Date 8-Jan-18

Chenab Engineering Works and Foundries Pvt Ltd Faisalabad Prepared By SAA
Estimation of Civil Works for Construction of Sand Plant Department Civil Engg.
Ref Civil-001
Sr. No. Item Description UOM Quantity Item Rate Amount Remarks
SECTION-1 PRELIMINARIES & EARTHWORKS Comparison
1.1 Earth Works AIZ RASULIAN SAJJAD AA Takno Art Remarks
1.1.1 Structural excavation in soil above sub soil water level M3 675 750 700 707 495.16 350
for levelling and grading of walls and columns
foundation as shown in drawings and specifications and
as per approval of the engineer.

1.1.2 Structural backfill in foundation and under floor with M3 400 400 350 353 329 283
approved suitable excavated soil from BOQ item 1.1.1
including breaking clods, dressing watering,
compacting mechanically in layers not exceeding
225mm thick depth to 95% modification proctor dry
density (MPD) from any lead and any lift compacted as
per specification and as per approval of the engineer.

1.1.3 Structural fill in foundation and under floor with M3 200 1200 1000 706 695 530
approved suitable borrowed soil including breaking
clods, dressing watering, compacting mechanically in
layers not exceeding 225mm thick depth to 95%
modification proctor dry density (MPD) from any lead
and any lift compacted as per specification and as per
approval of the engineer.

SECTION-2 CONCRETE WORKS


2.2 Reinforcement for Concrete
2.2.1 Provide and fix steel reinforcement grade 60 deformed
steel bars conforming to ASTM A615, including
cleaning, cutting, bending, placing, binding etc.,
including provision and cost of spacers and binder wire,
cost of chairs, over lapsnot shown on drawings etc., in
any kind of RCC work as specified.

a) Reinforcing steel bars of grade 60 (min. 60,000 psi yield Ton 16.5 150000 115000 125000 113800 115000
strength)
2.3 Structural Concrete
2.3.1 Provide and lay structural cement concrete of 3000 psi
cylinder crushing strength at 28-days using OPC,
Chenab sand and Sargodha crush stone including
formwork and its removal, placing, compacting,
finishing and curing complete in all respects (including
screening and washing of stone aggregate) but
excluding the cost of reinforcement as per
specifications.

a) RCC footing M3 105 16000 11000 10243 10195 12358


b) Lean Concrete M 3
26.1 6000 5000 6710 6200 5300
2.3.2 Ditto item above 2.3.1 but using structural cement
concrete 3500 psi cylinder crushing strength at 28 days.

a) RCC Columns M3 50 16500 12500 12009 11995.65 15880


SECTION-3 MASONRY WORKS
3.1 Brick Work
3.1.1 Provide and lay first class brickwork masonry 230mm or M3 25 10500 10000 7064 6985 8830
higher for underground trenches, in 1:5 cement:sand
mortar using Chenab sand including scaffolding and its
removal, raking out joints and making flush or groove
joints, curing including provision and fixing of angle
iron grouted in brickwork for trench cover as directed
by th engineer specified:
SECTION-7 SPECIAL ITEMS
7.2 Installation of Anchorage System
7.2.1 Provide and Installation of Anchorage (base plate and Ton 2.8 265000 240000 150000 220000 239000
anchor bolts) System over pedestal complete in all
respects, steel plate must confirm to Tensile Strength of
375~500MPa

Total 7047350 5542500 5269821 5105235.5 5472820


1000 600 16 2 0.0192 150.72
800 600 16 2 0.01536
200 200 10 28 0.0112
200 200 10 4 0.0016
200 200 12 10 0.0048
500 500 16 4 0.016
300 300 16 8 0.01152
200 200 16 4 0.00256
150 150 10 3 0.000675
250 250 12 4 0.003
950 250 16 6 0.0228
500 500 20 5 0.025
200 200 10 6 0.0024
500 500 20 3 0.015
800 500 20 1 0.008
350 350 16 8 0.01568
200 200 16 8 0.00512
800 800 16 1 0.01024
500 500 16 12 0.048
500 500 16 10 0.04
300 300 16 20 0.0288
400 250 20 18 0.036
300 220 16 4 0.004224
0.347179 2725.355

28.31257
Column1
Cost Estimate for Construction of Sand Plant & Pre Fabric
Type of Work
Civil Works for

Erection of Prefabricated Steel Shed


Machinery Erection
Fabrication
Structural Works
Structural Works
Electrical Works
Dismentling of Exist Structures
Column2 Column3
ate for Construction of Sand Plant & Pre Fabricated Shed
Estimated cost based on
Scope of Work Lowest bidder (Million)
Construction of sand plant and Shed as
per Drawings including steel plates and 5.5
acnchor bolts

Icluding all types of materials 10


Installation of sand plant machinery 2.5
Elevator & Hopper 5
Material for Plant 9
Miscellanous for construction 2
including all types of materials 3.5
0.5

Total Cost 38
Contingencies 10%
Gross Cost 41.8
Column4

Remarks
based on available information and
all types of materials necessary for
construction

from MS Izhar
From Chenab Team
From Chenab Team
From Chenab Team
From Chenab Team
Fast Cables and others