Vous êtes sur la page 1sur 2

Analysis of rate for Construction of granular sub-base by providing coarse graded material grading-I for first,

second layer & grading II for third layer, 350mm thick spreading in three uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to
achieve the desired density, complete as per technical clause 401 of MORT&H specifications.

Unit Cum
Lead 44 Km

1 Rate for providing spreading and compacting


24.8 GSB material in layers. Rs. 511.18

Add C.P. 47% = Rs. 240.25


-------------------
Rs. 751.43 (A)

2 Add difference of rate of material between quarry rate and rate taken in
premium list December 2013 including carriage beyond 5 km.

1.28 Cum @ Rs. 358.25 Rs. 458.56 (B)


----------------------
Total A +B Rs. 1209.99

Say Rs. 1210/- Cum

Certificate
1 It is certified that lead taken for carriage of material from nearest quarry is as per shortest
possible route.
2 It is certified that the rates for material are as per the rates of nearest quarry.
3 The rates are for estimating purpose only
4 The rates of labour are as per actual observations.

Divisional Engineer (C-I) & Projects


GMADA, SAS Nagar
Analysis of rate for Construction of granular sub-base by providing coarse graded material grading-I for first,
second layer & grading II for third layer, 350mm thick spreading in three uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller
to achieve the desired density, complete as per technical clause 401 of MORT&H specifications.

Unit Cum
Lead Km

1 Rate for providing spreading and compacting


24.8 GSB material in layers. Rs. 511.18

Add C.P. 47% Rs. 240.25


-------------------
Rs. 751.43 (A)

2 Add difference of rate of material between quarry rate and rate taken in
Premium list December 2013 including carriage beyond 5 km.

1.28 Cum @ Rs. 437.49 Rs. 559.99 (B)


----------------------
Total A +B Rs. 1311.42

Say Rs. 1311 /- Cum


Certificate
1 It is certified that lead taken for carriage of material from nearest quarry is as per shortest
possible route.
2 It is certified that the rates for material are as per the rates of nearest quarry.
3 The rates are for estimating purpose only
4 The rates of labour are as per actual observations.

J.E (C-I ) S.D.E (C-I) D.E (C-I)


GMADA, SAS Nagar