Sr. No. Descripition Unit Quantity Rate Cost Total
No.
(In Rs.) (In Rs.) (In Rs.)
1 2 3 4 5 6 7 8
27.17 Prime Coat @ 0.85kg per sqm
Providing and applying primer coat with bitumen emulsion SS 1 Sqm
on prepared surface of granular base including cleaning of road
surface and spraying primer at the rate of 0.85kg/sqm complete
as per technical clause 502 of MORT&H specifications
I Materials
(i) Bulk Bitumen Emulsion SS at site of work tonne 0.00085 20316.00 17.27
Total - I 17.27
Total = 19.00
II Labour
Taking output 3500 Sqm
(i) Mate Day 0.08 151.44 12.12
(ii) Mazdoor Unskilled (Semi Skilled Lower) Day 2.00 143.81 287.62
Machinery
(iii) Mechanical Broom hour 2.80 345.00 966.00
Total - II 3928.94