Académique Documents
Professionnel Documents
Culture Documents
The author / owner of this This document has been approved Date of Issue: Review
document is: for Issue by: Date:
1 INTRODUCTION
2 GENERAL.
3 VOLTAGE CONDITIONS ON LOW VOLTAGE BUNCHED WAVECON
CONNECTIONS
4 SIZES AND RATINGS
5 INSTALLATION
6 BWC PROTECTION REQUIREMENTS
7 BWC EARTHING REQUIREMENTS
8 METERING
9 CUSTOMER’ EQUIPMENT
10 ASSOCIATED DOCUMENTS
11 APPLICABLE STANDARDS
1 INTRODUCTION
1.1 This procedure details the processes to be followed when installing services to
customers being supplied at Low Voltage using single core bunched Wavecon
cables (BWC) for connections on to Scottish and Southern Energy Power
Distribution’s (SSEPD) network.
1.2 A copy of this procedure is available to prospective developers and consultants
to insure that a suitable access for SSEPD supply cables and metering
equipment is agreed at an early stage. The meter position should be on an
outside wall and preferably within 15 metres of the substation. Any other
arrangement must be agreed in detail by SSEPD.
1.3 A 1500kVA transformer can only supply a single customers. 1000kVA and
below can supply multiple customers.
1.4 The use of transformers with ratings greater than 1500kVA must be agreed
with SSEPD.
2 GENERAL.
2.1 For transformer supplying a single load 185 mm² 3 core bunched Wavecon
cable will be used on all installations with the exception of 1500kVA
transformers where 300 mm² bunched Wavecon cable will only be used. Where
two supplies are fed from the same transformer the number and size of the
Wavecon cables will be dictated by the load requirement of each circuit.
2.2 Detail of approved plant is given in The Plant Catalogue, TG-PS-148 and
substation design in TG-PS-883, Information to Assist Third Parties in the
Design and Installation of New Secondary Substations for Adoption for Use by
SSEPD. The unit substation can be fitted with either an oil-filled ring main unit
or an SF6/vacuum ring main unit.
2.3 Transformers are currently purchased with the ratings; 315, 500, 800, 1000 and
1500 kVA. A winter cyclic rating of up to 30% can be accommodated on the
transformers when situated outdoors. The maximum size transformer which
can be used to feed multiple customers metered at LV is 1000 kVA. A single
customer can be supplied from a 1500kVA transformer. On transformers up to
and including 1000 kVA, 500A, fused, 3 core feeder ways can be used to
supply the network in addition to any 800A or larger feeder ways.
2.4 Transformer sizes greater than 1500 kVA shall be connected with busbar to the
customer’s intake.
2.5 Transformers will only be fitted with Low Voltage Cabinets fitted with MCCBs or
ACBs as appropriate. There may be some outgoing feeder ways where
appropriate.
4.3 Where a cyclic rating is applicable, the maximum load is in Winter and the load
curve is to Curve G, as shown in appendix 1, then the Winter cyclic rating can
be applied. For any other conditions of loading the Summer continuous rating
shall be applied unless otherwise agreed in writing with SSEPD.
5 Installation
5.1 Diagram 1 shows how the cables shall be installed to get the required rating.
In all cases the neutral cable/s must be installed close to a 3 phase bunch of
cables.
5.2 It is important that the cables are laid in tight trefoil formation bound together to
minimise the magnitude of magnetic field emitted from the cable. Cable routes
shall not be run through buildings and the customer's intake position should be
on an outside wall.
5.3 If the intake position is not on an outside wall and the customer insists that the
intake is within the building, then the customer must be warned that the
magnetic fields radiated by the cables may interfere with sensitive electronic
equipment placed close to the cables and that SSEPD will not accept any
liability for any consequences caused by the installation.
5.4 In such cases the cables will only be laid in cable trenches and never through
or under office floors.
5.5 To get the rating of the cables as shown in the table it is important that they are
direct buried. Short runs of ducts up to 10 metres are acceptable. If it is
necessary to install the cables in long runs of duct then these will have to be
Bentonite filled.
5.6 Cables installed in unfilled ducts longer than 10m must have a derating of 20%
applied to the figures in table 1. Separate ducts are required for each cable.
Ducts shall have a minimum internal diameter of 100mm and must be laid in
trefoil plus an extra duct for the neutral as shown in Fig. 1.
R 150 In Air R
Br 150 In Air
Br Br
Bl Gy N Gy Bl N Bl Gy
(see Table 2) with 150 mm spacing between the groups of cables. With free air
movement and an average ambient temperature of 15 °C or less they will not
be derated assuming normal spacing of the group. Cables cannot be installed
in situations where the ambient temperature is normally above 25 C.
BUNCHED WAVECON CLEATS
3 Core Wavecon No. Cables in Stock No. Ellis Patents
Cable Size Group Part No.
185 mm² 3 (Trefoil) 068683 VRT-07
185 mm² 4 (Quad) 068684 VRQ-06
300 mm² 3 (Trefoil) 068685 VRT-10
300 mm² 4 (Quad) 068686 VRQ-08
Table 2
5.8 BWC terminated in MCCB and ACB shall use the flexible connector as shown
in figure . For all other connections the fixed connector shall be used.
Diagram 2
5.9 The maximum length of BWC is 100 metres. This is a total length which
includes an allowance for terminations.
5.10 Route lengths shall be considered to have a maximum length of 90m.
Cable entry
slot
Outside Wall
LV Extension
Chamber
2000
mm
Cable Trench
1000 mm Wide
by 830 mm deep
Wall or Other
LV Extension
Switchgear Chamber
Mounting
2000
mm Cable Trench
1000 mm Wide
by 830 mm
Deep
Cable entry
45º
Diagram 3
7.5 Different sizes of earthwire can be employed however they must be suitably
rated to the PSCC and permit a temperature rise of 375 °C with an ambient
temperature of 30°C with a fault duration of 2 seconds.
7.6 These earth wires are connected to the transformer neutral earth bar and
should be used to provide the low voltage neutral earth electrode. To get the
desired value of resistance the copper conductors should be supplemented
with driven earth rods. Where there is a need to segregate the Hv and LV earth
electrodes the first 5m of earthwire from the transformer shall be pvc covered.
8 METERING
8.1 Metering measurement current transformers will comply with the Balancing and
Settlement Code of Practice 5 for transformers up to and including 1000kVA
and Code of Practice 3 for transformers above 1000kVA.
8.2 The metering CTs will be provided by either SSEPD (where SSEPD are
installing the BWC) or the Third Party installer (where SSEPD will adopt the
BWC).
8.3 Metering panels will comply with SP-PS-359, Specification outlining
Termination Arrangements for 3rd Party Connections to SSEPD Low Voltage
Cable Networks.
9 CUSTOMER’ EQUIPMENT
9.1 The BWC is to be terminated at the customers end in a purpose made housing
which is designed to accommodate SSEPD metering CTs. All installations shall
be earthed to the TN-S (separate neutral and earth) system. The following
arrangements are permitted:-
a) An adapter chamber is built under the customer's incomer switchgear as
shown on drawings HO/65/037 for terminating up to 2 cables per phase or
HO/65/081 for terminating up to 3 cables per phase.
b) Free standing termination cabinet built to stand along side the customer's
switchgear with busbar entry to the customer's gear at the top. Drawing
HO/65/083 shows the housing requirements and HO/65/084 details the
busbar requirements.
c) These drawings are typical and the customer can arrange to have any type of
unit constructed providing the dimensions and sizes where stated on the
drawings are met. The unit must be supplied with three potential protection
fuses and a link for CT metering. (Refer to table 3 for construction drawings
for details).
d) The ownership boundary shall be at the LV metering current transformer links
in the customer’s switchgear with SSEPD owning the links.
9.2 Drawing Fig. 2 details the minimum trench requirements at the customer's end.
Again dimensions shown shall not be reduced as this will cause difficulties for
the cable installation crew. Where the cable trench enters the building from the
outside and runs under the switchgear it shall be continued in front of the gear
for at least 2000 mm from the wall to the end of the trench.
9.3 It should be noted that where SSEPD will have an MCCB or an ACB and the
customer has an incoming MCCB or ACB then the customer shall ensure that
there is adequate discrimination between the customer's breaker and that of
SSEPD.
10 ASSOCIATED DOCUMENTS
The following are associated documents;
11 APPLICABLE STANDARDS
11.1 Third Parties must obtain copies of non SSEPD Standards, such as BS
or ENA documents, from the issuing organisations at their own expense.
These documents may be subject to copyright.
11.2 Documents for use by third parties are classified as Public and are
available on the SSEPD website,
http://www.ssepd.co.uk/Library/ConnectionsUsefulDocuments/
11.3 Documents not displayed on the internet are not publically available as
they are deemed not to be needed by third parties. Where third parties
require copies of these SSEPD documents they can be requested from
the SSEPD Power Systems Document Administrator, Inveralmond
House, 200 Dunkeld Road, Perth PH1 3AQ.
11.4 There will be a cost of £150 for each copy of each document
(irrespective of size). This cost is due to the administration required to
ensure that updates to the documents (which are controlled) are sent out
to third parties.
DRAWINGS
The drawings in table 3 below are for information purposes only. Full sized version can be
obtained by contacting our connections team.
Table 3
Appendix 1
1
Load Curve G
0.9
0.8
0.7
0.6
Load (P.U.)
0.5
0.4
0.3
0.2
0.1
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Time (Hr)