Photovoltaic power plant 50MW:

1. Engineering for 50MW power plant


2. Topographical survey
3. Geotechnical survey
4. Detailed engineering
a. General PV plant design
b. Structures engineering and design
c. Trenches design
d. Engineering for power conversion stations
e. Engineering and design for junction boxes
f. Foundations and civil design
g. Maintenance building design
h. Retention basin design
i. Design for MV delivery substation
j. Design for grid connection
5. Procurement :
a. Procurement of PV modules
b. Procurement of Steel structures
c. Procurement of cables
d. Procurement of inverters and junction boxes
e. Procurement of power conversion stations
f. Procurement for substations equipment
g. Procurement of fencing material
h. Procurement of video monitoring
6. Constructions:
a. Fence
b. Retention basin
c. Earth works/roads including : Deforestation, Ground level recovery and roads
d. Trenches (opening/closing)
e. Concrete pile supports
f. MV delivery substation
g. Maintenance building
h. Assembly and installation of PV modules
i. Cables pulling and termination
j. Installation of Power conversion stations
k. Installation of junction boxes
l. Connection between power conversion station and MV delivery substation
m. Installation of video monitoring
n. Construction of HV substation if needed/ connection to the grid
7. Testing and commissioning
8. Start up