Vous êtes sur la page 1sur 12

Juan Nakpil & Sons v. Court of Appeals 144 SCRA 597, G.R. No. L- 1.

1. No, they are not exempted from liability. There is no dispute that the
47851 (October 3, 1996) earthquake is a fortuitous event or an act of god. But, if upon the happening of
a fortuitous event or an act of God, here concurs a corresponding fraud,
Facts: negligence, delay or violation or contravention in any manner of the tenor of
the obligation, which results in loss or damage, the obligor cannot escape
liability.
1. Philippine Bar Association (PBA) decided to construct an office building at
Intramuros, Manila. The principle embodied in the act of God doctrine strictly requires that the act
2. The construction was undertaken by the United Construction, Inc. (United) on must be one occasioned exclusively by the violence of nature and all human
an “administration basis”, on the suggestion of Juan J. Carlos (Carlos), the agencies are to be excluded from creating or entering into the cause of the
president and general manager of United. mischief. When the effect, the cause of which is to be considered, is found to
3. Plans and specifications for the building were prepared by the third-party be in part the result of the participation of man, whether it be from active
defendants Juan F. Nakpil & Sons(Nakpil) intervention or neglect, or failure to act, the whole occurrence is thereby
4. The building was completed on June 1966. HUMANIZED, as it were, and removed from the rules applicable to the acts of
5. On August 2, 1968, an unusually strong earthquake hit Manila and its environs God.
and the building in question sustained major damage.
6. PBA commenced an action for the recovery of damages arising from the partial
collapse of the building against United. In turn, United filed a third-party United was found to have made substantial deviations from the plans and
complaint against the architects (Nakpil) who prepared the plans and specifications and to have failed to observe the requisite workmanship in the
specifications. construction as well as to exercise the requisite degree of supervision. And the
7. Parties agreed to refer the technical issues involved in the case to a Nakpins were found to have inadequacies or defects in the plans and
Commissioner, Mr. Andres O. Hizon (Hizon). specifications prepared by them. The deviations made by United caused
8. On April 30, 1979 the building was authorized to be demolished at the expense indirectly the damage sustained and that those deviations not only added but
of United and Nakpil. also aggravated the damage caused by the defects made by the Nakpins.
9. Hizon submitted his report with the findings that while the damage sustained
by the PBA building was caused by the earthquake, they were also caused by
the (1) defects in the plans and specifications prepared by the architects, (2) Thus, one who negligently creates a dangerous condition cannot escape
deviations from said plans and specifications by United and (3) failure of United liability for the natural and probably consequences thereof, although the act of
to observe the requisite workmanship in construction of the building and of the a third person, or an act of God for which he is not responsible, intervenes to
contractors and architects to exercise the requisite degree of supervision in precipitate the loss. The destruction was not purely an act of God. Truth to tell
the construction of the said building. hundreds of ancient buildings in the vicinity were hardly affected by the
10. The United Architects of the Philippines, the Association of Civil Engineers, earthquake. Only one thing spells out the fatal difference; gross negligence
and the Philippine Institute of Architects filed with the Court a motion to and evident bad faith, without which the damage would not have occurred.
intervene as amicus curiae.
11. The amicus curiae gave the opinion that the plans and specifications of the
Nakpils were not defective. (In contradiction to the opinion of Hizon) Notes / Law / Doctrine:

Issue/s:
 (New Civil Code) Art. 1723. The engineer or architect who drew up the plans
and specifications for a building is liable for damages if within fifteen years from
1. Whether or not an act of God – an unusually strong earthquake – which caused the completion of the structure the same should collapse by reason of a defect
the failure of the building, exempts from liability, parties who are otherwise in those plans and specifications, or due to the defects in the ground. The
liable because of their negligence. contractor is likewise responsible for the damage if the edifice fags within the
same period on account of defects in the construction or the use of materials
of inferior quality furnished by him, or due to any violation of the terms of the
Ruling: contract. If the engineer or architect supervises the construction, he shall be
solidarily liable with the contractor.
Acceptance of the building, after completion, does not imply waiver of any of 1. Engineering Construction, Inc. (petitioner, ECI for brevity), being a successful
the causes of action by reason of any defect mentioned in the preceding bidder, executed a contract in Manila with the National Waterworks and
paragraph. Sewerage Authority (NAWASA), whereby the former undertook:
1. to furnish all tools, labor, equipment and materials, and
2. to construct the proposed 2nd Ipo-Bicti Tunnel, Intake and Outlet
The action must be brought within ten years following the collapse of the Structures, and Appurtenant Structures, and Appurtenant Features at
building. Norzagaray, Bulacan and to complete said works within 800 calendar
days. (Angat Hydro-electric Project and Dam)
2. The project involves two (2) major phases: (1) tunnel work covering a
 (New Civil Code) Art. 1174. Except in cases expressly specified by the law, or distance of 7 kilometres and (2) the outworks at both ends of the tunnel.
when it is otherwise declared by stipulation, or when the nature of the 3. The ECI already had completed the first major phase of the work (Tunnel
obligation requires the assumption of risk, no person shall be responsible for Excavation Work), all the equipment no longer needed there were transferred
those events which could not be foreseen, or which, though foreseen, were to another site where some projects were yet to be completed. Some portion
inevitable. of the Bicti site were still under construction (2 nd phase).
4. On November 4, 1967, Typhoon “Welming” hit Central Luzon, passing
 A Breach of an obligation due to an “Act of God”, the following must concur: through corporations’ Angat Hydro-electric Project and Dam.
1. The cause of the breach of the obligation must be independent of the will 5. Due to the heavy downpour, the water in the reservoir of the Angat Dam was
of debtor; rising perilously at the rate of 60 cm per hour. To prevent an overflow of
2. The event must be either unforeseeable or unavoidable; water from the dam, the National Power Corporation(NPC) caused the
3. The event must be such as to render it impossible for the debtor to fulfil opening of the spillway gates.
his obligation in a normal manner; 6. Extraordinary large volume of water rushed out of the gates, and hit the
4. The debtor must be free from any participation in, or aggravation of the installations and construction works of ECI at Ipo site with terrific impact, as a
injury to the creditor. result of which the latter’s stockpile of materials supplies, camp facilities and
permanent structures and accessories whether washed away, lost or
 “There is no mystery about these acts of negligence. The collapse of the PBA destroyed.
building was no wonder performed by God. It was a result of the imperfections
in the work of the architects and the people in the construction company. More Issue/s:
relevant to our mind is the lesson from the parable of the wise man in the
Sermon on the Mount “which built his house upon a rock; and the rain
descended and the floods came and the winds blew and beat upon that house; 1. Whether or not the destruction and loss of ECI’s equipment and facilities
and it fen not; for it was founded upon a rock” and of the “foolish upon the were due to force majeure, which will exempt NPC from liability.
sand. And the rain descended and man which built his house the floods came,
and the winds blew, and beat upon that house; and it fell and great was the fall Ruling:
of it. (St. Matthew 7: 24-27).” The requirement that a building should withstand
rains, floods, winds, earthquakes, and natural forces is precisely the reason
why we have professional experts like architects, and engineers. Designs and 1. No, NPC will not be exempted from liability. NPC was undoubtedly negligent
constructions vary under varying circumstances and conditions but the because it opened the spillway gates of the Angat Dam only at the height of
requirement to design and build well does not change.” – Justice Gutierrez typhoon “Welming” when it knew very well that it was safer to have opened
the same gradually and earlier, as it was also undeniable that NPC know of
the coming typhoon at least four days before it actually struck.
National Power Corporation v. Court of Appeals 161 SCRA 334, G.R. No.
L-47379 (May 16, 1998)
The typhoon was an act of God or what we may call force majeure, NPC
Facts: cannot escape liability because its negligence was the proximate cause of
the loss and damage.
As we have ruled in Juan F. Nakpil & Sons v. Court of Appeals: event that the barge, exclusively controlled by appellant, rammed the bridge
supports raises a presumption of negligence on the part of appellant or its
employees manning the barge or the tugs that towed it. For in the ordinary
“If upon the happening of a fortuitous event or an act of God, there concurs a course of events, such a thing does not happen if proper case is used. Res
corresponding fraud, negligence, delay or violation or contravention in any ipsa loquitur.
manner of the tenor of the obligation, which results in loss or damage, the
obligor cannot escape liability. NLS stresses the precautions (due diligence) taken by it: (1) that it assigned
two of its most powerful tugboats to tow down river its barge, and (2) that it
The principle embodied in the act of God doctrine strictly requires that the assigned to the task the more competent and experienced among its patrons,
act must be one occasioned exclusively by the violence of nature and human (3) had the towlines, engines and equipment double-checked and inspected;
agencies are to be excluded from creating or entering into the cause of the (4) that it instructed its patrons to take extra precautions. These very
mischief. When the effect, the cause of which is to be considered, is found to precautions, completely destroy the NLS’defense.
be in part the result of the participation of man, whether it be from active
intervention or neglect, or failure to act, the whole occurrence is thereby Caso fortuito or force majeure by definition, are extraordinary events not
HUMANIZED, as it were, and removed from the rules applicable to the acts foreseeable or avoidable, events that could not be foreseen, or which, though
of God. foreseen, were inevitable.” It is, therefore, not enough that the event should
not have been foreseen or anticipated, as is commonly believed, but it must
Republic v. Luzon Stevedoring Corporation 21 SCRA 279, G.R. No. L- be one impossible to foresee or to avoid. The more difficulty to foresee the
21749 (September 29, 1967) happening is not impossibility to foresee the same. The very measures
adopted by NSC prove that the possibility of danger was not only foreseeable,
Facts: but actually foreseen, and was not caso fortuito.

1. Barge owned by Luzon Stevedoring Corporation(defendant, LSC for brevity) LSC, knowing and appreciating the perils posed by the swollen steam and its
was being towed down the Pasig river by tugboats belonging to the same swift current, voluntarily entered into a situation involving obvious danger; it
corporation.` therefore assured the risk, and cannot shed responsibility merely because the
2. The barge rammed against one of the wooden piles of the Nagtahan Bailey precautions it adopted turned out to be insufficient.
Bridge, smashing the posts and causing the bright to list. The river, at that time,
was swollen and the current swift, on account of the heavy downpour of Manila
and the surrounding provinces.
3. Republic of the Philippines (PH) sued LSC for actual and consequential
damages caused by its employees.

Philcomsat v. Globe Telecom 429 SCRA 153, G.R. No. 147324 (May
Issue/s:
25, 2004)

1. Whether or not the collision of LSC’s barge with the supports or piers of the Facts:
Nagtahan bridge was in law caused by fortuitous event or force majeure.
1. Globe Telecom, Inc. (Globe) is engaged in the coordination of the provision of
Ruling:
various communication facilities for the military bases of the United States of
America (US) in the Clark Air Base and Subic Naval Base.
1. No. Considering that the Nagtahan bridge was an immovable and stationary 2. Saud communication facilities were installed and configured for the exclusive
object and uncontrovertibly provided with adequate openings for the passage use of the US Defense Communications Agency (USDCA).
of water craft, including barges like of NSC’s, it is undeniable that the unusual 3. Globe contracted Philippine Communications Satellite Corporation
(Philcomsat) for the provision of the communication facilities.
4. Philcomsat and Globe entered into an agreement whereby Philcomsat obliged Events made impossible the continuation of the Agreement until the end of its
itself to establish, operate and provide an IBS Standard B earth station (earth five-year term without fault on the part of either party. Such fortuitous events
station) for the exclusive use of the USDCA. Globe promised to pay Philcomsat rendered Globe exempt from payment of rentals for the remainder of the term
monthly rentals for each leased circuit involved. of the Agreement.
5. Philcomsat installed and established the earth station and the USDCA made
use of the same.
6. Senate passed and adopted its resolution, expressing its decision not to Philcomsat would like to charge globe rentals for the balance of the lease term
concur in the ratification of the Treaty of Friendship, Cooperation and Security without being any corresponding telecommunications service subject of the
and its Supplementary Agreements that was supposed to extend the term of lease. It will be grossly unfair and iniquitous to hold globe liable for lease
the use by the US of Subic Naval Base, among others. charges for a service that was not and could not have been rendered due to
7. PH government sent a Note Verbale to the US government through the US an act of the government which was clearly beyond globes control.
Embassy, notifying it of the Philippine termination of the RP-US Military Base
Agreement. The withdrawal of all US military forces from Subic Naval Base
should be completed by December 31. 1992. 2. Yes. The US military forces and personnel completely withdrew from Cubi
8. Globe notified Philcomsat of its intention to discontinue the use of the earth Point only on December 31, 1992. Thus, until that date, USDCA had control
station. over the earth station and had the option of using the same. Furthermore,
9. Philcomsat demand payment of rentals for the balance of lease term, despite Philcomsat could not have removed or rendered ineffective said
the non-use of earth station. communication facility until after December 31, 1992 because Cubi Point was
accessible only to US naval personnel up to that time.
Issue/s:
3. No. The award of attorney’s fees is the exemption rather than the rule. In cases
where both parties have legitimate claims against each other and no party
1. Whether the termination of the RP-US Military Base Agreement, the non- actually prevailed, such as in the present case where the claims of both parties
ratification of the Treaty of Friendship, Cooperation and Security, and the were sustained in part, an award of attorney’s fees would not be warranted.
consequent withdrawal of US military forces and personnel from Cubi Point
constitute force majeure which would exempt Globe from complying with its Exemplary damages may be awarded in cases involving contracts, if the erring
obligation to pay rentals under its Agreement with Philcomsat. party acted in wanton, fraudulent, reckless, oppressive or malevolent manner.
2. Whether Globe is liable to pay rentals under the Agreement for the month of It was not shown that Globe acted wantonly or oppressively in not heeding
December 1992. Philcomsats demands for payment of rentals. Globe had valid grounds for
3. Whether Philcomsat is entitled to attorney’s fees and exemplary damages. refusing to comply with its contractual obligations after 1992.

Ruling:
Yobido v. Court of Appeals 281 SCRA 1, G.R. No. 113003 (October
17, 1997)
1. Yes. Philcomsat and Globe had no control over the non-renewal of the term of
the RP-US Military Base Agreement when the same expired in 1991, because Facts:
the prerogative to ratify the treaty extending the life thereof belonged to the
Senate. Neither did the parties have control over the subsequent withdrawal
of the US military forces and personnel from Cubi Point in December 1992. 1. Spouses Tito and Leny Tumboy and their minor children named Ardee and
Jasmin boarded a Yobido Liner bus.
As a consequence of the termination of the RP-US Military Base Agreement 2. The left front tire of the bus exploded.
the continued stay of all US Military forces and personnel from Subic Naval 3. The bus fell into a ravine which resulted in the death of 28-year old Tumboy
Base would no longer be allowed, hence, plaintiff would no longer be in any and physical injuries to other passengers.
position to render service it was obligated under the Agreement.
Issue/s:
1. Whether or not the Yobido (bus-owner) be exempt from liability because the 4. From crop year 1957-1958 up to crop year 1967-1968, Gatuslao has been
tire blowout was no more than a fortuitous event that could not have foreseen. milling all the sugarcane grown and produced with the Mill of BMMC.
5. From crop year 1920-21 to crop year 1967-68, the canes of planters adhered
Ruling: to the mill of BMMC were transported from the plantation to the mill by means
of cane cars and through railway system operated by BMMC.
6. BMMC has been hauling planter Gatuslao’s sugar cane to its mill or factory
1. No. Under the circumstances of the present case, the explosion of the new tire continuously until crop year 1967 – 1968.
may not be considered a fortuitous event. It is settled that an accident caused 7. The milling contract between BMMC and owners of the hacienda Helvetica
either by defects in the automobile or through the negligence of its driver is not expired at the end of the 1964-1965 crop year.
a caso fortuito that would exempt the carrier from liability for damages. 8. The portion of the railway traversing the hacienda Helvetica was closed as per
decision of the court.
A common carrier may not be absolved from liability in case of force majeure 9. The use of the railroad tracks(traversing hacienda Helvetica) was temporarily
or fortuitous event alone. The common carrier must still prove that it was not allowed due to the intervention of the President of the Philippines, which is until
negligent in causing the death or injury resulting from an accident. 1967-1978 milling season only.
10. Gatuslao loaded their cut cranes on trucks provided by the Bacolod-Murcia
Agricultural Cooperative Marketing Association, Inc. (B-MACMA) during 1968-
In culpa contractual, once a passenger dies or injured, the carrier is presumed 1969 crop year.
to have been at fault or to have acted negligently. This presumption may only 11. BMMC had not been able to use its cane cars and railway system for the cargo
be overcome by evidence that the carrier had observed extraordinary crop year 1968-1989.
diligence.
Issue/s:
The Yobido failed to rebut the testimony of Leny Tumboy that the bus was
running so fast that she cautioned the driver to slow down. These contradictory 1. Whether or not the termination of petitioner’s right of way over the hacienda
facts must, be resolved in favor of liability in view of the presumption of Helvetica caused by the expiration of its amended milling contracts with the
negligence of the carrier in the law. Coupled with this is the established landowners of the land in question is fortuitous event or force majeure which
condition of the road tough, winding and wet due to rain. It was incumbent will exempt petitioner BMMC from fulfillment of its contractual obligation.
upon the defense to establish that it took precautionary measures considering 2. Whether or not BMMC was able to provide adequate and efficient
partially dangerous condition of the road. transportation facilities of the canes of Gatuslao and the other planters milling
with BMMC during the crop year 1968-69.
Yobido failed to discharge its duty to overthrow the presumption of negligence
Ruling:
with clear and convincing evidence.

1. No. The terms of the milling contracts were clear and undoubtedly there was
Bacolod-Murcia Milling v. Court of Appeals 182 SCRA 24, G.R. No. no reason for BMMC to expect otherwise. The closure of any portion of the
81100-01 (February 7, 1990) railroad track, not necessarily in the hacienda Helvetica but in any of the
properties whose owners decided not to renew their milling contracts with the
Facts: Central upon their expiration, was foreseeable and inevitable.

1. Bacolod-Murcia Milling Co., Inc.(BMMC) is the owner and operator of the sugar Despite its awareness that the conventional contract of lease would expire in
central in Bacolod. crop year 1964-1965 and that refusal on the part of any one of the landowners
2. Alonso Gatuslao (Gatuslao) is a registered plantor of the Bacolod-Muria Mill to renew their milling contracts and the corresponding use of the right of way
District. on their lands would render impossible compliance of its commitments, BMMC
3. BMMC and Gatuslao executed an “Extension and Modification of Milling took a calculated risk that all the landowners would renew their contracts.
Contract.
The closure of the railway lines was not an act of God nor it constitute force 1. Whether or not in a contract of agency (consignment of good for sole) it is
majeure. It was due to the termination of the contractual relationships of the necessary that there be prior conviction for robbery before the loss of the article
parties, for which BMMC is charged with knowledge. Owners of the hacienda shall exempt the consignee from liability for such loss.
Helvetica notified BMMC as far back as August 1965 of its intention not to 2. Whether or not Abad was negligent.
allow the passage of the railway system thru its land after the aforesaid crop
year. Adequate measures should have been adopted by BMMC to forestall Ruling:
such paralyzations but the records show none.

1. No. To avail of the exemption granted in the law, it is not necessary that the
2. No, BMMC failed to provide adequate transportation facilities to Gatuslao and persons responsible for the occurrence should be found or punished, it would
other adherent parties. only be sufficient to establish that the enforceable event, the robbery in this
case did take place without any concurrence fault on the debtor’s part, and this
The inadequacies of the reparto or trailer allotment as well as the state of can be done by preponderance of evidence.
unpreparedness on the part of BMMC to meet the problem posed by the
closure of the railway lines. A court finding that a robbery has happened would not necessary mean that
those accused in the criminal action should be found guilty of the crime; nor
would a ruling that those actually accused did not commit the robbery be
It was established that after Gatuslao had cut his sugarcanes for hauling, no inconsistent with a finding that a robbery did take place.
trailers arrived and when two trailers finally arrived on October 1968 after
several unheeded requests, they were left on the national highway about one
kilometer away from the loading station, the means of transportation provided 2. No. In 1961, when the robbery in question did take place, for at that time
by BMMC is very inadequate to answer the needs of Gatuslao. criminality had not by far reached the levels attained in the present day. The
diligence that Abad portrayed when she went home before she was robbed
was not a sign of negligence on her part.
Austria v. Court of Appeals 31 SCRA 527, G.R. No. L-29640 (June
10, 1971) Khe Hong Cheng v. Court of Appeals 355 SCRA 701, G.R. No. 144169
(March 20, 2001)
Facts:
Facts:
1. Maria G. Abad received from Guillermo Austria one (1) pendant with diamonds
to be sold on commission basis or to be returned on demand.
1. The Philippine Agricultural Trading Corporation shipped on board the vessel
2. Maria Abad while walking home, two men snatched her purse containing
M/V PRINCE ERIC, owned by Khe Hong Cheng (petitioner, Cheng for brevity),
jewelry and cash, and ran away.
3,400 bags of copra at Masbate, for delivery to Zamboanga del Norte.
3. Thus, Abad failed to return the jewelry or pay its value notwithstanding 2. The shipment of copra was covered by a marine insurance policy issued by
demands. American Home Insurance Company (respondent Philam’s assured).
4. Austria filed an action against Abad and Abad’s husband for recovery of the
3. M/V/ PRINCE ERIC, sank, resulting in the total loss of the shipment. Because
pendant or of its value, and damages.
of the loss, the insurer, American Home, paid the amount of P354,000.00.
5. Abad raised the defense that the alleged robbery had extinguished their
4. American Home instituted a Civil Case to recover the money paid to the
obligation.
consignee, based on breach of contract of carriage.
5. While the case was still pending, on December 20, 1989, Cheng executed
Issue/s: deeds of donations of parcels of land in favour of his children. (The same deed
was registered on December 27, 1989)
6. The trial court rendered judgement against Cheng on December 29, 1993, four
years after the donations were made and the TCTs were registered in the
donees names.
7. A writ of execution was issued; however, it was not served. An alias writ of  (New Civil Code) Article 1150. The time for prescription for all kinds of
execution was, thereafter, applied for and granted. Despite earnest efforts, the actions, when there is no special provision which ordains otherwise, shall be
sheriff found no property under the name of Butuan Shipping Lines and/or counted from the day they may be brought.
Cheng to levy or garnish the satisfaction of the trial court’s decision.  (New Civil Code) Article 1383. An action for rescission is subsidiary; it cannot
8. On January 17, 1997, the sheriff, accompanied by counsel of respondent be instituted except when the party suffering damage has no other legal means
Philam, went to Butuan City to enforce the alias writ of execution, they to obtain reparation for the same.
discovered that petitioner Cheng no longer had any property and he had  Requisites of accion pauliana
conveyed the subject properties to his children.
9. Philam filed a complaint for the rescission of the deeds of donation executed 1. Plaintiff asking for rescission has a credit prior to the alienation, although
by Cheng in favour of his children and for the nullification of their titles. demandable later.
2. Debtor has made a subsequent contract conveying a patrimonial benefit to a
Issue/s: third persons.
3. Creditor has no other legal remedy to satisfy his claim, but would benefit by
rescission of the conveyance to the person.
1. Whether or not the action to rescind the subject deeds of donations already 4. Act being impugned is fraudulent.
prescribed. 5. The third parsons who received the property conveyed, if by onerous title, has
been an accomplice in the fraud.
Ruling:
 Accion pauliana presupposes the following:
1. No. An accion pauliana accrues only when the creditor discovers that he has
no other legal remedy for the satisfaction of his claim against the debtor other 1. A judgment;
than an accion pauliana. The accion pauliana is an action of a last resort. 2. Issuance by the trial court of a writ of execution for the satisfaction of the
judgement; and
Respondent Philam only learned about the unlawful conveyances made by 3. The failure of the sheriff to enforce and satisfy the judgement of the court.
petitioner Cheng in January 1997 when its counsel accompanied the sheriff to 4. It requires that the creditor has exhausted the property of the debtor.
Butuan City to attach the properties of Cheng. There they found that he no
longer had any properties in his name. it was only then that respondent  Successive measures must be taken by a creditor
Philam’s action for rescission of the deeds of donation accrued because then
it could be said that respondent Philam had exhausted all legal means to 1. Exhaust the properties of the debtor through levying by attachment and
satisfy the trial court’s judgement in its favour. execution upon all the property of the debtor; except such as are exempt from
execution;
2. Exercise all the rights and actions of the debtor, save those personal to him
Since respondent Philam filed its complain for accion pauliana against Cheng (accion subrogatoria);
on February 25, 1997, barely a month from its discovery that Cheng had no 3. Seek rescission of the contracts executed by the debtor in fraud of their rights
property to satisfy the judgement award against him, its action for rescission (accion pauliana).
of the subject deeds clearly had not yet prescribed.
Siguan v. Lim 318 SCRA 725, G.R. No. 134685 (November 19, 1999)
Note / Doctrine:
Facts:

 Alias executionis a second writ of execution issued in the same cause, to


enforce a judgment not fully satisfied by the original writ. 1. On 25 and 26 August 1990, Rosa Lim (respondent, LIM) issued two Metrobank
 (New Civil Code) Article 1389. The action to claim rescission must be checks to satisfy her debts to Maria Antonia Siguan (petitioner, SIGUAN).
commenced within four years. 2. Upon presentment by SIGUAN with the drawee bank, the checks were
dishonoured for the reason account closed.
3. Criminal case for violation of BP 22 was filed by SIGUAN against LIM.  Requisites of accion pauliana
4. On December 29 1992, RTC convicted LIM as charged. The case is pending
before this Court for review. 1. Plaintiff asking for rescission has a credit prior to the alienation, although
5. On August 10, 1989, LIM executed a Deed of Donation in favour of her demandable later.
children, and the same was registered with the Office of the Register of Deeds 2. Debtor has made a subsequent contract conveying a patrimonial benefit to a
on July 2, 1991. third persons.
6. June 23, 193, SIGUAN filed an accion pauliana against LIM and her children, 3. Creditor has no other legal remedy to satisfy his claim, but would benefit by
to rescind the questioned Deed of Donation and to declare as null and void the rescission of the conveyance to the person.
new transfer certificates of title. 4. Act being impugned is fraudulent.
5. The third parsons who received the property conveyed, if by onerous title, has
Issue/s: been an accomplice in the fraud.

 (New Civil Code) Article 1381. Contracts entered into in fraud of creditors
1. Whether or not the questioned Deed of Donation was made in fraud of
may be rescinded only when the creditors cannot in any manner collect the
petitioner and, therefore, rescissible.
claims due to them.
 (New Civil Code) Article 1383. The action for rescission is but a subsidiary
Ruling: remedy which cannot be instituted except when the party suffering damage
has no other legal means to obtain reparation for the same.
1. No. The rescission required the existence of creditors at the time of alleged  (New Civil Code) Article 1387(1). All contracts by virtue of which the debtor
fraudulent alienation, and this must be proved as one of the bases of the alienates property by gratuitous title are presumed to have been entered into
judicial pronouncement setting aside the contract. Without prior existing debt, in fraud of creditors when donor did not reserve sufficient property to pay all
there can neither be injury nor fraud. While it is necessary that the credit of the debts contracted before the donation.
plaintiff in the accion pauliana must exist prior to the fraudulent alienation, the  (New Civil Code) Article 759. Donation is always presumed to be in fraud of
date of the judgment enforcing it is immaterial. creditors when at the time thereof the donor did not reserve sufficient property
to pay his debts prior to the donation.
 (New Civil Code) Article 1384. Rescission shall only be to the extent
Since LIMs indebtedness to SIGUAN was incurred in August 1990, or a year
necessary to cover the damages caused.
after the execution of the Deed of Donation, the first requirement of accion
 Only the creditor who brought the action for rescission can benefit from the
pauliana was not met.
rescission; those who are strangers to the action cannot benefit from its
effects.
Even assuming arguendo that petitioner became a creditor of LIM prior to the  Revocation is only to the extent of the plaintiff creditors unsatisfied debts;
celebration of the contract of donation, still her action for rescission would not as to the excess, alienation is maintained.
fare well because the third requisite was not met. It is essential that the party
asking for rescission prove that he has exhausted all other legal means to
obtain satisfaction of his claim. SIGUAN neither alleged nor proved that she
did so. On his score, her action for rescission of the questioned deed is not EASTERN SHIPPING LINES, INC. vs. CA, GR. No. 97412, July 12, 1994
maintainable even if the fraud charged actually did exist.

FACTS: Two fiber drums of riboflavin were shipped from Yokohama, Japan
The fourth requisite for an accion pauliana to prosper is not present either. (4)
the act being impugned is fraudulent. It was not sufficiently established that on board the vessel owned by herein petitioner Eastern Shipping Lines. When
the properties left behind by LIM were not sufficient to cover her debts existing
it arrives in Manila, it was put unto the custody of Metro Port Service, Inc. The
before the donation was made.
latter excepted to one drum which is said to be in bad order and which damage

Note / Doctrine: was unknown to Eastern Shipping Lines. Later, Allied Brokerage Corporation
received the shipment from Metro Port Service, Inc. With one drum damaged, stipulation, the rate of interest shall be 12% per annum to be
Allied Brokerage Corporation made deliveries to the consignee's warehouse. computed from default under and subject to the provisions of Article
The latter excepted to one drum that is damaged. Eastern Shipping Lines 1169 of the Civil Code.
averred that due to the one drum that is damaged and due to the fault and
negligence of Metro Port Service, Inc. and Allied Brokerage Corporation, the 2. When an obligation, not constituting a loan or forbearance of money,
consignee suffered losses. The two failed and refused to pay the claims for is breached, an interest on the amount of damages awarded may be
damages. Consequently, Eastern Shipping Lines was compelled to pay the imposed at the discretion of the court at the rate of 6% per annum. No
consignee being subrogated to all the rights of action of said consignee against interest, however, shall be adjudged on unliquidated claims or
Metro Port Service, Inc. and Allied Brokerage Corporation. Trial ensued and damages except when or until the demand can be established with
on appeal of the case, the appellate court affirmed the decision of the trial court reasonable certainty. Accordingly, where the demand is established
ordering Metro Port Service and Allied Brokerage to pay Eastern Shipping with reasonable certainty, the interest shall begin to run from the time
Lines, jointly and severally, the amount of P19,032.95, with the present legal the claim is made judicially or extrajudicially (Art. 1169, Civil Code) but
interest of 12% per annum from the date of filing of the complaints, until fully when such certainty cannot be so reasonably established at the time
paid. Metro Port Service and Allied Brokerage opposed especially as to the the demand is made, the interest shall begin to run only from the date
payment of interest contending that the legal interest on an award for loss or the judgment of the court is made (at which time the quantification of
damage should be 6% in view of Article 2209 of the Civil Code. damages may be deemed to have been reasonably ascertained). The
actual base for the computation of legal interest shall, in any case, be
ISSUE: Whether or not the payment of legal interest on an award for loss or on the amount finally adjudged.
damage is twelve percent (12%) or six percent (6%).
3. When the judgment of the court awarding a sum of money becomes
HELD: Article 2209 of the New Civil Code provides that if the obligation final and executory, the rate of legal interest, whether the case falls
consists in the payment of a sum of money, and the debtor incurs in delay, the under paragraph 1 or paragraph 2, above, shall be 12% per
indemnity for damages, there being no stipulation to the contrary, shall be the annum from such finality until its satisfaction, this interim period being
payment of interest agreed upon, and in the absence of stipulation, the legal deemed to be by then an equivalent to a forbearance of credit.
interest which is six percent per annum. With regard particularly to an award
of interest in the concept of actual and compensatory damages, the rate of Dario Nacar vs Gallery Frames
interest, as well as the accrual thereof, is imposed, as follows:
FACTS:
1. When the obligation is breached, and it consists in the payment of a
Dario Nacar filed a labor case against Gallery Frames and its owner Felipe
sum of money, the interest due should be that which may have been Bordey, Jr. Nacar alleged that he was dismissed without cause by Gallery
stipulated in writing. Furthermore, the interest due shall itself earn Frames on January 24, 1997. On October 15, 1998, the Labor Arbiter (LA)
found Gallery Frames guilty of illegal dismissal hence the Arbiter awarded
legal interest from the time it is judicially demanded. In the absence of Nacar P158,919.92 in damages consisting of backwages and separation pay.
Gallery Frames appealed all the way to the Supreme Court (SC). The Supreme 2. Non-Monetary Obligations (such as the case at bar)
Court affirmed the decision of the Labor Arbiter and the decision became final
a. If already liquidated, rate of interest shall be 6% per annum, demandable
on May 27, 2002.
from date of judicial or extra-judicial demand (Art. 1169, Civil Code)
After the finality of the SC decision, Nacar filed a motion before the LA for
b. If unliquidated, no interest
recomputation as he alleged that his backwages should be computed from the
time of his illegal dismissal (January 24, 1997) until the finality of the SC Except: When later on established with certainty. Interest shall still be 6% per
decision (May 27, 2002) with interest. The LA denied the motion as he ruled annum demandable from the date of judgment because such on such date, it
that the reckoning point of the computation should only be from the time Nacar is already deemed that the amount of damages is already ascertained.
was illegally dismissed (January 24, 1997) until the decision of the LA (October
15, 1998). The LA reasoned that the said date should be the reckoning point 3. Compounded Interest
because Nacar did not appeal hence as to him, that decision became final and – This is applicable to both monetary and non-monetary obligations
executory.
– 6% per annum computed against award of damages (interest) granted by
ISSUE: Whether or not the Labor Arbiter is correct. the court. To be computed from the date when the court’s decision becomes
HELD: No. There are two parts of a decision when it comes to illegal dismissal final and executory until the award is fully satisfied by the losing party.
cases (referring to cases where the dismissed employee wins, or loses but 4. The 6% per annum rate of legal interest shall be applied prospectively:
wins on appeal). The first part is the ruling that the employee was illegally
dismissed. This is immediately final even if the employer appeals – but will be – Final and executory judgments awarding damages prior to July 1, 2013 shall
reversed if employer wins on appeal. The second part is the ruling on the apply the 12% rate;
award of backwages and/or separation pay. For backwages, it will be – Final and executory judgments awarding damages on or after July 1, 2013
computed from the date of illegal dismissal until the date of the decision of the shall apply the 12% rate for unpaid obligations until June 30, 2013; unpaid
Labor Arbiter. But if the employer appeals, then the end date shall be extended obligations with respect to said judgments on or after July 1, 2013 shall still
until the day when the appellate court’s decision shall become final. Hence, as incur the 6% rate.
a consequence, the liability of the employer, if he loses on appeal, will increase
– this is just but a risk that the employer cannot avoid when it continued to SPOUSES ANDAL vs PNB
seek recourses against the Labor Arbiter’s decision. This is also in accordance
with Article 279 of the Labor Code. FACTS:
Sept. 7, 1995, petitioners obtained a loan from respondent bank (P21.8M) for
Anent the issue of award of interest in the form of actual or compensatory which 12 promissory notes were executed, with varying interest rates (17.5-
damages, the Supreme Court ruled that the old case of Eastern Shipping Lines 27%). It was agreed that the rate of interest may be increased or decreased
vs CA is already modified by the promulgation of the Bangko Sentral ng with prior notice to the petitioners in the event of changes in interest rates
Pilipinas Monetary Board Resolution No. 796 which lowered the legal rate of prescribed by law or the Monetary Board.
interest from 12% to 6%. Specifically, the rules on interest are now as follows:
1. Monetary Obligations ex. Loans: Petitioners also executed a real estate mortgage in favor of the respondent
bank over 5 parcels of lands, including all improvements thereon, covered by
a. If stipulated in writing: Transfer of Certificate Titles of the Registry of Deeds.
a.1. shall run from date of judicial demand (filing of the case) Respondent bank advised petitioners to pay their loan, otherwise they would
declare it due and demandable. Petitioners paid P14.8M to avoid foreclosure.
a.2. rate of interest shall be that amount stipulated Respondent bank executed a release of real estate mortgage over two of the
b. If not stipulated in writing parcels of land. Despite payment, respondent foreclosed the remaining real
estate mortgage over the remaining three parcels of land.
b.1. shall run from date of default (either failure to pay upon extra-judicial
demand or upon judicial demand whichever is appropriate and subject to the A public auction sale resulted in respondent bank as the winning bidder. A
provisions of Article 1169 of the Civil Code) Certificate of sale of the properties was issued.
b.2. rate of interest shall be 6% per annum
Petitioners filed a complaint for annulment of mortgage, sheriff’s certificate of and binding. They are liable to pay interest from the time they defaulted until
sale, declaration of nullity of the increased interest rates and penalty charges the obligation is fully paid.
plus damages.
Petition is DENIED and the CA decision is AFFIRMED with the
CONTENTION OF THE PETITIONERS: MODIFICATION that the 12% interest per annum shall be applied from the
1. They tried to pay their loan obligation but the exorbitant rate date of default until June 30, 2013, after which date and until fully paid, the
of interest unilaterally determined and imposed by the obligation shall earn interest at 6% per annum.
respondent bank.
2. They signed the promissory notes in blank, relying on the
representation that they were bank requirements ADVOCATES FOR TRUTH IN LENDING, INC. VS. BANGKO SENTRAL
3. The exobrbitant and unilateral interest rates are a form of MONETARY BOARD, ET.AL.
unjust enrichment, giving respondent
4. bank no right to foreclose the mortgages Parties of the Case

RTC Ruling: In favor of petitioners, ordering that the rate of interest be reduced Petitioners: Advocates for Truth in Lending, INC. & Eduardo B. Olaguer
to 6% in accordance with Art. 2209, NCC and declaring the foreclosure sales (President of AFTIL).
as void.
Respondents: Bangko Sentral Monetary Board
CA Ruling: Affirmed the RTC decision with the modification that the interest
Facts of the Case
be 12% per annum instead of 6%. Stipulations in a contract have the force of
law between the parties so long as they are not contrary to law, morals, etc. Advocates for Truth in Lending, Inc. (AFTIL) is a non-profit, non-stock
Since parties expressly stipulated in the promissory notes that a rate of interest corporation organized to engage in pro bono concerns and activities relating
would be applied, the petitioners are bound thereby. to money lending issues. It was incorporated in July 9, 2010, and a month later,
it filed this petition, joined by its founder and president, Eduardo Olaguer, suing
The CA finds it more credible that the petitioners had signed blank promissory as a taxpayer and a citizen.
notes which respondent bank had filled with high interest rates. This violates
History of Central Bank’s power to fix max interest rates
the principle of mutuality of contracts. Since the interest rates in the promissory
notes are void, the rate of interest should be 12% (since what is involved is a 1. R.A. No. 265, which is created the Central Bank on June 15, 19481.
loan or forebearance of money). R.A. No. 265, which is created the Central Bank on June 15, 1948,
empowered the CB-MB to set the maximum interest rates which banks
Petitioners-spouses insist that "if the application of the doctrine of operative may charge for all types of loans and other credit operations.
facts is upheld, as applied in Caraig vs. Alday, interest in the instant case would
be computed only from the finality of judgment declaring the foreclosure sale
null and void. If Mercado vs. China Banking Corporation, applying by analogy 2. The Usury Law was amended by P.D. 1684 giving the CB-MB
the rule on void usurious interest to void potestative interest rate, is further authority to prescribe different maximum rates of interest which may
sustained, no interest is due when the potestative interest rate stipulation is be imposed for a loan or renewal thereof of the forbearance of any
declared null and void, as in the instant case. money, goods or credits, provided that the changes are affected
gradually and announced in advance. Section 1-a of Act No. 2655 now
reads:
ISSUES: Whether interest should be imposed on the loan.

3. In its Resolution No. 2224 dated December 3, 1982, the CB-MB issued
RULING: Yes. The petitioners had agreed to payment of interest on CB Circular No. 905, Series of 1982, effective on January 1, 1983. It
their loan obligation. The subsequent declaration that the rate of interest was removed the ceilings on interest rates on loans or forbearance of any
illegal does not entitle them to stop payment of interest. Only the rate was money, goods or credits: Sec. 1. The rate of interest, including
declared void, but the stipulation requiring them to pay interest remains valid commissions, premiums, fees and other fees charges, on loan or
forbearance of any money be charged or collected by any person,
whether natural or juridical, shall not be subject to any ceiling several cases, CB Circular No. 905 “ did not repeal nor in anyway
prescribed under or pursuant to the Usury law, as amended. amend the Usury Law but simply suspended the latter’s effectivity”.

Thus, according to the Court, by lifting the interest ceiling, CB Circular


4. R.A. No. 7653 establishing the BSP (Bangko Sentral ng Pilipinas) to No. 905 merely upheld the parties’ freedom of contract to agree freely
replace CB: on the rate of interest. It cited Art. 1306 of the New Civil Code, under
which the contracting parties may establish such stipulations, clauses,
terms and conditions as they may deem convenient, provided they are
Sec. 135. Repealing Clause – except as may be provided for in not contrary to law, morals, good customs, public order, or public
Sections 46 and 132 of this Act, Republic Act No. 265, as amended, policy.
the provisions of any other law, special charters, rule or regulation
issued pursuant to said Republic Act No. 265, as amended, or parts 3. The BSP-MB has authority to enforce CB Circular No. 905.
thereof, which may be inconsistent with the provisions of this Act are Moreover, the rule is settled that repeals by implication are not
hereby repealed. President Decree No. 1792 is likewise repealed. favored, because laws are presumed to be passed with deliberation
and full knowledge of all laws existing pertaining to the subject. An
implied repeal is predicated upon the condition that a substantial
conflict or repugnancy is found between the new and prior laws unless
Issues of the Case irreconcilable inconsistency and repugnancy exists in the terms of the
new and old laws. We find no such conflict between the provisions of
1. Whether under R.A. No. 265 and/or P.D. No. 1684, the CB-MB had
Act 2655 and RA NO. 7653.
the statutory or constitutional authority to prescribe the maximum rates
of interest for all kinds of credit transactions and forbearance of The lifting of the ceilings for interest rates does not authorize
money, goods or credit beyond the limits prescribed in the Usury Law; stipulations charging excessive, unconscionable, and iniquitous
interest.
2. If so, whether the CB-MB exceeded its authority when it issued CB With regard particularly to an award of interest in the concept of
Circular No. 905, which removed all interest ceilings and thus actual and compensatory damages, the rate of interest, as well
suspended Act No. 2655 as regards usurious interest rates; as the accrual thereof, is imposed, as follows:

The 12% per annum rate under CB Circular No. 416 shall
3. Whether under R.A. No. 7653, the new BSP-MB may continue to apply only to loans or forbearance of money, goods, or credits, as well
enforce CB Circular No. 905. as to judgments involving such loan or forbearance of money, goods,
or credit, while the 6% per annum under Art. 2209 of the Civil Code
Ruling of the SC applies “when the transaction involves the payment of indemnities in
1. CB-MB has the statutory or constitutional authority to prescribe the concept of damage arising from the breach or a delay in the
the max rates of interest for all kinds of credit transactions and performance of obligations in general with the application of both rates
forbearance of money, goods or credit beyond the limits reckoned from the time the complaint was filed until the amount is fully
prescribed in the Usury Law both under RA 265 and PD 1684 paid. In either instance, the reckoning period for the commencement
of the running of the legal interest shall be subject to the condition that
the courts are vested with discretion, depending on the equities of
2. The CB-MB merely suspended the effectivity of the Usury Law each case, on the award of interest.”
when it issued CB Circular No. 905.
Dispositive portion:
Petition for certiorari is DISMISSED.
The power of the CB to effectively suspend the Usury Law pursuant to
P.D. No. 1684 has long been recognized and upheld in many cases.
As the Court explained in the landmark case of Medel v. CA, citing

Vous aimerez peut-être aussi