Vous êtes sur la page 1sur 15

DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola

1 SSS VS. MOONWALK DEVELOPMENT AND HOUSING notify Lustre until 16 months later when it wrote its
CORPORATION demand letter to Lustre.
SC: Lustre cannot be held liable for damages. Article
FACTS: 1170 of the Civil Code states that: those who in the
o Plaintiff SSS approved the application of Defendant performance of their obligations are guilty of delay are
Moonwalk for a loan of P30,000,000 for the purpose liable for damages. The delay in the performance of the
of developing and constructing a housing project. obligation, however, must be either malicious or
o Out of P30,000,000 approved loan, the sum of negligent. ICAB, there is no imputation, much less
P9,595,000 was released to defendant Moonwalk. evidence, that Lustre acted with malice or negligence in
o A third Amendment Deed of Mortgage was failing to sign the check. Such omission was mere
executed for the payment of the amount of inadvertence on the part of Lustre.
P9,595,000. FACTS:
o Moonwalk made a total payment of P23,657,901.84 Atty. Felipe Lustre purchased a Toyota Corolla from
to SSS for the loan principal of P12,254,700. Toyota Shaw, Inc. He made a down payment, and the
o After settlement of the account, SSS issued to balance of the purchase price to be paid in 24 equal
Moonwalk the release of Mortgage for Moonwalk’s monthly installments. Lustre thus issued 24 postdated
Mortgaged properties. checks. The 1st was dated 10 April 1991, subsequent
o In letter to Moonwalk, SSS alleged that it committed checks were dated every 10th of each succeeding
an honest mistake in releasing defendant. month.
o That Moonwalk has still 12% penalty for failure to As security, Lustre executed a contract of chattel
pay on time the amortization which is in the mortgage over the vehicle. Paragraph 11 thereof
penal clause of the contract. provided for an acceleration clause stating that should
o Moonwalk’s counsel told SSS that it had completely paid its the mortgagor default in the payment of any installment,
obligation to SSS and therefore there is no recovery the whole amount remaining unpaid shall become due.
of any penalty. In addition, the mortgagor shall be liable for 25% of the
principal due as liquidated damages.
ISSUE: Is the penalty demandable even after the Toyota Shaw assigned all its rights and interests in the
extinguishment of the principal obligation? chattel mortgage to RCBC.
The first 22 PDCs were encashed and debited by RCBC
HELD: No. There has been a waiver of the penal clause as from Lustre’s account, except the PDC dated 10 August
it was not demanded before the full obligation was fully paid 1991 (5th PDC out of 24 PDCs), which was unsigned.
and extinguished. Default begins from the moment the Previously, the amount of the 5th PDC was debited from
creditor demands the performance of the obligation. In Lustre’s account but was later recalled and re-credited to
this case, although there were late amortizations Lustre’s account. Because of the recall, RCBC refused
there was no demand made by SSS for the payment of the to encash the last 2 PDCs (pursuant to RCBC policy).
penalty hence Moonwalk is not in delay in the payment of Lustre was not informed of RCBC’s actions.
the penalty. No delay occurred and there was no On 21 January 1993, RCBC sent a demand letter to
occasion when the penalty became demandable and Lustre, demanding payment of balance of the debt (3
enforceable. Since there was no default in the installment payments), including liquidated damages.
performance of the main obligation-payment of the loan- Lustre refused. RCBC filed an action for replevin and
SSS was never entitled to recover any penalty. damages against Lustre. Lustre interposed a
If the demand for the payment of the penalty was made counterclaim for damages.
prior to the extinguishment of the obligation which
are: 1. principal obligation 2. The interest of 12% on the Procedure:
principal obligation 3.The penalty of 12% for late RTC: Dismissed RCBC’s complaint. RTC ordered RCBC
payment for after demand, Moonwalk would be in delay to accept the payment equivalent to the 3 checks and to
and therefore liable for the penalty. release/cancel the mortgage on the car. On the
counterclaim, RCBC ordered to pay Lustre moral
2 RCBC vs. CA damages, exemplary damages and attorney’s fees.
Short version/ Summary: RCBC filed an action for CA: Affirmed RTC.
replevin and damages against Felipe Lustre on the
ground that he defaulted in his payments of 3 PDCs Issue/s: WON Lustre is liable for damages on the
issued for installment payments of a Toyota Corolla. ground of delay in the performance of his obligation. NO.
The 4th PDC issued by Lustre was recalled for signature.
The subject check, however, was recalled only after the Held/Ratio:
amount covered thereby had been deducted from Assuming that Lustre was guilty of delay in payment of
Lustre’s account. It was subsequently re-credited back to the value of the unsigned check, he cannot be held liable
Lustre’s account for lack of signature. RCBC did not for damages. Article 1170 of the Civil Code states that:
those who in the performance of their obligations are
1
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
guilty of delay are liable for damages. The delay in the However, the materials were not delivered on time. The
performance of the obligation, however, must be petitioner went to the store several times to ask for the
either malicious or negligent. ICAB, there is no delivery. Eventually, the Petitioner was forced to dismiss
imputation, much less evidence, that Lustre acted with his hired workers since his materials did not arrive.
malice or negligence in failing to sign the check. Such Petitioner determined to fulfill his wife’s request,
omission was mere inadvertence on the part of Lustre. purchased materials from other stores. After his wife was
buried, Petitioner sued the Respondent for damages of
Toyota salesperson testified that he verified whether delay. Respondent claims that delay happened because
Lustre had signed all checks and in fact returned 3 or 4 of a fortuitous event since the truck tires were flat.
unsigned checks to him for signing. Lustre signed these Issue: Was there a delay in the performance of the
returned checks, and only then did the Toyota Respondent’s obligation?
salesperon release the car to Lustre.
Held: Yes. The Respondent was negligent and incurred
SC noted that RCBC did not object to the unsigned delay in performing his obligations. The Petitioner
check when all the PDCs were delivered to it by Toyota suffered as a consequence of the delay or contractual
Shaw. breach. There was a specific time, date and place
agreed upon the delivery of the materials. The said
In view of the lack of malice or negligence on the part of condition was agreed upon by both the Petitioner and
Lustre, RCBC’s blind and mechanical invocation of the Respondent.
paragraph 11 of the contract of chattel mortgage was There is a non performance of a reciprocal obligation
unwarranted. since according to Article 1169, the moment one of the
parties fulfill his obligation, delay by the other begins. In
SC also said that this whole controversy could have this contract of purchase and sale, the Petitioner had
been avoided if only RCBC bothered to call up Lustre already accomplished his part which is the payment of
and ask him to sign the check! RCBC failed to act with the price. It falls onto the Respondent now to
good faith and is therefore liable for moral damages immediately fulfill his obligation to deliver the goods
suffered by Lustre, who has been a client of RCBC for otherwise delay would attach. An award of moral
20 years. Lustre also suffered shame and damages is incumbent in this case as the Petitioner has
embarrassment after the case was filed as he was a suffered gravely.
lawyer, married to another lawyer, and known to the
community of golfers. SC also allowed exemplary 4 PANTALEON VS. AMEX
damages and attorney’s fees. FACTS: AMEX is a corporation engaged in providing
credit services through the operation of a charge card
3 BARZAGA VS. CA system. Pantaleon was a cardholder since 1980.
Facts: Ignacio Barzaga’s wife succumbed to a
debilitating ailment and died on December 19, 1990. Pantaleon, his wife, daughter and son went on a guided
Forewarned, she expressed her wish to be buried before European tour and subsequently arrived in Amsterdam.
Christmas. After her death on December 21, 1990 3pm, While in Coster Diamond House,his wife wanted to
Ignacio Barzaga (Petitioner) went to the hardware store purchase some diamond pieces, amounting to $13, 826.
of Angelito Alviar (Respondent) to inquire about the Pantaleon presented his credit card which was swiped.
availability of certain materials to be used in building his He was then asked to sign the charge slip which was
wife’s niche. Also asking if materials could be delivered electronically transferred to AMEX’s Amsterdam office.
at once, the Respondent’s employee replied that if the However, Coster was not able to receive approval from
store had pending deliveries that afternoon then all AMEX for the purchase so Pantaleon asked the clerk to
subsequent purchases made would be delivered the cancel the sale. The store manager convinced
following day. Pantaleon to wait for a few minutes and subsequently
told Pantaleon that AMEX was asking for bank
Petitioner left that day and returned the following day on references and Pantaleon responded by giving names of
December 22, 1990, 7am. Petitioner came to follow up his Phil. depository banks. Still, it was not approved. But
his purchase of construction materials, stressing to the Coster decided to release the items even without
employees of the hardware store that he would need the AMEX’s approval since the tour couldn’t go on without
materials to be delivered to the cemetery (only a them.
kilometer away from the hardware store) by 8 am as he
would have hired workers who would start working at the In all, it took AMEX a total of 78 minutes to approve
site. Respondent’s employee agreed to deliver at the Pantaleon’s purchase and to transmit the approval to the
specified time, date and place and with such assurance jewelry store.
Barzaga purchased the materials and paid in full P
2,100.00. This was followed by two similar incidents when the
family then had another trip to the US. They also
2
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
experienced inconvenience using the AMEX credit card petitioner before any delay would redound to the injury of
in purchasing golf equipment and children’s shoes. his several traveling companions – gave rise to the
moral shock, mental anguish, serious anxiety, wounded
When they got to Manila, Pantaleon sent a letter to feelings and social humiliation sustained by Pantaleon,
AMEX, demanding an apology for the humiliation and as concluded by the RTC.
inconvenience. AMEX responded that the delay in
Amsterdam was due to the amount involved, saying that 5 LORENZO SHIPPING vs. BJ MARTHEL
the purchase deviated from his established charge
purchase pattern. Dissatisfied, Pantaleon filed an action FACTS: Petitioner Lorenzo Shipping is engaged in
for damages in RTC. coastwise shipping and owns the cargo M/V Dadiangas
Express. BJ Marthel is engaged in trading, marketing an
The testimony of AMEX’s credit authorizer Edgardo dselling various industrial commodities. Lorenzo
Jaurique, the approval time for credit card charges would Shipping ordered for the second time cylinder lines from
be three to four seconds under regular circumstances. the respondent stating the term of payment to be 25%
Here, it took AMEX 78 minutes to approve the upon delivery, the balance payable in 5 bi-monthly equal
Amsterdam purchase. SC attributed the unwarranted installments, no again stating the date of the cylinder’s
delay to Jaurique, who had to go over Pantaleon’s past delivery. It was allegedly paid through post dated checks
credit history, his payment record and his credit and but the same was dishonored due to insufficiency of
bank references before he approved the purchase. funds. Despite due demands by the respondent,
In 2009, the SC reversed the ruling in CA; and said that petitioner failed contending that time was of the essence
AMEX was guilty of mora solvendi or debtor’s default. in the delivery of the cylinders and that there was a delay
AMEX as debtor had an obligation as the credit provider since the respondent committed said items “within two
to act on Pantaleon’s purchase requests, whether to months after receipt of fir order”. RTC held respondents
approve or disapprove them, with "timely dispatch." bound to the quotation with respect to the term of
payment, which was reversed by the Court of appeals
ISSUES: ordering appellee to pay appellant P954,000 plus
1. Whether or not AmEx had committed a breach of its interest. There was no delay since there was no
obligations to Pantaleon. demand.
2. Whether or not AmEx is liable for damages.
ISSUE: Whether or not respondent incurred delay in
RULING: performing its obligation under the contract of sale
1. Yes. The popular notion that credit card purchases
are approved “within seconds,” there really is no strict, RULING: By accepting the cylinders when they were
legally determinative point of demarcation on how long delivered to the warehouse, petitioner waived the
must it take for a credit card company to approve or claimed delay in the delivery of said items. Supreme
disapprove a customer’s purchase, much less one Court geld that time was not of the essence. There
specifically contracted upon by the parties. One hour having been no failure on the part of the respondent to
appears to be patently unreasonable length of time to perform its obligations, the power to rescind the contract
approve or disapprove a credit card purchase. is unavailing to the petitioner.

Petition is denied. Court of appeals decision is affirmed.


The culpable failure of AmEx herein is not the failure to
timely approve petitioner’s purchase, but the more 6 SOLAR HARVEST vs. DAVAO CORRUGATED
elemental failure to timely act on the same, whether FACTS:
favorably or unfavorably. Even assuming that AmEx’s Solar Harvest, Inc., entered into an agreement with
credit authorizers did not have sufficient basis on hand Davao Corrugated Carton Corp., for the purchase of
to make a judgment, we see no reason why it could not corrugated carton boxes, specifically designed for
have promptly informed Pantaleon the reason for the petitioner’s business of exporting fresh bananas.
delay, and duly advised him that resolving the same Petitioner deposited their full payment but alleged that
could take some time. they did not receive any boxes from respondent,
hence, they wrote a demand letter for reimbursement.
2. Yes. The reason why Pantaleon is entitled to Respondent, meanwhile, stated that the boxes had been
damages is not simply because AmEx incurred delay, completed and that petitioner failed to pick them up from
but because the delay, for which culpability lies under the former’s warehouse as agreed upon. Respondent
Article 1170, led to the particular injuries under Article also averred that petitioner even placed an additional
2217 of the Civil Code for which moral damages are order of 24,000 boxes without any advanced payment
remunerative. The somewhat unusual attending from petitioner. Respondent then demanded petitioner to
circumstances to the purchase at Coster – that there remove the boxes from the factory and to pay the
was a deadline for the completion of that purchase by
3
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
balance for the additional boxes as well as for the Cathay through which it accords its frequent flyers
storage fee. several privileges, including priority for upgrading of
RTC ruled in favor of respondent. CA affirmed and booking without any extra charge whenever an
averred that respondent would not be liable for breach of opportunity arises. Upon being informed of this change,
contract as petitioner had not yet demanded from it the Dr. Vasquez refused the same, saying that it would not
delivery of the boxes. look nice for them as hosts to travel in First Class and
ISSUE: Whether petitioner’s claim for reimbursement is their guests, in Business Class, not to mention that they
actually one for rescission of contract under Article 1191 also had to discuss business matters during the flight.
of the Civil Code. He asked Ms. Chiu to have other passengers transferred
instead. Shocked by this unusual reaction to a seat
HELD: upgrade, Ms. Chiu, after consulting with her supervisor,
Art. 1191. The power to rescind obligations is implied in informed them that if they would not avail of the
reciprocal ones, in case one of the obligors should not privilege, they would not be allowed to take the flight.
comply with what is incumbent upon him. Eventually, after talking with his friends, Dr. Vasquez
The right to rescind a contract arises once the other agreed. He and his wife took the First Class Cabin. Back
party defaults in the performance of his obligation. In in Manila, after apparent inaction on the part of Cathay,
determining when default occurs, Art. 1191 should be the Vasquezes filed a damage suit, asking for
taken in conjunction with Art. 1169 of the same law, temperate, moral and exemplary damages, as well as
which provides: attorney’s fees. They attributed discourteous and
Art. 1169. Those obliged to deliver or to do something humiliating behavior to Ms. Chiu. Cathay answered that
incur in delay from the time the obligee judicially or seat upgrading is a common practice among airlines.
extrajudicially demands from them the fulfillment of their
obligation. The TC ruled for the spouses, awarding them nominal
However, the demand by the creditor shall not be (P100,000 each), moral (P2M each), exemplary (P5M
necessary in order that delay may exist: each) and attorney’s fees (P1M each). The CA
1. When the obligation or the law expressly so declares; affirmed, but deleted the award of exemplary damages
or and reduced the awards of moral and nominal damages
2. When from the nature and the circumstances of the and attorney’s fees.
obligation it appears that the designation of the time
when the thing is to be delivered or the service is to ISSUES:
be rendered was a controlling motive for the 1. WON Cathay breached its contract of carriage with
establishment of the contract; or the Vs when it upgraded their seat accommodation.
3. When demand would be useless, as when the obligor
has rendered it beyond his power to perform. 2. WON the upgrading was made in bad faith or with
Evident from the records was the lack of demand by fraud.
petitioner upon respondent to fulfill its obligation to
manufacture and deliver the boxes. Without a previous 3. WON the Vasquezes are entitled to damages.
demand for the fulfillment of the obligation, petitioner
would not have a cause of action for rescission against RULING
respondent as the latter would not yet be considered in
breach of its contractual obligation. 1. YES. The Vazquezes never denied that they were
members of Cathay’s Marco Polo Club. They knew
7 CATHAY PACIFIC VS. SPS. VASQUEZ that as members of the Club, they had priority for
upgrading of their seat accommodation at no extra cost
FACTS: Private respondents were passengers of when an opportunity arises. But, just like other
petitioner booked on its Flight CX-905 with the route of privileges, such priority could be waived. The Vazquezes
Manila to Hongkong and back. They, along with their should have been consulted first whether they wanted to
maid and two friends, went to HK for pleasure and avail themselves of the privilege or would consent to a
business. While the maid’s boarding pass was for change of seat accommodation before their seat
the Economy Class, the spouses’ and their two assignments were given to other passengers. Normally,
friends’ indicated that they were on the Business one would appreciate and accept an upgrading, for it
Class. However, while in Kai Tak Airport, after checking would mean a better accommodation. But, whatever
in their luggage and presenting their boarding passes to their reason was and however odd it might be, the
the ground stewardess, they were informed by Ms. Chiu, Vazquezes had every right to decline the upgrade and
a ground attendant, that there was a seat change from insist on the Business Class accommodation they had
Business to First Class for the spouses. It is to be noted booked for and which was designated in their boarding
that the Vasquezes are frequent flyers of the airline and passes. They clearly waived their priority or preference
are Gold Card members of its Marco Polo Club. The when they asked that other passengers be given the
Marco Polo Club is part of the marketing strategy of upgrade. It should not have been imposed on them over
4
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
their vehement objection. By insisting on the upgrade, awards for moral and exemplary damages are
Cathay breached its contract of carriage with the eliminated, so must the award for attorney’s fees.
Vazquezes.
The most that can be adjudged in favor of the
2. NO. The Vazquezes were not induced to agree to Vazquezes for Cathay’s breach of contract is an
the upgrading through insidious words or deceitful award for nominal damages under Article 2221 of the
machination or through willful concealment of material Civil Code, which reads as follows:
facts. Upon boarding, Ms. Chiu told the Vazquezes that
their accommodations were upgraded to First Class in Article 2221. Nominal damages are adjudicated in order
view of their being Gold Card members of Cathay’s that a right of the plaintiff, which has been violated or
Marco Polo Club. She was honest in telling them that invaded by the defendant, may be vindicated or
their seats were already given to other passengers and recognized, and not for the purpose of indemnifying the
the Business Class Section was fully booked. Ms. Chiu plaintiff for any loss suffered by him.
might have failed to consider the remedy of offering the
First Class seats to other passengers. But, we find no MERALCO vs. RAMOY
bad faith in her failure to do so, even if that amounted to FACTS: The National Power Corporation (NPC) won an
an exercise of poor judgment. Neither was the transfer of ejectment case against several persons allegedly
the Vazquezes effected for some evil or devious illegally occupying its properties in Baesa, Quezon City.
purpose. As testified to by Mr. Robson, the First Class To execute such, NPC requested from MERALCO that
Section is better than the Business Class Section in the electrical service connection of those residential and
terms of comfort, quality of food, and service from the commercial establishments beneath the NPC lines be
cabin crew. immediately disconnected and MERALCO agreed upon
determination of the affected establishments by NPC.
3. YES. Case law establishes the following requisites One of which includes the residence of the plaintiffs- the
for the award of moral damages: (1) there must be an Ramoys.
injury clearly sustained by the claimant, whether ISSUE: WON MERALCO is liable for damages to the
physical, mental or psychological; (2) there must be a Ramoys for the sudden disconnection of their electric
culpable act or omission factually established; (3) the power supply.
wrongful act or omission of the defendant is the
proximate cause of the injury sustained by the claimant; HELD: Yes. MERALCO is liable for damages to the
and (4) the award for damages is predicated on any of Ramoys for the sudden disconnection of their electric
the cases stated in Article 2219 of the Civil Code. power supply which turned out to be without any valid
ground, pursuant to Articles 1170 and 1173 of the Civil
Moral damages predicated upon a breach of contract of Code. Therefore, MERALCO failed to exercise the
carriage may only be recoverable in instances where the required utmost diligence as a public utility service
carrier is guilty of fraud or bad faith or where the mishap provider, hence, liable for culpa-contractual being
resulted in the death of a passenger. Where in breaching negligent in its performance of its obligation derived from
the contract of carriage the airline is not shown to have the Service Contract between MERALCO and its
acted fraudulently or in bad faith, liability for damages is consumers, one of which is the Ramoys.
limited to the natural and probable consequences of the
breach of the obligation which the parties had foreseen 9 AREOLA vs. CA
or could have reasonably foreseen. In such a case the FACTS: Prudential Guarantee cancelled Areola’s
liability does not include moral and exemplary damages. personal accident insurance on the grounds that the
The breach of contract of carriage, which consisted in latter failed to pay his premiums 7 months after issuing
the involuntary upgrading of the Vazquezes’ seat the policy. Areola was supposed to pay the total amount
accommodation, was not attended by fraud or bad faith. of P1,609.65 which included the premium of P1,470.00,
The Court of Appeals’ award of moral damages has, documentary stamp of P110.25 and 2% premium tax of
therefore, no leg to stand on. P29.40. The statement of account had a stipulation not
considering it a receipt. It also reminded the customer to
The deletion of the award for exemplary damages by the ask for a receipt after payment. There was also a
Court of Appeals is correct. It is a requisite in the grant of stipulation calling for a demand for a provisional receipt
exemplary damages that the act of the offender must be after payment to an agent. A provisional receipt was sent
accompanied by bad faith or done in wanton, fraudulent to petitioner telling him that the provisional receipt would
or malevolent manner. Such requisite is absent in this be confirmed by an official one. The company then
case. Moreover, to be entitled thereto the claimant must cancelled the policy for non-payment of premiums. After
first establish his right to moral, temperate, or being surprised, Areola confronted a company agent and
compensatory damages. Since the Vazquezes are not demanded an official receipt. The latter told him that it
entitled to any of these damages, the award for was a mistake, but never gave him an official receipt.
exemplary damages has no legal basis. And where the Areola sent a letter demanding that he be reinstated or
5
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
he would file for damages if his demand was not met. Prudential averred that the equitable relief sought by
The company then told him that his payments weren’t in petitioner-insured was granted to the filing of the
full yet. The company replied to Areola by telling him that complaint, petitioner-insured is left without a cause of
there was reason to believe that no payment has been action. Reinstatement effectively restored petitioner-
made since no official receipt was issued. The company insured to all his rights under the policy.
then told him that they would still hold him under the
policy. The company then confirmed that he paid the The court held that Malapit's fraudulent act of
premium and that they would extend the policy by one misappropriating the premiums paid by petitioner-
year. insured is directly imputable to respondent insurance
company. A corporation, such as respondent insurance
Thereby, the company offered to reinstate same policy it company, acts solely thru its employees. The latters'
had previously cancelled and even proposed to extend acts are considered as its own. Malapit represented its
its lifetime on finding that the cancellation was erroneous interest and acted in its behalf. His act of receiving the
and that the premiums were paid in full by petitioner- premiums collected is well within the province of his
insured but were not remitted by the authority. Thus, his receipt of said premiums is receipt
company's branch manager, Mr. Malapit. by private respondent insurance company who, by
provision of law is bound by the acts of its agent.
However, they were too late for Areola already filed an
action for breach of contract in the trial court. Article 1910 thus reads:
Art. 1910. The principal must comply with all the
The company’s defense lay in rectifying its omission; obligations which the agent may have contracted within
hence, there was no breach of contract. the scope of his authority.
As for any obligation wherein the agent has exceeded
The court ruled in favor of Areola and asked Prudential his power, the principal is not bound except when he
to pay 250,000 pesos in moral and exemplary damages. ratifies it expressly or tacitly.
The court held that the company was in bad faith in
cancelling the policy. Had the insured met an accident at Malapit's failure to remit the premiums he received
that time, he wouldn’t be covered by the policy. cannot constitute a defense for private respondent
This ruling was challenged on appeal by respondent insurance company; no exoneration from liability could
insurance company, denying bad faith in unilaterally result therefrom. The fact that private respondent
cancelling the policy. The AC absolved Prudential on the insurance company was itself defrauded due to the
grounds that it was not motivated by negligence, malice anomalies that took place does not free the same from
or bad faith in cancelling subject policy. Rather, the its obligation to petitioner Areola. As held in Prudential
cancellation of the insurance policy was based on what Bank v. Court of Appeals
the existing records showed. The court even added that
the errant manager who didn’t remit the profits was “A bank is liable for wrongful acts of its officers done in
forced to resign. Areola then filed for a petition in the the interests of the bank or in the course of dealings of
Supreme Court. the officers in their representative capacity but not for
acts outside the scope of their authority. Accordingly,
ISSUES: 1. Did the erroneous act of cancelling subject a banking corporation is liable to innocent third persons
insurance policy entitle petitioner-insured to payment of where the representation is made in the course of its
damages? business by an agent acting within the general scope of
2. Did the subsequent act of reinstating the wrongfully his authority even though the agent is secretly abusing
cancelled insurance policy by respondent insurance his authority and attempting to perpetrate a fraud upon
company, in an effort to rectify such error, obliterate his principal or some other person.”
whatever liability for damages it may have to bear, thus
absolving it? Prudential is liable for damages for the fraudulent acts
committed by Malapit. Reinstating the insurance policy
HELD: Yes. No. Petition granted. cannot obliterate the injury inflicted. A contract of
insurance creates reciprocal obligations for both insurer
RATIO: and insured. Reciprocal obligations are those which
1. Petitioner alleged that the manager’s misappropriation arise from the same cause and in which each party is
of his premium payments is the proximate cause of the both a debtor and a creditor of the other, such that the
cancellation of the insurance policy. Subsequent obligation of one is dependent upon the obligation of the
reinstatement could not possibly absolve respondent other.
insurance company from liability, due to the breach of
contract. He contended that damage had already been 2. Due to the agreement to enter into a contract of
done. insurance where Prudential promised to extend
protection to petitioner-insured against the risk insured,
6
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
there was a debtor creditor relationship between the two was a strong wind, and a strong wind in this case is not
parties. Under Article 1191, the injured party is given a fortuitous, it was neither unforeseeable nor unavoidable,
choice between fulfillment or rescission of the obligation places with strong winds are the perfect locations to put
in case one of the obligors fails to comply with what is up a windmill, since it needs strong winds for it to work.
incumbent upon him. However, said article entitles the
injured party to payment of damages, regardless of HELD: WHEREFORE, the appealed decision is
whether he demands fulfillment or rescission of the MODIFIED. Respondent VICENTE HERCE JR. is
obligation. directed to pay petitioner JACINTO M. TANGUILIG the
balance of P15,000.00 with interest at the legal rate from
The damages would be nominal because the insurance the date of the filing of the complaint. In return, petitioner
company took steps to rectify the contract. There was is ordered to "reconstruct subject defective windmill
also no actual or substantial damage inflicted. Nominal system, in accordance with the one-year guaranty" and
damages are "recoverable where a legal right is to complete the same within three (3) months from the
technically violated and must be vindicated against an finality of this decision.
invasion that has produced no actual present loss of any
kind, or where there has been a breach of contract and Obligations and Contracts Terms: Fortuitous Events-
no substantial injury or actual damages whatsoever have Refers to an occurrence or happening which could not
been or can be shown.” be foreseen, or even if foreseen, is inevitable. It is
necessary that the obligor is free from negligence.
10 TANGUILIG vs. CA Fortuitous events may be produced by two (2) general
causes: (1) by Nature, such as but not limited to,
FACTS: Herce contracted Tanguilig to construct a earthquakes, storms, floods, epidemics, fires, and (2) by
windmill system for him, for consideration of 60,000.00. the act of man, such as but not limited to, armed
Pursuant to the agreement Herce paid the downpayment invasion, attack by bandits, governmental prohibitions,
of 30,000.00 and installment of 15,000.00 leaving a robbery, provided that they have the force of an
15,000.00 balance. Herce refused to pay the balance imposition which the contractor or supplier could not
because he had already paid this amount to SPGMI have resisted.
which constructed a deep well to which the windmill
system was to be connected since the deepwell, and 11 NAKPIL & SONS vs. CA
assuming that he owed the 15,000.00 this should be FACTS: Private respondents – Philippine Bar
offset by the defects in the windmill system which Association (PBA) – a non-profit organization formed
caused the structure to collapse after strong winds hit under the corporation law decided to put up a building in
their place. According to Tanguilig, the 60,000.00 Intramuros, Manila. Hired to plan the specifications of
consideration is only for the construction of the windmill the building were Juan Nakpil & Sons, while United
and the construction of the deepwell was not part of it. Construction was hired to construct it. The proposal was
The collapse of the windmill cannot be attributed to him approved by the Board of Directors and signed by the
as well, since he delivered it in good and working President, Ramon Ozaeta. The building was completed
condition and Herce accepted it without protest. Herce in 1966.
contested that the collapse is attributable to a typhoon, a
force majeure that relieved him of liability. The RTC In 1968, there was an unusually strong earthquake
ruled in favor of Tanguilig, but this decision was which caused the building heavy damage, which led the
overturned by the Court of Appeals which ruled in favor building to tilt forward, leading the tenants to vacate the
of Herce. premises. United Construction took remedial measures
to sustain the building.
ISSUE: Can the collapse of the windmill be attributed to
force majeure? Thus, extinguishing the liability of PBA filed a suit for damages against United
Tanguilig? - Yes, in order for a party to claim exemption Construction, but United Construction subsequently filed
from liability by reason of fortuitous event under Art 1174 a suit against Nakpil and Sons, alleging defects in the
of the Civil Code the event should be the sole and plans and specifications.
proximate cause of the loss or destruction of the object
of the contract. - In Nakpil vs. Court of Appeals, the S.C. Technical Issues in the case were referred to Mr. Hizon,
held that 4 requisites must concur that there must be a as a court appointed Commissioner. PBA moved for the
(a) the cause of the breach of the obligation must be demolition of the building, but was opposed. PBA
independent of the will of debtor (b) the event must be eventually paid for the demolition after the building
either unforeseeable or unavoidable; (c) the event be suffered more damages in 1970 due to previous
such to render it impossible for the debtor to fulfill his earthquakes. The Commissioner found that there were
obligation in a normal manner; and (d) the debtor must deviations in the specifications and plans, as well as
be free from any participation in or aggravation of the defects in the construction of the building.
injury to the creditor. - Tanguilig merely stated that there
7
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
ISSUE: Whether or not an act of God (fortuitous event) Luzon Stevedoring knew the perils posed by the swollen
exempts from liability parties who would otherwise be stream and its swift current, and voluntarily entered into
due to negligence? a situation involving obvious danger; it therefore assured
the risk, and cannot shed responsibility merely because
HELD: Art. 1723 dictates that the engineer/architect and the precautions it adopted turned out to be insufficient. It
contractor are liable for damages should the building is thus liable for damages.
collapse within 15 years from completion.
 FAR EAST BANK & TRUST CO. vs. CA
Art. 1174 of the NCC, however, states that no person FACTS: Private respondent Luis A. Luna applied for,
shall be responsible for events, which could not be and was accorded, a Fareast card issued by petitioner
foreseen. But to be exempt from liability due to an act of FEBTC.
God, the ff must occur:
Clarita informed FEBTC that she lost her credit card. In
1) cause of breach must be independent of the will of the order to replace the lost card, Clarita submitted an
debtor affidavit of loss. In cases of this nature, the bank's
2) event must be unforeseeable or unavoidable internal security procedures and policy would
3) event must be such that it would render it impossible be torecord the lost card, along with the principal card,
for the debtor to fulfill the obligation as a "HotCard" or "Cancelled Card" in its master file.
4) debtor must be free from any participation or
aggravation of the industry to the creditor. Luis then tendered a despedida lunch for a close friend.
When he presented his fareast card to pay for the lunch,
In the case at bar, although the damage was ultimately the card was not honored, forcing him to pay in cash the
caused by the earthquake which was an act of God, the bill. Naturally, Luis felt embarrassed by this incident.
defects in the construction, as well as the deviations in
the specifications and plans aggravated the damage, Private respondent Luis Luna, through counsel,
and lessened the preventive measures that the building demanded from FEBTC the payment of damages.
would otherwise have had. Adrian V. Festejo, a vice-president of the bank,
expressed the bank's apologies, admitting that they have
12 REPUBLIC vs. LUZON STEVEDORING failed to inform Luis about its security policy.
FACTS: A barge being towed by tugboats "Bangus" and
"Barbero" all owned by Luzon Stevedoring Corp. Private respondents then filed a complaint for damages
rammed one of the wooden piles of the Nagtahan Bailey in the RTC, which rendered a decision ordering FEBTC
Bridge due to the swollen current of the Pasig after to pay private respondents moral damages, exemplary
heavy rains days before. The Republic sued Luzon damages, and attorney’s fees.
Stevedoring for actual and consequential damages.
Luzon Stevedoring claimed it had exercised due ISSUE: Whether or not private respondents are entitled
diligence in the selection and supervision of its of moral damages.
employees; that the damages to the bridge were caused
by force majeure; that plaintiff has no capacity to sue; HELD: NO. In culpa contractual, moral damages may
and that the Nagtahan Bailey bridge is an obstruction to be recovered where the defendant is shown to have
navigation. acted in bad faith or with malice in the breach of the
contract.
ISSUE: Whether or not the collision of appellant's barge
with the supports or piers of the Nagtahan bridge was in Concededly, the bank was negligent for failing to inform
law caused by fortuitous event or force majeure. Luis of his own card's cancellation. Nothing in the
findings of the trial court and the appellate court can
HELD: There is a presumption of negligence on part of sufficiently indicate any deliberate intent on the part of
the employees of Luzon Stevedoring, as the Nagtahan FEBTC to cause harm to private respondents. The
Bridge is stationary. For caso fortuito or force failure to inform Luis is not considered to be so gross
majeure (which in law are identical in so far as they that it would amount to malice or bad faith. Malice or bad
exempt an obligor from liability) by definition, are faith implies a conscious and intentional design to do a
extraordinary events not foreseeable or avoidable, wrongful act for a dishonest purpose or moral obliguity; it
"events that could not be foreseen, or which, though is different from the negative idea of negligence in that
foreseen, were inevitable" (Art. 1174, Civ. Code of the malice or bad faith contemplates a state of mind
Philippines). It is, therefore, not enough that the event affirmatively operating with furtive design or ill-will.
should not have been foreseen or anticipated, as is
commonly believed, but it must be one impossible to Article 21 of the Code contemplates a conscious act to
foresee or to avoid. The mere difficulty to foresee the cause harm. In relation to a breach of contract, its
happening is not impossibility to foresee the same. application can be warranted only when the defendant's
8
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
disregard of his contractual obligation is so deliberate as respondents Security Consultant to Galaxy and its
to approximate a degree of misconduct certainly no less security guards are ordinarily no more than requests
worse than fraud or bad faith. Most importantly, Article commonly envisaged in the contract for services entered
21 is a mere declaration of a general principle in human into by a principal and a security agency. They cannot
relations that clearly must, in any case, give way to the be construed as the element of control as to treat
specific provision of Article 2220 of the Civil Code respondents as the employers of Rosete.
authorizing the grant of moral damages in culpa
contractual solely when the breach is due to fraud or bad 15 FIL ESTATE PROPERTIES vs. SPS RONQUILLO
faith. FACTS: On December 29, 1995, petitioner Fil-Estate
Properties, Inc. (Fil-Estate) entered into a contract to sell
The decision is modified by deleting the award of moral a condominium unit to respondent spouses Gonzalo and
and exemplary damages to private respondents; in its Consuelo Go. The spouses paid a total of P3,
stead, petitioner is ordered to pay nominal damages 439,000.07 of the full contract price set at P3,
sanctioned under Article 2221 of the Civil Code 620,000.00.

14 SALUGADA vs. FEU Fil-Estate failed to develop the condominium project. On


FACTS: Petitioner Joseph Saludaga was a sophomore August 4, 1999, the spouses demanded the refund of
law student of respondent Far Eastern University (FEU) the amount they paid, plus interest. When Fil-Estate did
when he was shot by Alejandro Rosete (Rosete), one of not refund the spouses, the latter filed a complaint
the security guards on duty at the school premises on against petitioner for reimbursement plus interest before
August 18, 1996. Petitioner was rushed to FEU-Dr. the Housing and Land Use Regulatory Board (HLURB).
Nicanor Reyes Medical Foundation (FEU-NRMF) due to In answer, Fil-Estate claimed that respondents had no
the wound he sustained. Meanwhile, Rosete was cause of action since the delay in the construction of the
brought to the police station where he explained that the condominium was caused by the financial crisis that hit
shooting was accidental. Saludaga thereafter filed a the Asian region, a fortuitous event over which petitioner
complaint for damages against respondents on the had no control.
ground that they breached their obligation to provide
students with a safe and secure environment and an HLURB Regional Director approved the decision of the
atmosphere conducive to learning. Respondents, in turn, Housing and Land Use Arbiter in favor of the spouses
filed a Third-Party Complaint against Galaxy Go. The Court of Appeals affirmed the actions taken by
Development and Management Corporation (Galaxy), the HLURB and the Office of the President and declared
the agency contracted by respondent FEU to provide that the Asian financial crisis could not be considered a
security services within its premises and Mariano D. fortuitous event.
Imperial (Imperial), Galaxys President, to indemnify them
for whatever would be adjudged in favor of petitioner, if Fil-Estate explained that the extreme economic exigency
any; and to pay attorneys fees and cost of the suit. and extraordinary currency fluctuations could not have
been reasonably foreseen and were beyond the
ISSUES: What is the source of FEU’s obligation to contemplation of both parties when they entered the
indemnify Saludaga? What is needed to prove that this contract. It further asserted that the resultant economic
obligation of FEU exists? collapse of the real estate industry was unforeseen by
the whole Asia and if it was indeed foreseeable, then all
In the alternative, is FEU vicariously liable under Article those engaged in the real estate business should have
2180 of the Civil Code. foreseen the impending fiasco.

HELD: Culpa contractual. It is settled that in culpa ISSUE: Whether or not the Asian financial crisis could be
contractual, the mere proof of the existence of the considered a fortuitous event.
contract and the failure of its compliance justify, prima
facie, a corresponding right of relief. In the instant case, HELD: No. The Supreme Court held that the Asian
we find that, when petitioner was shot inside the campus financial crisis cannot be generalized as unforeseeable
by no less the security guard who was hired to maintain and beyond the control of the business corporation. A
peace and secure the premises, there is a prima facie real estate enterprise engaged in the pre-selling of
showing that respondents failed to comply with its condominium units is concededly a master in projections
obligation to provide a safe and secure environment to on commodities and currency movements and business
its students. risks. The fluctuating movement of the Philippine peso in
the foreign exchange market is an everyday occurrence,
No. Respondents cannot be held liable for damages and fluctuations in currency exchange rates happen
under Article 2180 of the Civil Code because every day, thus, not an instance of caso fortuito.
respondents are not the employers of Rosete. The latter
was employed by Galaxy. The instructions issued by 17 SEONE vs. FRANCO
9
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
Lulu, joined by her husband Cesar, filed a complaint
FACTS: This is an appeal from a judgment of the Court against Sicam with the RTC of Makati seeking
of First Instance of Zamboanga in favor of the plaintiff, indemnification for the loss of pawned jewelry and
holding that the right of action upon the mortgage debt payment of AD, MD and ED as well as AF.
which was the basis of the claim presented against the
plaintiff’s estate had already prescribed. The mortgage in The RTC rendered its Decision dismissing respondents’
question, which is to secure the payment of the sum of complaint as well as petitioners’ counterclaim.
P4,876.01, the debtor agreeing to pay the sum “little by Respondents appealed the RTC Decision to the CA
little.” After 27 years, nothing has been paid either of the which reversed the RTC, ordering the appellees to pay
principal or of the interest. The obligation seems to leave appellants the actual value of the lost jewelry and AF.
the duration of the period for the payment thereof to the Petitioners MR denied, hence the instant petition for
will of the debtor. It appears also that it was the intention review on Certiorari.
of the instrument to give the debtor time within which to
pay the obligation. ISSUE: Are the petitioners liable for the loss of the
pawned articles in their possession? (Petitioners insist
ISSUE: Whether or not the creditor may demand that they are not liable since robbery is a fortuitous event
immediate performance of the obligation, given that and they are not negligent at all.)
there is no date stipulated by the parties as to when it
should become due and payable. HELD: The Decision of the CA is AFFIRMED. YES
Article 1174 of the Civil Code provides:
HELD: In such cases this court has held, on several Art. 1174. Except in cases expressly specified
occasions, that the obligation is not due and payable by the law, or when it is otherwise declared by
until an action has been commenced by the mortgagee stipulation, or when the nature of the obligation requires
against the mortgagor for the purpose of having the the assumption of risk, no person shall be responsible
court fix the date on and after which the instrument shall for those events which could not be foreseen or which,
be payable and the date of maturity is fixed in pursuance though foreseen, were inevitable.
thereof. Such being the case, as action should have
been brought for the purpose of having the court set a Fortuitous events by definition are extraordinary events
date on which the instrument should become due and not foreseeable or avoidable. It is therefore, not enough
payable. Until such action was prosecuted no suit could that the event should not have been foreseen or
be instrument. It is, therefore, clear that this action is anticipated, as is commonly believed but it must be one
premature. The instrument has been sued upon before it impossible to foresee or to avoid. The mere difficulty to
is due. The action must accordingly be dismissed. foresee the happening is not impossibility to foresee the
Ordinarily when an action of this sort is dismissed the same.
plaintiff may at once begin his action for the purpose of
fixing a date upon which the instrument shall become To constitute a fortuitous event, the following elements
due. From the undisputed facts in this case and from the must concur:
facts and conditions that very probably cannot be (a) the cause of the unforeseen and unexpected
charged hereafter, it is our present opinion that such occurrence or of the failure of the debtor to comply with
action is itself prescribed. The judgment was affirmed, obligations must be independent of human will;
with cost against the appellant. (b) it must be impossible to foresee the event that
constitutes the caso fortuito or, if it can be foreseen, it
19 SICAM vs. JORGE must be impossible to avoid;
(c) the occurrence must be such as to render it
FACTS: On different dates, Lulu Jorge pawned several impossible for the debtor to fulfill obligations in a normal
pieces of jewelry with Agencia de R. C. Sicam located in manner; and,
Parañaque to secure a loan. (d) the obligor must be free from any participation in the
aggravation of the injury or loss.
On October 19, 1987, two armed men entered the
pawnshop and took away whatever cash and jewelry The burden of proving that the loss was due to a
were found inside the pawnshop vault. fortuitous event rests on him who invokes it. And, in
On the same date, Sicam sent Lulu a letter informing her order for a fortuitous event to exempt one from liability, it
of the loss of her jewelry due to the robbery incident in is necessary that one has committed no negligence or
the pawnshop. Respondent Lulu then wroteback misconduct that may have occasioned the loss.
expressing disbelief, then requested Sicam to prepare Sicam had testified that there was a security guard in
the pawned jewelry for withdrawal on November 6, but their pawnshop at the time of the robbery. He likewise
Sicam failed to return the jewelry. testified that when he started the pawnshop business in
1983, he thought of opening a vault with the nearby bank
for the purpose of safekeeping the valuables but was
10
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
discouraged by the Central Bank since pawned articles We expounded in Cruz v. Gangan that negligence is the
should only be stored in a vault inside the pawnshop. omission to do something which a reasonable man,
The very measures which petitioners had allegedly guided by those considerations which ordinarily regulate
adopted show that to them the possibility of robbery was the conduct of human affairs, would do; or the doing of
not only foreseeable, but actually foreseen and something which a prudent and reasonable man would
anticipated. Sicam’s testimony, in effect, contradicts not do. It is want of care required by the circumstances.
petitioners’ defense of fortuitous event.
A review of the records clearly shows that petitioners
Moreover, petitioners failed to show that they were free failed to exercise reasonable care and caution that an
from any negligence by which the loss of the pawned ordinarily prudent person would have used in the same
jewelry may have been occasioned. situation. Petitioners were guilty of negligence in the
operation of their pawnshop business. Sicam’s testimony
Robbery per se, just like carnapping, is not a fortuitous revealed that there were no security measures adopted
event. It does not foreclose the possibility of negligence by petitioners in the operation of the pawnshop.
on the part of herein petitioners. Evidently, no sufficient precaution and vigilance were
adopted by petitioners to protect the pawnshop from
Petitioners merely presented the police report of the unlawful intrusion. There was no clear showing that
Parañaque Police Station on the robbery committed there was any security guard at all. Or if there was one,
based on the report of petitioners’ employees which is that he had sufficient training in securing a pawnshop.
not sufficient to establish robbery. Such report also does Further, there is no showing that the alleged security
not prove that petitioners were not at fault. On the guard exercised all that was necessary to prevent any
contrary, by the very evidence of petitioners, the CA did untoward incident or to ensure that no suspicious
not err in finding that petitioners are guilty of concurrent individuals were allowed to enter the premises. In fact, it
or contributory negligence as provided in Article 1170 of is even doubtful that there was a security guard, since it
the Civil Code, to wit: is quite impossible that he would not have noticed that
the robbers were armed with caliber .45 pistols each,
Art. 1170. Those who in the performance of their which were allegedly poked at the employees.
obligations are guilty of fraud, negligence, or delay, and Significantly, the alleged security guard was not
those who in any manner contravene the tenor thereof, presented at all to corroborate petitioner Sicam’s claim;
are liable for damages. not one of petitioners’ employees who were present
during the robbery incident testified in court.
**
Article 2123 of the Civil Code provides that with regard Furthermore, petitioner Sicam’s admission that the vault
to pawnshops and other establishments which are was open at the time of robbery is clearly a proof of
engaged in making loans secured by pledges, the petitioners’ failure to observe the care, precaution and
special laws and regulations concerning them shall be vigilance that the circumstances justly demanded.
observed, and subsidiarily, the provisions on pledge,
mortgage and antichresis. The robbery in this case happened in petitioners’
pawnshop and they were negligent in not exercising the
The provision on pledge, particularly Article 2099 of the precautions justly demanded of a pawnshop.
Civil Code, provides that the creditor shall take care of
the thing pledged with the diligence of a good father of a NOTES:
family. This means that petitioners must take care of the
pawns the way a prudent person would as to his own We, however, do not agree with the CA when it found
property. petitioners negligent for not taking steps to insure
themselves against loss of the pawned jewelries.
In this connection, Article 1173 of the Civil Code further
provides: Under Section 17 of Central Bank Circular No. 374,
Art. 1173. The fault or negligence of the obligor consists Rules and Regulations for Pawnshops, which took effect
in the omission of that diligence which is required by the on July 13, 1973, and which was issued pursuant to
nature of the obligation and corresponds with the Presidential Decree No. 114, Pawnshop Regulation Act,
circumstances of the persons, of time and of the place. it is provided that pawns pledged must be insured, to wit:
When negligence shows bad faith, the provisions of
Articles 1171 and 2201, paragraph 2 shall apply. Sec. 17. Insurance of Office Building and Pawns- The
place of business of a pawnshop and the pawns pledged
If the law or contract does not state the diligence which to it must be insured against fire and against burglary as
is to be observed in the performance, that which is well as for the latter(sic), by an insurance company
expected of a good father of a family shall be required. accredited by the Insurance Commissioner.

11
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
However, this Section was subsequently amended by - Austria’s theory is for robbery to fall under the category
CB Circular No. 764 which took effect on October 1, of a fortuitous event and relieve the obligor from his
1980, to wit: obligation under a contract, pursuant to A1174, NCC,
there ought to be prior finding on the guilt of the persons
Sec. 17 Insurance of Office Building and Pawns – The responsible therefor. To adopt a different view, he
office building/premises and pawns of a pawnshop must argued, would be to encourage persons accountable for
be insured against fire. (emphasis supplied). goods or properties received in trust or consignment to
where the requirement that insurance against burglary connive with others, who would be willing to be accused
was deleted. Obviously, the Central Bank considered it in court for the robbery, in order to be absolved from civil
not feasible to require insurance of pawned articles liability for the loss or disappearance of the entrusted
against burglary. articles.

The robbery in the pawnshop happened in 1987, and ISSUES:


considering the above-quoted amendment, there is no • WON in a contract of agency (consignment of
statutory duty imposed on petitioners to insure the goods for sale) it is necessary that there be prior
pawned jewelry in which case it was error for the CA to conviction for robbery before the loss of the article shall
consider it as a factor in concluding that petitioners were exempt the consignee from liability for such loss.
negligent. RULING
o NO. To constitute a caso fortuito that would
Nevertheless, the preponderance of evidence shows exempt a person from responsibility, it is necessary that
that petitioners failed to exercise the diligence required (1) the event must be independent of the human will (or
of them under the Civil Code. rather, of the debtor's or obligor's); (2) the occurrence
must render it impossible for the debtor to fulfill the
20 AUSTRIA v. CA (1991) obligation in a normal manner, and that (3) the obligor
FACTS: must be free of participation in, or aggravation of, the
- Maria Abad received from Austria one pendant with injury to the creditor.
diamonds valued at P4,500 to be sold on a commission o A fortuitous event, therefore, can be produced
basis or to be returned on demand. On 1 by nature, e.g., earthquakes, storms, floods, etc., or by
- On 1 February 1961, however, while walking home to the act of man, such as war, attack by bandits, robbery,
her residence in Mandaluyong, Rizal, Abad was said to etc., provided that the event has all the characteristics
have been accosted by two men, one of whom hit her on enumerated above.
the face, while the other snatched her purse containing o A1174’s emphasis of the provision is on the
jewelry (including the pendant) and cash, and ran away. events, not on the agents or factors responsible for
The incident became the subject of a criminal case filed them. To avail of the exemption granted in the law, it is
in CFI Rizal against certain persons (People vs. Rene not necessary that the persons responsible for the
Garcia, et al.) occurrence should be found or punished; it would only
- Austria, upon Abad’s failure to return the jewelry or pay be sufficient to establish that the unforeseeable event,
for its value notwithstanding demands, filed an action the robbery in this case, did take place without any
against her and her husband for recovery of the pendant concurrent fault on the debtor's part, and this can be
or of its value, and damages. done by preponderant evidence. To require in the
- CFI Manila ordered Abads, jointly and severally, to pay present action for recovery the prior conviction of the
Austria P4,500.00, with legal interest thereon, plus culprits in the criminal case, in order to establish the
P450.00 as reasonable attorneys' fees, and the costs. It robbery as a fact, would be to demand proof beyond
held that Abads failed to prove the fact of robbery, or, if reasonable doubt to prove a fact in a civil case.
indeed it was committed, that Maria was guilty of o Re: third requirement: Under the circumstances
negligence when she went home without any prevailing at present in the City of Manila and its
companion, although it was already getting dark and she suburbs, with their high incidence of crimes against
was carrying a large amount of cash and valuables, and persons and property, that renders travel after nightfall a
such negligence did not free her from liability for matter to be sedulously avoided without suitable
damages for the loss of the jewelry. precaution and protection, Maria’s conduct, in returning
- CA overruled the finding of CFI on the lack of credibility alone to her house in the evening, carrying jewelry of
of the two defense witnesses who testified on the considerable value, would be negligent per se, and
occurrence of the robbery, and holding that the facts of would not exempt her from responsibility in the case of a
robbery and Abad’s possession of the pendant on that robbery. The SC was not persuaded, however, that the
unfortunate day have been duly established, declared same rule should obtain ten years previously, in 1961,
Abads not responsible for the loss of the jewelry on when the robbery in question did take place, for at that
account of a fortuitous event, and relieved them from time criminality had not by far reached the levels
liability for damages to the owner. attained in the present day.

12
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
o There is also no merit in Austria’s argument that  Art 1174: no person shall be responsible for a
to allow the fact of robbery to be recognized in the civil fortuitous event which could not be foreseen, or
case before conviction is secured in the criminal action, which, though foreseen, was inevitable
would prejudice the latter case, or would result in  tire blowout - mechanical defect of the conveyance
inconsistency should the accused obtain an acquittal or or a fault in its equipment which was easily
should the criminal case be dismissed. A court finding discoverable if the bus had been subjected to a
that a robbery has happened would not necessarily more thorough or rigid check-up before it took to the
mean that those accused in the criminal action should be road
found guilty of the crime; nor would a ruling that those  When a passenger boards a common carrier, he
actually accused did not commit the robbery be takes the risks incidental to the mode of travel he
inconsistent with a finding that a robbery did take place. has taken. After all, a carrier is not an insurer of the
The evidence to establish these facts would not safety of its passengers and is not bound absolutely
necessarily be the same. and at all events to carry them safely and without
injury. However, when a passenger is injured or
22 YOBIDO vs. CA dies while travelling, the law presumes that the
FACTS: Spouses Tito and Leny Tumboy and their minor common carrier is negligent. (see Art. 1756)
children named Ardee and Jasmin, boarded a Yobido  Art. 1755 provides that a common carrier is bound
Liner bus bound for Davao City. Along the trip, the left to carry the passengers safely as far as human care
front tire of the bus exploded. The bus fell into a ravine and foresight can provide, using the utmost
around 3 ft. from the road and struck a tree. The incident diligence of very cautious persons, with a due
resulted in the death of Tito and physical injuries to other regard for all the circumstances. In culpa
passengers. contractual, once a passenger dies or is injured, the
Factual backdrop based on testimony of Leny: the carrier is presumed to have been at fault or to have
winding road the bus traversed was not cemented and acted negligently. This disputable presumption may
was wet due to the rain; it was rough with crushed rocks. only be overcome by evidence that the carrier had
The bus which was full of passengers had cargoes on observed extraordinary diligence as prescribed by
top. Since it was running fast, (at a speed of 50-60kph Arts. 1733, 1755 and 1756 or that the death or
based on another witness’ testimony) she cautioned the injury of the passenger was due to a fortuitous
driver to slow down but he merely stared at her through event.
the mirror.  The explosion of the new tire may not be
considered a fortuitous event; there are human
A complaint for breach of contract of carriage was filed factors involved in the situation; the fact that the tire
by Leny and her children against Alberta Yobido, the was new did not imply that it was entirely free from
owner of the bus, and Cresencio Yobido, its driver; manufacturing defects or that it was properly
Yobidos raised the affirmative defense of caso fortuito; mounted on the vehicle.
they also filed a third-party complaint against Philippine
Phoenix Surety and Insurance, Inc. 23 JUNTILLA vs. FONTANAR
Facts: Herein plaintiff was a passenger of the public
Upon a finding that the third party defendant was not utility jeepney on course from Danao City to Cebu City.
liable under the insurance contract, the lower court The jeepney was driven by driven by defendant Berfol
dismissed the third party complaint. Camoro and registered under the franchise of Clemente
Fontanar. When the jeepney reached Mandaue City, the
ISSUE: Whether the tire blow-out is a fortuitous event right rear tire exploded causing the vehicle to turn turtle.
In the process, the plaintiff who was sitting at the front
HELD: No. seat was thrown out of the vehicle. Plaintiff suffered a
 Characteristics of fortuitous event: lacerated wound on his right palm aside from the injuries
a) The cause of the unforeseen and unexpected he suffered on his left arm, right thigh, and on his back.
occurrence, or the failure of the debtor to comply with his
obligations, must be independent of human will; Plaintiff filed a case for breach of contract with damages
b) It must be impossible to foresee the event which before the City Court of Cebu City. Defendants, in their
constitutes the caso fortuito, or if it can be foreseen, it answer, alleged that the tire blow out was beyond their
must be impossible to avoid; control, taking into account that the tire that exploded
c) The occurrence must be such as to render it was newly bought and was only slightly used at the time
impossible for the debtor to fulfill his obligation in a it blew up.
normal manner; and
d) the obligor must be free from any participation in the Issue: Whether or not the tire blow-out is a fortuitous
aggravation of the injury resulting to the creditor event?

13
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
Held: No. In the case at bar, the cause of the unforeseen Magsarili and Charlie Antolin in the amount of P4,000.00
and unexpected occurrence was not independent of the each or a total of P12,000.00.
human will. The accident was caused either through the
negligence of the driver or because of mechanical The insurance policy involved explicitly limits PCSI's
defects in the tire. Common carriers should teach drivers liability to P12,000.00 per person and to P50,000.00 per
not to overload their vehicles, not to exceed safe and accident.
legal speed limits, and to know the correct measures to
take when a tire blows up thus insuring the safety of We have ruled in Stokes vs. Malayan Insurance Co.,
passengers at all times. Inc., that the terms of the contract constitute the
measure of the insurer's liability and compliance
24 PERLA COMPANIA DE SEGUROS vs. SARANGAY therewith is a condition precedent to the insured's right
FACTS: Milagros Cayas was the registered owner of a of recovery from the insurer.
Mazda bus. Said passenger vehicle was insured with
Perla Compania de Seguros, Inc. (PCSI) under a policy In the case at bar, the insurance policy clearly and
issued on February 3, 1978. On December 17, 1978, the categorically placed PCSI's liability for all damages
bus figured in an accident in Naic, Cavite injuring several arising out of death or bodily injury sustained by one
of its passengers. One of them, 19-year old Edgardo person as a result of any one accident at P12,000.00.
Perea, sued Milagros Cayas for damages in the Court of Said amount complied with the minimum fixed by the law
First Instance; while three others, namely: Rosario del then prevailing, Section 377 of Presidential Decree No.
Carmen, Ricardo Magsarili and Charlie Antolin, agreed 612 (which was retained by P.D. No. 1460, the
to a settlement of P4,000.00 each. At the pre-trial, Insurance Code of 1978), which provided that the liability
Milagros Cayas failed to appear and hence, she was of land transportation vehicle operators for bodily injuries
declared as in default. After trial, the court rendered a sustained by a passenger arising out of the use of their
decision in favor of Perea to compensate the Perea with vehicles shall not be less than P12,000. In other words,
damages of Pl0,000.00 for medical fees; P10,000.00 for under the law, the minimum liability is P12,000 per
exemplary damages; P5,000.00 for moral damages; passenger. PCSI's liability under the insurance contract
P7,000.00 for Attorney's fees. not being less than P12,000.00, and therefore not
contrary to law, morals, good customs, public order or
On November 11, 1981, Milagros Cayas filed a public policy, said stipulation must be upheld as
complaint for a sum of money and damages against effective, valid and binding as between the parties.
PCSI in the Court of First Instance. Milagros Cayas filed
a motion to declare PCSI in default for its failure to file In like manner, we rule as valid and binding upon Cayas
an answer. The motion was granted and Cayas was the condition in the policy in requiring her to secure the
allowed to adduce evidence ex-parte. On July 13, 1982, written permission of PCSI before effecting any payment
the court rendered judgment by default ordering PCSI to in settlement of any claim against her. There is nothing
pay Milagros Cayas P50,000 as compensation for the unreasonable, arbitrary or objectionable in this
injured passengers, P5,000 as moral damages and stipulation as would warrant its nullification. The same
P5,000 as attorney's fees. was obviously designed to safeguard the insurer's
Said decision was set aside after the PCSI filed a motion interest against collusion between the insured and the
therefor. In due course, the court promulgated a decision claimants.
in favor of Cayas, but removed the award of moral
damages. In her cross-examination before the trial court, Milagros
Cayas admitted that PCSI did not give any written
PCSI appealed to the Court of Appeals, which, in its authority that Cayas were supposed to pay those claims.
decision of May 8, 1987 the lower court's decision. Its It being specifically required that PCSI's written consent
motion for reconsideration having been denied, PCSI be first secured before any payment in settlement of any
filed the instant petition charging the Court of Appeals claim could be made, Cayas is precluded from seeking
with having erred in affirming in toto the decision of the reimbursement of the payments made to del Carmen,
lower court. Magsarili and Antolin in view of her failure to comply with
the condition contained in the insurance policy.
ISSUE: Whether or not the amount of award of damages
was proper. Clearly, the fundamental principle that contracts are
respected as the law between the contracting parties
RULING: NO. PCSI seeks to limit its liability only to the finds application in the present case. Thus, it was error
payment made by Cayas to Perea and only up to the on the part of the trial and appellate courts to have
amount of P12,000.00. It altogether denies liability for disregarded the stipulations of the parties and to have
the payments made by Cayas to the other three (3) substituted their own interpretation of the insurance
injured passengers Rosario del Carmen, Ricardo policy.

14
DUMLAO, Cheyenne Hope OBLICON Assignment #2 COMPILED DIGESTS San Beda College of Law - Mendiola
We observe that although Milagros Cayas was able to HELD: No. The Supreme Court held that the Asian
prove a total loss of only P44,000.00, PCSI was made financial crisis cannot be generalized as unforeseeable
liable for the amount of P50,000.00, the maximum and beyond the control of the business corporation. A
liability per accident stipulated in the policy. This is real estate enterprise engaged in the pre-selling of
patent error. An insurance indemnity, being merely an condominium units is concededly a master in projections
assistance or restitution insofar as can be fairly on commodities and currency movements and business
ascertained, cannot be availed of by any accident victim risks. The fluctuating movement of the Philippine peso in
or claimant as an instrument of enrichment by reason of the foreign exchange market is an everyday occurrence,
an accident. and fluctuations in currency exchange rates happen
every day, thus, not an instance of caso fortuito.
WHEREFORE, the decision of the Court of Appeals is
hereby modified in that petitioner shall pay Milagros
Cayas the amount of Twelve Thousand Pesos (P12,000.
00) plus legal interest from the promulgation of the
decision of the lower court until it is fully paid and
attorney's fees in the amount of P5,000.00. No
pronouncement as to costs.

25 FIL-ESTATE PROPERTIES vs. GO


FACTS: On December 29, 1995, petitioner Fil-Estate
Properties, Inc. (Fil-Estate) entered into a contract to sell
a condominium unit to respondent spouses Gonzalo and
Consuelo Go. The spouses paid a total of P3,
439,000.07 of the full contract price set at P3,
620,000.00.

Fil-Estate failed to develop the condominium project. On


August 4, 1999, the spouses demanded the refund of
the amount they paid, plus interest. When Fil-Estate did
not refund the spouses, the latter filed a complaint
against petitioner for reimbursement plus interest before
the Housing and Land Use Regulatory Board (HLURB).
In answer, Fil-Estate claimed that respondents had no
cause of action since the delay in the construction of the
condominium was caused by the financial crisis that hit
the Asian region, a fortuitous event over which petitioner
had no control.

HLURB Regional Director approved the decision of the


Housing and Land Use Arbiter in favor of the spouses
Go. The Court of Appeals affirmed the actions taken by
the HLURB and the Office of the President and declared
that the Asian financial crisis could not be considered a
fortuitous event.

Fil-Estate explained that the extreme economic exigency


and extraordinary currency fluctuations could not have
been reasonably foreseen and were beyond the
contemplation of both parties when they entered the
contract. It further asserted that the resultant economic
collapse of the real estate industry was unforeseen by
the whole Asia and if it was indeed foreseeable, then all
those engaged in the real estate business should have
foreseen the impending fiasco.

ISSUE: Whether or not the Asian financial crisis could be


considered a fortuitous event.

15

Vous aimerez peut-être aussi