Vous êtes sur la page 1sur 24

Door D - 1.2 X 2.

1
Window W - 1.2 X 1.2
Length of long wall is = 13.3 m
Length of Short wall = 5.3 m.
Item Description No Length Width Depth Qty Total Remarks
No. . (m) (m) (m) Qty.
1

5
Earth work excavation :-

1. Earth work 2 13.3 1.0 0.9 23.94


Excavation:-
Long Wall
Short Wall 2 5.3 1.0 0.9 9.54 33.48 m3
Sand filling below foundation :-
2. Sand filling :- 2 13.3 1.0 0.15 3.99
Long Wall

Short Wall 2 5.3 1.0 0.15 1.59 5.58 m3


P.C.C layer with mix 1:4:8 below foundation :-
3. P.C.C layer:- 2 13.3 1.0 0.15 3.99
Long Wall

Short Wall 2 5.3 1.0 0.15 1.59 5.58 m3


Brick work in First footing :-
4. Long Wall 2 13.1 0.8 0.3 6.28

Short Wall 2 5.5 0.8 0.3 2.64 8.92 m3


Brick work in Second footing:-

5. Long Wall 2 12.9 0.6 0.3 4.644

Short Wall 2 5.7 0.6 0.3 2.05 6.696 m3


Brick work in Basement:-

6. Long Wall 2 12.8 0.5 0.45 5.76

Short Wall 2 5.8 0.5 0.45 2.61 8.37 m3


D.P.C layer with CM 1:1 over Basement – 50 mm thick:-
7. Long Wall 2 12.8 0.5 - 12.8

Short Wall 2 5.8 0.5 - 5.8 18.6 m2


Basement filling with river sand:-
The length in longer direction - 11.8 m.
Width length in shorter direction = 5.8 m and Depth = 0.3 m.

8. Basement filling with 1 11.8 5.8 0.3 20.53 20.53 m3


sand
Flooring Concrete with P.C.C mix 1:4:8 :-

The length in longer direction - 11.8 m.

Width length in shorter direction = 5.8 m and Depth = 0.15 m.

9. Flooring Concrete with 1 11.8 5.8 0.15 10.27 10.27 m3


Mix 1:4:8
Floor finishing with CM 1:3 :-
The length in longer direction - 12.0 m.
Width length in shorter direction = 6.0 m and Depth = 50 mm.

10. Floor finishing with 1 12.0 6.0 - 72 72 m2


CM 1:3
Brick work in super structure with CM 1:5

11. Long Wall 2 12.6 0.3 3.0 22.68


Short Wall 2 6 0.3 3.0 10.8
Parapet wall Long 2 12.6 0.3 1.0 7.56
wall
Short wall 2 6 0.3 1.0 3.6 44.64 m3

Deductions in Brick
work with CM 1:5
Lintel 1 37.2 0.3 0.15 1.674

Door 1 1.2 0.3 2.1 0.756


Window 5 1.2 0.3 1.2 2.16 4.59 m3
Total Brick work in Super structure and Parapet wall 40.05 m3
R.C.C WITH MIX 1:2:4 - Lintel, sunshade and Roof Slab

12. R.C.C ROOF SLAB 1 12.6 6.6 0.15 12.47 m3 14.65 m3


WITH MIX 1:2:4
Lintel – Long Wall 2 12.6 0.3 0.15 1.134 m3
Lintel – Short Wall 2 6 0.3 0.15 0.54 m3
R.C.C LINTEL CUM 6 1.5 0.45 0.125 0.506 m3
SUNSHADE WITH MIX
1:2:4 - SUNSHADE
13. Inner Plastering work 1 12.0 6.0 - 72.0 m2
with CM 1:3 – 12mm
thick - Ceiling
Plastering
Sunshade plastering 6x 1.5 0.45 - 8.1 m2 80.1 m2
work with CM 1:3 – 12 2
mm thick

Inner wall plastering 2 12 - 3.0 72.0 m2


with CM 1:4 – 12 mm
thick Long wall
Inner wall plastering 2 6 - 3.0 36.0 m2
with CM 1:4 – 12 mm
thick Short wall

Outer Plastering work 2 12.6 - 5.95 149.9 m2


with CM 1:4 – 12 mm
thick Long wall
Outer Plastering work 2 6.6 - 5.95 78.54m2 228.48 m2
with CM 1:4 – 12 mm
thick Short wall
Inner wall plastering 108.0 m2
with CM 1:4 – 12 mm
thick
Outer Plastering work 228.48 m2 336.48 m2
with CM 1:4 – 12 mm
thick
Deductions in 1 1.2 - 2.1 2.52 m2
plastering work with
CM 1:4 - Door
Deductions in 5 1.2 - 1.2 7.2 m2 9.72 m2
plastering work with
CM 1:4 - Window
Total wall Plastering work with CM 1:4, After deductions 326.76m2

Total Plastering work (80.1 + 326.76) 406.l86m2


14. Weather proof coarse 1 12.2 - 6.2 75.64 m2 75.64 m2
over roof slab with lime
and brick jelly coarse
finished with tiles
15. White and colour Qty. taken from Item no. 13 406.l86m2
washing
ABSTRACT ESTIMATE

Sl. Item Qty. Unit Rate Per Cost


No.
1 Earth work in foundation 33.48 m3 m3
2 Sand filling below footing with river sand 0.558 m3 m3
3 P.C.C layer with 1:4:8, below footing 0.558 m3 m3
4 Brick work in I & II footing with CM 1:4 15.62 m3 m3
5 Brick work in Basement wit CM 1:4 8.37 m3 m3
6
7