Vous êtes sur la page 1sur 3

AN EXPERT WRITES...

Delay analysis – a return


Bob Breeze
Stapleton International,
London and Darlington

to common sense?
Recent developments in
establishing causation in fact
Introduction The Protocol
There have been dozens of books, hundreds The Protocol Guidance suggests at section 3
of articles and thousands of debates about the way in which applications for extensions
how delay analysis should be carried out of time (‘EOT’) are to be assessed during
when looking at a construction project the course of the project. This has, however,
from a retrospective point of view to try to been extended by common usage by
determine exactly what caused a delay to independent experts and consultants when
the completion date. A committee set up addressing a retrospective critical path
by the Society of Construction Law (SCL) analysis of a delayed project in a dispute
produced, after much debate, the Delay resolution process.
and Disruption Protocol (the ‘Protocol’) In particular, clause 3.2.6 of the Protocol
which was published in October 2002. This states that that the Updated Programme
was welcomed by many in the construction should be the primary tool used to guide
industr y as a valiant attempt, in its own the Contract Administrator (‘CA’) in
words, to ‘provide useful guidance on determining the amount of the EOT. The
some of the common issues that arise on EOT should be granted to the extent that
construction contracts’. This erstwhile the employer risk event is predicated to
document tried to cover both live projects prevent the works being completed by the
and also the forensic approach to be ‘then planned prevailing contract
adopted in circumstances where a dispute completion date’.
had arisen and even where such a dispute The Protocol recommends that in
had been referred to a formal procedure for deciding a contractor’s entitlement to an
resolution such as arbitration or litigation. EOT, the adjudicator, judge or arbitrator
It did of course come with a number of should, so far as is practicable, put him/
health warnings on the packet. For instance, herself in the position of the CA at the
it clearly stated that ‘it is not intended that time when the employer risk event
the Protocol should be a contract document. occurred. The above approach is often
Nor does it purport to take precedence over referred to as an entitlement to an EOT.
the express terms of a contract or be a The Protocol even suggests this
statement of the law’. However, these entitlement approach should be applied
warnings in the author’s view seem to have in cases where there are concurrent
been often overlooked or ignored and the delaying events, that is, where two or more
Protocol has been used in disputes to try to delaying events arise at different times,
support an argument that a delaying event but the effects of them are felt (in whole
does not in fact have to delay overall or in part) at the same time.
completion of the project to entitle the This can be represented graphically as in
contractor to an extension of time. Further Figure 1 below:
explanation is required.

44 CONSTRUCTION LAW INTERNATIONAL Volume 7 Issue 2 June 2012


Figure 1 – The entitlement approach

In the above example, the contract works are In his judgment, The Hon Mr Justice Hamblen
already running late and the contract stated: ‘If, for example, a two day variation was
completion date will not be met. The prevailing instructed the day before the sea trials date, and
completion date when the employer risk event was a variation of a type which would need to be
occurred was five days after the contract completed before sea trials, then, if there was an
completion date. However, the Protocol states extension of time clause Adyard would be
that it is the impact on the contract completion entitled to a one day extension of time, or, if
date which is to be analysed. In the above case, there was no such clause, Adyard could rely on
this would give rise to a three-day EOT; that the prevention principle.’
being the period by which the employer risk Adyard submitted that this was the correct
event over-runs the contract completion date, approach regardless of what other events may
despite the fact that the contractor was already have been delaying the works and regardless of
going to be five days late and in fact no further whether the variation would have any impact on
delay occurred as a result of the employer risk the actual progress of the works. It argued that
event in question. Perhaps it is time for the one looks only at the event/act in question and
SCL Protocol now to be updated to reflect how it relates to the contractual completion
current thinking? date. So, if the project was already in six months
irretrievable delay it would make no difference
Recent authority to the causation analysis. Adyard would still get
its extension of time or be entitled to rely on the
This point was aired in the case of Adyard Abu prevention principle.
Dhabi v SDS Marine Services [2011] EWHC 848 The Judge then went on to conclude that
(Comm) where the Commercial Court had Adyard’s approach was wrong as a matter of
to determine whether SDS could rescind two both principle and authority. It was wrong in
shipbuilding contracts and reclaim the sums it principle because in essence Adyard’s case was
had paid to Adyard. Adyard had commenced that there was no need to prove causation in
proceedings, arguing that SDS could not rescind fact. On its case there was no need to prove that
as SDS had caused delays to the project. Adyard the event or act caused any actual delay to the
also argued the prevention principle but the progress of the works and a notional or
Court found against Adyard in that respect. The theoretical delay would suffice. It was also
Court also had to consider whether Adyard had contrary to common sense.
proved that SDS had in fact caused the delay to The Judge referred to the quote from the
the project in any event. Protocol highlighted at the beginning of this
article. In such circumstances the Protocol can,
Causation in law and fact he said, be of little assistance in relation to the
Adyard’s case was that causation was established legal causation issues which arise in this case.
by showing that the duration of the employer’s The parties’ experts agreed that there was no
risk event (a minor variation in this case to actual delay, whether viewed prospectively or
two sliding doors) went beyond the original retrospectively, caused by any employer risk
contractual sea trial date (which was equivalent event and that the common-sense view of the
in this case to the delivery date), regardless of events on-site should not be ignored.
what other events may have been delaying the It followed that the actual delay had to be
works and whether or not the variation did have proved and Adyard’s causation claim failed.
any impact on the actual progress of the works. In a graphic form, the situation is as set out in
Figure 2 below:

CONSTRUCTION LAW INTERNATIONAL Volume 7 Issue 2 June 2012 45


FEATURE
AN EXPERT
ARTICLE
WRITES...

Figure 2 – The causation approach

In the subsequent case of Jerram Falkus Conclusion


Construction Limited v Fenice Investments Inc
In summary, these cases send out a clear
[2011] EWHC 1935 (TCC), completion of
message that theoretical delay analysis
the works was delayed by several months and
techniques will not do in terms of proving
the employer, Fenice, claimed liquidated
causation in fact and in law. For any employer
damages. Jerram disputed this entitlement.
risk event to give rise to an EOT claim it
It argued that Fenice had prevented
must as a matter of fact cause actual delay
completion and that there was no mechanism
or further delay to the then prevailing
in the contract for extending time in this
anticipated completion or delivery date and
event since the Joint Contracts Tribunal
not the contract completion date. In the
(JCT) clause 2.26 Relevant Event dealing
author’s view, this is a welcome return to a
with prevention events had been deleted
common-sense approach.
from the contract. Time for completion was
claimed to be at large and Fenice could not
therefore levy liquidated damages. Bob Breeze is Group Managing Director of Stapleton
Coulson J examined the leading authorities International and acted as the independent delay
in the area of prevention including the analysis expert for SDS Marine Services in the Adyard
Adyard case. Here the court saw a distinction case. He can be contacted at bob.breeze@
between a situation where the contractor stapletonint.com or tel: +44 1325 488048.
would not have completed by the due date
because of its own delay (where the
prevention principle would apply in respect
of a distinct non-concurrent period of
employer-caused delay) and the situation
described in the Adyard case which indicated
that if there were two concurrent causes of
delay, only one of which could be described
as employer prevention and the other was
the responsibility of the contractor, the
prevention principle could not be relied on.
Coulson J considered that the contractor
must prove that the alleged act of prevention
caused delay to the actual progress of work
and stated: ‘The contractor must be able to
demonstrate that the employer’s acts or
omissions have prevented the contractor
from achieving an earlier completion date
and that, if that earlier completion date
would not have been achieved anyway,
because of concurrent delays caused by the
contractor’s own default, the prevention
principle will not apply.’

46 CONSTRUCTION LAW INTERNATIONAL Volume 7 Issue 2 June 2012

Vous aimerez peut-être aussi