Assignment 2

Construct an activity on arrow network based on the activity described below. Show all your
work, label activities in the network by their activity letters and node numbers. Remove any
redundant dependencies and label dummy activities.

NO. Activity name Precedence Duration


1 T1 - 3
2 R2 - 4
3 H - 2
4 D2 T1 6
5 W T1 9
6 S T1 10
7 E1 T1,R2 8
8 X H 6
9 F D2,W 5
10 P2 D2,W 7
11 P1 W 6
12 T2 S,E1,H 3
13 R1 F,P2 7
14 O2 P1,T2 9
15 E F,P2,P1,T2 10
16 L O2,X 11
17 G L 5
Float Calculations
Activity name duration Early Late Late start Early Total Critical
star finish fininsh float activity
T1 3 0 3 0 3 0 yes

R2 4 0 7 0 4 3 No

H 2 0 15 0 2 13 No

D2 6 3 26 3 12 17 No

W 9 3 12 3 12 0 yes

S 10 3 15 3 13 2 No

E1 8 4 15 7 13 3 No

X 6 2 27 15 27 19 No

F 5 12 33 26 17 16 No

P2 7 12 33 26 19 14 No

P1 6 12 18 12 18 0 yes

T2 3 13 18 15 18 2 No

R1 7 19 43 33 43 16 No

O2 9 18 27 18 27 0 yes

E 10 19 43 33 43 14 No

L 11 27 38 27 38 0 yes

G 5 38 43 38 43 0 yes