Académique Documents
Professionnel Documents
Culture Documents
Application Form
Date
Reference
Received
Please complete the following:
Contact Information
1.1
Applicant
Warrington Borough Council
organisation name:
1.2
Applicant contact
Steve Hunter
name:
1.3
E-mail: shunter@warrington.gov.uk
1.4
Telephone No.: 01925 442 684
All bids and responses provided are required to be supported by sufficient, proportionate and
robust evidence. The below table sets out the recommended minimum level of evidence
required from applicants and which tabs must be completed as part of the bid submission in the
accompanying Business Case Summary spreadsheet, depending on the level of funding
requested from the New Stations Fund:
Small bids: NSF Qualitative discussion of TAG Essential: (1) Financial Forecasts,
Funding < £1m impacts (2) AST
Medium bids: NSF Monetising where possible Essential: (1) Financial Forecasts,
Funding £1m-5m (2) AST
Large bids: NSF WebTAG or Green Book Essential: (1) Financial Forecasts,
Funding > £5m assessment (2) AST, (3) TEE / PA / AMCB
Figure 2.1.1 sets out an extract of the Northern network map which shows the
position of Warrington West Station on the Cheshire Lines Committee (CLC)
corridor between Manchester and Liverpool city centres. The station would also
benefit from direct connections to Manchester Airport.
2.1
Proposed
station name
and location
coordinates
Figure 2.1.2, over the page, shows the local context of the proposed Warrington
West Station and its proximity to large existing and future areas of development
of both residential and commercial nature.
Figures 2.1.3 and 2.1.4 are photos illustrating the site of the proposed station.
The former shows the vacant site within Chapelford Urban Village where the
station building and car park are proposed. The latter shows the location on the
CLC where the station platforms, lifts and stair access are envisaged.
Chapelford Urban Village is a former US air force base where, since the late
1990’s, development of over 2000 homes has taken place. Already the village
benefits from a vibrant local centre, a Sainsbury’s supermarket, primary school
and local pub/restaurant - as well as a soon-to-be constructed health centre, all
of which is within easy walking distance of the proposed station site..
When complete, the full development will comprise of around 2200 homes.
The overall aim of the scheme is to provide an effective and attractive gateway
into West Warrington which allows easy access and integration with a range of
modes of travel. The station facility should reflect the predicted level of
passenger demand and the local setting within an established residential area
with further significant planned residential and employment growth in the local
catchment.
• Secure cycle parking for 50 cycles with provision for easy expansion;
• Taxi rank;
• Service vehicle area for Train Operating Company / Network Rail use.
Platforms
The platforms will be located to the east of Skelton’s Bridge. The boarding
length of the new platforms will be approximately 156m, allowing for standard
24m length, six-car trains, with an overrun distance of 12m and a standard
platform width of 3m. Access will be to the rear of the platform. If, in the future,
there was a requirement to allow eight-car trains to stop at Warrington West,
there would be no constraint to extending the platform in the Warrington
direction. This may result in the platform being closer to the track curve but this
should not present any significant difficulties.
The platform will be located at the base of the cutting and, as such, there will be
a need to have retaining structures running the length of the westbound
platform. It has been assumed that these retaining walls will consist of smooth,
non-porous facing bricks with an anti-vandal finish to enable easy maintenance.
For the eastbound platform, an engineered battered slope will be utilised,
removing the need for more expensive retaining structures.
It is intended that high quality shelters will be used and positioned at the centre
of each platform. Lighting on the platforms will be designed to promote a sense
of personal safety for users. Each platform will be equipped with a help point,
as well as access to rail timetables and passenger information.
The CCTV system would also extend to the platforms and would be designed to
ensure that the privacy of neighbouring residential properties is not encroached
upon. It is intended that each platform will have the facility to be locked at night
and that lifts would be secured down to the platforms outside of train operating
areas.
It is proposed that the platform will be accessed via a combination of stairs and
lifts. The stairs will be in compliance with all relevant standards and guidance.
Following consideration of the physical constraints in this location, lifts are
deemed to be a more practical means of access to the platform level than ramps
since the extent of level difference between Skelton’s Bridge and the platforms
would require ramp lengths in excess of 130m. This length of ramp is
considered to be impractical from the perspective of an unassisted user and, as
such, lifts provide a more practical option.
The lifts will be of a standard Network Rail specification and will comply with the
DfT’s Train and Station Services for Disabled Passengers Code. WBC has
indicated their preference for the addition of a glass viewing port or glass doors
to allow an increased level of security for lift users. The lift will operate in a
through and through method and will be contained within its own lift shaft.
The focus of the design concept for the station is that cyclists and pedestrians
have priority and dedicated rights of way. This principle complements the
‘Greenways’ concept that has been adopted by WBC and features in the
Masterplan for the Urban Village and wider area. The extent of the well-
developed pedestrian and cycle network in west Warrington is shown Figure
3.15.1.
Pedestrians accessing and using the station will have priority over all other
forms of transport within the station site. The detailed design will provide for
quality signage and lighting throughout the area to give safe, informed and
secure routes to the station as well as providing linkages into the wider
communities both north and south of the railway. Facilities will be provided for
cyclists, including cycle lockers and covered cycle shelters which will be in close
proximity to the station building entrance and within the area covered by CCTV.
In developing the scheme towards a detailed design, we would look to
undertake further consultation with, local cycling groups, Northern Rail (the
proposed Station Facility Operator) and also Cheshire Constabulary.
Car Parking
A 268 space car park is provided immediately adjacent to the Chapelford Urban
Village development immediately to the north-east of the station building. This
facility would include14 disabled spaces to accord with national guidance which
would be located next to the building. It is assumed that internal circulation
within the car park will be bidirectional and that the area will be provided with
high quality CCTV coverage and lighting. A parking charge of circa £1 per day is
proposed in order to encourage access to the station by sustainable modes and
to cover the ongoing maintenance and renewal costs of the car park.
A taxi rank and drop-off / pick-up facility will be included within the scheme for
private cars as well as stands for Hackney Carriages. The design has been
developed in order to prevent conflict between direct pedestrian desire-lines and
vehicular movements, whilst still providing drop-off facilities in close proximity to
the station building and the platforms. Appropriate Traffic Regulation Orders
and signage will be required to prevent unwanted fly parking and overly-long
waiting.
Bus Facilities
The station will be served by three bus stops with adjacent layover space
positioned outside of the station building to give flexibility to support commercial
services, shuttle buses to Lingley Mere and Omega employment sites and to
cater for Rail Replacement services when required. These stops will mainly
serve the large catchments to the west and north of the station.
It is currently proposed that all stops will meet or exceed the Council’s current
standards with raised boarding, quality shelters, Real Time Information and
static printed timetables.
Station Building
Over the last 3 months the proposed station building has undergone a value
engineering exercise to both reduce costs and to ensure that the preferred
scheme represents best value. To this end, in consultation with the proposed
station operator (Northern) the size of the building has been reduced
significantly. The location has also been adjusted to miss an underground utility
which would otherwise require costly relocation.
Subsequently the main station public area will now be an open flexible space
with TVMs and makes full use of video wall technology now in use at a number
of Northern’s other stations. As well as the open public space, the building will
house the communications and plant rooms, staff welfare and rest areas as well
as staff and public toilet facilities. The station building can, if required, support a
small area for a retail concession in the future.
Figure 2.2.1 below shows the general arrangement drawing for the building
which will be subject to further iteration during the detailed design process in
consultation with the operator.
Prior to commencement of the work on the existing cables the Project Team will
assess the condition of all the cables, the cable lengths and cable joint
positions. Where necessary Balfour Beatty will replace the affected cables to
allow sufficient spare cable length to ensure the first slew onto the sleeper ends
can be completed, followed by a subsequent slew into the new trough route or
the new platform duct route.
Cess Drainage
2.3 The condition of the existing cess drainage will be assessed prior to the
commencement of any work to confirm its suitability and condition for
Rail
incorporation into the permanent works. The current drainage proposal is to
infrastructure
relocate the drain run under the station platform structure. The new drainage
system will be accessed from the station platform via a network of covered
manholes. The existing cess drainage will be connected into the new drainage
alignment via carrier pipes along the full lengths of the station platform. Once
clear of the platform the new drainage alignment will terminate back into the
cess drainage or outfall.
The Automatic Warning System and indicator positions which are currently
installed on the track will be relocated to make allowance for the new station
platform location and the associated operational warning systems that the train
operates. These positions are to be confirmed, relocated and re-commissioned
under signal notice and possession working.
The track is to be realigned to allow for the new platform location and coping
edge and also to remove the track curvature approach into the platforms and the
station.
The new station platforms will be installed with a safe passenger train release
from the platform. This signal must be installed for the safe operation of the train
to leave the station.
Figure 2.3.1:
Controlled excavation
works protected by a
Vortok safety barrier
under ALWS
Figure 1.3.2:
Figure 2.3.3:
Outline the proposed service timetable and stopping patterns at the station
It is proposed that there will be three trains an hour (all provided by Northern
Rail) to call at Warrington West in each direction during normal operating hours.
In addition, two stopping services are to call at Warrington West. These currently
operate between Liverpool Lime Street and Manchester Oxford Road, but are
2.5 likely to be extended through to Buxton/New Mills Newtown once the Northern
Hub infrastructure enhancements in the Castlefield corridor have been
implemented (due to removal of the bay platform at Manchester Oxford Road).
Timetable
Whilst these services operate as skip stop services along the CLC (for
and stopping
operational reasons), direct services from Warrington West to all stations along
patterns
the CLC route will be offered through a combination of the two stopping services.
One of these stopping services currently calls at Sankey for Penketh station.
Once the new station is opened, this call will transfer to Warrington West.
Sankey for Penketh station will remain open but will only be served by one
service in the peak hour in each direction (i.e. four trains per day in total).
The Northern Rail Franchise Agreement has now been signed and formally
adopted for the Northern franchise. Rail North has confirmed that “Warrington
West is in the formal Train Service Requirement (TSR) which can be found at
https://www.gov.uk/government/publications/northern-rail-2016-rail-franchise-
agreement. We would expect Northern to comply with their obligations under the
franchise agreement” (Rail North email 7 October 2016).
High level capacity analysis has been undertaken based on MOIRA data. This
analysed demand across two screen lines at Hunts Cross/Halewood and
Deansgate/Trafford Park on the CLC, reflecting flows from the corridor into
Liverpool and Manchester respectively. MOIRA was run with current and post
2019 service patterns (TPE via Chat Moss, new Northern Connect service to
Manchester Airport via Warrington Central) to reflect the future demand patterns
on the route.
2.6
More detail regarding this analysis is contained in the report “Warrington West
Station: Second Update of Scheme Business Case” (AECOM, Nov 2016),
Passenger contained in Appendix C.
capacity
In summary, the introduction of the new timetable on the CLC and Chat Moss
routes between Liverpool and Manchester (planned for December 2017) will see
a reduction in demand crossing the CLC screenlines, as defined above, of circa
20% to 25%. In addition, Northern Rail’s planned rolling stock for the CLC
services will result in a 25% increase in seats across the screenlines in the peak
hour (17% increase in total capacity). A combination of these two impacts, and
accounting for demand growth, leads to the conclusion that the additional
demand generated by Warrington West can be expected to be catered for by the
planned levels of capacity across Northern Rail’s CLC services.
OR;
if subsidy is required, demonstrate how subsidy will be met for the first three
years
2.8 Also, it is not envisaged that the opening of Warrington West itself will trigger
the requirement for any additional rolling stock on the CLC services. This has
been explained in our response to Question 2.6.
Rolling stock
requirements There is a wider rolling stock commitment as part of the new Northern Rail
Franchise Agreement that will see all rolling stock operating on the CLC route
being either brand new or fully refurbished by 2019/20. This will also bring
capacity benefits to these services.
Outline and provide evidence of the impact of the proposed station on other
services and how these impacts will be minimised
2.9 - Changes in train loadings on both CLC and Chat Moss services
The actual demand impact of the increase in journey time for through passengers
has been included in the demand forecasting and business case analysis.
Further details are contained in the report “Warrington West Station: Second
Update of Scheme Business Case” (AECOM, Nov 2016), contained as
Appendix C.
- Additional calls on the semi-fast services would be low risk. The trains
concerned will no longer be operating Trans-Pennine to and from
Scarborough, and during 2018 brand new high performance DMU rolling
stock will be deployed; and
WBC will continue to work with rail industry partners via the railway industry
processes to confirm and finalise the timetable in preparation for the opening of
Warrington West.
Current Network rail GRIP Stage status of the proposed station. Provide
evidence of the development work completed. Provide evidence of progress
made to take the project through further GRIP stages if applicable
The current Warrington West scheme has been progressed over a number of
years and through a series of iterations which have all included extensive
liaison with Network Rail, in particular their Project Engineers and Route Asset
2.10 Managers. The project is currently working through a reiteration of GRIP
Stage 3 and will achieve Stage Gate review in January 2017. However, it
GRIP Stage should be noted that a number of the core disciplines have already attained
AIP status and have been signed off by the DPE as such. Specifically P-Way,
Signalling and Drainage AIPs have all been accepted. A record of this approval
is included at Appendix D).
All other disciplines have progressed through the Option Selection phase of
GRIP 3 and have completed draft AIPs which have been submitted and
discussed with all RAM teams. Furthermore, the proposed scheme adopts an
ownership model wherein only the platforms, lifts, stairs and footbridge are
transferred to Network Rail ownership. The Station Building and Car-Park will
be owned by Warrington Borough Council and as such will not be subject to
the review processes included within GRIP.
The Strategic Case should set out a clear rationale for the scheme, supporting the need
for investment. You should consider the objectives of the new or re-opening station are
and why a new or re-opening station is considered the best way of meeting local transport
objectives and addressing transport issues in the area.
Set out the strategic case for the project, citing policies and strategies of the promoting
organisation and third parties. The case should be clearly made as to why a new or-re-
opened station is the best way to achieve the policy objectives stated.
Outline and explain the transport issues and challenges faced in the area
Public transport accessibility analysis has been undertaken for key destinations
using TRACC software, which is a multi-modal transport accessibility tool. The
plots display journey times by public transport, (including walking time), in 10
minute isochrones bands up to 60 minutes. These have been produced for
journeys originating from the west of Warrington.
Current Figure 3.1.1 shows the current level of public transport accessibility from the
transport west of Warrington with one train per hour in the AM Peak – this can be
issues and contrasted with the public transport accessibility with three trains per hour
challenges (including one semi-fast service) from the new station (Figure 3.1.2).
It is notable that journey times (including walk and wait time) to Manchester
City Centre reduce from 40-60 minutes to 30-40 minutes with the scheme in
place.
The journey time to Liverpool City Centre also reduces to 30-40 minutes
compared to 40-50 minutes at present. This demonstrates the benefits of the
enhanced service frequency from the station, in addition to the introduction of a
semi-fast service.
Figure 3.1.2: Accessibility from the west of Warrington by public transport (AM
Peak 07:00 – 09:00) – (3 trains per hour, including 1 semi-fast)
In 2011 39% of all trips for journeys to work were made by car to Liverpool City
Centre, journeys to work from the study areas was nearly double with 73%
using private car. This pattern was repeated with journeys to work from the
study area to Manchester City, with 52% using a car compared to 39% for all
trips to Manchester City Centre. This highlights that on average journeys to
work made from the study area are higher than all trips to either Liverpool or
Manchester. A new railway station at Warrington West would provide an
alternative mode to travel for journeys to work rather than by private car.
Figure 3.1.3 over the page highlights the prominence of Birchwood Business
Park in the east, Warrington Town Centre in the central region, and Lingley
Mere, Omega, and Gemini employment sites in the west of Warrington
Borough as key destinations for employment. Warrington Bank Quay,
Warrington Central and Birchwood railway stations are well used, providing
suitable public transport access to the key employment destinations in the west
and central region of the borough. However with regard to the west, over 80%
of those travelling to Lingley Mere, Omega and Gemini employment
opportunities travelled by car (2011 Census). This statistic, combined with
annual station entries and exits at Sankey-for-Penketh railway station of only
134,156 in 2014-15 points to a clear need to enhance public transport
accessibility in the west for major employment sites.
Rail use across the country is growing and Warrington is no exception. There
are six rail stations in Warrington Borough including Birchwood, Glazebrook,
Padgate, Sankey-for-Penketh, Warrington Bank Quay and Warrington Central.
In the last 5 years, total passenger entries and exits at Warrington’s six rail
stations has increased by 27% (824,489 entries and exits).
Long term forecasts for rail usage show demand continuing to increase at
a similar rate as seen in Table 3.1.2 below, spurred on by investment in
infrastructure including electrification schemes, new stations, the Northern
Hub, and High Speed 2. Against this background, the provision of rail
services cannot stand still and this highlights the need for additional
capacity in rolling stock, and also in improved accessibility to the rail
network – including new rail stations.
Current patronage trends highlight Birchwood is a well-used asset for the east
of the borough (686,668 entries and exits); while Sankey-for-Penketh, Padgate
and Glazebrook, attract from only a small catchment area due to limited nearby
parking opportunities. There are currently (Sankey-for-Penketh stations) up to
200 boarders per day on average (134,156 entries and exits in 2014-15), of
which the majority are regular commuters/education trips in the Liverpool
direction.
% increase
2010- 2011- 2012- 2013- 2014-
Station 2010-11 to
11 12 13 14 15
2014-15
Birchwood 527 555 550 583 687 30%
Glazebrook 47 48 50 55 49 4%
Padgate 80 92 94 107 128 59%
Sankey-for-
100 120 112 118 134
Penketh 34%
Warrington
879 895 923 1,012 1,081
Bank Quay 23%
Warrington
1,406 1,568 1,593 1,662 1,785
Central 27%
Warrington
Borough
Council 3,039 3,278 3,322 3,537 3,864 27%
(WBC)
Total
The analysis highlights traffic congestion and its effect on journey reliability is
an issue for Warrington town centre. Observed average speeds in the vicinity
of Bridgefoot roundabout and Brian Bevan Island are below 10mph indicating
these locations as clear pinch points on the network. This is influenced by a
lack of vehicular route choices through the town centre.
The impact of high traffic levels on access is a key driver for pursuing the
delivery of a new railway station at Warrington West. Population growth
experienced between 2001 and 2011 combined with projections to 2021 and
beyond, as well as the high percentage of work related trips undertaken by car
in Warrington, points to the need for more sustainable travel options.
Air Quality
Figure 3.1.6 and Figure 3.1.7 highlight the levels of nitrogen oxide and nitrogen
dioxide within the surrounding area of the proposed new rail station measured
by micrograms per cubic metre as defined by DEFRA. Levels of both NO2 and
NO are high along link roads into Warrington Town Centre and these routes
have been identified to form part of the proposed Warrington Town Centre
AQMA. The Local Plan Core Strategy details an objective of improvements to
air quality throughout the borough. The reduction in congestion, as a result of
realistic alternatives to using the private car, is one area where air quality
impacts should be sought.
Figure 3.1.6: Air Quality Nitrogen Oxide (NO) near Warrington West
For the purposes of the Strategic Case and defining the target population, a
study area was defined using Lower Super Output Areas (LSOA) (Figure
3.2.1). This application takes account of LSOAs which fall within a 1km buffer
of the new Warrington West railway station to present data against Warrington,
Cheshire and Warrington LEP and England averages 1.
3.2
Target
population
The population in the defined study area, surrounding the proposed station,
increased by 14% between 2001 and 2011. This is higher than the Warrington,
Cheshire and Warrington LEP and England averages over the same period
(Table 3.2.1). Population increase between 2001 and 2011 is represented
geographically for Warrington in Figure 3.2.2 below.
Population
Area
2001 2011 Change Change (%)
1
A separate catchment area has been defined for modelling and appraisal purposes
Figure 3.2.3 highlights a 2011 population density of 50-75 persons per hectare
surrounding the proposed Warrington West Station. Since 2011, there has been
additional growth in housing at Chapelford Urban Village which is not currently
reflected in the density presented. Critically, even without this additional growth,
the population density observed in proximity to the proposed railway station site
is greater than the surrounding area.
Figure 3.2.3: 2011 Population Density (persons per hectare) (by LSOA)
Figure 3.2.4 highlights that the town centre, Birchwood and Warrington West
are key employment destinations in Warrington. The Warrington West target
population is considered the third largest destination in terms of employees with
in excess of 11,000 jobs.
This figure does not include the recent development on Omega North and South
in the last 2 years, which with the opening of major manufacturing and
distribution units has created in excess of 3,000 jobs
According to the Centre for Cities, Cities Outlook 2015 paper, Warrington was
ranked within the top 10 cities for business growth in the United Kingdom
between 2004 and 2013 (increase of 1,575 businesses; 29.2% change).
Investment in a new railway station will enhance connectivity to existing
employment opportunities for the target employment population in the west at
Omega, Gemini and Lingley Mere, further strengthening business growth and
providing the platform for WBC and Cheshire and Warrington LEP to achieve
their growth aspirations.
Transport has a significant role in both the creation and alleviation of social
problems, helping to shape society, determining where people work, shop,
study and partake in leisure and social activities. At local authority level,
Warrington ranks 147th out of 326 local authorities on the rank of ‘Average
LSOA score’.
2
Warrington Joint Strategic Needs Assessment (JSNA) December 2015
The consulation highlighted that 21% of respondents would use the proposed
station three to five times a week. Leisure and work purposes were reported as
the highest uses for the proposed station. Figure 3.2.7 illustrates that walking
was the most popular mode to travel to and from the station, with 80 responses
and with cycling receiving 23 responses. Access to the stations by these
sustainable modes would help to reduce congestion in the area.
Figure 3.2.7: Expected access mode of travel to and from Warrington West
from local catchment area (1-2km from station)
Objective 1
Support sustainable economic development across the west of
Warrington
Sub-objective 1.1
Facilitate sustainable take up of residential development sites in the west of
Warrington.
Sub-objective 1.2
Facilitate sustainable take up of commercial development / job growth at
surrounding employment locations including Omega, Lingley Mere and
Gemini.
Objective 2
Improve accessibility / quality of public transport to/from the west of
Warrington
Sub-objective 2.1
Provide an integrated, high quality and secure gateway from the rail network
to residential and employment opportunities in the west of Warrington.
Sub-objective 2.2
Enhance accessibility from the west of Warrington to employment
opportunities in Liverpool City Centre, Manchester City Centre and
Warrington Town Centre.
Objective 3
Support improvements to quality of life factors in the west of Warrington
Sub-objective 3.1
Contribute towards limiting future traffic growth and congestion levels on the
local and Strategic Road Network in the west of Warrington.
Sub-objective 3.2
Contribute towards mitigating air quality issues that result from transport
related emissions in the west of Warrington.
Sub-objective 3.3
To encourage a shift to sustainable travel modes, including the promotion of
active travel for residents in the west of Warrington.
As demonstrated in section 3.1, car mode share from the study area to
Liverpool City Centre and Manchester City Centre is significantly higher than the
overall mode share to these centres. Analysis shows that generalised journey
times (includes access, wait in addition to in-vehicle time) from Chapelford to
Liverpool and Manchester City Centres are forecast to reduce by 39% and 37%
respectively following the opening of the new station (with 3 trains per hour).
The enhanced service frequency, location of the station and high quality station
facilities will combine to deliver mode shift to public transport. As demonstrated
in Figure 3.15.1, the proposed site also has high quality walking and cycling
linkages, which will encourage passengers to access the station by sustainable
modes.
The scheme will therefore have benefits in terms of mitigating traffic growth,
congestion on the Strategic Road Network, including the M62 between
Liverpool, Warrington and Manchester. There will also be benefits in terms of
air quality and reduced carbon emissions as the scheme is forecast to reduce
car vehicle km on the road network by 4,231,000km per annum (by 2020).
From Northern Rail’s perspective, the new station will provide the opportunity to
introduce state-of-the-art station operations (e.g.: smart-wall technology, and
roving staff with hand-held devices) and the opportunity to introduce more
efficient operating practices (e.g.: removal of booking office infrastructure). The
incorporation of these standards will allow Northern Rail to designate the station
a ‘Northern Connect’ station in line with their intended premium service
branding.
Existing rail users currently using other neighbouring stations will use
Warrington West instead. In particular some demand (circa 4%) will be diverted
from Warrington Central to Warrington West, thus providing some relief at this
station. Warrington Central is a relatively constrained station site with a large
usage (1.78m journeys in 2014/15) and so any initiative to spread the rail usage
away from this station could be seen to be a benefit.
There will be smaller levels of transfer of rail journeys away from some of the
stations on the Chat Moss route (Earlstown, St Helens Jct, etc), leading to a
small reduction in train loadings on that corridor – which could be seen as a
minor benefit at times of peak loadings.
3.5
Demonstrate how the new station would link to economic growth aspirations
and help to stimulate economic activity
Economic
growth Cheshire and Warrington Matters
The Strategic Economic Plan sets outs the following growth targets:
B2 1,600sqm
B8 13,000sqm
The Northern Route Utilisation Strategy (RUS) seeks to balance supply and
demand and set out Network Rail’s longer term vision for improvements across
the network.
The Strategy forecasts significantly increased growth in rail usage over the
next ten to twenty years. Passenger growth into the cities of Leeds, Liverpool,
Manchester, Newcastle and Sheffield by 2024 could be as much as between
41 and 52 per cent, increasing to between 56 and 66 per cent in 2029.
The Regional Urban Market Study is one of four Market Studies published by
Network Rail as a key element of the new ‘Long Term Planning Process’
(LTPP). Three of these studies consider different passenger markets whilst the
remainder considers freight.
The strategic goals are split by the overall goals for transport (in bold) and the
subsequent goals for Regional Urban rail:
The strategic goals identified within the Regional Urban Market Study are
closely aligned with the scheme objectives for the new railway station,
with a focus on economic growth influenced by accessibility to
employment, as well as quality of life considerations such as reducing
congestion and reducing the environmental impact of the railway.
The Market Study provides the first step towards the North of England
Route Study, which will set out Network Rail’s vision for rail services
across the north with a time horizon through to 2043. The Market Study
sets the objectives and conditional outputs and a review of forecast
exogenous demand growth under varying economic and social
conditions. The North of England Route Study process is expected to
start during 2017.
Rail is uniquely positioned to deliver these aims and features prominently with
high profile projects such as HS2 and Northern Powerhouse Rail
accompanying nearer term improvements in connectivity and service quality. In
combination with the accompanying National Productivity Investment Fund this
represents the largest investment in the railways since Victorian times,
underlying the Government’s confidence in the rail sector to deliver significant
transport improvements in our region.
Warrington West supports this policy landscape by delivering a high quality rail
asset strategically located to meet burgeoning travel demand currently served
by a capacity constrained highway network.
In 2012, the Government published the NPPF which sets out the Government’s
planning policies for England and how they are expected to be applied. The
NPPF identifies three mutually dependent dimensions to achieving sustainable
development including the economy, environment and society. In this context,
the NPPF outlines a focus on building a strong and competitive economy, and
acknowledges the role of transport in facilitating development and contributing
to wider economic growth, sustainability and health objectives. Additionally,
the NPPF has a focus on the support of sustainable travel, enabling a
reduction in congestion.
The plan has as its first objective “driving up housing supply” with an ambition
to “deliver one million new homes over the next five years”.
DCLG has interests in a number of sites around Warrington for which the
proposed station will improve accessibility.
In March 2015, the Transport for the North (TfN) Partnership Board, unveiled
their vision for the North with a report on the Northern Transport Strategy. This
is a joint publication from Government, Northern City Regions and Local
Enterprise Partnerships, working together with Highways England, Network
Rail and HS2 setting out the ambitions for TfN.
The aim is to establish the North as a global powerhouse and address the
economic imbalance between the North and the South East. The vision for the
North is for a vibrant and growing economy, a magnet for inward investment,
which capitalises on the strengths of the Northern cities, supported by state-of-
the-art transport connections to clusters of thriving businesses.
The report emphasises local connectivity and the need for high quality
local transport to enable businesses to link to each other and people to
get to work, education and leisure opportunities. A new Warrington West
station will directly contribute towards this objective, enhancing local
transport connectivity to businesses in the west of Warrington.
The NPIER identified the key economic sectors that could drive growth and
development across the North, and the strategic fit of transportation as an
economic catalyst. The Review identified the opportunities where pan-Northern
key sectors and collaboration can support local activities. The Review aimed to
understand the scale, form and causes of the North’s economic and social
gaps, as well as the four prime capabilities alongside three enabling
capabilities.
The Review identified the ‘business as usual’ scenario would mean that the
gap between the North’s economy and the rest of England would continue to
widen. At present the North’s GVA per capita is averaging about 25% against
the rest of England, and almost 15% when London is removed. Furthermore,
this gap has widened since the 2008/09 recession. Six main factors driving the
productivity gap were identified and these included sub-optimal transport links
and underinvestment in transport, lower levels of investment and lack of
agglomeration.
The Cheshire and Warrington Local Area profile noted enabling sectors,
such as transport and logistics, are important to the economy particularly
with the significant investments in developments in the region, for
example, at Port Warrington and Omega at Warrington. The Review
describes the strong commuting flows to neighbouring areas, particularly
Greater Manchester.
Table 1.8.1: Alignment of the scheme with the Strategic Economic Plan
Strategic Imperatives
Atlantic Gateway
This new station will support the objectives of the Atlantic Gateway by
unlocking the full investment potential of the Warrington West area and
supporting a wider programme of projects which together support
business locations of international importance and scale – reinforcing
Warrington as a nationally important hub for energy, engineering,
software and telecoms and logistics.
Warrington Means Business
The regeneration framework, originally published in 2013 and due for review in
December this year, sets out WBC and Warrington and Co.’s programme and
intent to drive, progress, encourage and facilitate future economic growth for
Warrington, reinforcing the area as a strong national driver of prosperity. The
Warrington North Sustainable Transport Package included in ‘Warrington
Means Business’ calls for the provision of a new Warrington West railway
station at Chapelford and a bus link to serve Omega.
Warrington Council Strategy 2015-2018
The Strategy, ‘Growing a Strong Warrington’ outlines the Council’s vision to
2018. Council intend to work with residents, businesses and partners to make
Warrington a place where everyone can thrive, whilst dealing with the major
challenge of reductions in funding and increased demand for services. The
strategy outlines the need to lever investment into the borough as a priority to
promote the area as a place to do business. The strategy seeks to use capital
investment to encourage additional investment and infrastructure improvement
works to stimulate further economic growth. Investment in the form of a new
railway station at Warrington West will support the ongoing sustainable
development of new housing at Chapelford Urban Village and employment
opportunities at Omega, Lingley Mere and Gemini.
Warrington Local Core Plan
The Council’s vision for West Warrington identifies the area to be a strategic
place for employment (i.e. Gemini, Lingley Mere, and Omega) built on the
foundation of good design and sustainability with excellent transport links. The
Local Core Plan considers the railway station to be a key part of the public
transport network helping to provide travel links to employment opportunities in
the town centre and wider area.
The following policies of the Local Plan Core Strategy are considered to be of
relevance to the scheme: Policy CS4 – Transport; Policy MP1 – General
Transport; Policy MP4 – Public Transport; Policy MP6 – Transport
Infrastructure; Policy WW1 – Chapelford Urban Village; and Policy QE1 –
Environment and Environment Protection. Making the Place Work: Policy MP6
– Transport Infrastructure, states that the Council will safeguard land for the
provision of a new railway station at Chapelford Urban Village and identify
opportunities for park and ride. The new station is illustrated within the Local
Plan map provided below.
The LTP3 complements the Local Plan, setting out a strategic framework to
guide future provision of transport services for Warrington between 2011 and
2030. The delivery of the railway station lies at the heart of the transport
strategy for Warrington West, ensuring public transport access to and from
emerging employment and residential areas is attractive as it can be, thereby
providing the potential to significantly reduce the level of traffic congestion.
Table 3.8.2 demonstrates how the scheme meets the LTP transport objectives:
Improves everyone’s access The scheme will provide enhanced public transport
to health, employment, accessibility toward Liverpool, Warrington, Manchester, and
education, culture, leisure beyond via a new station on the CLC line.
and the natural environment
Improves everyone’s access The scheme will offer immediate advantages in providing
to the town centre by all improved access to Warrington Town Centre, and other
modes of travel destinations along the CLC and further afield (including
Leeds, York, Nottingham and Norwich). The new station
will connect with bus services to key employment sites.
Improves safety and security A new railway station will be designed to enhance safety
for all modes of travel and security for public transport.
Enhances the image and The scheme will support increased prosperity and profile
profile of the place of the area on a national stage. This can only be beneficial
to the local communities within West Warrington. It will
enhance the profile of Warrington as a place to do
business.
Improves the quality of A new railway station will include public realm
public space making improvements creating a gateway to the local Warrington
Warrington more welcoming West community.
Reduces the impact of traffic The scheme will promote increased public transport use
on air quality in Warrington which will contribute toward a reduction in traffic congestion
and helps to reduce carbon (key factor for air quality/carbon emission metrics). The
emissions and tackle climate station will include park and ride facilities, allowing users
change from outside walking distance with the opportunity to travel
and substantially increasing the catchment of people able to
access the rail network.
Integrates with transport A new railway station on the CLC will further integrate
networks outside Warrington Warrington West with transport networks outside
to enhance sustainability of Warrington and enhance sustainable cross boundary travel.
cross boundary travel
The Secretary of State provided the Franchisee with three key objectives in
the new Northern Franchise Agreement:
- To improve the efficiency
- To reduce the cost; and
- To enhance the revenue and earning potential of the delivery of
services to passengers.
Network Rail
The Strategic Business Plan for England and Wales identifies Northern Hub
as an opportunity to support economic growth in the North of England
through enhancing the network between Manchester and Liverpool.
Warrington Borough Council will work collaboratively with Network Rail and
their partners to ensure their key projects identified in the CP5 (2014-2019)
and overarching objectives for the rail network are achieved.
Merseytravel
Objective 3
Support improvements to quality of life factors in the west of
Warrington
Sub-objective 3.1
Contribute towards limiting future traffic growth and congestion levels on
the local and Strategic Road Network in the west of Warrington.
Sub-objective 3.2
Contribute towards mitigating air quality issues that result from transport
related emissions in the west of Warrington.
Sub-objective 3.3
To encourage a shift to sustainable travel modes, including the promotion
of active travel for residents in the west of Warrington.
Governance and Funding: Internal WBC funding for the scheme is limited.
In addition to this application for New Station Fund finance, the scheme
funding includes contributions from WBC, LEP/Government and the private
sector. Receipt of New Station Fund financial support is required to bridge
the funding gap and commence delivery of the scheme.
Contaminated Land: The sites previous use as an air base means that
there could be areas of contaminated land that will require removal and
remediation. Furthermore, material has been stored on the site during the
ongoing construction of the Chapelford Urban Village. Due to the proximity
of this land to the active diesel railway there is the possibility that it is also
Drainage: The site includes poor drainage in many areas which may be
related to the infilling of balancing ponds. Drainage schemes for the
disposal of surface waters for the entire site will need to be submitted to
Council by the contractor prior to commencing on site.
Traffic Generation and Access: The scheme includes a new car park
which will result in increased vehicular movements in the vicinity of the
station. The approved planning permit ensures that the new access roads
have the capacity to accommodate the increased traffic relating to the
station as well as movements associated with Chapelford Urban Village.
Station Calls: Securing the station calls has been a key risk for the
development of the scheme, which has culminated in their securement via
the Franchise Agreement. The Northern Rail Franchise Agreement has
now been signed and formally adopted for the Northern franchise. Rail
North has confirmed that “Warrington West is in the formal Train Service
Requirement (TSR) which can be found at
‘https://www.gov.uk/government/publications/northern-rail-2016-rail-
franchise-agreement’. We would expect Northern to comply with their
obligations under the franchise agreement” (Rail North email 7 October
2016). WBC will continue to work with rail industry partners via the railway
industry processes to finalise the timetable in preparation for the opening of
Warrington West.
The option appraisal initially assessed various public transport options, and
concluded that a heavy rail option was the most appropriate.
A long list of service options was then developed and circulated to the
stakeholders for comment. This included various timetable permutations.
The options considered included assessment of interventions at the existing
Sankey-for-Penketh station and/or a new station west of Warrington. Based
on the above, a short list of options was identified for consideration.
Four scenarios for Sankey station were discussed through consultation with
stakeholders; full closure, downgrading, no change and enhancement. It
was concluded that each of these scenarios would need to be
accommodated and assessed through to GRIP Stage 3. The latter of these
options – enhancement to Sankey-for-Penketh railway station – was taken
forward to the short list for further assessment.
Two workshops were held in September 2016 to test ideas with WBC
stakeholders, design team, Network Rail and the TOC. This work led to the
development of 2 additional costed options (in addition to the consented
planning design option). The second workshop was used to review the 3
new station options using an agreed RAG list. Programme
options/possession strategy/acceptability to planning was also reviewed as
part of this process.
Based on the above, four options were considered in the short list for
assessment. Table 3.12.1 summarise the three alternative options
subsequently discounted through the option assessment process; Option 3
(which is the preferred option) has already been discussed in our responses
to Questions 2.1 and 2.2.
- Option 2 has 60 less car parking spaces. The reduced car parking in
Option 2 impacts the Business Case and may lead to anti-social
parking in the residential areas; and
Scheme Objectives
A standalone qualitative assessment of the performance of the scheme
shortlisted options was also undertaken against the identified scheme
objectives. Table 3.12.2 summarises the performance of each route
(including the preferred option 3) using a 4 point scale with three ticks
representing strong alignment against an objective and no ticks representing
no alignment with an objective.
The assessment highlighted a strong alignment between Options 1 and 3 and
the scheme objectives. The location, function and facilities provided were
identified to deliver a gateway that supports existing and proposed residential
and employment in western Warrington. These two options were also
considered to promote the greatest potential to deliver modal shift toward rail
from the car supporting quality of life (objective 3). Conversely, Option 4
(upgrade to Sankey) did not demonstrate the same strategic alignment as the
constrained site is unlikely to facilitate sustainable residential and commercial
development at Chapelford and employment sites to the north. Option 2 did
not demonstrate the same strategic alignment as Option 1 and 3 owing to the
reduced function of the station without a building or staffing, and inability to
operate as a Northern Connect station.
Scheme Option 3
Option 1 Option 2 Option 4
Objectives (Preferred)
Objective 1 -
Objective 3
Chapelford Urban Village will be the predominant trip generator but the
employment sites will also be a major trip attractor. A station that meets the
long term transport needs of all these sites is required. Its role within the
emerging transport strategy for the area will need to fully integrate with other
modes to enable the station to realise its fullest potential. It is important to
note that the station site is already highly accessible by all modes of transport
with excellent walking/cycling links, a range of bus services already in place
which will directly serve the site and with excellent connections by road to the
planned large station car park, which will encourage park and ride use of the
station.
Without the scheme it is likely a high proportion of those journeys into
Warrington town centre and beyond to Manchester and Liverpool will be
undertaken by car, impacting on congestion and environmental issues.
The letter highlights the following reasons as to why that particular application
was unsuccessful at that time:
- Not all third party funding had been confirmed. As set out in our
response to Question 4.4, funding to just over £13m has now been
confirmed.
3.15
Demonstrate how the scheme will encourage the use of sustainable transport
modes (cycles, buses, electric vehicles etc.) by passengers when travelling to
Sustainable the station
transport
Pedestrian and Cycle Routes
The focus of the design concept for the station is that cyclists and pedestrians
have priority and dedicated rights of way. This principle complements the
‘Greenways’ concept that is currently being adopted by WBC and features in
the Masterplan for the Urban Village.
Pedestrians accessing and using the station will have priority over all other
forms of transport within the station site. The detailed design will provide for
quality signage and lighting throughout the area to give safe, informed and
secure routes to the station as well as providing linkages into the wider
communities both north and south of the railway.
In order to minimise the risk associated with damage to the existing rail
infrastructure, before any works proceed within the NR boundary, remedial
activities will be completed to replace and slew the existing Signalling and
Telecommunications cables currently visible on site away from the Cess and
on to the track sleeper ends. Using planned line-blocks, new Signalling and
Telecommunications cables will be laid, tested and placed into a split duct
along the length of the effected work area to confirmed cable joints or
agreed jointing positions. Under signal notice the Signalling and
Telecommunications cables will be tested, cut, jointed, tested and re-
commissioned returning the line back into full use prior to line re-opening.
Once the cables have been laid onto the sleeper ends, 1.25m (from running
rail) Vortok safety barrier will be installed on both sides of the track along the
entire length of the agreed worksite. Permanent Way safety access gates
(positions of safety) will be installed every 40m along the Vortok safety
barrier, supported with lighting for any night time working activities that are
required. This will provide a safe, green-working zone at trackside and will
be left in-situ for the duration of the project. Additional safety measures will
be taken, such as adjacent line working conditions between daytime and
night time train line-blocks to avoid unnecessary disruption to the safe
operation of the line.
Working behind the Vortok safety barrier ensures line speed is maintained at
80mph and there is a clear protection zone between the operational track
and the Cess / Cutting working area.
This involves the high risk works and will be fully planned with NR approval
as a night time track possession to ensure the maximum level of safety is
achieved. The activities that fall under this scope are as follows:-
- Lifting and placement of the pedestrian foot bridge across the track
alignment.
- Platform edge coping installations.
- Track slew and tamp to new track / station alignment.
The perimeter of the work site will be fully secured at all times to prevent
trespass or nuisance as a consequence of the works and security will be
provided out of hours to protect the rail network within the confines of the
work site.
Due regard will be given to night time working and illumination of the working
area to ensure that glare is avoided to oncoming trains as they pass the
worksite.
No works will be permitted to start on site until they are fully planned and
agreed with Network Rail in terms of design and working methodology. The
works will be monitored by Network Rail in conjunction with Balfour Beatty to
ensure that the rail network continues to operate unhindered by the project.
The Economic Case is used to identify the key economic impacts of the scheme, and its
overall value for money. This includes consideration of the passenger demand forecasts
and the assumptions made in the modelling. The Financial Case is used to present
evidence of the scheme’s affordability including revenue impacts, outturn and maintenance
costs.
4.1
Enter the calculated BCR for the New Station
Benefit Cost The BCR for the scheme is 4.1, which represents ‘very high value for money’.
Ratio (BCR)
Table 4.2.1 below sets out the cost breakdown for the development, design
and delivery of Warrington West Station. The cost includes: the provision of all
rail-side infrastructure including platforms, lifts and stair access; the station
building and plaza; and the large park and ride car park.
Item Cost £
Control/Electrical/telecoms £ 660,539.46
Track works £ 246,342.94
Structural works £ 5,482,184.39
Car park facilities £ 1,320,013.98
Station building £ 1,596,539.90
Station frontage/public realm £ 694,757.40
Sub total £10,000,378
Design £ 1,641,161
NR possession/management costs £ 2,664,020
Promoter costs £ 585,189
Construction contingency/risk £ 2,383,004
Total capital cost £17,273,752
4.4
Enter the total third party funding to the nearest £1000. Outline the sources of
the funds and provide evidence that funding has been committed
Total funds to
be provided The total funds to be provided by identified third party sources are £13,044,000
through (2016 prices).
identified third
party sources A breakdown of the funding sources is provided in Table 4.4.1 below. The
necessary evidence is contained in Appendix H accompanying this
application.
Total £13,044,000
4.5
Enter the details and the total to the nearest £1000. Costs should sustain the
asset for the agreed asset life
Annual
operations, Annual Operating Costs
maintenance
and repair The source for operating costs has been Arriva Rail North Limited. Estimated
costs annual operating costs for Warrington West are presented in the table below
and were supplied by Arriva Rail North Limited based on their observed
operating costs at similar stations that they currently operate.
Total £174,000
2016 prices
Therefore the overall net operating costs position for the scheme (which has
fed into the scheme appraisal) can be summarised as:
- net annual operating costs: £139,000
The costs are then converted into an ‘annual equivalent’ cost for input to the
scheme appraisal process.
Based on the above, the following renewals and replacement costs have been
determined for Warrington West:
Total £67,000
2016 prices
Arriva Rail North Limited has advised that they would not anticipate the LTC at
Sankey to change once Warrington West opens.
The above costs have been fed into the scheme appraisal.
Annual The NSF2 cannot be used to finance the net operating cost of the train
Operational service – the applicant must demonstrate that the proposed train service
Costs for covers its net operating cost from newly generated revenue
Train
Services OR;
the promoter must agree to fund the net funding shortfall for the first three
years, after which the service must cover its net operating cost from newly
generated revenue
Our response to Question 2.7 sets out the estimated net position in terms of
impacts on overall rail industry subsidy (the balance between net incremental
station operating costs and net incremental revenue arising from the
introduction of the new station). It is anticipated that the net incremental
revenue generated by the new station will cover the net incremental station
costs associated with running the new station.
4.7
Outline and explain all assumptions made when developing the project /
operating / service costs
Assumptions
The ongoing cost estimates have been sourced from the rail operator (Arriva
Rail North Limited) or have been worked up by WBC based on the capital
costs for the scheme. This has been explained in our response to Question
4.5. The costs advised by the train operator are based on observed costs at
similar stations that they currently operate and we are therefore confident that
they will be representative of the costs likely to be incurred at the new station.
The core proposition remains that once Warrington West opens then the level
of service provided at Sankey station will reduce accordingly. This will result in
the current staff shift transferring to Warrington West.
Within the scheme appraisal process an allowance has been made for real
price increases over time. Operating costs are increased by +1.2% per annum
and renewals and replacement costs by +1.5% per annum. Both are based on
evidence held by the consultant as used by other organisations. The value for
operating costs is a weighted average of staff and non-staff related real cost
increases.
The scheme appraisal assumes that these costs are split between WBC and
the rail industry, and these splits have been set out in our response to
Question 4.5 above, and summarised below
4.8
Outline and explain the contingency funding required and costs identified
through the risk assessment process
Contingency
funding The Value Engineering process has included the development of a fully
quantified register of risks.
This output from this is a Quantified Risk Register, which would be updated
and reviewed throughout the life of the project.
Financial values are assigned to each risk as part of this process, resulting in a
robust contingency allocation rather than a standard figure which is not
informed by an understanding of the specifics of the project.
4.9
Outline and explain any other dependencies which could impact on the cost
plan (for example, other works required to upgrade the line)
Other key
dependencies We are not aware of any further key dependencies which could impact on the
costs beyond any that have been noted in our responses to Questions 4.1 to
4.8.
4.10
Demonstrate how soon after the opening of the station will it become self-
financing (including the costs from services)
Station costs
Assuming a discount rate of 3.5%, the station is forecast to break even on
costs in 2029/30. This is based on the analysis undertaken in the Business
Case Summary Spreadsheet (Appendix G)
Inbound demand local For jobs located within 2km of Warrington West a trip-rate
commuting demand based approach was developed as a function of the number of
jobs. Trip rates derived from surveys undertaken at existing
local stations.
Table 4.11.2 sets out the annual demand for the new station over the first 20
years of operation, broken down by the core market segments. These results
include demand ramp-up assumptions (refer to Question 4.14) in the first years
of operation. Demand growth is either based on locally derived forecasts (local
catchment market segment) or adoption of Network Rail’s LTPP forecasts
relevant to the corridor.
Single journeys
4.12
Enter the % of annual passenger demand that is ‘new to rail’
Annual This can be deduced from Table 4.11.2 above in Question 4.11. In 2020 the
Demand - proportion of demand at Warrington West which is new to rail is 57%. In 2025
'new to rail' this figure becomes 62%.
4.13
Enter the % of annual passenger demand that is ‘abstracted from other
services’
Annual
This can be deduced from Table 4.11.2 above in Question 4.11. In 2020 the
Demand -
proportion of demand at Warrington West which has been abstracted from
'abstracted
other stations/services is 43%. In 2025 this figure becomes 38%.
from other
services' In addition, it should be noted that there is a proportion of rail demand lost due
to the increase in journey time for existing through passengers.
4.14
Passenger demand forecasts should allow for a 'ramp-up' of demand after
opening and identify and explain the date from when full demand will be
Peak achieved
Demand
The demand model estimates demand for forecast years 2018, 2020 and
Forecast
2040. Demand in other years is assumed to be determined by linear
interpolation. The station is expected to open in the middle of 2019 and
therefore our demand ramp-up profile, applied to calendar years in the model,
had to take account of an initial half-year.
All demand ramp-up factors have been sourced from PDFH V5.1 Section B12,
where different ramp-up profiles are presented for differing impacts.
Adjustments have been made to accommodate the initial half year and to allow
for the fact that commuters and non-commuters experience differing GJT
(Generalised Journey Time) impact ramp-up profiles. Table 4.14.1 presents
the demand ramp-up values used and indicates for which market segments
they have been applied to.
4.15
Existing rail users currently using other neighbouring stations will use
Warrington West instead. In particular some demand (circa 4%) will be
Wider diverted from Warrington Central to Warrington West, thus providing some
benefits relief at this station. Warrington Central is a relatively constrained station site
with a large usage (1.78m journeys in 2014/15) and so any initiative to spread
the rail usage away from this station could be seen to be a benefit.
There will be smaller levels of transfer of rail journeys away from some of the
stations on the Chat Moss route (Earlstown, St Helens Jct, etc), leading to a
small reduction in train loadings on that corridor – which could be seen as a
minor benefit at times of peak loadings.
It is estimated that there will be a net saving of nearly 4.5 million car kilometres
in 2025. This results from the transfer from car journeys, balanced to a degree
by additional car access movements to/from the new station. This reduction in
car km will have benefits in terms of mitigating traffic growth and congestion
within the Liverpool-Warrington-Manchester corridor, particularly on the M62.
A letter of support from Highways England is included in Appendix B. The
scheme is also important in terms of providing sustainable access and
facilitating uptake of key development sites in the area, including Omega,
Lingley Mere and Gemini 16.
The regeneration benefits in the local area which the station will be key to
unlocking are very significant. Over the next 10 - 15 years a further 1,600
homes will be built on Omega and other key sites as well as a further 12,000
jobs. It is crucial that this growth takes place in as sustainable manner as
possible and a new Warrington West station serving trips to and from Liverpool
and Manchester will be a core element of this.
Therefore, it is anticipated that the bulk of journeys from Warrington West will
be to the two key cities, Manchester and Liverpool, directly served by these
services. Calculations we have undertaken using MOIRA (based on
Warrington Central, but with the level of service expected at Warrington West)
indicate that Manchester attracts circa 40% of journeys and Liverpool 36% of
journeys. With circa 10% of journeys expected to be to other local ‘Warrington’
stations (Warrington Central, Birchwood, Padgate), it is clear that the majority
of journeys from Warrington West could be classified as being local journeys,
reflecting Warrington’s unique position between two of the North’s key
Regional Centres. This is an important consideration as the development of
the new station is supported by both TfGM and Merseytravel in encouraging
journeys to rail to these cities.
4.17
Outline and explain the data sources used and assumptions made in the
calculation of passenger demand forecasts
Data sources
and The demand forecasting model is a series of sub-models developed to
assumptions represent different market segments (these were set out in our response to
Question 4.11 above). It was originally developed in 2007 and has been
refreshed twice since (in 2013 and in 2016). The fundamental structure of the
models hasn’t changed, but the input data has been updated where
necessary/appropriate and amendments have been made to ensure that the
modelling and appraisal process remains in line with current WebTAG
guidance.
Forecast modelled years are 2018, 2020 and 2040. Note that in line with
WebTAG appraisal guidance, demand growth is currently capped from 2036 in
the scheme appraisal.
The latest Modelling and Appraisal Report (“Warrington West Station: Second
Update of Scheme Business Case” (AECOM, Nov 2016)) is included with this
application as Appendix C. The table below summarises what the key data
sources used are and assumptions made across each of the sub-models.
Park and Mode choice model (car v Defined catchment area to 38 destination
Ride (new rail) zones
users)
Imported model parameters (recalibrated)
The station is forecast to make a net positive contribution from opening and by
2030 is forecast to be generating circa £2m per annum in net revenue.
Annual This can be deduced from Table 4.18.1 in Question 4.18 above. In 2020 the
Passenger proportion of revenue at Warrington West which is new to rail is 50%. In 2025
Revenue - this figure becomes 57%.
'new to rail'
4.20
Enter the % of annual passenger revenue that is ‘abstracted from other
services’
Annual
Passenger This can be deduced from Table 4.18.1 in Question 4.18 above. In 2020 the
Revenue - proportion of revenue at Warrington West which has been abstracted from
'abstracted other stations/services is 50%. In 2025 this figure becomes 43%.
from other
services' In addition, it should be noted that there is a proportion of rail revenue lost due
to the increase in journey time for existing through passengers.
4.21
Outline and explain the revenue forecasts for money generated from car
parking at the new station
Car parking
revenue Car Park usage is forecast to reach capacity within the first two years of station
operation. As such, combined with the fact that no further real price increases
are modelled, revenue will be constrained from that point onward.
4.22
Outline and explain the revenue forecasts for money generated from other
facilities at the new station
Other
revenue No further revenue sources have been appraised
sources
4.23
Outline and explain any project / innovative approaches reducing the costs of
operating the railway and quantified benefits
Reducing the
costs of The Value Engineering process has included a consideration of the ongoing
operating the costs of managing the station assets and maximising the benefits that can be
railway derived.
Key to this process has been the review of the station building, and its size and
This has been due in large part by the decision to use a combination of a
‘smart wall’ and TVMs instead of ticket windows to serve passengers. The
technology has already been applied successfully by Northern at Harrogate
and Leeds stations, and the innovative approach is expected to save on
building capital and maintenance costs, through requiring less space and
provide a better customer experience.
4.24
Provide overview of any other impact appraisal for the new station e.g.
environmental impacts, time saving benefits, VOC benefits, reduction in road
Other impacts veh/km, socio-demographic etc.
It is estimated that there will be a net saving of nearly 4.5 million car kilometres
in 2025. This results from transfer from car journeys, balanced to a degree by
additional car access movements to/from the new station. This reduction in car
km will have a significant impact on levels of congestion within the Liverpool-
Warrington-Manchester corridor.
The Commercial Case should set out the procurement strategy of the new station, clearly
aligning this to the GRIP process.
Risks should be identified and plans put in place to ensure their appropriate management.
Contract management should outline key handover and lease dates to ensure the
successful handover of the project to the Station Facility Owner (SFO).
Balfour Beatty has recently proven that they are keen to work with
WBC on other schemes such as the Birchwood Pinch Point Project.
The recent success and experience with Balfour Beatty on the
Birchwood Pinch Point Project provides assurance and confidence
that the scheme can be delivered successfully via the SCAPE
Framework, as well highlighting the added value Balfour Beatty have
been able to contribute toward Warrington Borough Council
infrastructure projects.
The NEC3 contracts have been uniquely designed using the following
three key unique characteristics:
- Risk owners;
- Current Status;
- Current Action;
- Possible Delays;
- Event;
- Cause;
- Consequence;
- Mitigation; and
- Likelihood.
Since Balfour Beatty has come on board, the risk register has again
been revised. Further Risk Workshops were held attended by Balfour
Beatty, AECOM (Scheme Designer), WBC, the proposed station
operator (Northern) and Network Rail.
The high level key risks identified for the project are outlined below.
These risks inform the Quantified Risk Register (QRA) which is
attached at Appendix J. The QRA was last updated in October in 2016
and informs a robust cost estimate as part of the New Station Fund
application. The preparation of a QRA satisfies the requirement of
GRIP Stage 4.
The process has been developed through the delivery of over £300m
of schemes in the North West region in the last three years proving its
value and effectiveness when avoiding project delays or cost
increases.
Balfour Beatty will appoint a project Risk Champion who will oversee
the risk and opportunity management on the project. It will be their role
to promote the importance of the risk and opportunity management
process and to ensure effective communication and reporting of the
risks throughout the team.
1. Project Manager;
2. Programme Manager;
4. Programme Board;
The scheme risks have been considered and included as part of the
detailed QRA found in Appendix J. A further summary of the key
project risks is provided in question 5.3 above. The risks have been
identified, recorded and updated regularly throughout the scheme
development phase of the investment lifecycle. Management of these
risks will be an ongoing task through to practical completion.
5.6
Outline and explain who is taking any marginal risk, including on
Marginal Risk planning consent, demand, revenue availability and integration risk
Warrington Borough Council would bear the risks associated with land,
planning and environmental permissions. This includes risks linked to
requirement to amend the existing planning consent for the railway
station to reflect revised plans developed through the most recent
round of value engineering. It is noted, that the main NEC3
construction contract between Warrington Borough Council and Balfour
Beatty would be conditional on the resolution of these risks paving the
way for the delivery phase; therefore this approach is considered an
appropriate.
The operating model envisaged is that WBC will own the station
building, plaza and car park whilst Network Rail will own the ‘rail-side
infrastructure (e.g. platforms, bridge, lifts, etc). Northern Rail, as SFO,
will operate the station and pay a LTC (Long Term Charge) to Network
Rail covering the ‘rail-side’ infrastructure and a ‘management charge’ to
WBC for the buildings and car park.
5.8
Outline and explain the date from when the Station Facility Owner shall
Asset transfer date take control of the station
The SFO will take control of the station upon completion in March
2019.
The Management Case sets out the mechanisms to be used to deliver the project,
evidencing that it can be delivered in engineering, operational and planning terms and that
it has the full support of Network Rail and other key stakeholders.
This section should detail the management put in place to ensure the successful
development, delivery and ongoing operation of the station. A clear description of
responsibilities needs to be made clear in terms of the ongoing operation, maintenance
and repairs to the station.
Figure 6.1.1
Land set aside for station
under s299A agreement
The only parcel of land which is currently not in the ownership of interested
bodies or partners is a section of unregistered land to the south of the
proposed station. A short corridor of the land bounded by the rail
embankment and Sycamore Lane is required to form an emergency exit from
the Liverpool bound platform to a safe area adjacent to the public highway.
The council has already taken measures to secure this land, fencing off the
area and posting notices to any interested parties to come forward to claim
ownership. The council’s legal and estates departments are currently in the
process of agreeing the final mechanism by which this land can be secure in
public ownership to provide the emergency route. The fall-back position on
this is a Highways CPO, which is not expected to present any delays to the
project as to date no interested parties have come forward for this
unregistered land despite fencing and notices on site being in place for a
significant period of time.
Discussions relating to the matters above have been ongoing over the last 2
years between legal and estates professionals from Warrington BC, Network
rail and David Wilson Homes
Outline and explain the planning status and detail any planning
consent/conditions in place for the construction of a new station at the
proposed site?
Planning History
6.2
Planning status A complete list of planning applications relating to the former RAF
Burtonwood site to the north of the railway line within which the site falls is
included in Appendix M.
The Chapelford Urban Village (former Burtonwood Air Base site) was
granted outline planning permission in January 2000, subject to Planning
Agreement, with the Planning Agreement agreed on 13th May 2002
(99/40635). The Masterplan for the Urban Village included local amenities,
However, the scheme that gained planning consent in October 2015 has (as
described elsewhere in this bid) been subject to a value engineering exercise
to reduce the costs of the project. The resultant changes include a reduced
size and relocated station building and a realigned highway access and car
parking arrangement.
The programme for the project is included in Appendix P. The Project Plan
is included in Appendix O.
Project Management Approach
Good practice involves formal Programme and Project Management. The
Warrington West Railway Station would be delivered as an individual project
although it is recognised that there may be interdependencies relating to
other infrastructure works undertaken on the railway network.
The Prince2 approach to project management is the adopted project
management option with TfW and the client group. The TfW service has 50%
of staff trained to a minimum of Prince2 foundation, with further project
managers qualified up to Practitioner level.
Governance
In addition to funding sought through this application, given the scheme is
being funded by both CWEP and WBC there is a need to recognise that
scheme delivery will need to comply with all three of these organisations
independent governance structures. The following paragraphs outline the
key mechanisms which are applicable to project management of the scheme.
Cheshire and Warrington Local Enterprise Partnership
CWLEP determines local economic priorities to lead economic growth and
job creation within the local area. As part of this, CWLEP maintains the
highest standards of probity in the way that it discusses and makes decisions
on how the funding devolved to it by Government is spent. The Governance
structure for the CWLEP is outlined in Figure 6.3.1 below.
The scheme will also be delivered in accordance with the LEP Growth
Programme Assurance and Accountability Framework. This framework
provides a mechanism for the Accountable body (WBC), the LEP and key
stakeholders to be clear about their responsibilities and to ensure good
governance. The Assurance framework supports the development and
delivery of a rigorously appraised and prioritised investment programme for
Cheshire and Warrington which aligns to the LEP’s strategic priorities and
Enabling Programmes and Intervention Priorities and which positions the
sub-region to take maximum advantage of funding opportunities which may
arise3.
3
LEP Growth Programme Assurance and Accountability Framework(July 2015)
Network Rail
Activity Date
The Council will be the 3rd party sponsoring organisation for the delivery of
the scheme. The governance arrangements for delivering the scheme are
presented below:
6.4
Based on approval of New Station Funding in April 2017, Warrington
Date for site Borough Council’s delivery partner Balfour Beatty anticipate onsite works to
works commence in August 2017.
commencement
A complete programme is attached at Appendix P.
The above date is based Warrington borough council continuing to fund the
development work ‘at risk’ until the NSF bid is announced in an assumed
date in April 2017.
6.5
Date for Based on the anticipated start date for works on site, the programme date for
Substantial the completion of site works is February 2019. A complete programme is
Completion of attached at Appendix P.
site works Table 6.5.1: Substantial Completion of Key Elements of Station Delivery
6.7
Outline and explain constraints and dependencies which influence the
Project delivery project delivery programme. There should be evidence that consideration
programme – has been given to other programmes and projects which are underway
constraints and
dependencies Constraints
Traffic Generation The scheme includes a new car park which will
and Access result in increased vehicular movements in the
vicinity of the station. The planning permit ensures
that the new access roads have the capacity to
accommodate the increased traffic relating to the
station as well as that associated with Chapelford
Urban Village.
In December 2017, services along the CLC corridor will change. The
Transpennine service will transfer to the Chat Moss Line via Newton-le-
Willows, with Northern replacing this service with a new semi-fast service
running between Liverpool Lime Street and Manchester Airport, calling
additionally at Warrington West upon opening. The franchise agreement
identifies three services per hour for the new Warrington West railway
station, providing the opportunity to serve the whole Warrington West area
with an improved service frequency. At the time of writing, this remains the
plan for the December 2017 timetable change.
Northern Hub
Rolling Stock
As part of the new Northern franchise commitment, all rolling stock operating
on the CLC route will be either brand new or fully refurbished by 2019/20. In
addition, the Liverpool Lime Street to Manchester Airport “semi-fast” service
has been designated as a “Northern Connect” route. As such it will receive
new Class 195 trains offering free WiFi, plug sockets, tables, air conditioning
and seat reservations. Overall, the Northern franchise will see a significant
increase in capacity as a result of new services and additional rolling stock.
Warrington has assembled a team of people to ensure the project has the
resource and expertise available to deliver a successful project. Critical to
this for Warrington, is combining internal and external staff to create a
coherent team to work alongside Network Rail colleagues through the final
development and delivery of the project.
In this instance the team brings in AECOM and Mott Macdonald staff who
have a longstanding relationship with this scheme. The flexibility of the
framework contract is such that if additional resource is required
unexpectedly, we have resource and expertise to all on from all 5 framework
companies (the other 3 being WSP:PB, Atkins and Ch2MHill).
Warrington has decided to deliver this project through the Scape framework,
details of which are provided in greater detail elsewhere in this document.
The Scape framework brings in Balfour Beatty as the contracted delivery
partner, itself a leading construction company with a dedicated rail arm and
an extensive track record on the delivery of rail projects. Balfour Beatty has
in turn engaged AECOM as their design partner to provide design services.
This is providing efficiencies in the project development as key staff within
AECOM have a historic understanding of the scheme dating back to 2007.
Finally, in terms of legal and property issues, key individuals within the
relevant teams within Warrington are engaged on an ongoing basis and their
future support for the scheme is confirmed.
Figure 6.8.1 over page sets out the key roles within this resource plan and
the interface with rail partners in Network Rail and Northern.
Network Rail/TOC Interoperability and Construction Team Client Team Business Case Support
Interfaces CSM Assurance
Anthony Burgess- Mia Crowther Andrew Coates
NR Asset Protection Notified Body Project Director Financial Controller AECOM
Services (Nobo) Balfour Beatty
Mott MacDonald
Andrew Donnelly David Arthur
NR/Northern Michael Cook - Communications AECOM
Timetabling Design Manager
Designated Body Balfour Beatty
(Debo) Norman Perry Nick Ovenell
NR Project Engineers Mott MacDonald
Mott MacDonald Legal
OM John Harding –
Project Manager
(Design), AECOM
Assessment Balfour Beatty Darran Hunter
Body (Asbo) Property
Mott MacDonald Roman Strzala
Strzala Architects
To support our Management approach and demonstrate our preferred contractors experience
delivering projects on the rail network, the following presents examples of previous experience:
Case Study 1
Project: Blackfriars Station Redevelopment
and Bridge Upgrade
- Chairman’s Cup for the most notable project under construction in the City of London;
- Green Apple award 2011 - for use of the River Thames to transport materials and remove
waste from the site;
Relevance: The project demonstrates Balfour Beatty’s proven rail expertise covering track,
power, electrification, civils, signalling, and railway systems and technology. It also highlights
previous working example of the collaborative approach Balfour Beatty has with Network Rail
and the TOCs on major construction projects.
The project involved keeping the station fully operational through careful planning and major
temporary works and involved a number of complex operational interfaces with Network Rail,
London Underground, and Port of London Authority and the operating train companies, as well
as traffic management arrangements. To limit impact on the 300,000 people moving through
the construction site every day (rail, roads, underground and river) the majority of works were
undertaken at night and over weekends and holidays. The success of this approach is
conveyed by the fact there was no complaints over Christmas 2009.
Case Study 2
Project: East Kent Re-signalling Phase 2
- The creation of a new ‘Access for all’, three platform station at Rochester, including
pedestrian subway and the decommissioning of the old station;
- Platform extensions and a new turn-back facility at Rainham in the form of a new 12-car
bay platform; and
The project delivered an increase in capacity and capability on the line for five extra trains into
London in the mornings and one extra train in the evening, as well as delivering operational
savings and improved network integration with other modes of transport.
Awards/Recognition:
“Congratulations and well done to all involved in this phenomenal project and the successful
commissioning.” Atkins Project Director
"This is a huge success for Ian Grant and his team at East Kent Re-signalling. All involved
have worked incredibly hard and I'm proud of everyone's commitment and contribution.
Improving reliability for our train operator and customers is key and this is what we've done
this weekend.” Huw Edwards, Network Rail’s project director
Relevance: The station was constructed in and around busy commuter lines into London
which remained open throughout and the associated track works completed under specific
possession arrangements. The whole construction was completed with minor disruption to the
travelling public.
Case Study 3
Project: Crossrail South East Section Project (CSESP)
- Staged demolition and reconstruction of Abbey Wood Station with an interim station
implemented during construction. With regard to Abbey Wood station, it will include: a new,
larger ticket hall and spatial concourse that leads directly onto a wide forecourt connecting
the station to the Harrow Manorway Flyover; new platforms for both Elizabeth line and
North Kent services; six lifts providing step-free access to all platforms; better security
(new CCTV cameras); new customer information services/screens and speakers for
announcements; better seating on platforms; and improved lighting/platform canopy cover.
- Realignment of the existing North Kent Line (NKL) tracks to the south (includes widening
and draining the existing embankment to the south);
- Provision of two additional tracks for Crossrail located within the existing railway corridor;
- Installation of third rail (660 / 750 volts DC) for the North Kent Lines;
- The replacement of two existing footbridges with new footbridges (with ramp and stair
access);
- Replacement of the existing station footbridge with two new station footbridges which
provide cross platform interchange and secondary means of escape;
- Realignment of two existing roads to release construction of the new main station building;
- Diversion and protection of services along the length of the works; and
- Signalling modifications.
- The installation of 3.6km of new track and signalling equipment from Whitechapel to
Dalston Junction;
- The installation of a railway flyover connecting the southern end of the line to the existing
NR line;
- The construction of a new train maintenance and cleaning depot at New Cross Gate; and
- The construction of the Operations Building Complex (OBC) at New Cross Gate.
Awards/Recognition:
- Regional London and South East, Constructing Excellence award for excellence in
construction of a major project; and
- Design, supply, installation, testing and commissioning of the depot’s new signalling
system; and
7.1
Stakeholder Identify all key stakeholders involved in the project. Outline key details of
management plan the stakeholder management plan and attach full plan to application.
Are third parties able to claim any form of compensation as a result of the
NSF2 project?
Overall the scheme has identified 13 different internal/external
stakeholder groups. These range from technical professionals inputting
into the design/construction to local residents with concern about impact
of the scheme. The key stakeholder groups, and their contribution to the
project, can be found in the Stakeholder Management Plan, which is
included at Appendix Q.
Set out how this project will benefit the local community in both the
development and construction phase around offering opportunities for
work placement and apprenticeships and then ongoing once the station
is in operational use.
The council and its delivery partner Balfour Beatty are committed to
ensuring that the local benefits of this project are wide and long-lasting.
Alongside the enduring legacy the station will provide in terms of creating
a hub of public transport access, the construction of the project will
provide an invaluable opportunity to engage, train and inspire local
people.
A real recent example of how successful this has been can be seen from
Birchwood Pinch Point scheme. This highway scheme was completed in
the east of Warrington earlier this year. Balfour Beatty identified a specific
individual with the skills and responsibility for engaging local community
groups, schools and colleges. Their role is to help the community gain an
understanding and ownership of the works but also crucially, to open up
opportunities for employment and training through apprenticeships and
work experience placements.
To help explain how the KPIs under the Scape framework are set out, a
summary of the Employment and Skills plan for Birchwood Pinch Point
can be found at Appendix S.
Whilst the full scope of the community engagement for Warrington West
is yet to be finalised, a draft set of targets for Employment and Skills is
also included at Appendix S. This sets out an indicative plan to create 7
work experience placements, a minimum of 6 new local jobs and 3
apprenticeships.
7.3
Demonstrate that the proposed station and timetable is supported by NR
Stakeholder (support from Route Enhancements Manager), DfT (support from
Support Commercial Manager(s)) and the incumbent Train Operating Company
(TOC)
The key elements to note from this assessment are described below.
The proposed station has a broadly positive impact on all of the protected
characteristics. It will:
Be accessible by all - park and ride, taxi drop off, designated bus
stops, cycle parking and routes, pedestrian routes, wheelchair and
mobility scooter accessible site, station building and platforms via
lift facilities.
The detail design of the station will involve detailed consultation with
Disability and Old Peoples groups to ensure the station is accessible to
all.
9.1
Provide evidence that capital and operational costs have been
Station capital and independently verified and validated
operational costs
Estimates for scheme delivery were initially produced by Network Rail
under a now superseded ‘Design and Build’ procurement pathway.
9.2
Provide evidence that the proposed service and timetables have been
Service planning and independently verified and validated by Network Rail
timetables
To support our proposals across the whole of the Northern network we undertook
some limited Railsys modelling during the bid phase, which was necessarily focused
in the areas we considered high risk in terms of major timetable changes. We carried
out two Railsys exercises focused on central Manchester and the Leeds area. Whilst
the former did model all train services which operate via the Warrington Central route,
the model area did not stretch sufficiently far to explicitly model the route, nor calls at
Warrington West.
During the bid phase we shared our timetable proposals with Network Rail, and
understood their perspectives and concerns. Network Rail provided a letter of support
to accompany our bid submission, which stated that “…Arriva Rail North has shared
its timetable proposals that meet the Train Service Requirements. Additional services
that exceed the Train Service Requirements have also been shared. Network Rail
has highlighted areas where we required performance considerations to be
understood and mitigated and we are supportive of the focussed Railsys modelling
undertaken around Manchester and Leeds.”
[Email from Richard Harper (Production Director, Trains Bid Team, Arriva UK Trains
Ltd), 25 October 2016]
Key here is the fact that as part of the bidding process, Arriva gained
assurance from Network Rail that their timetable proposals were
workable and achievable. This included detailed Railsys modelling
through the key areas of the rail network where the services that will
call at Warrington West will operate. Network Rail has stated that they
are supportive of the work undertaken by Arriva in this regard.
Ultimately this work has translated into the Franchise Agreement that
has now been signed and formally adopted for the Northern franchise.
Rail North/Department for Transport has confirmed that Warrington
West is indeed in the Train Service Requirement in correspondence
reproduced at Appendix T.
The intention is that WBC will work closely with Network Rail and
Northern to complete this work with a view to closing out this element
of the train planning detail. We hope to agree the scope of the
modelling required in the coming weeks, and to include the Network
Rail checking and approvals role within the Client Requirements
Document, currently being finalised to inform the resulting Asset
Protection Agreement (APA) with Network Rail.
On that basis, the above position statement sets out what work has
been done to date and the approach to including further more detailed
timetable modelling within the scope of the APA is to be agreed with
Network Rail.
that this application does not form or imply any contract to provide funding
to allow Network Rail and the Department for Transport to undertake enquiries on this
application so as to satisfy themselves of its completeness and accuracy
the project does not form part of, nor conflict with, Network Rail’s commitments as part
of the Network Rail’s current CP5 delivery plan, or form part of a TOC’s franchise
commitments. The project does not replace or form part of another existing
commitment to the DfT or Network Rail.
Signed:
Please return this completed form along with supporting information by 25th November
2016 to Network Rail at the following e-mail address: Rebecca.Cooke@networkrail.co.uk
and/or by post to:
Rebecca Cooke
Network Rail,
The Quadrant:MK,
Loughton 3rd Floor
Elder Gate
Milton Keynes
MK9 1EN
Glossary of terms
“Station Facility Owner / SFO” the Train Operating Company that enters into a station
lease with Network Rail
“Train Operating Company / TOC” the operator of passenger and freight trains which
has entered into an Access Agreement with Network Rail