Vous êtes sur la page 1sur 66

9326 d2U /9926 BBU 2U/4U

Distributed Node B
Commissioning

All Rights Reserved © Alcatel-Lucent 2006


Agenda

 Distributed NodeB Description


 Distributed NodeB Commissioning
 Distributed NodeB Commissioning Testing

July 2014 All Rights Reserved © Alcatel-Lucent 2006


Distributed Node B
Description

All Rights Reserved © Alcatel-Lucent 2006


9326 d2U V2 Node B Presentation

9326 d2U V2 with xCCM-U + MDA (4xE1/T1)


eCEM-U or xCEM-U

xCCM-U MDA 4 x E1/T1 Fan Rack / RUC V2

9326 d2U V2 with xCCM-U + MDA (GE)


eCEM-U or xCEM-U

xCCM-U MDA GE Fan Rack / RUC V2

NOTE: For more information refer to Product Description or MOPG or PEI (Engineering rules) of the dedicated Product

4 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
9926 BBU (d2U V3) Node B Presentation

9926 BBU (d2U V3) with eCCM-U + MDA (4xE1/T1)


eCEM-U

eCCM-U MDA 4 x E1/T1 Fan Rack / RUC V2


9926 BBU (d2U V3) with eCCM-U + MDA (GE)
eCEM-U

eCCM-U MDA GE Fan Rack / RUC V2

NOTE: For more information refer to Product Description or MOPG or PEI (Engineering rules) of the dedicated Product

5 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
9926 BBU 4U (d4U V3) Node B Presentation

NOTE: For more information


refer to Product Description or
MOPG or PEI (Engineering
rules) of the dedicated
Product

6 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
xCCM-U for d2U V2 Presentation
 Refer to IEH521 sections
xCCM-U – with MDA 4 E1/T1 •Section 702 to perform CCM-U Board Migration
+
Procedure
 GPEC Training: Presentations of eModules and MD8
Eltek PSU Cabinet.
https://all1.na.alcatel-
lucent.com/Teams/GCDNetworks/WirelessGPEC/DeliveryReadine
ss/WCDMA/UTRAN/Training/W-CDMA_trainings.html

xCCM-U – with MDA GE

NOTE: For more information refer to Product


Description or MOPG or PEI (Engineering rules)
of the dedicated Product

7 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
eCCM-U for d2U V2 / d2U V3 / d4U Presentation
eCCM-U – with MDA 4 E1/T1

eCCM-U – with MDA GE

8 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
xCEM-U & eCEM-U for d2U V2 / d2U V3 / d4U Presentation

xCEM-U

eCEM-U

 Refer to IEH521 sections


•Section 703 to perform CEM-U Board Migration Procedure

9 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Optional Modules for d2U/d4U Presentation

LPPCM for d2U/d4U

eAM for d2U/d4U

10 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Distributed Node B
Commissioning

All Rights Reserved © Alcatel-Lucent 2006


Node B commissioning - Initial preparation steps
Start

The flow diagram outlines the


initial preparation steps for the Acquire and read all required
documentation for d2U/d4U
commissioning of a Node B to and RRH commissioning
connect the laptop on the CCM-
U and launch the TIL in local Acquire all required HW and
SW tools into your laptop
mode.
Is that the
Node B
N
Software is Follow Proc. 1:
already NodeB Software Installation
installed on on the laptop
the
Laptop?

Is that the
laptop has
already N
Follow Proc. 2:
used for
First Laptop Setting
TIL
connection
?
Y Follow Proc. 3:
TIL Connection

Perform the Node B Commissioning


Procedures or
Close the TIL GUI, the Web Browser and
remove the RJ45 cable from the CCM-U and
the laptop

End

12 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – SW Download to Node B and Activation

The flow diagram outlines Check the TCP/IP properties


Start
the steps for the Node B or redo the preparation steps
(refer to previous flowcharts)
commissioning to
Follow Proc. 3:
Download the Software to TIL Connection
the Node B and activate
Y The TIL is N
the new release with the Launched and
displays the
TIL in local Mode. GUI?
Y
DBS 4U Follow Proc. 4:
Is used? Specific Preparation

N
Follow Proc. 5:
NodeB Software
Downloading

Follow Proc. 6:
New Node B release
Activation

Follow Proc. 7:
Node B Configuration
Checks

Perform the Node B Commissioning


Procedures or
Close the TIL GUI, the Web Browser and
remove the RJ45 cable from the CCM-U and
the laptop

End

All Rights Reserved © Alcatel-Lucent 2006


Start

Node B commissioning – Set all Node B parameters


Follow Proc. 3: TIL Connection

The flow diagram outlines


Follow Proc. 7: Node B Configuration Checks
the steps for the Node B
commissioning to Set all Follow Proc. 8: Node B Setting BTS Parameters
Node B parameters with Follow Proc. 9: Node B Setting RRH Parameters
the TIL in local Mode.
Follow Proc. 10: Node B Setting Backhaul Parameters
If ATM Iub used If Hybrid Iub used If Iub over IP used

Follow Proc. 11 Follow Proc. 11: Node B Setting PCM E1 Parameters

Follow Proc. 12 Follow Proc. 12: Node B Setting PCM T1 Parameters

Follow Proc. 13 Follow Proc. 13: Node B Setting PCM&IMA Parameters

Follow Proc. 14: Node B Setting Ethernet Parameters Follow Proc. 14

Follow Proc. 15 Follow Proc. 15: Node B Setting ATM Parameters

Follow Proc. 16: Node B Setting IP Parameters Follow Proc. 16

If
Neid
= SN Follow Proc. 17: Node B Neid Exchange with the TIL
in TIL N
GUI
Y
Follow Proc. 18: Sending I&C Parameters to NodeB

Follow Proc. 19: Node B Reset in Connected Mode

Follow Proc. 20: I&C Parameters Verification

Follow Proc. 21: MCA Backup File

Follow Proc. 23: Final Commissioning Operations

End

All Rights Reserved © Alcatel-Lucent 2006


Node B commissioning – Node B Form Parameters

• The form of parameters based on the CIQ must be documented by the coordinator according to the
expected parameters and configuration.
• The form of parameters must be send by email or available on a link.
• The following table is the list of Node B parameters required prior to commissioning.

All Rights Reserved © Alcatel-Lucent 2006


Node B commissioning – Node B Form Parameters – PCM Parameters

PCM (E1) Parameters PCM (T1) Parameters

All Rights Reserved © Alcatel-Lucent 2006


Node B commissioning – Node B Form Parameters – PCM/IMA & ATM Parameters

All Rights Reserved © Alcatel-Lucent 2006


Node B commissioning – Node B Form Parameters – Ethernet & IP Parameters

18 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Node B Form Parameters – BTS Packaging

19 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Node B Form Parameters – BTS Packaging (Continued)

20 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Applicable IEH521 Sections & Methods Documents

Applicable IEH 521 Sections for WCDMA Node B commissioning

Applicable Methods documents for IEH 521 Sections 3xx

21 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Material Requirements

The hardware and software tools required to perform the commissioning method.

22 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Procedures Overview

The following table provides an


overview about the steps required to
perform commissioning of WCDMA Node
B dependant on the backhaul
interface.

23 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 1: Node B Software Installation on the Laptop
Description:
This procedure gives the process to use the hard disk of the PC as the source for the software upgrade.
Condition:
This procedure has to be executed only at the first time Procedure of Node B SW Installation on Laptop
(initial setup) to install the Node B software delivery Step Action
components on the PC.
1 Open the compress software (ex here: tar.gz)
If already done – no action is required.
Required Data 2 Select Options and Configuration
The following data are required for the setup: 3 Select Miscellaneous or Select all
• Node B software available on a Web server or
4 Remove the check box: TAR file smart CR/LF
• Node B software available on a CD conversion.
Procedure of Preparation before Node B SW Install. 5 Insert the Node B software release CD-ROM in the
Step Action CD-ROM drive.
NOTE: In this case the Node B Software into the CD-
1 Click Start in the Windows Taskbar. ROM is not compressed.
2 Select Programs/Windows Explorer. 6 Click on the CD-ROM drive letter
3 Double-click on C: to open it. 7 Click on the Delivery folder to select the NodeB SW
4 Verify that a Delivery folder is present on your 8 Press the CTRL + C to copy the Delivery folder in the
laptop. clipboard.
NOTE: The Delivery folder must be unique and only
dedicated to the last Software release delivery. 9 Click on C: to select it.

5 Check the type of Node B Software delivery 10 Press the CTRL + V to paste the clipboard content in
• If Node B Software delivery from a Web server C:
continue to the next procedure to perform step 1 up 11 Wait during the transfer
to step 4 and continue with step 7 up to the end.
• If Node B Software delivery using a CD-ROM Check on the folder C:/ delivery the existence of the
continue new SW2006 file UNB…
24 | Distributed Nodewith the next
B Commissioning | July procedure
2014 to perform step 5 All Rights Reserved © Alcatel-Lucent
up to the end. NOTE: The Node B SW is now available on the PC.
Node B commissioning – Proc 2: First Laptop Setting
Description:
This procedure gives the process for the first Laptop setting to prepare the first TIL connection with the WCDMA Node B.
Preconditions:
The following preconditions for this procedure step must be met:
• PC has never been set as TIL GUI
• Have Java run type environment installed into the laptop with the right version
• Have User ID and Password for TIL GUI available

First Laptop Setting Procedure


Step Action
1 In the Local Area Connection:
Select Internet Protocol Version 4 (TCP/IPv4)
2 Click on Properties
3 In TCP/IP Properties screen, in the IP Address tab:
Note and record the current configuration (if
necessary)
4 Modify properties to access Node B digital board:
• Select use the following IP address
5 Fill the following IP address:
• IP Address : 223.254.254.1
• Subnet mask : 255.255.240.0
6 Click OK to quit the TCP/IP Properties screen
7 Click OK to quit the network screen

25 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 3: TIL Connection
Description:
This procedure gives the process
• To connect the Laptop on the CCM-U board and TIL connection on
• To launch the TIL in Local Mode (direct connection to CCM-U board) CCM-U (Port 1)
Preconditions:
The PCMCIA card setting on the Laptop should be correctly configured according to Proc.2.
In case of Outdoor Node B and before opening the doors:

TIL Connection Procedure

Step Action
1 Connect the RJ45 (Cross-Cable) between Laptop and
the CCM-U board (Port1) TIL
NOTE: When connecting the RJ45 the Green LED
should light on Port 1 of the CCM-U
2 Start the Web Browser.
3 In the URL field of your web browser.
Enter the following address:
http://223.254.254.244/til/index.html
IMPORTANT: This URL field will be use for CCM-U
coming from factory only.
In case of re-use CCM-U from field customer, a
specific Node B IP address is required to enter into
the URL field:
http://<Node B IP Address>/til/index.html
4 Press Return
NOTE: During Java Applet downloading, a progress
bar isNode
26 | Distributed displayed.
B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 3: TIL Connection (continued)

TIL Connection Procedure (Continued)


Step Action
5 When the Java Applet is completely downloaded and
if not already filled.
• Enter your User Name.
• Enter your Default Path (the directory where the
results will be saved).
6 Click Start on the TIL Applet
NOTE: During TIL manager and test server
connection, a message is displayed.
7 In the Security window
• Enter the Login: nodeb
• Enter the Password: Nodeblnx
IMPORTANT:
The Login nodeb and the password nodeblnx will be
used during the TIL connection on the CCM-U not
built.
IMPORTANT:
During the TIL connection, a new Login and a new
Password could be required by the customer after
build the node B.
NOTE: to change the Login and Password can be
found in the manual Alcatel-Lucent 9353 Wireless
Management System -Security Fundamentals (refer
to the reference section)
8 Click OK
NOTE: At the end of the connection, the TIL board
27 | eModules migration
Distributed | Sept 2011 | July 2014
Node B Commissioning All Rights Reserved © Alcatel-Lucent 2006
screen is displayed.
Node B commissioning – Proc 3: TIL Connection (continued)

Example of TIL GUI for d2U

28 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 5: Node B Software Downloading
Description:
This procedure describes how to download the software into the Node B.
Preconditions:
The upgrade of Node B will be done from one software release to the current network release in local mode
(direct connection between the laptop up to the CCM-U board).
To use the hard disk of the PC as the source of the upgrade, the Node B software delivery components must be previously
installed on the PC
The Laptop Setting and TIL connections are already done and available.
Node B Software Downloading Procedure
Step Action
1 In the TIL GUI:
Go to Tools menu
2 Select Software Upgrade
3 Select New Software Download
4 In the Choose a delivery file dialog box:
Check that the name of the folder is the same as the
current network Node B release to download.
5 Double Click on the folder UN…
6 Select the File named FILE0_<Version>.
7 Click Choose a delivery file
NOTE: The software downloading starts and a
progress bar is displayed on the screen.

29 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 5: Node B Software Downloading (Continued)

Node B Software Downloading Procedure (Continued)


Step Action
8 Wait while the 2 steps are automatically performed:
• Step 1: Each file is transferred from the PC to the CCM-U board.
• Step 2: Files are transferred from the CCM-U to the others boards.

NOTE: The transfer files takes around:


• 6 mn for step 1.
• 4 mn for step 2.

NOTE: On the front panel of the CCM-U the lower rectangle LED is
blinking.
At the end of the download, a success message is displayed.
9 Click OK

30 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 6: New Node B Release Activation
Description:
This procedure describes how to activate the new software on the Node B.
Preconditions:
The laptop setting and TIL connections are already done and available.
The Node B software downloading is already perform

New Node B Release Activation Procedure

Step Action
1 In the TIL GUI:
Go to Tools menu
2 Select Software Upgrade
3 Select Activation and iBTS reset
4 Click OK to confirm the reset
5 Click OK to close the last screen
6 Close imperatively the WEB browser in order to take
into account the new TIL JAVA Applet
7 Wait while the Node B Startup
NOTE: The Node B startup takes:
• Around 3min for CCM-U
• Around 4min for other boards
8 Apply specific requirement after the Node B release
activation

31 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 6: New Node B Release Activation (Continue)

Latest Software release Verification Procedure


Step Action
1 Re-start the Web browser.
2 Re-start the TIL Applet
3 Verify that the TIL GUI shows the correct Node B
configuration and the latest software release.
4 Check the Distributed Node B Software reference
Version used, which is displayed at the bottom of
the TIL GUI.

5 End of this procedure

32 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 7: Node B Configuration Checks Procedure
Description:
This procedure describes how to check the Node B operational condition prior to start commissioning.
• Check MCA Status…
Node B Configuration Checks Procedure
• Check Hybrid Iub (HIUB)
• Check Node B Alarm Status Step Action
• Check GPSAM Status 1 In the TIL GUI:
• Check RRH Alarm Status Check the MS (MCA status) LED displayed on GPSAM
Preconditions: board
The TIL must be already connected to the CCM-U 2 Check that the information contained in the TIL
The software must be at the right version board's GUI complies with the Node B configuration:
• Check the Software Reference
• Check the Node B type
• Verify that the Serial Number is the same as the
Serial Number given by the packing list (refer to
planning part).
NOTE: If abnormal check occurred, contact the site
coordinator before going on.
3 Check that for Hybrid IuB configuration a maximum of
4 PCM lines is in active status by checking the HIUB
label must be in Green.
4 Check all Boards Alarms condition that there is no
alarm.
Check with label AL (Alarm) that no board appears in
alarms (RED color).
NOTE: To troubleshoot alarms check the Alcatel-
Lucent Node B Commissioning and Fault
Management User Manual: TIL (refer to references
section) and/or contact the support team.
33 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 7: Node B Configuration Checks Procedure (continue)

NOTE: To troubleshoot alarms check the Alcatel-Lucent


Node B Configuration Checks Procedure (Continued) Node B Commissioning and Fault Management User
Manual: TIL (refer to references section) and/or contact
Step Action the support team.
5 Check GPSAM Alarms condition that there is no
alarm.
Right click on the GPSAM board and select Alarms to
open the Alarm status.
Exception: expected alarms on GPSAM board are
allowed.
• User alarm
• Door contact alarm

6 Check RRH Alarms condition that there is no alarm.


On the GUI xCOB:
• Right click on the OIx GUI connected with the RRH
select RRH alarms.

7 In the Pop-up menu of RRH view


• Right click on the RRH and select Alarms to check
that no RRH appears in alarms (RED color).

8 In the Pop-up menu of RRH view,


Right click on the GUI to select Return to main GUI

34 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 7: Node B Configuration Checks Procedure (continue)

Execute procedure as per table below to save the I&C parameters to the default path.

Procedure to save the I&C Parameters


Step Action
1 In the TIL GUI:
Go to the I&C Menu
Select Save I&C parameters

2 In the File_name field of the dialog box


Type the name of the file where the old I&C parameter will be saved.
NOTE: This name must be equal to:
old_<NeId>.til with NeId=Serial Number of the Node B.

3 This command save the default configuration data before commissioning Node B.
Click Save.
NOTE: The file will be saved in
<Default path>/BTS@223.254.254.244/Icparam folder.
The <Default path> is the path defined during TIL launching.
NOTE: In case of problem, go back to this file in order to restore the default parameters.

35 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 8: Node B Setting BTS Parameters
Description:
This procedure describes how to set BTS parameters with the TIL:
• BTS Packaging
• Fallback to previous I&C data
• GPS Synchronization
Preconditions:
The laptop setting and TIL connections are already done and available.
The form of parameters based on the CIQ must be documented and available according to the expected configuration.
(refer to form parameters table from commissioning planning section)
The selection of the BTS Packaging parameter must be agreed with the coordinator to get the expected configuration.
(refer to BTS Packaging table from commissioning planning section)

Node B Setting BTS Parameters Procedure

Step Action
1 In the TIL GUI:
Go to I&C menu
2 Select Change I&C parameters
3 Select BTS
Note: with d4U only, on the TIL GUI / BTS an additional parameters appears above
the BTS Packaging parameter : BTS mode (Feature: d4U in Dual Mode)
 Select SingleMode for d4U in single mode with only one CCM-U used or
 Select SplitMode for d4U in dual mode with two CCM-U used (for 2 Node B in d4U)
For more information refer to IEH521 Section 705 Single to Dual Node B Migration
Procedures. (and an additional sheet 2NodeBs appears on the left of I&C parameters
TIL GUI for CEM-U allocation)

36 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 8: Node B Setting BTS Parameters (Continued)
Node B Setting BTS Parameters Procedure (Continued)

Step Action
4 For BTS Packaging
• Select the drop-down menu of the BTS packaging
according to the Node B configuration on field.

5 For Fallback to previous I&C data


• Select the drop-down menu of the Fallback to
previous I&C data

6 For GPS Synchronization if used


• Select the drop-down menu of the GPS
Synchronization.
7 Press the Send to BTS button only after completion
of all parameters setting in all relevant tabs.

37 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 9: Node B Setting RRH Parameters
Description:
This procedure describes how to set RRH parameters with the TIL
Preconditions:
The form of parameters based on the CIQ must be documented and available according to the expected configuration.
(refer to form parameters table from commissioning planning section)
The laptop setting and TIL connections are already done and available.
• Use case with RRH (Optical CPRI Link)
• Use case with TRDU (Electrical CPRI Link)

Node B Setting RRH Parameters Procedure


Step Action
1 In the TIL GUI:
Go to I&C menu
2 Select Change I&C parameters
3 Select RRH
4 For RRH Type:
• Select the drop-down menu of the RRH type.
NOTE: The default parameter value is CPRI
(1,2,3,4,5,6)
5 Press the Send to BTS button only after completion
of all parameters setting in all relevant tabs.

38 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 10: Node B Setting Backhaul Parameters
Description:
This procedure describes how to set Backhaul parameters with the TIL :
• Use case of ATM Iub network (ATM only)
• Use case of Hybrid Iub network (IP + ATM simultaneous)
• Use case of Iub over IP network (IP only)
Preconditions:
The laptop setting and TIL connections are already done and available.
The form of parameters based on the CIQ must be documented and available according to the expected configuration.
(refer to form parameters table from commissioning planning section)
The CCM-U must be equipped with the following daughter board according the network used:

Node B Setting Backhaul


Parameters Procedure
Step Action
1 In the TIL GUI:
Go to I&C menu
2 Select Change I&C parameters
3 Select BACKHAUL

39 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 10: Node B Setting Backhaul Parameters (continued)

Node B Setting Backhaul Parameters Procedure (Continued)


Step Action
4 For Type of Incoming Link:
• Select the drop-down menu of the Type of Incoming
Link.

NOTE:
Depending of the CCM-U board configuration and Transport
type select the correct value for “TYPE OF INCOMING LINK”.
-- For ATM Iub
-select E1/T1
-- For NIP IuB with optical fiber
- connect on ports 3 or 4 select STM
-- For NIP Iub without MDA GE
-connect on port 2 select Fast Ethernet
-- For NIP Iub with MDA GE
5 Press the Send to BTS button only after completion
of all parameters setting in all relevant tabs. -connect on port 5 select Gigabit Ethernet

40 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 11: Node B Setting PCM E1 Parameters
Description:
This procedure describes how to set PCM E1 parameters with the TIL.
This procedure applies in case of :
• The PCM protection module is present if necessary.
• The E1 PCM parameters of the site are different from the factory default parameters.
Preconditions:
The laptop setting and TIL connections are already done and available.
The form of parameters based on the CIQ must be documented and available according to the expected configuration.
(refer to form parameters table from commissioning planning section)
The following table shows the E1 factory default parameters:
NOTE: (1) Must not be modified.

Node B Setting PCM E1 Parameters


Procedure
Step Action
1 In the TIL GUI:
Go to I&C menu
2 Select Change I&C parameters
3 Select PCM

41 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 11: Node B Setting PCM E1 Parameters (continued)

Node B Setting PCM E1 Parameters Procedure (Continued)

Step Action
4 For PCM type:

5 For E1 Adaptation:

6 For PCM E1 frame:

42 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 11: Node B Setting PCM E1 Parameters (continued)

Node B Setting PCM E1 Parameters Procedure (Continued)


Step Action
7 For PCM receive sensitivity:
Select the default value

8 For E1 PCM CRC threshold:


Enter the value 915 if not already done
Step Action
Procedure if PCM Protection Module used 1 For Protection module: (If PCM protection module is
present)
Execute procedure as per table below if
PCM protection module used

2 Press the Send to BTS button only after completion of all


parameters setting in all relevant tabs.
43 | eModules migration | Sept 2011

43 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 12: Node B Setting PCM T1 Parameters
Description:
This procedure describes how to set PCM T1 parameters with the TIL.
This procedure applies in case of :
• The PCM protection module is present.
• The T1 PCM parameters of the site are different from the factory default parameters.

Preconditions:
The laptop setting and TIL connections are already done and available.
The form of parameters based on the CIQ must be documented and available according to the expected configuration.
(refer to form parameters table from commissioning planning section)
The following table shows the T1 factory default parameters:
NOTE: (1) Must not be modified.

Node B Setting PCM T1 Parameters


Procedure
Step Action
1 In the TIL GUI:
Go to I&C menu
2 Select Change I&C parameters
3 Select PCM

44 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 12: Node B Setting PCM T1 Parameters (continued)

Node B Setting PCM T1 Parameters Procedure (Continued)

Step Action
4 For PCM type:

5 For PCM T1 frame:


Select the frame profile Extended super frame
6 For PCM coding:
Select the coding profile B8ZS
7 For LBO:
Select the default value

8 Click Validate on the LBO view

45 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 12: Node B Setting PCM T1 Parameters (continued)

Node B Setting PCM T1 Parameters Procedure (Continued)

Step Action
9 For PCM receive CRC:
Select the default value

10 For PCM receive sensitivity:


Select the default value

11 For PCM CRC threshold:


Enter the value 320 if not already done

46 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 12: Node B Setting PCM T1 Parameters (continued)

Step Action
Procedure if PCM Protection Module used 1 For Protection module: (If PCM protection module is
present)
Execute procedure as per table below if
PCM protection module used

2 Press the Send to BTS button only after completion of all


parameters setting in all relevant tabs.
47 | eModules migration | Sept 2011

47 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 13: Node B Setting PCM&IMA Parameters
Description:
This procedure describes how to set PCM&IMA parameters with the TIL.
This procedure applies in case of ATM Iub or Hybrid Iub with:
• IMA Configuration or
• Drop and insert configuration.
• PCM carrying OAM link value is different from 1

Preconditions:
The laptop setting and TIL connections are already done and available.
The form of parameters based on the CIQ must be documented and available according to the expected configuration.
(refer to form parameters table from commissioning planning section)

Node B Setting PCM&IMA Parameters Procedure

Step Action
1 In the TIL GUI:
Go to I&C menu
2 Select Change I&C parameters
3 Select PCM&IMA
4 For IMA usage parameter:

Note: when IuB is over IP the parameter “IMA Usage” is


set to Standard
5 Press the Send to BTS button only after completion of
all parameters setting in all relevant tabs.

48 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 13: Node B Setting PCM&IMA Parameters (Continued)

Procedure If IMA Configuration used

Step Action
1 If the IMA Parameters are already displayed: (for IMA
Configuration)
Do not change the parameter value
2 For PCM with OAM link/Synchro in NIP parameter: (for
IMA Configuration)
Do not change the parameter value

3 For IMA Version parameter: (for IMA Configuration)


Do not change the parameter value
4 Press the Send to BTS button only after completion of
all parameters setting in all relevant tabs.

49 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 13: Node B Setting PCM&IMA Parameters (Continued)

Procedure If Drop & Insert Configuration used

Step Action
1 For Drop & Insert Configuration
In Mask of PCM timeslots used:
• Type the hexadecimal value in the rectangular box or
• Click inside the box to select the Time Slot (TS).

Details explanation: The hexadecimal value is getting


reflected by the graphic representative TS boxes.

NOTE: TS status can be changed individually by single


clicking the TS box. Status changed will be reflected by
the color change.
2 Press the Send to BTS button only after completion of
all parameters setting in all relevant tabs.

50 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 14: Node B Setting Ethernet Parameters
Description:
This procedure describes how to set Ethernet parameters with the TIL
Preconditions:
The laptop setting and TIL connections are already done and available.
The Backhaul Parameters must be already set.
• Use case of Hybrid Iub network (IP + ATM simultaneous)
• Use case of Iub over IP network (IP only)
The form of parameters based on the CIQ must be documented and available according to the expected configuration.
(refer to form parameters table from commissioning planning section)
Node B Setting Ethernet Parameters Procedure
Step Action
1 In the TIL GUI:
Go to I&C menu
2 Select Change I&C parameters
3 Select Ethernet

4 For VLAN ID:


Set OAM VLAN ID to the value provided by CIQ if Iub is
over IP
5 For VLAN TAGGING:
Set VLAN TAGGING to “Enabled” if Iub is over IP
If Iub over IP not used do not change the parameter
value
51 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 14: Node B Setting Ethernet Parameters (Continued)

Node B Setting Ethernet Parameters Procedure (continued)


Step Action
6 For LAG/HUBBING:
Keep the parameter value at No LAG and Hubbing
7 For Eth Port used for IF:
• Select the drop-down menu of the Eth Port used for IF.

8 For Eth Port used for Hubbing:


Do not Change the parameter value
9 Press the Send to BTS button only after completion of all
parameters setting in all relevant tabs.

Set “Eth Port used for iub IF” to :


- MotherBoard RJ45 if Iub is over IP and no MDA GE is available
- MDA RJ45 or MDA SFP1 or MDA SFP2 if Iub is over IP and MDA GE is available

52 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 14: Node B Setting Ethernet Parameters (Continued)

Node B Setting Ethernet Parameters Procedure (If CCM-U used with GE MDA)
Step Action
1 For VLAN ID: (If CCM-U used with GE MDA)
Keep the parameter value at 1
2 For VLAN TAGGING: (If CCM-U used with GE MDA)
Do not change the parameter value
3 For LAG/HUBBING: (If CCM-U used with GE MDA)
Select the parameter value at 0
4 For Eth Port used for IF: (If CCM-U used with GE MDA)
Select the parameter value at 4
5 For Eth Port used for Hubbing: (If CCM-U used with GE MDA)
Select the parameter value at 8
6 Press the Send to BTS button only after completion of all parameters setting in
all relevant tabs.

53 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 15: Node B Setting ATM Parameters
Description:
This procedure describes how to set ATM parameters with the TIL if necessary
Preconditions:
The laptop setting and TIL connections are already done and available.
• Use case of Hybrid Iub network (IP + ATM simultaneous)
• Use case of full ATM Iub network (ATM only)
The form of parameters based on the CIQ must be documented and available according to the expected configuration.
(refer to form parameters table from commissioning planning section)

Node B Setting ATM Parameters Procedure


Step Action
1 In the TIL GUI:
Go to I&C menu
2 Select Change I&C parameters
3 Select ATM Parameters
4 Type the OMC-B VP identifier parameter value
according to the customer information CIQ
(example here: 1)
5 Type the OMC-B VC identifier parameter value
according to the customer information CIQ
(example here: 32)
6 Do not change all other parameters values.
7 Press the Send to BTS button only after completion
of all parameters setting in all relevant tabs.

54 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 16: Node B Setting IP Parameters
Description:
This procedure describes how to modify the IP Address parameters with the TIL.
This procedure applies in case the IP network is not equipped with a DHCP server.
Preconditions: Node B Setting IP Parameters Procedure
The laptop setting and TIL connections are already done
and available. Step Action
• Use case of Hybrid Iub network (IP + ATM simultaneous) 1 In the TIL GUI:
• Use case of Iub over IP network (IP only) Go to I&C menu
The form of parameters based on the CIQ must be documented 2 Select Change I&C parameters
and available according to the expected configuration.
3 Select IP Parameters
(refer to form parameters table from commissioning
planning section) 4 For the Existence of a DHCP server
Select No
5 For the BTS IP Address
Type the BTS IP Address coming from the CIQ
6 For the OMC-B IP Address
Type the OMC-B IP Address coming from the CIQ
7 For the Sub-network mask
Type the Sub-network mask IP Address coming from
the CIQ
8 Do not change the other parameters value of:
• the OMC-B port
• the BTS port
• the Default Gateway IP Address
Note : “Default Gateway Ip Address” will be
available only if the Backhaul is IP.
9 Press the Send to BTS button only after completion
55 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
of all parameters setting in all relevant tabs.
Node B commissioning – Proc 17: Node B NeID Exchange (If Necessary)
Description:
This procedure describes how to retrieve and change the BTS NeID (Serial number) with the TIL.
The BTS NeID is locally stored from factory into the RUC memory of the Node B.
Preconditions:
The laptop setting and TIL connections are already done and available.
The Web browser is started with in the URL field the BTS IP@ according to :
>http://BTS IP@/til/index.html
The serial Number of the Node B must be available on the frame NeID label.
The form of parameters based on the CIQ must be documented and available according to the expected configuration.
(refer to form parameters table from commissioning planning section)
Node B NeID Exchange Procedure
Step Action
1 In the main TIL GUI:
Check the SerialNumber which is displayed on the bottom
of the page.
2 In the TIL GUI:
Go to I&C menu
3 Select
Change I&C
parameters
4 Select BTS
5 For Serial Number:
Type the right NeID number
NOTE: The NeID (= Serial Number) must be unique in the
same network and different from 012345.
6 56 | eModules
Press the |Send
migration Sept 2011to |BTS button only after completion of all
All Rights Reserved © Alcatel-Lucent 2006
56 | Distributed Node B Commissioning July 2014
parameters setting in all relevant tabs.
Node B commissioning – Proc 18: Sending I&C Parameters to the Node B
Description:
This procedure describes how to send the I&C parameters to the CCM-U board in order to update the MCA Module with the
TIL
Preconditions:
The laptop setting and TIL connections are already done and available.
All I&C parameters have been already correctly set with the previous procedures using the TIL
Sending I&C Parameters to Node B Procedure
Step Action
1 In the TIL GUI: Go to I&C menu
2 Select Change I&C parameters
3 Select BTS
4 For Fallback to previous I&C data: Select Deactivate
5 Click Send to BTS
NOTE: During MCA update, a message is displayed
6 Approximately 15 seconds after, a success message is displayed,
Click OK

DO NOT Reset BTS Equipment after changing the TIL parameters.


57 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Lets the activation to be performed during the integration.
Node B commissioning – Proc 19: Node B reset in Connected Mode
Description:
This procedure describes how to reset the Node B in connected mode with the TIL NOTE:
This procedure applies when at least one of I&C parameters has been modified. Reset in stand alone mode if the
BTS is not connected to WMS or
Preconditions:
Reset in connected mode if it is
The laptop setting and TIL connections are already done and available.
connected to WMS.
At least one of I&C parameters has been modified.
Node B reset in Connected Mode Procedure
Step Action
1 In the TIL GUI: Go to Tools menu
2 Select BTS reset
3 Select Reset in connected mode
4 Click OK in the Confirm the reset window
5 Click OK in the End of reset window
6 Wait while Node B Startup
NOTE: Node B Startup takes:
• Around 3mn for CCM-U
• Around 4mn for other board
7 Check that no card appears in alarm.
NOTE: All LEDs on each module should be green, except for
MCAs (MCA not configured).
8 In the TIL GUI: Go to Connection menu
9 Select Connect to BTS
10 Check if the Node B is now Connected to OMC-B.
58 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 20: I&C Parameters Verification
Description:
This procedure describes how to verify if the new I&C parameters are correctly saved in the MCA module with the TIL
Preconditions:
The laptop setting and TIL connections are already done and available.

I&C Parameters Verification Procedure


Step Action
1 In the TIL GUI: to verify that the TIL used is correct:
Check the CCM-U Iub network configuration:
• ATM or
• Iub over IP or
• Hybrid Iub
2 Check that the Software reference corresponds to an expected
SW Version. (ex: UA08.x or LR13.x…)
3 Check that the iBTS packaging corresponds to the site
configuration
4 Check that the Node B TIL GUI is
• Not connected to OMC-B and
• Config. file not found
5 In the TIL GUI: Go to I&C menu
6 Select Save I&C parameters

59 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 20: I&C Parameters Verification (Continued)

I&C Parameters Verification Procedure (Continued)


Step Action
7 In the File-name field of the dialog box:
Type the name of the file where the new I&C parameters will be
saved.
NOTE: This name must be equal to new_<NeId>.til with
NeId=Serial number of the Node B.
8 Click Save
NOTE: The file will be saved in:
<Default path>/BTS@223.254.254.244/Icparam folder.
The <Default path> is the path defined during TIL launching.
9 Open the file new_<NeId>.til
10 Verify the I&C parameters you have entered comply with those of
the report sheet.

60 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 21: MCA Backup File
Description:
This procedure describes how to create a MCA backup file with the TIL
This backup file must be stored on a customer server and will be reused exclusively in case of maintenance action with a
double fault (MCA and CCM-U failures).
Handover of the MCA backup file to the customer is coordinated by the TPM.
Preconditions:
The laptop setting and TIL connections are already done and available.
The I&C parameters verification must be completed.
MCA Backup File Procedure
Step Action
1 In the TIL GUI: Go to I&C menu
2 Select MCA recovery tools
3 In the MCA recovery tools dialog box:
• Select Prepare MCA file on CCM Board
• Click OK
4 At the end of the operation, a success message is displayed
concerning MCA file creation

• Click OK

61 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning – Proc 21: MCA Backup File (continued)

MCA Backup File Procedure (continued)


Step Action
5 In the MCA recovery tools dialog box:
• Select Save MCA file on local disk
• Click OK
6 At the end of the operation, a success message is displayed
concerning Save MCA file on local disk

• Click OK

7 Open the MCABackup folder present on your default path to


verify if MCA backup file exists.

NOTE: The number given in the file name must be the same as
the serial number (NEid) of the Node B.

NOTE: The default path is <Default


path>/BTS@223.254.254.244.
The <Default path> is the path defined during TIL launching.
8 Send by email the MCA backup file to the coordinator TPM.

=> The Node B is ready for integration


62 | Distributed Node B Commissioning | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Distributed Node B
Commissioning Testing

All Rights Reserved © Alcatel-Lucent 2006


Node B commissioning Testing – Proc 22: IP Ping Test
Description:
This procedure describes how to test the IP Link with the TIL
This test is not mandatory and is only applicable with an IP Network configuration (Hybrid Iub or Iub over IP)
Preconditions:
• The laptop setting and TIL connections are already done and available.
• The IP link (Hybrid Iub or Iub over IP) is physically connected on both sites.
• The IP address of the OMC-B.
MCA Backup File Procedure
Step Action
1 In the TIL GUI: Go to Tools menu
2 Choose IP Ping
3 In the IP Ping menu
Check the IP Address
to test

4 Click on Ping

5 A IP Ping Process window appears


Click OK
6 A IP Ping test result
window appears
Check that the test
result indicate
in the last IP Ping
Result: is Reachable
64 | Distributed Node B Commissioning Testing | July 2014 All Rights Reserved © Alcatel-Lucent 2006
Node B commissioning Testing – Proc 23: Final Commissioning Operations
Description:
This procedure describes how to perform final commissioning operations
Preconditions:
The laptop setting and TIL connections are already done and available.
The Node B has been reset in connected mode
The tests are successfully
Final Commissioning Operations Procedure
Step Action
1 Close the Web browser
2 Remove the cable between Port 1 of the CCM-U and the laptop
3 Finish filling out the report sheet available in the Commissioning
Test Records section 399
NOTE: All non-compliance cases have to be physically spotted on
site and described
4 Leave one copy of the report sheet on site and send one to the
coordinator.
5 Refer to the coordinator for any corrective action.
6 Clean the site
7 Now the Node B commissioning is finish and this Node B is ready to => The NodeB is ready to be
be integrated in an existing UTRAN, according to the UTRAN
version used and following the Integration Procedure IEH521 or : integrated in an existing
Alcatel-Lucent Node B UA08.1 Integration in an existing UTRAN UTRAN

65 | Distributed Node B Commissioning Testing | July 2014 All Rights Reserved © Alcatel-Lucent 2006
www.alcatel-lucent.com

66 | eModules migration | Sept 2011 All Rights Reserved © Alcatel-Lucent 2006