FINAL ESTIMATE OF MATERIALS

Clearing and Excavation

Equipment

1 concrete cutter/saw (4 hours, 500php/hr)

𝐶𝑜𝑠𝑡 = 4 × 500 = 𝟐𝟎𝟎𝟎 𝒑𝒉𝒑

Manpower

1 operator (4 hours, 50php/hr)

𝐶𝑜𝑠𝑡 = 4 × 50 = 𝟐𝟎𝟎 𝒑𝒉𝒑

𝑻𝒐𝒕𝒂𝒍 𝑪𝒐𝒔𝒕 = 2000 + 200 = 𝟐𝟐𝟎𝟎 𝒑𝒉𝒑

Concrete works

Materials

Total length of the additional drainage = 55m

Thickness = 0.11m

Width = 0.45m

𝑇𝑜𝑡𝑎𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 = 55 × 0.11 × 0.45 = 𝟐. 𝟕𝟐𝟐𝟓 𝒎.

𝑁𝑜. 𝑜𝑓 𝑏𝑎𝑔𝑠 𝑜𝑓 𝑃𝑜𝑟𝑡𝑙𝑎𝑛𝑑 𝑐𝑒𝑚𝑒𝑛𝑡 = 2.7225 × 9 = 24.5 ≈ 𝟐𝟓 𝒃𝒂𝒈𝒔

𝐶𝑜𝑠𝑡 = 25 × 230 = 𝟓𝟕𝟓𝟎 𝒑𝒉𝒑

𝑐𝑢. 𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑠𝑎𝑛𝑑 = 2.7225 × 0.5 = 1.36 ≈ 𝟏. 𝟒𝟎 𝒎𝟑


𝐶𝑜𝑠𝑡 = 1.4 × 430 = 𝟔𝟎𝟐 𝒑𝒉𝒑

𝑐𝑢. 𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑔𝑟𝑎𝑣𝑒𝑙 = 2.7225 × 1.0 = 2.7225 ≈ 𝟐. 𝟖𝒎𝟑

𝐶𝑜𝑠𝑡 = 2.8 × 735 = 𝟐𝟎𝟓𝟖 𝒑𝒉𝒑

Equipment

1 bagger mixer (16 hours, 500php/hr)

𝐶𝑜𝑠𝑡 = 16 × 500 = 𝟖𝟎𝟎𝟎 𝒑𝒉𝒑

Manpower

1 skilled (2-days, 500php/day)

𝐶𝑜𝑠𝑡 = 2 × 500 = 𝟏𝟎𝟎𝟎 𝒑𝒉𝒑

𝑻𝒐𝒕𝒂𝒍 𝑪𝒐𝒔𝒕 = 1000 + 8000 + 5750 + 602 + 2058 = 𝟏𝟕𝟒𝟏𝟎 𝒑𝒉𝒑

Masonry

Materials

Total length of the additional drainage = 55m

55
𝑛𝑜. 𝑜𝑓 𝐶𝐻𝐵 = × 2 = 275 𝑝𝑐𝑠.
0.4

𝐶𝑜𝑠𝑡 = 275 × 10 = 2750 𝑝ℎ𝑝

Mortar (Class A)

275
𝑁𝑜. 𝑜𝑓 𝑃𝑜𝑟𝑡𝑙𝑎𝑛𝑑 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = × 6.336 = 17.424 ≈ 𝟏𝟖 𝒃𝒂𝒈𝒔
100
𝐶𝑜𝑠𝑡 = 18 × 230 = 𝟒𝟏𝟒𝟎 𝒑𝒉𝒑

275
𝑐𝑢. 𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑠𝑎𝑛𝑑 = × 0.348 = 0.957 ≈ 𝟏𝒎𝟑
100

𝐶𝑜𝑠𝑡 = 1 × 430 = 𝟒𝟑𝟎 𝒑𝒉𝒑

Plaster (Class A)

Using 8mm plaster

𝑡𝑜𝑡𝑎𝑙 𝑎𝑟𝑒𝑎 = (55 × 0.2) ∗ 2 = 𝟐𝟐

𝑁𝑜. 𝑜𝑓 𝑃𝑜𝑟𝑡𝑙𝑎𝑛𝑑 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = 22 × 0.144 = 3.168 ≈ 𝟒 𝒃𝒂𝒈𝒔

𝐶𝑜𝑠𝑡 = 4 × 230 = 𝟗𝟐𝟎 𝒑𝒉𝒑

𝑐𝑢. 𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑠𝑎𝑛𝑑 = 22 × 0.008 = 0.176 ≈ 𝟎. 𝟐𝒎𝟑

𝐶𝑜𝑠𝑡 = 0.2 × 430 = 𝟖𝟔 𝒑𝒉𝒑

Manpower

1 skilled (3 days, 500php/day)

𝐶𝑜𝑠𝑡 = 3 × 500 = 𝟏𝟓𝟎𝟎 𝒑𝒉𝒑

𝑻𝒐𝒕𝒂𝒍 𝑪𝒐𝒔𝒕 = 4140 + 2750 + 430 + 920 + 86 + 1500 = 𝟗𝟖𝟐𝟔 𝒑𝒉𝒑

Reinforcement

Material

Using ∅ 10𝑚𝑚. , 6𝑚 𝑙𝑒𝑛𝑔𝑡ℎ 𝑟𝑒𝑏𝑎𝑟


Vertical Bar

Spacing = 0.70m

55
𝑛𝑜. 𝑜𝑓 𝑣𝑒𝑟𝑡. 𝑏𝑎𝑟(0.255𝑚 𝑙𝑒𝑛𝑔𝑡ℎ) = ( + 1) × 2 = 159.14 ≈ 160 𝑝𝑐𝑠 𝑜𝑓 0.255𝑚 𝑙𝑒𝑛𝑔𝑡ℎ
0.7

𝑓𝑜𝑟 6𝑚 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 ∅10𝑚𝑚 𝑟𝑒𝑏𝑎𝑟

6
𝑁= = 23.53 ≈ 23 𝑝𝑐𝑠 𝑜𝑓 0.255𝑚 𝑓𝑜𝑟 𝑒𝑣𝑒𝑟𝑦 6𝑚 𝑙𝑒𝑛𝑔𝑡ℎ 𝑟𝑒𝑏𝑎𝑟
0.255

160
𝑛𝑜. 𝑜𝑓 6𝑚 𝑙𝑒𝑛𝑔𝑡ℎ ∅10 𝑚𝑚 𝑟𝑒𝑏𝑎𝑟 = = 6.96 ≈ 𝟕 𝒑𝒄𝒔
23

Main Bar

Spacing = 0.35m

55
𝑛𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟(0.35𝑚 𝑙𝑒𝑛𝑔𝑡ℎ) = ( + 1) = 158.14 ≈ 159 𝑝𝑐𝑠 𝑜𝑓 0.35𝑚 𝑙𝑒𝑛𝑔𝑡ℎ
0.35

𝑓𝑜𝑟 6𝑚 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 ∅10𝑚𝑚 𝑟𝑒𝑏𝑎𝑟

6
𝑁= = 17.14 ≈ 17 𝑝𝑐𝑠 𝑜𝑓 0.35𝑚 𝑓𝑜𝑟 𝑒𝑣𝑒𝑟𝑦 6𝑚 𝑙𝑒𝑛𝑔𝑡ℎ 𝑟𝑒𝑏𝑎𝑟
0.35

159
𝑛𝑜. 𝑜𝑓 6𝑚 𝑙𝑒𝑛𝑔𝑡ℎ ∅10 𝑚𝑚 𝑟𝑒𝑏𝑎𝑟 = = 9.35 ≈ 𝟏𝟎 𝒑𝒄𝒔
17

Temperature Bar

Spacing = 0.35m

Lap Splices = 0.50m

55
𝑛𝑜. 𝑜𝑓 𝑡𝑒𝑚𝑝. 𝑏𝑎𝑟 (6𝑚 𝑙𝑒𝑛𝑔𝑡ℎ) = × 2 = 𝟐𝟎 𝒑𝒄𝒔
5.5
𝑡𝑜𝑡𝑎𝑙 𝑛𝑜. 𝑜𝑓 ∅10𝑚𝑚 (6𝑚 𝑙𝑒𝑛𝑔𝑡ℎ) = 7 + 10 + 20 = 𝟑𝟕 𝒑𝒄𝒔.

𝐶𝑜𝑠𝑡 = 37 × 130 = 𝟒𝟖𝟏𝟎 𝒑𝒉𝒑

𝑻𝑶𝑻𝑨𝑳 𝑪𝑶𝑺𝑻 = 2200 + 17410 + 9826 + 4810 = 𝟑𝟒, 𝟐𝟒𝟔. 𝟎𝟎 𝒑𝒉𝒑