͻ Generator Reactive Limits


ƒ All interconnections, units at Qlim
ͻ Generator Reactive Limits Power Factor
ƒ Unreasonable Qmax or Qmin based on Pmax
ͻ Generator Time Constants
ͻ Generator Inertia Constants
ƒ Units with very small inertia constant
ͻ Saturation Factors
ƒ Many units with saturation factors outside reasonable (and severe) ranges

5 RELIABILITY | ACCOUNTABILITY
Phase 2 Metrics Assessment
Observations

ͻ Speed Damping D
ƒ Non-classical gen models with non-zero damping value
ͻ Turbine-Governor Power Development Fractions
ƒ Units with governor model with fractions that do not add to 100%
ͻ GAST Model
ƒ NERC developing Modeling Notification for GAST; predominant in EI
ͻ Self-Excitation Parameter for DC Exciters
ƒ Many units with small positive rather than small negative value

6 RELIABILITY | ACCOUNTABILITY
Example Dynamic Data Results

Dynamics Metrics
Case SUM WIN SLL
Phase Metric Perf Score (%) Perf Score (%) Perf Score (%)
Gens without Models 142 / 3402 4.17 189 / 3347 5.65 153 / 3401 4.50
Netted Gens with Models 3 / 2616 0.11 14 / 2161 0.65 2 / 1892 0.11
Phase I Netted Generators 12 / 2616 0.46 22 / 2161 1.02 7 / 1892 0.37
Gens with Classical Models 3 / 4063 0.07 3 / 3985 0.08 3 / 4063 0.07
Inconsistent Reactances 110 / 3351 3.28 123 / 3359 3.66 110 / 3342 3.29
Inconsistent Time Constants 213 /3351 6.36 217 / 3359 6.46 213 / 3342 6.37
Unreasonable Inertia Constants 622 / 3354 18.55 622 / 3362 18.50 619 / 3345 18.51
Unreasonable Saturation Factors 1869 / 3351 55.77 1884 / 3359 56.09 1859 / 3342 55.63
Severe Saturation Factors 243 / 3351 7.25 255 / 3359 7.59 243 / 3342 7.27
PSS but no Excitation 18 / 1726 1.04 22 / 1711 1.29 12 / 1718 0.70
Phase II Inconsistent Speed Damping 313 / 3351 9.34 340 / 3359 10.12 312 / 3342 9.34
Inconsistent Lead-Lag Time Const 24 / 1444 1.66 34 / 1454 2.34 24 / 1430 1.68
Erroneous Power Dev Fractions 21 / 224 9.38 21 / 238 8.82 21 / 224 9.38
GAST Models 30 / 2337 1.28 31 / 2319 1.34 30 / 2322 1.29
DC Exciter Self-Excitation Errors 52 / 665 7.82 52 / 696 7.47 52 / 662 7.85
Inconsistent Type III Wind Speeds 1 / 102 0.98 1 / 77 1.30 1 / 103 0.97

7 RELIABILITY | ACCOUNTABILITY
Appendix Materials
Supporting Industry based on Findings
1.4

1.2

0.8

0.6

0.4

Exponential Characteristic
0.2
Quadratic Characteristic

• Tool developed by the USACE for


Unsaturated Characteristic

0
0 0.5 1 1.5 2 2.5 3

L I
ad fd

fitting open circuit and V-curve


test data for GENTPJ model
• Posted to NERC SAMS page (HERE)
with instruction manual (HERE).

8 RELIABILITY | ACCOUNTABILITY
MOD-032 Feedback Loop

MOD-032
Case Quality
Designee
Assessment
Review

Updated
New Base
Model
Cases
Checks

Coordinate
w/ Entities
9 RELIABILITY | ACCOUNTABILITY
Plant Level Controls and Protection
Modeling Improvements

ͻ Ensure models sufficient to recreate plant behavior; explore


known/historical events and required modeling improvements to
represent beforehand and post-mortem.
ƒ Identify modeling gaps and possible new models to address gaps
ƒ Plant-level, turbine, and boiler controls and protection
ƒ Short- and mid-term post-disturbance behavior

10 RELIABILITY | ACCOUNTABILITY
Modeling Notifications

ͻ Notifications posted HERE


ͻ Proactively address modeling
issues used across industry

Engineering Develop Feedback Notify


Identify Problems
Analysis Guidance with SMEs Industry

11 RELIABILITY | ACCOUNTABILITY
Case Fidelity

12 RELIABILITY | ACCOUNTABILITY
Renewable Energy Modeling

ͻ Growing penetration of renewables across North America


ͻ Growing importance for accurate and robust modeling
ͻ Clear outcome and next step of NERC ERSWG and DERTF
ͻ Need concerted focus industry-wide on renewable models
ͻ Share and develop modeling practices
ͻ Educate system planners on renewables models available
ͻ Ensure uniform robust implementations
ͻ Tackle new or updated renewables modeling techniques
ͻ Understand impacts and concerns with renewables in weak grids

13 RELIABILITY | ACCOUNTABILITY
Plant Modeling Focuses

ͻ Non-uniform software implementation issues


ͻ Frequency response and ‘baseload flag’ implementation
ͻ Auxiliary equipment limit modeling
ͻ Phasing out of obsolete models
ͻ Improvements in case fidelity

14 RELIABILITY | ACCOUNTABILITY
Where Can We Help?

15 RELIABILITY | ACCOUNTABILITY
16 RELIABILITY | ACCOUNTABILITY
Disturbance-Based PPMV

Ryan D. Quint, NERC


Power Plant Model Verification and Testing Workshop
September 2016
MOD Standards Drivers

ͻ Disturbance-based model verification is one method to verify


models used for planning and operating the BPS
ƒ Not a required practice; rather an alternative method
ƒ May be an effective means of compliance with MOD standards,
depending on circumstances

ͻ MOD-026-1 language, for example:


ƒ …“model response matches the recorded response…from either a
staged test or a measured system disturbance”
ƒ …“modeled response did not match the recorded response to a
transmission system event”
ƒ …“following receipt of a technically justified unit request” from the TP…
o Technical justification: …“demonstrating that the simulated unit or plant
response does not match the measured unit or plant response.”

2 RELIABILITY | ACCOUNTABILITY
Disturbance-Based PPMV Overview

3 RELIABILITY | ACCOUNTABILITY
Data Recording Locations

4 RELIABILITY | ACCOUNTABILITY
PPMV Playback Model

ͻ Major software vendors now have “playback model”


ͻ Injects voltage and frequency (or angle) into simulation
ͻ Separates tested model from rest of system at point of
measurement

5 RELIABILITY | ACCOUNTABILITY
Disturbance-Based
Verification Comparison

PLAY-IN DATA (INPUTS)

MEASURES OF SUCCESS (OUTPUTS)

6 RELIABILITY | ACCOUNTABILITY
Disturbance-Based PPMV Process

1. System Disturbance Measurements

2. Steady-State Case Creation

3. Dynamics Case Creation

4. Transient Stability Simulation

5. Model vs. Actual Comparison

7 RELIABILITY | ACCOUNTABILITY
Independent Verification

ͻ Which data is correct? Turns out neither were correct…


ͻ “1 good measurement is worth 1000 expert opinions”

8 RELIABILITY | ACCOUNTABILITY
What a Good Model Looks Like

ͻ Approximates general shape of response very well


ͻ Minor differences between events

9 RELIABILITY | ACCOUNTABILITY
What a Bad Model Looks Like

ͻ Does not approximate general shape of response well


ͻ Substantial differences in comparison (between events)

10 RELIABILITY | ACCOUNTABILITY
Verification vs. Calibration

ͻ Verification: yes/no check on response of model vs. actual


ƒ Effective means for ensuring modeled response approximates actual
ƒ Proven to identify plant issues such as controller failure or mode of
operation different than modeled
ƒ Should be used over multiple events

vs.
ͻ Calibration: tuning model to match measured response
ƒ Needs to be supervised by engineering judgment
ƒ Requires very good understanding of plant behavior and baseline model
ƒ Should not be used to replace baseline testing
ƒ Should not solely rely upon numerical curve fitting techniques

11 RELIABILITY | ACCOUNTABILITY
Beyond Standards:
Performance Monitoring

12 RELIABILITY | ACCOUNTABILITY
Reliability Guideline:
PPMV using PMUs

ͻ Guideline approved by NERC


Planning Committee Sept 2016
ͻ Overview of mechanics and
considerations for performing
disturbance-based verification
ͻ Appendix of available playback
model and tools
ͻ First step in supporting industry
with model verification

13 RELIABILITY | ACCOUNTABILITY
14 RELIABILITY | ACCOUNTABILITY
Workshop Objectives

Ryan D. Quint, NERC


Power Plant Model Verification and Testing Workshop
September 2016
Workshop Objectives

ͻ Bring together array of industry expertise


ͻ Understanding plant dynamic behavior, modeling, and controls
ͻ Baseline testing procedures
ͻ Operational limitations
ͻ Manufacturing perspective
ͻ Utility experience
ͻ Industry tools and practices
ͻ Technical considerations for MOD-025, -026, and -027
ͻ Reliability benefits of accurate modeling
ͻ Path forward and next steps

2 RELIABILITY | ACCOUNTABILITY
3 RELIABILITY | ACCOUNTABILITY
Key Takeaways and
Next Steps
Ryan D. Quint, NERC
Power Plant Model Verification and Testing Workshop
September 2016
Key Takeaways

ͻ Modeling
ƒ Accurate modeling critical for reliable operation and planning of the bulk
power system
ƒ Power plant controls and technologies are evolving and the models need
to reflect these changes accordingly
ƒ Plant-level controls can and should be modeled, as appropriate, if they
affect the unit in the dynamics timeframe
ƒ Accurate models essential for reliable and economic operation of the
bulk power system
ͻ Model Verification
ƒ Generator testing programs have benefits beyond standards compliance
ƒ Sustained model verification proven beneficial for GOs and TPs
ƒ “Baseline testing” needs to be defined and/or used appropriately
o Development of a baseline model via test and/or calculation is essential

2 RELIABILITY | ACCOUNTABILITY
Key Takeaways

ͻ Model Verification (cont.)


ƒ Reverification of that baseline model can be either by additional testing
or measurement-based approaches
ƒ Planners should require sufficient, clear, and comprehensive reports of
the development of a baseline model and/or reverification – “trust but
verify”
ƒ Technical challenges with MOD standards that should be addressed from
engineering standpoint – lessons learned, examples, guidance, etc.
ͻ Disturbance-Based PPMV
ƒ Reliability Guideline developed and approved by NERC PC
ƒ Used as a yes-no verification step of power plant model performance
ƒ Collaboration and coordination between T and G has proved very
effective
ƒ Proving effective for renewable models as well, more focus needed from
wind and solar
3 RELIABILITY | ACCOUNTABILITY
Key Takeaways

ͻ Plant Performance
ƒ Boiler and turbine controls/interactions should be considered in more
detail to determine an appropriate level of modeling, as applicable
ƒ Frequency response and adequate modeling of FR a continued concern
with continued NERC focus
ƒ Plant-level controls should not interfere with sustained primary
response of governor and excitation systems
ͻ Transmission Planning and Operations Perspective
ƒ Auxiliary protection and performance needs to be better understood by
the planners in system studies – understand vulnerabilities of ride-
through limitations
ƒ System operators can and have limited or shut off units if models are
inadequate to represent reality – need representative models for
reliability

4 RELIABILITY | ACCOUNTABILITY
Potential Next Steps

ͻ Develop standards guidance material for developing and


verification of models as per MOD standards
ͻ Task force focusing on model verification (testing) and
generator capability
ͻ Regional workshops on verification and testing for related MOD
standards
ͻ Coordinate more closely with manufacturing industry – create
forum for open bi-directional engineering discussion
ͻ Focus areas:
ƒ Plant auxiliary limitation modeling
ƒ Removal of obsolete/non-representative models
ƒ Case quality correction – saturation, model parameters, limits, etc.

5 RELIABILITY | ACCOUNTABILITY
Logistics

ͻ Survey to workshop participants


ƒ Workshop delivery & material
ƒ Technical comments/considerations that NERC should look into
ͻ Materials will be posted shortly to NERC website
ƒ Will send email to participants with link and list of registrants – contact
information redacted

6 RELIABILITY | ACCOUNTABILITY
7 RELIABILITY | ACCOUNTABILITY
Overview of EPRI
PPPD Tool
Anish Gaikwad
agaikwad@epri.com
Pouyan Pourbeik
ppourbeik@peace-pllc.com
NERC Workshop
September 2016

© 2016 Electric Power Research Institute, Inc. All rights reserved.


BACKGROUND ON PPPD
ƒ 2007 EPRI started a fresh approach to R&D on power plant
model validation – not based on any previous R&D

ƒ 2007 – developed first proto-type of the Power Plant


Parameter Derivation (PPPD) tool, for automating model
parameter derivation based on staged testing

ƒ 2008 to 2009 – extended in a novel way, to allow the use of


on-line data (either disturbance data or on-line step tests)

ƒ Since 2010 EPRI has supported the tool through a User’s


Group, which current has 31 members (utilities, ISOs, etc.) –
3 are international members
2
© 2016 Electric Power Research Institute, Inc. All rights reserved.
PPPD CAPABILITIES & FUNCTIONALITY
ƒ Power Plant Parameters Derivation (PPPD) is a stand alone
executable software tool

ƒ Licensed through the EPRI Modeling and Model Validation


Tools User’s Group (MMVTUG)

ƒ The tool allows user’s to validated generator, exciter and


turbine-governor models using either:
– Measured field testing data (e.g. off-line tests)
– On-line voltage regulator (and turbine-governor speed-ref) step tests
– Digitally recorded disturbance data during system disturbances
while unit is on-line (e.g. from PMU or DFR)

3
© 2016 Electric Power Research Institute, Inc. All rights reserved.
HOW IT IS APPLIED
ƒ The novel aspect is the ability to use on-line disturbance
data for model validation
ƒ It can also be used to process data collected during
“emulated disturbances”, e.g. on-line voltage regulator step
tests, digital turbine-governor speed-reference step tests

Grid Disturbance Measured

Vt (pu)
0.96 Fitted

0.95
0 20 40 60 80 100 120

PMU/DFR

Ifd (pu)
2

at Plant 1.95
0 20 40 60 80 100 120
2.1

Vfd (pu)
2

1.9
0 20 40 60 80 100 120
Time (seconds)

4
© 2016 Electric Power Research Institute, Inc. All rights reserved.
DATA RECORDING AND CAPTURE
A B C

Three phase generator


stator voltages from
secondary of PTs

PT Two (or three) generator stator currents from


secondary of CTs
CT

Digital Fault
Generator Recorder
(can be a
dedicated DF or
an inbuilt DFR in
Field current measured
exciter)
Field across the field shunt
Winding

Digital Fault Recorder


(DFR)

HV GSU (from PMU or DFR)


Excitation System

Field voltage measured


From excitation system output

5
© 2016 Electric Power Research Institute, Inc. All rights reserved.
VALIDATION PROCESS
Collect Disturbance
Data from DFR

PPPD Scale data into per


unit format and
import into software
tool

Automated Software Tool

Adjust parameters Simulate event


based on non-linear
recursive least-
square algorithm
Compare simulated
No and measured data.
Do they adequately
match?

Yes

Finished

6
© 2016 Electric Power Research Institute, Inc. All rights reserved.
KEY BENEFITS OF PPPD
ƒ Many practical aspects of generator model validation (based
on over a decade of experience in generator testing) are
built into the tools functionality

ƒ Can be used with both on-line and off-line data

ƒ Simple to learn and use, with GUI

ƒ IEEE standard exciter models built-in; outputs in GE PSLFTM


and Siemens PTI PSS®E format

ƒ User’s group to share experience and learning

7
© 2016 Electric Power Research Institute, Inc. All rights reserved.
EXCITER/GENERATOR RESPONSE
On-line, disturbance monitoring

On-line, full-load, step test

8
© 2016 Electric Power Research Institute, Inc. All rights reserved.
EXCITER/GENERATOR RESPONSE
(NO GENERATOR FIELD DATA)
0.99

0.98

0.97
Voltage (pu)

0.96

0.95
Measured
0.94 Optimized Fit
Initial Estimate
0.93
0 10 20 30 40 50 60
Time (seconds)

9
© 2016 Electric Power Research Institute, Inc. All rights reserved.
GOVERNOR RESPONSE

Gas Turbine Response fit


with GGOV1 using PPPD
105
Measured
Fitted
100

95
P (MW)

90

85

80

75
0 50 100 150 200 250
Time (seconds)

10
© 2016 Electric Power Research Institute, Inc. All rights reserved.
GOVERNOR RESPONSE
Large steam-turbine

11
© 2016 Electric Power Research Institute, Inc. All rights reserved.
EXPERIENCE WITH PPPD
ƒ User’s Group since 2010
ƒ Presently 31 group members (utilities, ISOs, GOs) – 3 are
international
ƒ Amongst the members well over 100 synchronous
generators validated (generator + exciter)
ƒ In the past couple of years UG members have started
working on turbine-governor model validation and tens of
units validated
ƒ Applied both using on-line disturbance monitoring (DFR or
PMU) and on-line step-tests
ƒ Applied in WECC, ERCOT and EI

12
© 2016 Electric Power Research Institute, Inc. All rights reserved.
CONTINUED WORK
ƒ The tool is constantly updated – in 2016 Version 9.0 will be
released

ƒ Updates to PPPD in 2016 include:


– Addition of wind and PV “generic” models (previously EPRI REMV)
– Addition of static var system “generic” models (previously EPRI
SVSMV)

13
© 2016 Electric Power Research Institute, Inc. All rights reserved.
REMV TOOL – WILL BE PART OF PPPD
IN VERSION 9.0

So far applied to dozens of WTGs and a few PVs


Also, applied to two Wind Power Plants
14
© 2016 Electric Power Research Institute, Inc. All rights reserved.
SVSMV TOOL – WILL BE PART OF
PPPD IN VERSION 9.0

PMU
Vt Vt‘I
It It‘T

SVS

Over half a dozen SVCs/STATCOMs validated

15
© 2016 Electric Power Research Institute, Inc. All rights reserved.
OTHER TOOLS
ƒ The MMVTUG includes also load modeling tools, which are
outside the scope of the current discussion

ƒ EPRI LMPD – allows to estimation of load parameters for the


composite load model using disturbance data

ƒ EPRI LCET – allows for creation of composite load model


data cards based on climate and demographics data, etc.

16
© 2016 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity

17
© 2016 Electric Power Research Institute, Inc. All rights reserved.
Generator Baseline Testing
Instrumentation and Steady State Calculations

Greg Brooks
US Army Corps of Engineers
Walla Walla District
NERC Power Plant Model Verification and Testing Workshop
September 21, 2016

US Army Corps of Engineers


BUILDING STRONG®
Agenda

ƒ Data Collection

ƒ Generator Steady State Test Procedures


and Parameter Fitting

BUILDING STRONG®
Data Collection

BUILDING STRONG®
Measurement Points

CT IT
PT
VT
Field

Vfd
Stator

Ifd

Turbine Gate Position


Blade Angle (Kaplan)

BUILDING STRONG®
General Considerations
ƒ Use calibrated transducers
Ź The meters may not be
ƒ Your test gear is the cheap part
Ź Minimize setup time
• Good connectors (don’t wire your gear in the field)
• Labeling and color coding
• Use good cable management
Ź Have a bulletproof, efficient calibration and
signal check procedure
BUILDING STRONG®
Noise Mitigation
ƒ Shielded Twisted pairs
Ź Reduces EMI
ƒ Keep unshielded leads short and twisted
ƒ Use balanced differential signals

BUILDING STRONG®
Stator Values Transducers
ƒ VT – Use a little transformer
Ź Scales and Isolates
ƒ IT - Passive Clamps
Ź No batteries
Ź Contribute some phase shift
• Correct with linear interpolation
• Park Transformation
• Find the power angle, add the correction, then
recalculate P and Q using S and the new power
angle
BUILDING STRONG®
Field Values
ƒ Avoid clearance issues in the exciter
Ź Measure at the meters or slip rigs
ƒ Use adequate isolation transducers
ŹVERY IMPORTANT!

BUILDING STRONG®
Transducer Calibration
ƒ Be calibrated, the meters on the board
may not be.
ƒ Voltage drop when ifd isn’t measured
directly at the shunt
Ź Use an analog meter and don’t lift any leads
RC

A Vm, Rm Shunt

RA

BUILDING STRONG®
Governor Values
ƒ Gate and Blade (Kaplan)
Ź Auxiliary outputs from digital governors
• Be careful of voltage references!
Ź Linear string transducers

BUILDING STRONG®
Data Acquisition
ƒ Sample Rate: 2 kHz
ƒ Simultaneous or Sequential
Ź The closer the better
ƒ Differential inputs reject common mode
noise
ƒ 16 Bit is sufficient
ƒ Real time data

BUILDING STRONG®
Essential Requirements
ƒ Acquisition Hardware
ƒ Acquisition Software
ƒ Data Processing Software
ƒ Simulation Software
ƒ 6 hours of time on the unit at varying
operating points
ƒ Lots of time back in the office

BUILDING STRONG®
Generator Steady State Test
Procedures
&
Parameter Fitting

BUILDING STRONG®
Generator Model
GENTPJ

BUILDING STRONG®
Steady State Parameters
GENTPJ

ƒ ifdo - air gap line field current at 1.0 p.u. VT


ƒ S1.0 - open circuit magnetic saturation factor at 1.0 p.u. VT
ƒ S1.2 - open circuit magnetic saturation factor at 1.2 p.u. VT
ƒ Xd - D axis synchronous reactance, pu
ƒ Xq - Q axis synchronous reactance, pu
ƒ Xl - stator leakage reactance, pu
ƒ kis - stator current saturation factor

BUILDING STRONG®
Open Circuit Saturation Curve
1.2

ƒ Duration - 20 minutes

Terminal Voltage, per unit


1

0.8

ƒ Purpose 0.6

0.4

Ź Estimate ifdo, S1.0, S1.2 0.2

ƒ Hazards
0
0 200 400 600 800
Field Current (Amps)

Ź Stationservice voltage limits (if connected)


Ź Extended time at low VT
Ź Exceeding maximum VT

BUILDING STRONG®
Open Circuit Saturation Curve
Procedure
ƒ Generator Status: offline at rated speed
ƒ Manually adjust VT in steps
Ź Only adjust in one direction until extreme is reached
ƒ Example
Ź From 14.8 kV down to 8 kV, then up to 14.8 kV
Ź Use 200 V steps waiting for 5 seconds between
ƒ Record VT and ifd

BUILDING STRONG®
Open Circuit Saturation Curve
1.2

ifdo
1
Terminal Voltage, per unit

Hysteresis
0.8

0.6
Measured

Air Gap Line

Saturation Curve
0.4

Parameters: ifdo, S1.0, S1.2


0.2

0
0 100 200 300 400 500 600 700 800 900

Field Current (Amps)

BUILDING STRONG®
Open Circuit Saturation Curve
1.4

Steps
1.2 1) Estimate ifdo ifd1.2 itest1.2
2) Saturation Factors
Terminal Voltage, per unit

1 ifdo itest1.0

0.8
_1.0=( _ 1.0 _ 1.0)/ _ 1.0

_1.2=( _ 1.2 _ 1.2)/ _ 1.2


0.6

0.4

0.2

Air Gap Line Saturation Curve

0
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 2.4

Field Current, per unit

BUILDING STRONG®
Open Circuit Saturation Curve
Quadratic Model

. .
.
ƒ = =
. .

ƒ < =
ƒ
Ź = 1+
ƒ Vary parameters in blue to find best fit

BUILDING STRONG®
V-Curve & Reactive Limits
0.6

0.5

Reactive Power, per unit


0.4
ƒ Duration - 60 minutes 0.3

ƒ Purpose 0.2

Ź Estimate Xd, Xq, Xl, Kis 0.1

Ź Verify reactive limits 0


0 0.5 1 1.5 2 2.5
Field Current, per unit
ƒ Hazards
Ź Motoring
Ź System conditions put limits beyond safe operation
• Excessive VT, IT, or ifd
• ifd below 1/3 of ifd at 0 VAR, and MW at test

BUILDING STRONG®
V-Curve & Reactive Limits
Procedure
ƒ Perform at +0, 70%, and 90% MW
ƒ Start at 0 MVAR
ƒ Slowly lower MVARs toward lower limit
Ź Stop at reactive limit or discomfort
ƒ Slowly raise MVARs toward upper limit
Ź Stop at reactive limit or discomfort
ƒ Slowly lower MVARs to 0 MVAR
ƒ Adjust MW and repeat

BUILDING STRONG®
Generator Capability Curve
V-Curve & Reactive Limit Test

0.8

Reactive Power, Per Unit

0.3

Stator Heating Limit


Active Power, Per Unit
Overexcitation Limiter
0.0 0.2 0.4 0.6 0.8 1.0 1.2
Underexcitation Limiter
-0.2
+0% Power Test

70% Power Test

90% Power Test

-0.7

-1.2

BUILDING STRONG®
V-Curve
0.6

Parameters: S1.0, S1.2, Xd, Xq, Xl, kis


0.5
Absolute eactive Power, per unit

0.4

0.3

Measured P=0%

0.2 Measured p=70%

Measured P=90%

Model
0.1

0
0 0.5 1 1.5 2 2.5
Field Current, per unit

BUILDING STRONG®
Automatic Curve Fitting
ƒ Never a substitute for engineering
ƒ Gets you close very quickly
ƒ Starting point
Ź Factory Specifications
Ź Prior test data
Ź Pay attention to the per unit base

BUILDING STRONG®
Starting Point
Manually Find ifdo
Manually Find ifdo
Manually Find ifdo
Manually Find ifdo
Manually Find ifdo
Manually Find S1.0
Manually Find S1.0
Manually Find S1.0
Manually Find S1.0
Automatically Solve
Use the Solver For the Rest
Questions?

BUILDING STRONG®
Generator model
Generator model - genrou
Generator model - gentpj
Generator models - genrou gentpj

Different ancestry
genrou
- used at GE
- descended from - gensal
- analog computer modeling

gentpj
- used at Westinghouse
- probably originated in digital form
Generator models - genrou gentpj

Different assumptions in deriving useable digital models


from the basic Maxwellian starting point (several slides ago)

Both use open circuit magentization curve as the basis for representing
saturation throughout the structure

Use different approaches to recognizing effect of saturation

Differing assumptions regarding behavior of currents in rotor circuits

genrou assumes sudden change in stator current


affects ‘both’ rotor circuits instantaneously

gentpj assumes sudden change in stator current


affects only ‘surface’ rotor body circuit
instantaneously - with delay in effect on field/deep
rotor body circuit
Generator models - genrou gentpj

genrou and gentpj are both approximations

They use different assumptions and result in slightly different approximations

Stator current affects magnetic saturation in two distinct ways


a) it modifies the ‘marco’ spatial distribution of flux around the
machine
b) it modifies the ‘micro’, spatial distribution of flux density in
the stator teeth

genrou and gentpj with Kis=0 both recognize effect a)


gentpj with Kis>0 has been introduced to provide approximate
representation of effect b)

genrou and gentpj are far from the only possibilities for generator modeling
in fact, I prefer and a different model for much of my own work
Generator models - genrou gentpj

Stator current affects magnetic saturation in two distinct ways


a) it modifies the ‘marco’ spatial distribution of flux around the machine
b) it modifies the ‘micro’, spatial distribution of flux density in the stator teeth

genrou and gentpj with Kis=0 both recognize effect a)


gentpj with Kis>0 has been introduced to provide approximate
representation of effect b)
Generator models - genrou gentpj
Generator models - genrou gentpj
Generator models - genrou gentpj
Generator models - genrou gentpj
1 1

2vbus1
1vt1
0.95 0.95

0.9 0.9
0 5 10 15 20 0 5 10 15 20

180 100

160 80

1pg1

1qg1
140 60

120 40
0 5 10 15 20 0 5 10 15 20

6 3.5

5
3
1efd1

1if1
4
2.5
3

2 2
0 5 10 15 20 0 5 10 15 20

3 2

1.5
2
1elmv1

1elmt1
1
1
0.5

0 0
0 5 10 15 20 0 5 10 15 20
Time, sec Time, sec

junkf.cha / junkj.cha
Generator develops synchronizing and
damping torques
Generator develops synchronizing and
damping torques

5 5

4 4

3 3
Ks(f)

Ks(f)
2 2

1 1

0 0
10 -3 10 -2 10 -1 10 0 10 1 10 2 10 -3 10 -2 10 -1 10 0 10 1 10 2

1.4 0.5

1.2
0.4
1

0.8 0.3
Kd(f)

Kd(f)
0.6 0.2
0.4
0.1
0.2

0 0
-3 -2 -1 0 1 2
10 10 10 10 10 10 10 -3 10 -2 10 -1 10 0 10 1 10 2
Frequency, Hz Frequency, Hz

Strong network connection Weak network connection


We do care about damping !!!
Generator Low Voltage
Ride-Through

NERC Power Plant Model Verification and Testing


September 20-21, 2016

Robert J. O’Keefe
American Electric Power
22
TPL-001-4 R3.3.1.1 & R4.3.1.2 – Generator Low
Voltage Tripping

“Tripping of generators where simulations show


generator bus voltages or high side of the GSU
voltages are less than known or assumed generator
low voltage ride through capability. Include in the
assessment any assumptions made.”
33

Voltage PRC-024-2 Attachment 2


44
TPL-001-4 R3.3.1.1 & R4.3.1.2 – Generator Low
Voltage Tripping

If PRC-024-1 R2 & Attachment 2 applies to generator


voltage tripping relays only (Might perhaps be better titled “Generator Voltage
Relay Setting Curve”)…

What about other possible mechanisms of generator low


voltage tripping?
Specifically, drop out of critical plant aux equipment?

Auxiliary bus UV protection & equipment contactor drop out are the UV
tripping mechanisms identified by AEP Generation
55
TPL-001-4 R3.3.1.1 & R4.3.1.2 – Generator Low
Voltage Tripping

PRC-024 SDT retreated from comprehensive voltage ride-


through applicability and dealt exclusively with generator relay
settings that affect voltage ride-through

Left unaddressed are voltage ride-through questions related


especially to plant auxiliary equipment essential to unit
operation, or required by environmental regulations for unit
operation
66
TPL-001-4 R3.3.1.1 & R4.3.1.2 – Generator Low
Voltage Tripping

AEP Generation Remarks:

“Addressing PRC-024-1 for the generators alone is a massive task; adding the auxiliary
equipment would require an implementation plan years longer than what is approved”

“There is no definitive standard or guide in industry regarding contactor drop out,


however, 82% is a reasonable estimate based on Generation experience”

“There is not a great deal of certainty around when units will trip. I expect that all units
will be different”

“Testing for ride through was perceived to be quite difficult which is why the drafting
team, urged by industry comment, did not require it. Some additional measures were
added into the [PRC-024] standard at one point but had to be taken back out due to
industry push back”
77
TPL-001-4 R3.3.1.1 & R4.3.1.2 – Generator Low
Voltage Tripping

Good generating plant design provides for supply of


critical plant loads from generator bus, NOT THE
SWITCHYARD OR HIGH SIDE OF GSU!

If that is the case, may be rare that auxiliary equipment


trip voltage would be reached outside of close-in faults
88
Challenges In Determining Generator Ride-
Through In Extreme Event Scenarios

• Wide differences in generating unit performance / Incomplete data

• Auxiliary bus UV protection:

• UV settings, time delays, whether a unit even has auxiliary bus protection vary widely
• Known UV settings at or below 72 percent
• Time delays vary between instantaneous to 10 seconds or more

• Contactor dropout of critical generating unit auxiliary equipment

• UV level below which AEP Generation experience says contactor dropout may be
expected: 82 percent
• No standard on contactor dropout

My Interim TPL recommendation: 85 percent at generator terminals


exceeding normal fault clearing duration
99

Sample Events

Following are plots of generator bus voltage (low side of GSU) from
stable delayed clearing fault scenarios (754 Data Survey) and FIDVR
events

What may be concluded about generator


ride-through in these instances?
10 10

Will it Trip?

1.2
Per Unit Voltage

Time
Scale:

0 – 2.5
seconds

.20
11 11

Will it Trip?
12 12

Will it Trip?
13 13

Will it Trip?
14 14

Will it Trip?
15 15

Will it Trip?
16 16

Will it Trip?
17 17

Will it Trip?
18 18

Will it Trip?
19 19

Will it Trip?
20 20

Will it Trip?
21 21

Will it Trip?
22 22

Will it Trip?
23 23

Will it Trip?
24 24

Will it Trip?
25 25

Will it Trip?
26 26

Will it Trip?
27 27

Will it Trip?

Such cases not commonly encountered in


normal course of planning or operations…

Yet TPs still need clear indication on ride-


through capability of generating resources
28 28

TPL-001-4 R4.5 – Simulation of extreme events

“If the analysis concludes there is Cascading


caused by the occurrence of extreme events, an
evaluation of possible actions designed to reduce
the likelihood or mitigate the consequences of the
event(s) shall be conducted.”
29 29
What are some practical steps to
minimize the uncertainty?

ͻ Guideline on sourcing critical plant auxiliary


equipment to harden against LV events?
ͻ Guideline on plant auxiliary LV ride-through
correlated to transient stability?

ͻ Existing generation
ͻ New generation
30 30

HOW DO WE BETTER
DEFINE / PREDICT
CONVENTIONAL PLANT LV
RIDE-THROUGH WITHOUT
IMPOSING EXCESSIVE
BURDEN ON GENERATORS?

Thank you!
Power Plant Modeling
Generator Control Systems
Shawn Patterson
Bureau of Reclamation
NERC Power Plant Model Verification and Testing Workshop
September 20, 2016
Simplified Generator

Field Winding
Stator

N
+

DC Voltage (from exciter)

S -

Rotor
Excitation Control System
Portion included in exciter models
Manual
Control DC
Field Current 3 phase
AC voltage

Exciter
(DC
Voltage Generator
Source)

Terminal
Raise/ Automatic Voltage
Lower Voltage Feedback
Command Regulator
Reference
Adjuster
Voltage Regulators Use
Feedback Control

Difference between
Desired and Actual
Output

AVR Exciter + Generator Generator Terminal Voltage


Desired
Output Output
+ System to be
Controller
controlled

Feedback
Rotating DC Exciters - Older Systems
Non-continuously acting voltage regulator

AVR
Changes resistance

Field
Pilot
Exciter
PE Rheostat EXC
GEN
(Exciter for
Main Exciter) Main Exciter
Exciter Field Main (Generator) Field
Feedback
Rotating (DC) Exciter

Setpoint

Block Diagrams,
Transfer Functions,
B Laplace Transforms Saturation
Magnetic Amplifier Systems

Manual Control

Field
Rheostat EXC
GEN
Amplidyne
(or Mag Amp)

AVR

Induction Motor PMG Amplidyne


SCR Pilot Exciters

Static Pilot Exciter

From
Station
Service
EXC
GEN
or
Generator
Terminals

Rotating main exciter


Amplification Stage

Controller Options

At least 4 model options to choose from


Rotating AC Exciters
Rectifier may be stationary or rotating,
controlled or uncontrolled

DC
Source EXC
GEN
If controlled here, Direct control of main
slower response field here (faster)

AVR
AC Rotating Exciter with Rectifier
At least 12 model options to choose from
Static Systems

Static Exciter (SCR Bridge)

Rectifier Bridge
Supplied by
Main Generator
Terminals or
GEN
Other AC Power
Source

AVR
Limiter Input Options

PSS Input
Q
MACHINE CAPABILITY

Overexcitation Limiter

MVAR
out Stator
Heating Limit
P

MVAR
in

Underexcitation Limiter
Overexcitation Limiter
Stability Control

Response

Timing
Underexcitation Limiter

Activation Stability Control


Reactive Current Compensation

G Allows
VAR
sharing
between
G parallel
generators

Vc = Vt+jXcIt

Voltage Droop
Power System Stabilizer

Most models are entirely digital,


i.e., all model parameters
determined by settings file

Analog systems have a simpler model


Governors Use
Feedback Control

Difference between
Desired and Actual
Output
Gate/Valve
Opening

Governor Prime Mover - Generator Frequency (Power)


Desired
Output Output
+ System to be
Controller
controlled

Feedback
Mechanical Governor
Gate Motion

Controller Hydro
Mechanical Governor

Valve Motion

Steam
Electro – Hydraulic Governor

Electronics
(analog or digital)

Hydro
Hydraulics
Prime Mover

Water Flow to Mechanical Torque

Hydro
Prime Mover
Steam Pressure to Mechanical Torque

Valve position

Optional Controller(s)

Steam
Complex Control Systems

Gas Turbine
Outer Loop Control Systems

Speed Governor

Speed (System Frequency) Power increase raises


Deviation frequency
Speed Adjust
+
Governor Turbine Power

Other Setpoints Power Setpoint


Load, Temperature,
Etc., Controllers
Generic Model
For Steam or
Gas Turbines
Unresponsive Governor Model
References
• IEEE Standard 421.5-2016, IEEE Recommended
Practice for Excitation System Models for Power
System Stability Studies
• IEEE PES Technical Report PES-TR1, Dynamic Models
for Turbine-Governors in Power System Studies,
January 2013
Primary Frequency Response Initiative
NERC Power Plant Model Verification and
Testing
Troy Blalock
NERC RS Chairman
September 21, 2016
Why Primary Frequency
Response Is Important

ͻ Essential for Reliability of the Interconnections


ƒ Cornerstone for system stability
ƒ Line of defense to prevent Under Frequency Load Shedding(UFLS)
ƒ Prevent equipment damage
ͻ Essential for System Restoration
ƒ Droop response is critical in restoration efforts
ƒ Hydro units and gas turbines are some of the first units to be restarted
ͻ Compliance with NERC Standards BAL-003-1, BAL-001
ƒ Prevent future regulations related to generator frequency response
performance
ͻ To accurately predict system events (Transmission Models)

2 RELIABILITY | ACCOUNTABILITY
The Capability Goal

Every BES Generator should have a working governor and be set


in accordance with Frequency Response Guideline for system
reliability and system restoration and provide primary
frequency response between Pmin and Pmax.
ƒ Exemptions Nuclear, existing wind solar, or possibly some others
(environmental. etc)

LGIA and SGIA should be modified to require the same for all
future generation.

3 RELIABILITY | ACCOUNTABILITY
Reliability Guideline: Primary
Frequency Control

• Posted 12/15/2015

4 RELIABILITY | ACCOUNTABILITY
Next Step: Generator Survey

• Three Interconnections: Eastern, Western and Quebec conduct


periodic generator surveys based on selected events over
multiple years to measure generators individual performance.
ƒ Generator owners would complete and provide survey data for all
synchronized BES generators exceptions: startup or shut down
exempted.
ƒ Surveys should be sent within timely manner of selected frequency
excursions. RS representatives in coordination with NERC shall select
events with consideration of Point C or Nadir and/ or below
recommended deadband with potential the maximum number of units
on line between Pmin and Pmax.
ƒ Recommended at least two event a years spaced out in such a way to
allow generator to address any issues discovered.
ƒ Survey will be “voluntary” but could be followed up with NERC Section
800 data request for any survey responses not provided.
5 RELIABILITY | ACCOUNTABILITY
Troy Blalock, P.E.
South Carolina Electric & Gas Company
601 Old Taylor Rd.
Cayce, SC 29033
Mail Code J42, Cayce, SC 29033
Office #: 803-217-2040
Cell #: 803-206-8984
Fax #: 803-933-8220
Email: Jblalock@scana.com

6 RELIABILITY | ACCOUNTABILITY
What is the Reliability Issue

Majority of generators in BA’s fleet/ East and West


Interconnections are currently incapable of providing primary
frequency responsive and we continue to commission new
generation and the trend continues.
Problems
1) Dead Bands Settings
2) Lack of coordination with plant
DCS or other outer loop
controls

7 RELIABILITY | ACCOUNTABILITY
Turbine OEM Reach Out to Customer Base

8 RELIABILITY | ACCOUNTABILITY
2012 Frequency Response Initiative
Report

Page 37, Frequency Response Initiative Report, October 2012

9 RELIABILITY | ACCOUNTABILITY
What has been learned – Outer
Loop Control

Coordination with plant DCS is a requirement when


operating in MW Set Point Coordinated Control.

10 RELIABILITY | ACCOUNTABILITY
Improvements

No Frequency Algorithm
in DCS
3 -175 MW GE7FA Gas Mark VIe Turbine
3/3/2015

Frequency Algorithm in
Plant DCS

11 RELIABILITY
R ELIABILIITY | A
ACCOUNTABILITY
CCOUNTABILITY
Eastern Profile Changing ? New Trend

03/22/16 11:32 EDT 06/05/16 17:15 EST

1111 MW Trip 918 MW Trip


12 RELIABILITY | ACCOUNTABILITY
Power Plant Modeling:
Benefits for non-controls People
Brandon Bouwman
U.S. Army Corps of Engineers – Hydroelectric Design Center
NERC Power Plant Model Verification and Testing Workshop
September 20, 2016
Brandon’s Three Rules for Controls Settings

1. DO NOT break anything


There is absolutely no point to power plant model validation if the
generator doesn’t work

2. DO NOT piss off the operator


Operators will “re-calibrate” what is not understood or a nuisance

3. Set tuning and operate as-needed/requested


We can all agree what makes good sense for the system:
Reliable power delivery is good for the country, wallets, and environment
for everyone involved
Benefits of Power Plant Model Validation

1. Actually operate a unit over its full range – can find issues, mis-coordination, etc.

2. Observe unit behavior – find areas of rough running, resonance, maintenance,


and other issues that may be mitigated or avoided

3. Check that expectations for the plant match reality by verifying models, system
layout, capabilities, etc.
Know the limits of a computer code vs. the vagaries of real, high-definition life.
Benefits of Power Plant Model validation
Operator experiences and exposure is diminishing due to:
SCADA
Automation
“Black Box” approach
Training reductions
?

?
?
Case Study 1: Ultimate Step Test
Know what you’re
doing before you
do it.

Testing sounds like


fun, interesting work,
but misplacing a
decimal point can be
nearly (or actually)
catastrophic
Case Study 2: Sticky Wickets
As-found…
Case Study 2: Sticky Wickets
TThat looked weird…
So we did it again

TThis one looks better


Case Study 2: Sticky Wickets
Third time – that’s more like it!

Reason?
Case Study 3: Power-gate Curves

Know your variables! Block


diagrams don’t always have
everything included
Case Study 4: Operator Training

This is an 80 MVA machine


Case Study 4: Operator Training

Much better synchronizing with


proper speed matching
Case Study 5: Limiter / UEL coordination

Plots received from transmission authority show


significant ~1Hz oscillation
Case Study 5: Limiter / UEL coordination
Event occurs at the
same
Location on the
capability curve each
time;
Interaction with limiter
Case Study 5: Limiter / UEL coordination
1. Event occurs at the
same location on the
capability curve each
time

2. Events involve
interaction with limiter

3. Out of 14 identical
units with the exact
same digital exciter
settings, only 2 exhibit
this behavior

4. Confirmed not
SCADA
Case Study 5: Limiter / UEL coordination

Reduced limiter gain


solved the issue, but no
root cause found.
Conclusion:
The point of all of these examples is to understand both the
model of your controls and the
reality of your plant.

1. Models, controls systems, and machinery are not separate.

2. They’re also not infallible.

3. Validation is not a burden, but an opportunity to deeply check our systems as a whole.
ERCOT Experience on Power Plant Model
Validation

José Conto

NERC Technical Workshop:


Power Plant Model Verification and Testing
Sept 20-21, 2016
Agenda
• ERCOT
• System Studies
• Model Validation

2
The ERCOT Region

At a glance
• About 90% of Texas load - 24 million consumers
• Competitive-choice customers: 75% of load
• More than 7 million electric-service ID’s
(premises)
• More than 46,500 circuit miles of high-voltage
transmission
• More than 550 generating units
• More than 77,000 megawatts (MW) of expected
available summer peak capacity

• Record peak demand: 71,197 MW (Aug. 11, 2016)

PUBLIC 3
The ERCOT Grid

Transmission Investment and Development


• In 2015, $1.1 billion in transmission added
• 1,093 circuit miles of transmission improvements completed
• 1,514 circuit miles of transmission planned
• $5.6 billion under development over the next five years

Generation Development
• Over 54 GW new generation added since 1999, 148 units decommissioned
• 16,189 MW generation committed for the future
• Over 61 GW of active generation requests under review,
o Includes more than 24 GW of wind (January 2016)
o Solar in queue: 1,417 MW in 2016, 1,765 MW in 2017

Solar and Wind Generation


• 288 MW of installed solar capacity
• Nearly16 GW of installed wind capacity
• Wind generation record: 14,023 MW (Feb. 18, 2016)
• Wind penetration record: 48.28 percent (March 23, 2016)

PUBLIC 4
Planning Studies

• Transmission Planning Criteria


– Full interconnection model (+ 69 kV network)

– Voltage stability margins, transient voltage


response, damping criteria

– UVLS, UFLS and Load Resources (market


program where load trip at 59.7 Hz)

– Combined Cycle unit governor model

PUBLIC 5
Studies outside the box

• LVRT and HVRT studies on new interconnection

• Small Signal Stability study

• Panhandle Wind Power expansion

• SSR studies for all new interconnections.


Screening studies by ERCOT, full studies by TP’s

PUBLIC 6
PMUs in ERCOT

• Total 98 PMUs @ 42
locations (Dec. 2015)

Future PMUs
- New generating Facilities over 20 MVA
- FACTS devices
- Transmission Facility (associated constraint)

PUBLIC 7
Generator Dynamic Model Validation

• PMU’s provide high accuracy measurements with unit online for


comparison against simulation output

• Iterative process will produce a model that matches the actual dynamic
behavior of the equipment in the field

• Automation of the process and use of parallel-computing techniques


greatly eases the workload associated with matching simulation
models with measured response

• PMU’s can be used to satisfy generator model validation requirements


set in NERC standards MOD-026-1 and MOD-027-1

PUBLIC 8
Single machine outage – Frequency Event

138 kV bus

Red: PMU Blue: Simulation

After droop adjustment

Red: PMU Black: Simulation

PUBLIC 9
PUBLIC
1

0.96
0.98
1.02
1.04
1.06
1.08
1.1
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
1.80
2.00
2.20
2.40
2.60
2.80
3.00
3.20
3.40
3.60
3.80
4.00
4.20
4.40
PMU_V

4.60
4.80
5.00
Wind Generator Model Validation

Simulation_Default

10
Model Translation – Wind Turbine PSSe UDM to TSAT

Generator Terminal Voltage (93018) Generator Active Power (93018) Generator Reactive Power (93018)

Q (MVAr)
P (MW)
V (pu)

time (s) time (s) time (s)

TSAT TSAT TSAT

Bus Frequency (154)


f (Hz)

time (s)

TSAT

PUBLIC
Thanks!

José Conto
Principal, Dynamic Studies
ERCOT System Planning
(512) 248-3141
Jose.Conto@ercot.com

12
Excitation system

Essential to provide magentizing current to


generator field winding

Typically power rating is about 1/4 - 1/3 percent of


generator MVA rating

Must be capable of
today - fast control of megawatt-level real power
readily practical with electronics
legacy - fast control of multi-kilowatt level real power
prior to about 1945 - had to be electromechanical
1945 - about 1975 - had to be electromagnetic
Excitation system

Control genrator terminal voltage

Manages sharing of reactive power load among


generators on a common bus or three winding transformer

Limits high field current of prevent excessive heating of generator field


winding (OEL)

Limits low field current to avoid undesirable effects of underexcitation (UEL)


Static excitation system

Controlled rectifier Hundreds of volts - thousands of amps


Excitation power transformer 1 - several MVA
Inner control loop
Voltage regulator Digital - milliwatts - watts
Brushless rotating exciter system

Uncontrolled rectifier Hundreds of volts - thousands of amps


Brushless exciter Many kilowatts - few megawatts
Voltage regulator Digital - milliwatts - watts
Real Power Dynamics
Real Power Dynamics - Gas turbine plant
Gas turbine plant

P-I-D governor Gas turbine engine


Acceleration limit controller Temperature limit controller
Load controller
Combined cycle plant
Combined cycle plant
Real power dynamics - Hydro plant
Beware of obselete models

There has been extensive new model development

Reflects current digital ‘front end’ practice


Improves hydraulic servo modeling
Improves Francis/Kaplan turbine modeling
Hydro plant
Baseline Testing
Excitation Systems
Shawn Patterson
Bureau of Reclamation
NERC Power Plant Model Verification and Testing Workshop
September 21, 2016
Model Development
• base \’bas\ n. 1 a: the bottom support of something; that on which a
thing stands or rests b: a fundamental principle or groundwork;
foundation; basis
• vt. 1: to establish, as a fact or conclusion

Identify individual model components


Not a black box fit!
Every parameter must be derived on a technical basis

Measured or calculated
Then measure the overall output response to an input

Compare the complete model response to measurement


General Principles
• Control theory basics (Diff. Eqs., s-domain, transfer functions)
• The more data, the better the model
• Break the models into as many parts as possible
• Test signals and measurement devices must have higher bandwidth
than the equipment/models
• Understand the limitations (signal accuracy, model fidelity, system
changes, noise, hysteresis, bandwidth…)
• There are no exclusively right or necessary ways to do things
• but there are many ways to get things wrong!
Transfer Function

Input System Output


U(s) G(s) Y(s)

G(s) = Y(s)/U(s)

To identify a system by comparing outputs,


model inputs must be identical to test inputs
The excitation control system is a closed loop

In the middle of this model is the generator


So first get this right

Open Circuit Saturation Characteristic

- Base Field Current


- Generator Gain
Then this

Saturation Characteristic under load

Steady State Model


This must be right

Generator Transient Model

T’do

T’do can be identified anytime a changing


Vt is measured offline with a known
Efd, e.g., VAR rejection, exciter shutdown,
step in Efd (manual control mode), etc.
Exciters - get rotating exciters first

Calculate

Measure or get
From manufacturer
Control Loops
Break the problem down
• Isolate components if possible
• Open loop tests if possible
• Offline tests remove power system influence
• Sometimes possible to measure components while unit is shut down
• Test AVR first without PSS, Compensation
• Testing at reduced load removes effect of local mode oscillation
• In general, linear elements should be measured, nonlinear elements
are calculated
Model Parameters
• Linear parameters
• gains, time constants
• Small signal tests/analysis
• Step and frequency response tests

• Nonlinear Parameters
• limits, gain multipliers
• Large signal tests, or calculate
Calculated and measured Calculated

Measured

If analog: measure (or calculate and measure ) Adjust parameters as necessary


If digital: transfer time constants directly to model based on complete model response
Small signal tests
• Step response
• Frequency Response

• Input into Vref


• Input scaling typically 1 volt / percent terminal voltage
• +/- 1 volt usually small enough to maintain linearity, but get good
signal/noise

• Input signals must be frequency rich


• Measurements must be sampled at greater than 10 times the model
bandwidth
Frequency Response
• Input sine signals into Vref summing junction into voltage regulator
• Step through many frequencies over the response range of the
system
• 0.05 Hz to 10 Hz
• Measure Vt for output signal
• Bode plot for response of Vt/Vref
• Entire closed loop response of exciter/generator
Transfer Function

Input System Output


u = U sin(wt) G(jw) y = Y sin(wt+f)

Frequency Response of System is G(jw)

Gain at w = |G(jw)| = Y/U, Phase at w = f


Step Response

A step input into the


AVR summing junction
provides a frequency rich
signal

Measure and compare all signals!


(Efd, Ifd, MW, MVAR)
Small Signal Responses
• Ensure response is essentially linear
Offline
Note if signals
+/- 1 % steps are limited
Into Vref

Efd should be fairly symmetrical,


and have no flat spots
Frequency Response

Some models
are better than others
at frequencies higher
3 Hz

IEEE standard models


only “guaranteed” up
to 3 Hz

Offline response eliminates system (and other) influences


on the results
Power System Stabilizer
Strictly speaking, this model represents an integral-of-accelerating-power
stabilizer (dual input), which is always digital, but is often a generic model for analog
circuits as well

An analog PSS consists of only circled portions, and should be tested/validated


in its entirety, each portion separately
Power System Stabilizer
Digital systems can be tested to various extents based on design

Why test a 100% digital component?


Depends on your level of trust with the equipment

Trust but verify!


Power System Stabilizer
PSS Frequency Response
40
Measured
20 Model Frequency response of PSS
Gain (dB)

can be modeled very well


0

-20
-2 -1 0 1 2
10 10 10 10 10
Freq (Hz)

100
Phase (deg)

-100

-200
-2 -1 0 1 2
10 10 10 10 10
Freq (Hz)
Power System Stabilizer

Local mode oscillation


is difficult to match

Step response with PSS disabled to compare damping when enabled


Power System Stabilizer

Local mode oscillation


is the only measurement
available to verify PSS
effectiveness

Step response with PSS to compare damping when enabled


Reactive Current Compensation

Step Response with


compensation enabled
and disabled to verify
effective Xcomp
Overexcitation Limiter

Challenge limit with a step input.


Note levels, timing, reset value, and
response characteristics. Perform test
in simulation

Timing

Pickup

Reset
Overexcitation Limiter

Alternatively, this model can


be populated by careful analysis
of the model and excitation
system manual

Test the model thoroughly


Underexcitation Limiter

Same approaches as
overexcitation limiter.

This can be performed


during MOD-025
testing
References
IEEE Standard 421.5-2016, IEEE Recommended Practice for
Excitation System Models for Power System Stability Studies

IEEE Task Force on Generator Model Validation Testing of the Power


System Stability Subcommittee, “Guidelines for Generator Stability
Model Validation Testing,” IEEE PES General Meeting 2007,
paper 07GM1307
Power Plant Model Validation:
BPA Experience
NERC Workshop
September, 2016

Steve Yang
Bonneville Power Administration

1
BPA Overview
• Bonneville Power
Administration (BPA) is a
federal Power Marketing
Agency in Pacific Northwest
• BPA markets power from 31
Federal dams and the
Columbia Generating Station
Nuclear Plant
• BPA operates more than
15,000 miles of
transmission, including
4,735 miles of 500-kV lines

ƒ BPA operates several large paths in the Western Interconnection – California


Oregon AC Intertie (4,800 MW), Pacific HVDC Intertie (3,100 MW), Northern
Intertie (3,100 MW), and Montana Intertie (2,200 MW)

2
Outline

• Dynamic Disturbance Recorders for


PPMV at BPA
• PPMV tools and process with a case
study and examples
• When models and reality don’t agree
• Summary

3
Dynamic Disturbance Recorders (DDRs)
for Model Validation at BPA
• Phasor Measurement Unit (PMU)
– Output voltage and current phasors, calculated frequency,
active and reactive power
– Data can be archived locally and streamed to a control center
in real time
– Minimum filtering is preferred for model validation

• Point on Wave Recorders


– Technologies:
• DFRs with continuous recording capabilities (BEN6000)
• Portable Power System Monitor (PPSM)
– Output: point on wave voltages and currents
– Data is archived locally, retrieved via FIN network
– Phasor calculations are done off-line
– Preferred technology for electronically connected equipment

Modern DDRs can combine Phasor and Point on Wave recording


4
DDRs at Point-of-Interconnection (POI)
• BPA has installed DDRs at power plant POIs since 1996
• BPA developed Power Plant Model Validation (PPMV) application using
DDR data and GE PSLF play-in function (added in 2001)
• BPA requires PMU installation for all new generation including the wind

Substation Power Plant

Point of
Interconnection
V I
G

G
Record:
- POI bus voltage
- POI bus frequency
- Power plant MWs and MVARs

DDR needs to be placed at Power Plant POI 5


BPA’s DDR Coverage at POI

• Conventional –
• 14 plants,
• 133 generators,
• 21,345 MW of generation

• Wind –
• 12 plants
• 1,200 MW of generation

• More to be added
6
BPA PPMV Tools

• BPA PPMV
• Sequence of GE PSLF EPCLs and MATLAB programs

• BPA-PNNL PPMV
• Stand-alone data management program and
automated PSLF interfaces

• EPRI PPPD
• Stand-alone MATLAB based software
7
PPMV Process: Initial Set-up
Extract power plant data from WECC
basecase and build a sub-system

Enter plant information

8
PPMV Process: Event Notifications

• BPA frequency event detection program


• BPA event detector
• WECC JSIS event alerts
• DFR triggers
• StreamReader trending displays

9
PPMV Process: Collect and Review Data

10
PPMV Process: Run Validation

11
Initial Results

12
When models and reality don’t agree

• Model validation studies need to be done over several events

• It is very rare to get a good match for all events because


operating mode can be different (e.g. generator is ramping,
generator on AGC responding to a contingency)

• Frequent reasons for systemic model mismatch include:


• Wrong powerflow data
• PSS status / gain
• Inertia time constant

13
Transformer Name Plate and Tap Setting

Check transformer impedances and taps

14
New Transformer Data

15
PPMV Process: Review Results

16
PPMV Process: Generate Report

17
WECC Re-Certification of Centralia
Power Plant

18
Calibration

• EPRI Power Plant Parameter Derivation (PPPD) is most


mature, a user group is established including 23
participants
• Bernie Lesieutre @ University of Wisconsin uses a unique
approach of pattern matching – which is useful to
provide insight in model inaccuracies
• Others:
• MATLAB
• University of Texas – Particle Swarm Optimization
• PNNL – Kalman filter
• Georgia Tech – super-calibrator
• Idaho Power developed in-house optimizers

19
Calibration
Before calibration After calibration

• PPMV can complement model development and calibration, there are successful
case studies. However, engineering expertise and knowledge of generator
controls are essential
• Beware of curve fitting exercises 20
If All Fails Repeat Baseline Test

21
After Re-test

MOD-027

MOD-026

22
Going Beyond the Standards

23
Performance Monitoring and
Detection of Control Failures
• PMU monitoring provides detection of generator abnormalities
Power
700

680
Unexpected action
660

640
PSS failure from plant controller
Active Power [MW]

620

600
Power
580 550

560
540
540 Observed
Expected 530
520

Active Power [MW]


500 520
2 3 4 5 6 7 8 9 10
Time (sec)
510

50
500
Observed
490 Expected
Reactive Power (MVAR)

0 480
0 10 20 30 40 50 60 70 80 90 100
Time (sec)

-50 Abnormal runback in


reactive power
-100 24
0 5 10 15 20 25 30 35 40 45 50
Time (sec)
Summary
• PPMV using Dynamic Disturbance Recorders
– Provide a cost-effective approach for periodic model verification as
required by MOD-026,MOD-027 and WECC policy
– Give Transmission Planners independent way to validate power plant
dynamic performance and models
– Can be used in real-time performance monitoring

• Several technology solutions are available

• Model validation tools are mature and well-developed


– A number of success stories
– Disturbance model validation is a part of regular business process at
BPA

25
Thank You!
Contact information:
Steve Yang (hyang@bpa.gov)

26
GE Perspective
Power plant modelling & verification

e
Observations
Observations Global trends
• Plant operating in load control with no • Loss of inertia from renewable growth
frequency bias
• Reduction in primary response due to lag in • Faster + higher primary response
plant level load control loop or requirements
communication
• Assumption that AGC target contains • Reserve margin capability/enforcement
frequency bias necessary
• Co-ordination AGC – Plant control –Turbine • Droop setting reductions ( ie IESO 3 %
governor requirement for GT in CCGT)
• Frequency signal resolution limitations in
plant controller • Dead band reductions or modification
• Large steam governor dead band vs boiler
stability vs hydraulic system capability • Proliferation of different requirements

Missteps Common questions


• Disabling plant load control to sustain • Plant upgrades : where to set 4% droop …
primary response ISO, prevailing ambient, max rated capability,
handling of peaking features
• Applying primary response in two zones
without co-ordination • Role of ACE vs plant response
e
MOD-025
Generator Real and Reactive Power Capability
x Many units may not have operated with as many (+) or (-) VARs in their lifetimes,
so they could be pushed to their limits
x Prior to testing: Make sure all excitation system components are in good operating condition to
handle the field current and var variations
¾ Brushless exciter: Inspect diodes, fuses, armature, connections, etc
¾ Static exciter: Inspect thyristors, fuses, collector, brushes
¾ Confirm proper coordination between AVR under-excitation limiter (UEL) and loss-of-field
(40) protection (already required per NERC PRC-019)
x Consider having AVR expert on-site during testing in case any unexpected alarms or limits occur
x Testing for over-excited (lagging) reactive power:
¾ VAR changes only on tested unit will often result in reaching generator or switchyard
over-voltage limits
¾ By absorbing VARs on adjacent and neighboring generators, switchyard voltage can be
held down, allowing tested generator to achieve more lagging reactive power
x Testing for under-excited (leading) reactive power:
¾ VAR changes only on tested unit will often result in reaching generator or switchyard
under-voltage limits or “shrunken” UEL limit based on reduced voltage
¾ By increasing VARs on adjacent or neighboring generators, switchyard voltage can be
propped up, allowing tested generator to achieve more leading reactive power

Page 1 NERC PPMVT Workshop – Manufacturer Panel Confidential © Siemens Energy, Inc. 2016. All rights reserved. September 2016
MOD-026
Generator Excitation Control System Model Verification
x Model comparison with test results is more productive when excitation system
model reflects:
¾ Actual AVR settings, rather than “typical” settings
¾ Updated IEEE model, when appropriate.
ƒ Example: IEEE Type ST4B and ST6B models for static excitation systems with
P-I control became available in 2005 in IEEE 421.5-2005 standard
x Testing typically includes AVR signal injection into AVR voltage summing junction via:
¾ Test points on analog AVRs
¾ Software signals on most modern digital AVRs
x Types of excitation systems which can be tested, modeled, simulated and validated
by Siemens:
¾ All Siemens excitation systems including RG3, Thyripol, Thyrisiem
¾ All legacy Westinghouse excitation systems, including WTA, WTA-300, WDR,
MGR, PRX, Magastat
¾ Selected third party excitation systems (Cutler-Hammer, Basler, Semipol, etc.)
¾ Other systems with coordination between plant owner and AVR OEM.

Page 2 NERC PPMVT Workshop – Manufacturer Panel Confidential © Siemens Energy, Inc. 2016. All rights reserved. September 2016
MOD-026
Generator Excitation Control System Model Verification

Model validation of Siemens Thyripol excitation system


Terminal using IEEE Type ST6B
Voltage

Field
Voltage

Page 3 NERC PPMVT Workshop – Manufacturer Panel Confidential © Siemens Energy, Inc. 2016. All rights reserved. September 2016
MOD-027
Turbine/Governor Model Verification
• Settings affecting turbine-governor models and model validation
in modern turbine control systems:
¾ Proportional gain (affects droop)
¾ Integral gain (affected by reset or repeat time constant)
¾ Dead band (set in terms of rpm)
• Signal injection into frequency error summing junction via software in modern
digital control systems
• Types of turbine control systems which can tested, modeled, simulated and
validated by Siemens :
¾ All Siemens controls systems, including
SPPA-T3000, SPPA-T2000, TXP, Simatic S5 and S7 systems
¾ All legacy Westinghouse control systems including AEH*, DEH*, WDPF
* Cannot perform with signal injection
¾ All Siemens turbines with non-OEM controls, including
Allis Chalmers, Westinghouse
¾ Selected third party control systems

Page 4 NERC PPMVT Workshop – Manufacturer Panel Confidential © Siemens Energy, Inc. 2016. All rights reserved. September 2016
MOD-027
Turbine/Governor Model Verification

SGT603 (rev0) Model


for Siemens
SGT6-2000E(8)
Gas Turbine

Page 5 NERC PPMVT Workshop – Manufacturer Panel Confidential © Siemens Energy, Inc. 2016. All rights reserved. September 2016
Establishing the Baseline Model

John Undrill

NERC Workshop
September 2016
You should not assume that the equipment in the plant matches
the data used in initial setup of the model

It is important that the equipment, and at-site documentation, be


seen by people who know what to look for

The I&C engineer at the plant should/may know the transducers,


wiring, and terminations

but

He may never have seen a transfer fucntion diagram of his


equipment and has never run a dynamic simulation of a power
system
Operating practices are important

Voltage regulator should be in auto-voltage mode


PSS should be ON

Turbine may be in

Droop mode, responsive to frequency without


overriding action by load controller

Droop mode, responsive to frequency but


with overriding action by load controller

Load controller may have/not have frequency bias


Practical points

Plots of results must be displayed quickly after the


test is done

Must respect the white knuckle limits of the plant


personned

Offsets in plots are a fact of life - ambient contitions


change - input output curves should match in
principle - fit in great detail is likely to be misleading

Drawings may be old, wrong, completely lost

Beware of instruments that have recent calibration


stickers on them but, neverthess, but reading wrong
by large factors
Manufacturer’s field personnel will be familiar with their equipment
and able to plug in their ‘engineering’ terminals

Then they can (may be able to)


- look up parameter values
- read operating values (eg exciter field amps)
- show some transfer function information
- apply well defined test disturbances
- record dynamics tests with good bandwidth

They will/may know details of their equipment that are site specific,
undocumented, disabled, nonstandard additions

There is no value in an dedicated (or automated) effort to match


a transfer function model to test results if the ‘as operating’
configuration of the plant does not match the transfer function model
Risks are small but must be understood

Old equipment that is working correctly can break if disturbed


- brittle terminal blocks, dodgy switches
- wait for replacement parts - delay in return to service

New equipment that has worked correctly in one operating


condition may fail to work, or work incorrectly, in different
conditions required by test
- delay in return to service

Protection may be set tighter than it is thought to be

Unexpected trips do not inspire confidence

Costs of delays in return to service can far exceed the direct


costs and fees of testing/modeling
Cautions and precautions

The generator capability curve does not define the prudent


range of testing

Auxiliary bus conditions are as important as conditions at


the generator terminals and at the high voltage bus

Protection should not be altered - neither settings not status

Test plan should respect both protection and alarm limits


Basics of Power System Control
Real Power

NERC Workshop

September 2016

John Undrill

1
Basics of Power Systems Dynamics


Newtonian dynamics 2H = Tengine − Telec
dt
dω Pengine − Pelec
2H =
dt ω

Engine power and Pelec = Penom + Delec ω


load can vary with frequency
Pengine = Psnom + Dengine ω

dω Psnom − Penom − (Dengine − Delec )ω


Basic equation of motion 2H =
dt ω
Basics of Power Systems Dynamics

Basic equation of motion

No governor, constant ΔPlnom


Δω =
engine power (Dengine + Dload )

Proportional governor ΔPenom = Kp Δω

ΔPlnom
Governor gain = Kp Δω =
Kp + Dengine + Dload

ΔPlnom ΔPlnom
= =
Kp + D D + R1

This describes the steady state frequency offset but does not describe
the dynamic behavior of the system
Governing Droop

The governor

- does not control speed

- does not control power

- does control the relationship between


speed and power

(special cases)

off line - power is zero


- controls speed

tied to infinite bus - speed is fixed


- controls power
Turbine Load Control

Adjust frequency by Adjust power allocation by


collective adjustment of differential adjustment of
speed-load references speed-load references
Governing Droop - Proportional Governor

Want this Build this

n = nref − R Pengine

Kp (nref − n) = Pengine

R = 1/Kp

n = nref − R Pengine
Note that we have used valve stroke as a surrogate for engine power
Proportional governor

This is oversimplified -
This is more realistic -
Would always be stable if it
Four 90deg phase shifts
could be built -
Small steam turbine / small gas turbine
Could not be built
5 percent load increase on isolated engine

0.0 Divx 10 Divy 10 Time 25.0


Name Min Max Col CpPu F Fa Fb Fc Fd
0 s0 0.5 0.7 1 1.0 1 0.0 0.0 0.0 0.0
1 s1 0.5 0.7 2 1.0 1 0.0 0.0 0.0 0.0
2
3
s2
s3
0.995
0.995
1.005 3
1.005 ____
4
1.0
1.0
1
1
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
power

Kp = 20 speed Kp - 25

Droop = 0.05 Red Tv = 0.05


Green Tv = 0.15
Red valve Blue Tv = 0.25
Green power Cyan Tv = 0.35
0.0 Divx 10 Divy 10 Time 25.0
Name Min Max Col CpPu F Fa Fb Fc Fd
Blue speed 1
2
s1
s2
0.5
0.995
0.7 ____
1.005
1
1
1.0
1.0
1
1
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0

Kp = 33, 25, 20

Red R = 0.03
Green R = 0.04
Blue R = 0.05

0.0 Divx 10 Divy 10 Time 25.0


Name Min Max Col CpPu F Fa Fb Fc Fd
2 s2 0.995 1.005 1 1.0 1 0.0 0.0 0.0 0.0
Proportional - Integral Governor

At node 0 error = nref − n − Rv


When error is zero n = nref − Rv
Could achieve droop by using feedback of valve stroke or electrical power

(Valve stroke is a surrogate for engine power)


Control of Load Sharing
P-I Governor - Choice of Droop Value

R = 0.05 R = 0.005
Operator
adjusts
speed-load
references
to adjust
allocation of
power output

red
0.0 Divx 10 Divy 10 Time 100.0 0.0 Divx 10 Divy 10 Time 100.0
Name Min Max Col CpPu F Fa Fb Fc Fd Name Min Max Col CpPu F Fa Fb Fc Fd
1 s1 0.0 1.0 2 1.0 1 0.0 0.0 0.0 0.0 1 s1 0.0 1.0 2 1.0 1 0.0 0.0 0.0 0.0
2 s2 0.98 1.02 1 1.0 1 0.0 0.0 0.0 0.0 2 s2 0.98 1.02 1 1.0 1 0.0 0.0 0.0 0.0
6 s6 0.0 1.0 3 1.0 1 0.0 0.0 0.0 0.0 6 s6 0.0 1.0 3 1.0 1 0.0 0.0 0.0 0.0

0.0 Divx 10 Divy 10 Time 250.0 0.0 Divx 10 Divy 10 Time 250.0
Name Min Max Col CpPu F Fa Fb Fc Fd Name Min Max Col CpPu F Fa Fb Fc Fd
1 s1 0.0 1.0 2 1.0 1 0.0 0.0 0.0 0.0 1 s1 0.0 1.0 2 1.0 1 0.0 0.0 0.0 0.0
2 s2 0.98 1.02 1 1.0 1 0.0 0.0 0.0 0.0 2 s2 0.98 1.02 1 1.0 1 0.0 0.0 0.0 0.0
6 s6 0.0 1.0 3 1.0 1 0.0 0.0 0.0 0.0 6 s6 0.0 1.0 3 1.0 1 0.0 0.0 0.0 0.0
R enewable Energy Modeling
NERC PPMVT Workshop

Matt Richwine
September 20, 2016
W ind Plant Model Network
Equivalent
Station Turbine
System Transformer(s) MV Collector Transformer Equivalent
Equivalent Equivalent WTG
System

R2, X2 R1, X1, B1


Rt2, Xt2 Rt1, Xt1

HS SS LS SS HS WTG
WTG Bus
Xfmr Bus Xfmr Bus Xfmr Bus

Bus typically used for voltage regulation

• Recommended network for representing wind farms in positive sequence RMS models for
transmission planning
• Aggregation of the collector and turbines has been established for many years in
industry[1]

2
NERC Model Workshop
9/20/2016
Generic Renewables Models
Generic RMS Models
Renewables Models, 1st Generation
Renewables Models, 2nd Generation (WECC)
Renewables Models, IEC61440-27 (ENTSO-E)
Exciter-like
functions
Generator-like
functions
• Not all modules are
required for all wind
turbine types
• Some modules are also
used for solar plant
representation Governor-like
functions

2nd Generation Renewables Model (developed by WECC) 3


NERC Model Workshop
9/20/2016
T ypes of Renewables Models
Very Detailed Less Detailed

Typical Applications
• Equipment Interactions • Interconnection • Bulk Transmission
• Very Weak Systems Studies Planning Studies
• Special Purpose Studies • Special Transmission
Planning Studies

Selection of Model Depends on Application


4
NERC Model Workshop
9/20/2016
V oltage Reference Step Test
• Wind plant is in voltage regulation
mode at the 345kV bus
• +1% voltage reference step at the POI
• Second Generation Generic Models used
for validation (WECC Model)
• Response without voltage droop
• In satisfaction of NERC MOD-026-1
Verification of Models and Data for Plant
Volt/Var Control Functions
Vref/Vreg
or Qref/Qgen Plant Level
Control Vterm
fref/freq and Pgen
Plant_pref/Pgen
Qgen

Iqcmd
Qref Iq
Electrical Ipcmd Generator/
Pgen Ip
Torque Pref Control Converter
Prefo Control
Pord
Z

Zref Pgen
Drive-Train

Pm

Pitch T
Aero
Control

5
NERC Model Workshop
9/20/2016
P lant Interactions V1reg
G1 X1 Xg Vinf

X2
Challenge:
V2reg
Plant volt/VAr (MOD-026) model validation can be
confounded by other local voltage-regulating devices G2
(wind farms, solar plants, STATCOMs, SVCs, etc). Factors
include:
• Weak grids (Xg >> X1, X2): Interaction likely
• Non-dominant plant (X1 >> X2): G1 hard to isolate
• Non-linear response (ie. deadbands): Non-linear
plant must be fully modeled or disabled

Occurrence:
• Wind plants are often located on weak grids
• Wind plants are often clustered where wind is good
• SVCs/STATCOMs are often used in weak grids for
voltage support
• Deadbands are common in volt/var controls

Critical to Understand the Local System


6
NERC Model Workshop
9/20/2016
P lant Interaction in Test Data

Linear System – Good Test Data

Good Linearity – Slope


indicative of Grid Strength

Noisy Region

Non-Linearity – Unusable Test Data


Control
Shunt Interaction
Switching

Noisy Region

7
NERC Model Workshop
9/20/2016
P MU Measurements Vref +
+
Verr PI Iq X
Vbus

Volt/VAr Challenge: Vmeas

Imposing a voltage (from a PMU recording) at V1reg to


validate G1’s model open the voltage regulation control PMU
loop
V1reg
G1 X1 Xg Vinf

X2
PMU V2reg
G2

Mitigation Option:
Imposing a voltage (from a PMU recording) farther up-
stream can leave the feedback loop closed and
improve model validation
However, data recorded farther up-stream often
includes more interacting equipment – becomes
difficult to isolate one device
V1reg PMU
G1 X1 Xg Vinf
Test data courtesy of BPA
X2
V2reg
8
G2 NERC Model Workshop
9/20/2016
P MU Measurements
Important to check when using PMU
data for Volt/VAr model validation:
1. No non-linearity in the local system
(close enough to interact significantly
with the plant under test)

2. No in-feeds from other equipment

3. Sufficient impedance between the


point-of-regulation and the PMU
point-of-measurement (or a way to
deal with errors from open-loop
control)

9
NERC Model Workshop
9/20/2016
Questions?
T hank You!

Matt Richwine
GE Energy Consulting
Matthew.Richwine@ge.com
518-385-4407

11
NERC Model Workshop
9/20/2016
References

[1] E. Muljadi, C.P. Butterfield, A. Ellis, J. Mechenbier, J. Hocheimer, R. Young, N. Miller, R. Delmerico, R. Zavadil, J.C. Smith, ”Equivalencing the
Collector System of a Large Wind Power Plant”, presented at the IEEE Power Engineering Society, Annual Conference, Montreal, Quebec,
June 12-16, 2006.
[2] Richwine, M.P.; Sanchez-Gasca, J.J.; Miller, N.W., "Validation of a second generation Type 3 generic wind model," in PES General Meeting |
Conference & Exposition, 2014 IEEE, July 2014

12
NERC Model Workshop
9/20/2016
Capacitor Bank Switching Test

• Shunt capacitor switching test (10MVAr rated


bank at HV bus)
• Voltage regulation mode
• Wind plant responds by reducing reactive
power when the bank is switched in,
increasing when switched out
• Power (wind speed) decreasing
• 3 models validated[2]:
• GE models
• Generic – 1st generation
• Generic – 2nd generation

13
NERC Model Workshop
9/20/2016
A ctive Power Response – GE Model
• Frequency step injection test – release of an over-frequency step (or fast
ramp) test
• Plant responds according to its frequency droop curve (example shown)
• Wind speed is not fed into the model
• Close match of active power achieved

Example Droop Curve


14
NERC Model Workshop
9/20/2016
A ctive Power Response – Generic
• Second Generation Generic Model –
active power response is at the plant
controller module (REPC_A)
• Frequency step injection of 200mHz
• Frequency response settings are 5%
droop, 36mHz deadband
• Measured wind speed is not fed in to
the model
• Power declines quickly but recovers
more slowly when released
• Power is “wind following” outside the
event…larger and slower variations
• Power is more regulated during the
event… smaller deviations (as
expected)

15
NERC Model Workshop
9/20/2016
© Copyright 2013, First Solar, Inc.
Introduction
• Test results from NREL-DOE test on FS PV plant
• 3 Tools/Platforms
a) PNNL-BPA Power Plant Model Validation (PPMV) Tool
b) GE PSLF Tuning (Manual)
c) EPRI Renewable Energy Model Validation (REMV) Tool
• Conducted 3 tests
a) Under-Frequency Test
b) Capacitor Switching Test

© Copyright 2013, First Solar, Inc.


c) Reactive Power Control Test
• PMU Data recorded at 30 Hz

Figure Courtesy - Dmitriy Kosterev, Steve Yang, Pavel Etingov, “PMU-based application for power plant model validation (PPMV)”, NASPI Working Group Meeting, March 23-24, 2015
Event 1 –Under-Frequency Test
• Frequency time series from actual event in ERCOT measured on November 29, 2011 was used
• Centralized Power Plant Controller (PPC) emulated this frequency response
• Plant operated in curtailed mode with 50% of plant capacity left as reserve
• Very aggressive droop setting of 1.67% was implement during test

© Copyright 2013, First Solar, Inc.


3
Under-Frequency Test Results

PPMV Tool GE PSLF

REMV Tool

© Copyright 2013, First Solar, Inc.


4
Event 2 –Capacitor Switching Test
• “Staged test” data used for this model validation task
• Capacitor bank located at medium voltage collector bus engaged during test
• 5 MVAR reactive power target set in SCADA HMI
• Inverters could not meet reactive power target within its power factor capability range
• PPC engaged 4.75 MVAR capacitor bank automatically to meet the target
• Capacitor switching dynamics adequately captured in simulation

© Copyright 2013, First Solar, Inc.


5
Capacitor Switching Test Results

PPMV Tool GE PSLF

© Copyright 2013, First Solar, Inc.


REMV Tool

6
Event 3 –Reactive Power Control Test
• “Staged test” data used for this model validation task
• Centralized Power Plant Controller (PPC) was set in VAR control mode
• During test, set point for reactive power was changed from 0 MVAR to roughly 1.6 MVAR and
back to 0 MVAR
• PPC issued reactive current command to achieve desired reactive power at POI.

© Copyright 2013, First Solar, Inc.


7
Reactive Power Control Test Results
PPMV Tool GE PSLF

REMV Tool

© Copyright 2013, First Solar, Inc.


8
Conclusions & Future Work
• PV plant model validation using staged test data and natural event data is presented
• Existing PV plant models as approved by WECC REMTF/MVWG group is capturing plant dynamics
adequately under natural events and under staged tests conditions
• System operators could provide actual event data to help verify model adequacy and validate model
performance when subjected to real-time grid disturbances
• Similar model validation exercise for another PV facility rated above 250 MW is under progress,
results will be presented when validation is complete.
• More tests like over-frequency event will also be tested in future

© Copyright 2013, First Solar, Inc.


9
Questions ?

Sachin Soni
Sachin.soni@firstsolar.com
623-255-9981

© Copyright 2013, First Solar, Inc.


10
Sept 20, 2016

NERC PPMVT Workshop


Generator Governor Frequency Response
2004 NERC Operating Policy 1, Generation Control and
Performance, Section C

ƒ “Governor limits – Turbine control systems that provide


adjustable limits to governor valve movement (valve
position limit or equivalent) should not restrict travel more
than necessary to coordinate boiler and turbine response
characteristics.”

ƒ Auxiliary equipment capacity limits.


ƒ Process deviation limits
ƒ Operator define unit load limits.

© ABB Group
September 30, 2016 | Slide 2
Generator Governor Frequency Response
Primary Frequency Control Consideration

© ABB Group
September 30, 2016 | Slide 3
Basics of Power System Control
Reactive Power

NERC Workshop

September 2016

John Undrill

1
Control and sharing of reactive power load requires droop

Collective adjustment of voltage references changes voltage

Differential adjustment of voltage references changes distribution of reactive power


Basics voltage regulator

Ef d = K(Vref − vt )

(Ef d − vt )
Q=
Xs
K Xs
vt = vref − Q
K +1 K +1
Ef d = K(Vref − (vt − Xc Q))

(Ef d − vt )
Q=
Xs
K Xs − KXc
vt = vref − Q
K +1 K +1
Ef d = K(Vref − (vt − Xc Q))

(Ef d − vt )
Q=
Xs
K Xs − KXc
vt = vref − Q
K +1 K +1

Make K >> 1
Then K/(K+1) ~= 1
Then

vt = vref + Xc Q
Rising series current compensation

Could we -

Choose X_c = X_t

vt = vref + Xc Q then the AVR controls


high side bus voltage
vbus = vref − Xt Q
Bad idea !!!!

vbus = vref − (Xt − Xc )Q


MVAR adjustment - Raise Qa - Lower Qb

No compensation Drooping compensation Xc=-.11


Good response Quicker response
1 sec time constant Less sensitive
Rising compensation Xc=-.11
Slow response
Excessively sensitive sensitive

Rising compensation Xc=-.13


!!!!
Emerson Process Management
Power & Water Solutions
Steam Turbine Controls Modeling
Unit Control Modes – Coordinated Controls
• Coordinated Mode
– Developed in late ‘70s and early ‘80s to
answer a long-standing controls
problem
– Boiler and steam turbine want to fight
each other (Throttle Pressure vs. MWs)
and didn’t “coordinate” with each other
– Both Boiler Master and Turbine Master
receive a common “unit” setpoint which
limits disparities between steam
generation and steam use (flow)
– Tuning and configuration of these
closed-loop controls determines how
responsive the unit will be during a
system frequency event (boiler slow,
turbine fast)
Unit Control Modes – Turbine Following & Sliding Pressure
• Turbine Following Mode
– Steam turbine valves respond to
Throttle Pressure changes while the
boiler firing rate determines MWs
– Not responsive to frequency events
(boiler too slow)
• Sliding Pressure Mode
– Steam turbine valves are either wide
open or locked in a position
– Minimizes throttling enthalpy losses
– Most efficient mode
– Boiler firing controls both Throttle
Pressure and MWs
– Not responsive to frequency
Turbine Protection Circuits Affecting Frequency Response
• Speed Regulation
– Pinches modulating steam valves closed
proportionally to overspeed
• Power/Load Unbalance (PLU)
– Overspeed protective circuit looking at
mechanical vs. electrical load
– Slams valves without tripping to prevent
overspeed on sudden load loss
• Overspeed Protection Control (OPC)
– Slams governing valves at 103% rated
speed, but allows re-opening
• Fast Valving / Early Valve Actuation
– Rapid valve closure at high load loss to
prevent overspeed and rotor angle instability
First Solar Power Plant Controller

VChadliev@firstsolar.com
© Copyright 2013, First Solar, Inc.
First Solar Plant Control System Architecture
x Modern solar PV plants can contribute to the reliability and
efficiency of grid operation through sophisticated Power
Plant Controller by offering the following capabilities:

o Voltage / VAR control and/or Power Factor regulation


o Fault ride-through
o Real power control, ramping, and curtailment
o Primary frequency regulation
o Frequency Droop Response

© Copyright 2013, First Solar, Inc.


x Centralized Solar PV pant controller can also play an
important role during NERC’s MOD 026-1 & 027-1
verification process
2
First Solar Plant Control System Architecture
ͻ Monitor conditions at the POI and compare PCS PLC
them with the Set Points
e e-
ͻ Send commands to inverters to PCS PLC -
make output adjustments and achieve
POI requirements e--
zzz
zzz
Grid
zzz
e-
Point
of Inter- zzz
connection
(POI) Control Signal e-

© Copyright 2013, First Solar, Inc.


PCS PLC
Voltage
MW
MVAR zzz
PCS PLC zzz
Closed Loop ~100 ms Cycles zzz
zzz
Electricity Flow
e-
e- 3
Agua Caliente 290MW (AC)

Palo Verde Nuclear


Generating Station
Hassayampa
Agua Caliente Substation

California

Hoodoo Wash

IInc.
Arizona

First SSolar,
Substation

2013, Fi
i h 2013
Copyright l
North Gila 500kV Palo Verde-Hassayampa
Substation Transmission Line

©C
4
Agua Caliente - Typical Plant Operating Day (March 19, 2014)
1.2 110%

Power (PU)
0.9
Power (PU) and Reactive Power (PU)

Voltage (PU) and Power Factor


105%

0.6

Voltage (PU) Power Factor


0.3 100%

0.0
Reactive Power (PU)

© Copyright 2013, First Solar, Inc.


95%

-0.3

-0.6 90%
4:00 8:00 12:00 16:00 20:00
Time of Day 5
Agua Caliente Voltage Support – Event on March 21, 2014

© Copyright 2013, First Solar, Inc.


6
Agua Caliente Voltage Support – Event on March 21, 2014
1.2 110%
500kV Palo Verde -
Hassayampa line Power (PU)
taken out of service
0.9
Power (PU) and Reactive Power (PU)

105%

0.6

Voltage (PU)
100%
Voltage (PU)
PU))
Night
0.3
Shutdown

© Copyright 2013, First Solar, Inc.


95%
0.0
The PV plant is asked to
Reactive Power (PU)
support voltage by APS
Operators.
-0.3 90%
4:00 8:00 12:00 16:00
Time of Day 7

Vous aimerez peut-être aussi