Académique Documents
Professionnel Documents
Culture Documents
2. Oil filtering equipment 15 ppm, was externally examined, tested and found satisfactory
3. 15 ppm bilge alarm and automatic stopping device were tested and found in good order
4. Operational instructions for the oil filtering equipment and piping diagram are displayed
5. Sufficient storage of filtering and / or coalescing is provided
Others:
6. Overboard discharge valve was externally examined and found satisfactory.
7. Fuel system and ballast system are separated from each other except as provided in Regulation 16 (2).
8. Installation for ballast discharge to reception facilities is in good condition, if applicable.
9. Testing of homogenizers, sludge incinerators or other recognised means for the control of sludge, where fitted.
10. Holding tank for oily bilge water is in good condition, where fitted
11. Dedicated Sludge tank and a designated pump installation (separate by bilge system) verified and are in good condition.
12. Installation for oil residues discharge to shore reception facilities is in good condition.
12.1 There is no discharge connections of the sludge tank to the bilge system, oily bilge water holding tank(s), tank top or oily
water separators except that: the sludge tank discharge piping and bilge-water piping is connected to a common piping
leading to the standard discharge connection, which does not allow for the transfer of sludge to the bilge system.
13. Standard discharge connection is in good order.
14. Vessel is provided with a revised oil record book Part I in accordance with regulation 17 and Part II in accordance with reg.36
and entries were made duly.
15. Vessel is provided with a S.O.P.E.P. in accordance with regulation 37 (Tankers >5000dwt which shall have prompt access to
computerized, shore-based damage stability and residual strength calculation programs as required by reg.37.4)
40. Oil filtering equipment was internally examined and found satisfactory.
41. Pumps of filtering equipment with bilge piping and pipes to sludge tank were examined and found in good condition
42. All oil, water, steam and drain valves of oil filtering equipment were opened, examined and found satisfactory
43. Coalescer and / or filter cartridge were renewed
44. The oil contents meter for the 15 ppm alarm was tested and calibrated according to manufacturer's instruction
45. 15 ppm bilge alarm was tested according to manufacturer's instruction
46. Cargo pump room boom protection of height of not less than B/15 or 2 meters (whichever is lesser, with a minimum value of 1
meter) has been verified. (Applies to Oil tankers >5000DWT and built >1/1/2007)
47. Vessel with Fuel oil tanks of total capacity above 600cbm meets one of the following requirements.
(Applies to all ships built >1/8/2010)
i) Fuel oil tanks located at a minimum distance inboard of shell plating as per reg. 12A
ii) Meets the accidental oil fuel outflow performance standards as per reg.23
were inspected internally and the effectiveness of COW and stripping system were verified
50. The operation test of all tank valves was carried out and found in satisfactory condition
51. COW piping was pressure tested up to kg / cm²
(working pressure kg / cm²) and found in satisfactory condition
Note : Pressure tested shall be 1.5 times working pressure of COW piping
52. Double shut-off valves / blind flanges for heater fitted in the COW system were removed, inspected and found in satisfactory
condition
53. Confirming that the closing devices installed in the cargo transfer system and interconnections mentioned on Reg. 26 as
appropriate
54. Describe in detail system and equipment or parts which have been altered or modified (Additional pages to be attached if
necessary)
55. The alterations or modifications together with manuals or operational procedures have been approved.
56. Verification of the type approval certificate of the following newly installed equipment carried out.
57. Describe in detail parts which remain to be examined, and deficiencies, if any (Additional pages to be attached if necessary)
V. CERTIFICATE
58. The I.O.P.P. Certificate with No. was endorsed on
Date:
Surveyor to International Naval Surveys Bureau - I.N.S.B.