Vous êtes sur la page 1sur 3

Back to Basics

F rom Materials Evaluation, Vol. 66, No. 5, pp: 462-464.


Copyright © 2008 The American Society for Nondestructive Testing, Inc.

Fabrication of Flawed Blocks for Ultrasonic


Testing in Lieu of Radiographic Testing
by Ronald Kruzic*

This paper discusses a methodology and their size, orientation and location can
C o n s t ruction codes and stan- that can be used to construct flawed welds be determined, a number of factors must
dards sometimes, with restrictions, to be utilized for these purposes if accept- be decided upon:
permit substituting ultrasonic test- able to the parties involved. ■ the ultrasonic technique(s) used: pulse
ing for radiographic testing. This /echo, time of flight diffraction, phased
“Back to Basics” article paper dis- array and so on
■ whether or not the block can be flipped
cusses re q u i rements for creating
flawed welds to be used for such ul-
trasonic testing. The minimum
It is suggested that during the qualification process (the need
for similar weld details in both the inner
and outer diameter, and the presence of
number of flaws, and their types, lo- weight be given to the cladding or overlays present)
cations and sizes, are discussed,
along with concepts important in more critical points such ■ the number of individual setups (zones)
fabricating a flawed block standard. necessary for complete coverage of the re-
as sizing, categorization quired examination volume.
For example, suppose it were deter-
and grouping calls. mined that for a particular weld it was nec-
essary to utilize four time of flight diffrac-
tion setups to provide adequate coverage of
the examination volume, and a weld over-
David S. Kupperman lay was involved so that the block could not
Associate Technical Editor be flipped. Per code, a minimum of three
flaws are required, but in this case the mini-
Initial Considerations mum would be four, as at least one flaw per
For either an ASME procedure demon- zone should be considered as the new mini-
stration or API operator practical examina- mum. See Figure 1 for an example.
Background tion qualification, the same basic initial in- For an API based examination, the
any of today’s construction codes formation is required to be accumulated: minimum number of flaws is not speci-

M and standards allow for the substi-


tution of ultrasonic testing (UT) for
radiographic testing (RT) as long as certain
namely, base material and its heat tre a t-
ment, thicknesses, welding processes and
joint details. Since the ASME (pro c e d u re
fied in the Appendix. The testing pro-
gram details must be by agreement with
the purchaser. It is felt that a minimum of
conditions are met. For example, Sections I based) and API (practical based) qualifica- 10 flaws should be considered. This could
and VIII of the ASME Boiler and Pressure tions are so different, they will largely be yield a reasonable number of flaws, both
Vessel Code (2006), including Code Case discussed separately. individual and grouped, so as to create an
2235-9, allow the substitution of UT for RT For an ASME based examination, before adequate grading scheme for the opera-
if the procedure is demonstrated on a qual- the decision as to the exact number of flaws tors (Figure 2).
i fication block as being able to detect dis-
continuities that are of an acceptable size for
the thickness involved, and have an indicat-
ed length equal to or greater than the actual
length (that is, discontinuities significant
enough to be considered flaws). Under Ap-
pendix U of the API 620 (2008) and API 650
(2007) standards, the substitution is allowed
if the operators pass a practical examina-
tion for UT on a blind test plate that in-
cludes having operators testing elements
that are contained in the Appendix.

* Chicago Bridge and Iron Company, 14105


South Route 59, Plainfield, IL 60544; (815) 439-
6000; fax (815) 439-6006; e-mail <rkruzic@cbi
.com>. Figure 1 — Minimum flaws for four-zone testing.

462 Materials Evaluation/May 2008


Figure 2 — Ten flaw layout example.

The ten flaws in Figure 2 would not separation distance from the nearest sur- Block Creation
only allow for 10 individual location, sizing face is less than or equal to one-half its Once the number, categorization, size, ori-
(length and height) and categorization depth for ASME or less than one-half its entation and locations of the EDM slits have
(surface or subsurface) calls, but also three height for API; a subsurface flaw is one been determined, then it becomes a matter of
grouping calls (flaws 1 and 2, 4 and 5, and 8 whose separation distance from the near- creating the flawed block. Amethodology for
and 9), for a total of 56 grading points (note est surface is greater than one-half its this is to first partially weld together two
that a flaw need not be surface-breaking to depth for ASME or equal to or gre a t e r plates with the same joint details and filler
be categorized as a surface flaw). Another than one-half its height for API.) See Fig- metal to be utilized in production. The plate
grading point could be the surface break- ure 3 for examples. material shall meet the same requirements as
ing confirming magnetic particle/liquid ■ API requires the test plates to have not that for a UT calibration block per Section V,
penetrant testing (MT/PT), thus upping only both surface and subsurface flaws, but Article 4, T-434 of the ASME Boiler and Pres-
the potential points to 66. It is suggested have both acceptable and unacceptable sure Vessel Code. Portions of the weld are left
that weight be given to the more critical flaws. They also must include groupings of uncompleted (underfilled) for the EDM slits
points such as sizing, categorization and flaws. The weld flaws should probably also to be embedded, and the remaining areas
grouping calls. See Table 1 for an example have the slits orientated in the same fash- completed for EDM slits that are to be left
of a possible scheme with weight factors. ion as ASME’s, though this is not so stated open to the surface (Figure 4).
Also needed to be factored in would be any in the Appendix. For the weld embedded flaws, their
miscalls or false calls made by the operators. final desired depth (in ASME’s language)
or height (in API’s) must be increased by
Table 1 Number of calls in possible the amount of weld penetration expected
grading scheme when the unwelded portions are complet-
ed during the selected embedding welding
Location 10 process (by depth or height, the texts refer
Size to the through-wall flaw dimension, drawn
Length 10 × 2* = 20 normal to the inside pressure retaining sur-
Height 10 × 2* = 20
face of the component). Then a machinist
Categorization† 10 × 2 = 20
Grouping 3 × 2* = 6 burns the notches and the incomplete por-
Accept/Reject 13‡ tions of the weld are completed (Figure 5).
MT/PT 10 A radiograph is recommended to further
Total 99 document the flaw locations as well as to
identify any flaws that may have been un-
* weight factor intentionally introduced during welding.
† surface/subsurface The last thing required is to decide what
‡ 10 individual and 3 grouping calls is the flaw size to be utilized for the proce-
dure demonstration or operator practical ex-
aminations for the newly embedded flaws.
Suggested Flaw Type Figure 3 — Flaw/joint examples. Three sides of the EDM slit are normally un-
Since these flawed welds are for new
construction codes and standards and not
for inservice or fitness-for-purpose type ex-
aminations for specific service-induced
flaws or failure mechanisms, and to keep
the costs involved in block fabrication to a
reasonable level, it is felt that electric dis-
charge machined (EDM) slits are a reason-
able choice and would be representative of
the more critical planar type flaws (that is,
cracks and nonfusion).
Additional details concerning the flaws
must be considered:
■ ASME requires that the demonstration
weld’s flaws be oriented to simulate flaws
parallel to the production weld’s fusion
line. One surface flaw per surface (inner
and outer diameter) and one subsurface
flaw are the minimum called for. (A s u r- Figure 4 — Joint pre-welding example.
face flaw is defined here as a flaw whose

Materials Evaluation/May 2008 4 6 3


affected by the embedding process; there-
fore, its length is accurately known and
only the depth (or height) to be used
needs to be decided upon. If it is agreed
that the expected amount of penetration
can be utilized, then the original desired
flaw depth (height) can be utilized plus
this amount added. If it is decided that
the amount of penetration must be deter-
mined, this means testing it with ultra-
sonic techniques that have been pro v e n
successful at doing so. Figure 6 illustrates
an estimated penetration example.

Conclusion
Whether the aforementioned method-
Figure 5 — EDM slits. ology is utilized for flawed block fabrica-
tion or other schemes, it is highly re c o m-
mended, due to the cost and fabrication
time, to always first come to a agreement
with the user or purchaser as to not only
the block fabrication scheme, but also the
number, size and locations of the flaws
prior to fabrication.

References
API, API 620: Design and Construction of Large,
Welded, Low-Pre s s u re Storage Ta n k s, 11th edi-
tion, Washington, DC, American Petro l e u m
Institute, 2008.
API, API 650: Welded Steel Tanks for Oil Storage,
11th edition, Washington, DC, American Pe-
troleum Institute, 2007.
ASME, ASME Boiler and Pre s s u re Vessel Code,
New York, American Society of Mechanical
Engineers, 2007.

Figure 6 — Estimated penetration example.

464 Materials Evaluation/May 2008

Vous aimerez peut-être aussi