Académique Documents
Professionnel Documents
Culture Documents
REINFORCEMENT (R/f)
◾ Introduction
Reinforced concrete is the most commonly used structural material in Basic Civil Engineering
google.com/+Basiccivilengineering
engineering construction. Although concrete is strong in resisting
Learn all basic aspect of civil engineering.
compressive stress, it is weak intention. Hence to withstand tensional
stresses, steel is need in concrete. The reinforcement in concrete may be Follow +1
simple bars or rods bend and tied to a given schedule with stirrups. The + 1,287
nominal diameters of bars used at site were Y10, Y12, Y16, Y20, Y25 and R6.
Like Us on Facebook
Bar location can be vary as follows:
Basic Civil
Notation for Slab- Engineering
T1 -Top outer layer, T2 -Top second layer
There is a steel yard in the site for storing, cutting and bending of bars.
Reinforcement bars are cut into required lengths and bent into required
shapes shown on the bar schedule either manually or by means of
machinery.
In manual operations, laborers used the bar bending bench on which
strong nails are fixed and GI pipes with suitable lengths to bend the bars.
That is used for smaller diameter bars. For bending of larger diameter bars,
bar bending machine is used. After bending all reinforcement bars were
bundled and clearly numbered according to the bar mark so that steel fixers
will not face any difficulty when fixing them.
While prepared the bar schedule, we used the unit weight of reinforcement
bar.
R6 0.222
R10 0.610
T10 0.617
T12 0.888
T16 1.580
T20 2.469
T25 3.858
T32 6.313
In the site several steps were adopted for that purpose. Those are, Use of
12m long r/f bars rather than using shorter bars. For example 6m bars off
cuts of 12m bars were used to prepare stools, separators etc.
◾ Off cuts of larger diameter (25mm) bars-for spacer bars
◾ Lapping
Binding Wires
R/f bars are jointed with using wires which is called “binding wires”. Hackers
are used to bind these wires.
Cover Blocks
They were made up of 1:3 ratio of cement mortar. Cover blocks should
be immersed in water for 28 days to get the maximum strength.All the
beams were checked to ensure adequate cover blocks are provided to the
bottom and sides of the beam reinforcement. Main bars of the columns
were adjusted to ensure the covering requirements before concreting.
Stools of correct height were used to maintain the require gap between top
and bottom reinforcement nets and cover blocks were also provided to
bottom reinforcement.
◾ Concrete cover for steel bar is much necessary to protect the steel
against corrosion (rusting) and to provide resistance against fire.
◾ In case of ground resting floor slab (Top surface) and retaining walls
the cover is 50m.
◾ Stirrups
These stirrups are usually one piece of steel that is bent into a
rectangular shape. The stirrup typically wraps around the bottom and top
bars of the beams. A designer should specify the size, spacing and location
along the length of the beam where the stirrups are required. In my site
specify the stirrup dimensions in our section drawings, so that the stirrup
can be manufactured prior to installation. The installer should be careful to
fabricate the stirrup from one piece of steel and adequately overlap each
end.
◾ Stools
Stools are used to separate the top reinforcement mesh and bottom
reinforcement mesh. Dimension of the Stools could be change as
requirement. Those should be strength enough to bear the loads without
changing the gap of two layers. 12 mm or 16 mm bars are used to make the
stools.
Fig 5: Stools
◾ Number of bars
◾ Lap lengths
◾ Column Reinforcement
The column reinforcement bars should be stared from the Footing. The
upper column reinforcement bars are cranked at the laps and connected.
Special care should be taken in this to ensure the lap lengths. After erection
of main reinforcements, cover blocks were attached to column
reinforcements to maintain the required cover for column reinforcement.
Most of Columns centers were located at intersections of grid lines.
Stirrup spacing
According to the Column reinforcement details drawing the
reinforcement detail for a typical internal Column, from to basement to
ground floor is as follows.
E.g.:
E.g-
Footing
◾ Beam Reinforcement
First the top most reinforcement bars are hung over the beam formwork
and then the stirrups are placed and bound at correct positions. Thereafter
the bottom reinforcement bars are placed and bound to the stirrups. After
that the rest of the reinforcement bars and tension bars are inserted into
the cage according to structural drawings. Then cover blocks are fixed to
bottom and side reinforcements before placing the concrete.
Top reinforcement of the beam shall be lapped at the middle of the span
of between two supports. Bottom reinforcement of the beam shall be
lapped at the end of the span of the two supports. Considering the region
where the maximum bending movement is existing.
Lapping is did the place which the tension is didn’t act. Normally 2/3 of
the length is choosing for lapping. When lapping top & bottom re-bar, it is
better to follow the following method.Otherwise, it might cause to reduce
the concrete covering thickness of the topmost& bottom most slab
reinforcement.
Because the actual bond stress varies along the length of a bar anchored in
a zone of tension. The main requirement for safety against bond failure is to
provide a sufficient extension of the length of the bar beyond the point
where the steel is required to develop its yield stress and this length must
be at least equal to its development length. However, if the actual available
length is inadequate for full development, special anchorages must be
provided, such as bends, hooks.
E.g- (Anchorage length 45 d (for top bars),12 d (for bottom bars)) where “d”,
“Ø” is diameter of the Bar.
= 72.5mm
Anchorage length (x) = 45 x diameter of the bar(20 Ø)
= 827.5 mm
◾ Slab Reinforcement
First step of the fixing of slab reinforcement was placed the bottom most
R/F (B1) of the slab. Before placing the re-bar, correct spacing given in the
detailing drawing were marked by using piece of choke on the slab
formwork. After placed the (B1) R/F then placed the (B2) R/F and bound both
R/F layers together by using binding wire. Then cover blocks for bottom
most R/F were fixed. Finally, Top R/F (T2), Topmost R/F (T1)& distribution
bars were placed according to the drawing and fixed together by using
binding wire. Then Stools were fixed to separate the both top & bottom R/F
net as fulfilled the thickness.
Bar crank
Bar cranking is the process of bending up the bottom steel bars in upward
direction. It is mainly to prevent upward bending moment near the joint.
Also useful for attaching stirrup bar effectively. Cranking is also used in two
way slabs.
Share
Comments
comments
Bar bending