of Khyber Pakhtunkhwa
Jan/2018 02
Workable
1. MC Representatives 10
2. Contractor Total No. of Chinese=22
Representative 6 Chinese, 2 engineers and labours for E&M work at
powerhouse
1 Engineer (GRC) and labours for civil works at powerhouse.
2 Chinese, 2 operators and labours for Switchyard.
1 site engineer and labours for civil work at fire-fighting tank.
1 Site Manager, 1 site supervisor, 1 site engineer and labours
for civil work on transmission line.
1 Supervisor and labours for civil work at Intake.
Chinese and labours for E&M work at intake.
3. Progress of Work
A. Critical Issues
i. Transmission Line
Expected completion date: 30-11-17
Foundation of towers= 38/38 completed.
Erection of towers= 35/38 erected.
No work on Transmission Line since 26th Dec, 2017
Page 1 of 3
Pakhtunkhwa Energy Development Organization (PEDO), Govt. of Khyber Pakhtunkhwa
iv. Penstock P7
Substantially completed
v. Dry Commissioning
Commissioning of gates at weir/Intake is in progress
iii. Colony
Completion date as per approved work schedule:30-6-17
Expected completion date: 31-03-2018
# Steel fixing & Form work of Column for 3rd Portion of Family Flats Block-I
is in progress
# Work on car park of family flats block-II is in progress
iv. Hospital/RE-House
Page 2 of 3
Pakhtunkhwa Energy Development Organization (PEDO), Govt. of Khyber Pakhtunkhwa
Court Cases:
Total No. of 12
Employees
Absent
On tour/ leave
Present on site 06
Page 3 of 3