Activity / Scope Milestone date

Clearing and Grubbing 3/15/2018


Soil Excavation 4/12/2018
Weathered Rock Excavation 6/20/2018
Rock Excavation 8/4/2018
Hauling and Disposal 9/10/2018
Installation of Reinforced Concrete Pipe 10/14/2018
Embankment 10/26/2018
Slope Protection Works 11/11/2018
Sub-base Preparation 12/7/2018
Base Course 12/17/2018
Concreting Works 1/17/2019
Miscellenous Works 2/15/2019
`