Pakhtunkhwa Energy Development Organization (PEDO), Govt.

of Khyber Pakhtunkhwa

Daily Situation Report

Start Date: 25-06-2012


36.6 MW
Project Name Target Date: 30-06-2017
Daral Khwar Hydropower Project
Expected completion: 31-01-2018
Project Director
Engr. Habib Khan

Data Date Constraints


Month/year Date
Weather Conditions

Jan/2018 02
Workable

1. MC Representatives 10
2. Contractor Total No. of Chinese=22
Representative  6 Chinese, 2 engineers and labours for E&M work at
powerhouse
 1 Engineer (GRC) and labours for civil works at powerhouse.
 2 Chinese, 2 operators and labours for Switchyard.
 1 site engineer and labours for civil work at fire-fighting tank.
 1 Site Manager, 1 site supervisor, 1 site engineer and labours
for civil work on transmission line.
 1 Supervisor and labours for civil work at Intake.
 Chinese and labours for E&M work at intake.
3. Progress of Work
A. Critical Issues
i. Transmission Line
 Expected completion date: 30-11-17
 Foundation of towers= 38/38 completed.
 Erection of towers= 35/38 erected.
 No work on Transmission Line since 26th Dec, 2017

ii. Grid Interconnection


 Expected completion date: 30-11-17
 Tariff petition has been submitted to NEPRA.
 Interconnection study has been approved by PESCO and it has been further
submitted to CPPA-G for vetting as advised by PESCO.
 The interconnection design report at Madyan Grid has been submitted to
PESCO for review and same is being pursued.
 Interconnection study report to GM Power System Planning, NTDC
Resubmitted for vetting
 PESCO allowed for Construction of line bays & other works at Madyan grid
station.
 PESCO Issued the approved drawings for the construction of line bays at
Madyan grid Station

Page 1 of 3
Pakhtunkhwa Energy Development Organization (PEDO), Govt. of Khyber Pakhtunkhwa

Daily Situation Report

iii. Switchyard installation


 Substantially completed.
 Finishing work is in progress

iv. Penstock P7
 Substantially completed

v. Dry Commissioning
 Commissioning of gates at weir/Intake is in progress

B. Other issues/ Works

i. Intake Structure/Sand trap


 Substantially Completed.
 Finishing works in Progress.

ii. Valve Chamber/ Surge Tank


 Substantially completed
 Finishing work is in progress

iii. Colony
 Completion date as per approved work schedule:30-6-17
 Expected completion date: 31-03-2018
# Steel fixing & Form work of Column for 3rd Portion of Family Flats Block-I
is in progress
# Work on car park of family flats block-II is in progress

iv. Hospital/RE-House

 Excavation and Survey for foundation of Hospital is in Progress


 Foundation of separation wall for RE House is in Progress
 Backfilling for RE-House is in progress

Special issues/ Problems (If any):

Page 2 of 3
Pakhtunkhwa Energy Development Organization (PEDO), Govt. of Khyber Pakhtunkhwa

Daily Situation Report

Court Cases:

Attendance Visits Incidents (if Any)

Site Staff Internal External Guest Damages Causalities Thefts

Total No. of 12
Employees
Absent
On tour/ leave
Present on site 06

Page 3 of 3