Vous êtes sur la page 1sur 2

After this you need to go through the following steps.

1) Assign control key QM04 which is having confirmation required option in its configuration.

2) spro-> Qm -> Basic settings -> maintain settings at plant level

in Inspection lot creation tab make sure

Order type : Ind.settlement 'QL01' and coll settlement 'QL02'.

3) spro-> Qm -> quality inspection-> inspection lot creation -> Maintain inspection types

Here assign order type QL02 for your inspection type.

4) spro-> Qm -> Environment ->Central functions-> Maintain QM order types

Here assign Cat 6 QM Order to settlement order types QL01, QL02.

5) Then create QM order in QK01 for your material with material, Plant, Inspection type combination.

Here enter need to enter order type QL01, controling area, cost center, Functional area, Profit center.

After creating you can view the QM order number in MM03 for this inspection type.

6) Then after result recording while saving system will through a pop up to enter the actual consumption values
of activities.

7) You can look the cost analysis in usage decision Extras-> costs.
QM order won't be assigned to inspection lot.We have to create QM order with the combination of material,
inspection type, plant. For one materials we will assign one or more inspection type correct!!!

So for each inspection type assigned in material master we have to create the QM order. QM order will be
shown in MM03 once created in QK01. After this cost will calculated for this order each time when we record
the results and enters the consumed activities for that inspection type.

Here to through the pop up after result recording to enter the actual activities we have to use control key QM04
for operation in inspection plan.