Vous êtes sur la page 1sur 18

Task Name Start Date End Date Duration Start Date in Number Form 43132.

End Date Duration Start Date in Number Form 43132.00 Use this number for the Minimum Bound of the Horizontal Axis to set the beginning of the chart.

Develop timeline, Build log data 2/1/2018 2/6/2018 5


2/1/18 2/21/18 3/13/18 4/2/18 4/22/18 5/12/18 6/1/18 6/21/18 7/11/18
Introductory Research & Propose Perfortion Interval 2/4/2018 2/7/2018 3 Devel op time l ine, Bui ld l og data
Introductory Res ea rch & Propos e Perfortion Interval
Prepare 1st Presentation 2/7/2018 2/11/2018 4
Pre pare 1st Presentation

1st Presentation 2/15/2018 2/15/2018 1 1st Pres entation


Rese arch for Li terature Revi ew
Research for Literature Review 2/10/2018 3/13/2018 31 Ana lyze l ogs - Lithol ogy, Sw, Rese rve Determination
Prepa re Li terature Revi ew Pres entation
Analyze logs - Lithology, Sw, Reserve Determination 2/15/2018 2/26/2018 11
2nd Pres entation - Li terature Review
Prepare Literature Review Presentation 2/24/2018 3/26/2018 30 Des i gn of Perforation Progra m
Desi gn of Sand Control
2nd Presentation - Literature Review 3/29/2018 3/30/2018 1
Des i gn of Compl etion Progra m
Design of Perforation Program 4/2/2018 4/16/2018 14 Desi gn of Artifical Li ft Progra m
Project Economi cs /Sensi tivi ty Ana l ys i s
Design of Sand Control 4/16/2018 4/30/2018 14 Project Wri teup

Design of Completion Program 5/1/2018 5/22/2018 21 Proof Rea d


Prepa re Fi na l Report
Design of Artifical Lift Program 5/23/2018 6/6/2018 14 Prepare Fi nal Presentation
Final Pres entation
Project Economics/Sensitivity Analysis 6/6/2018 6/23/2018 17

Project Writeup 4/10/2018 6/29/2018 80

Proof Read 6/30/2018 7/8/2018 8

Prepare Final Report 7/8/2018 7/12/2018 4

Prepare Final Presentation 7/12/2018 7/20/2018 8

Final Presentation 7/22/2018 7/23/2018 1

43306.00

Key: Calculated Cell Manual Entry Cell

These cells will be automatically calculated based on These cells require manual input so the calculated cells
the inputs on other cells. have data to work with.
Duration
Task Name Start Date End Date (Days)

Task One 7/25/2016 7/30/2016 5

Task Two 7/27/2016 8/1/2016 5

Task Three 7/27/2016 8/4/2016 8

Task Four 7/29/2016 8/6/2016 8

Task Five 8/1/2016 8/9/2016 8

Task Six 8/1/2016 8/5/2016 4

Task Seven 8/3/2016 8/10/2016 7

Task Eight 8/5/2016 8/12/2016 7

Task Nine 8/3/2016 8/9/2016 6

Task Ten 8/6/2016 8/10/2016 4

Task Eleven 8/7/2016 8/13/2016 6

Task Twelve 8/10/2016 8/16/2016 6

Task Thirteen 8/14/2016 8/19/2016 5

Task Fourteen 8/15/2016 8/23/2016 8

Task Fifteen 8/16/2016 8/26/2016 10

Task Sixteen 8/17/2016 8/28/2016 11

Task Seventeen 8/18/2016 8/29/2016 11


Days Complete Days Percent Start Date in Number Form 42576.00
Remaining Complete

2.50 2.50 50%


7/25/16 7/30/16 8/4/16
3.75 1.25 75% Ta s k One

2.00 6.00 25% Ta sk Two

8.00 0.00 100% Ta s k Three

6.00 2.00 75% Ta sk Four

1.40 2.60 35% Tas k Fi ve

Ta sk Si x
1.75 5.25 25%
Ta s k Seven
4.90 2.10 70%
Tas k Ei ght
0.90 5.10 15%
Tas k Ni ne
2.40 1.60 60%
Ta sk Ten
3.90 2.10 65%
Ta sk El even
1.50 4.50 25%
Ta s k Twelve
1.50 3.50 30% Ta s k Thi rte en

4.00 4.00 50% Ta s k Fourteen

4.00 6.00 40% Ta s k Fi fteen

3.85 7.15 35% Ta s k Si xteen

1.65 9.35 15% Ta sk Seventeen


Ta sk Seventeen

Key: Calculate

These cells will be automatical


inputs on other cells.
Use this number for the Minimum Bound of the Horizontal Axis to set the beginning of the chart.

8/4/16 8/9/16 8/14/16 8/19/16 8/24/16 8/29/16 9/3/16


Calculated Cell Manual Entry Cell

cells will be automatically calculated based on the These cells require manual input so the calculated
s on other cells. cells have data to work with.
of the chart.

8/29/16 9/3/16
Duration
Task Name Start Date End Date (Days)

Task One 7/25/2016 7/30/2016 5

Task Two 7/27/2016 8/1/2016 5

Task Three 7/27/2016 8/4/2016 8

Task Four 7/29/2016 8/6/2016 8

Task Five 8/1/2016 8/9/2016 8

Task Six 8/1/2016 8/5/2016 4

Task Seven 8/3/2016 8/10/2016 7

Task Eight 8/5/2016 8/12/2016 7

Task Nine 8/3/2016 8/9/2016 6

Task Ten 8/6/2016 8/10/2016 4

Task Eleven 8/7/2016 8/13/2016 6

Task Twelve 8/10/2016 8/16/2016 6

Task Thirteen 8/14/2016 8/19/2016 5

Task Fourteen 8/15/2016 8/23/2016 8

Task Fifteen 8/16/2016 8/26/2016 10

Task Sixteen 8/17/2016 8/28/2016 11

Task Seventeen 8/18/2016 8/29/2016 11


Days Complete Days Percent Start Date in Number Form 42576.00
Remaining Complete

2.50 2.50 50%


7/25/16 7/30/16 8/4/16
3.75 1.25 75% Ta sk One

2.00 6.00 25% Ta sk Two

8.00 0.00 100% Ta s k Three

6.00 2.00 75% Tas k Four

1.40 2.60 35% Ta s k Fi ve

Tas k Si x
1.75 5.25 25%
Ta s k Seven
4.90 2.10 70%
Ta s k Ei ght
0.90 5.10 15%
Ta s k Ni ne
2.40 1.60 60%
Ta sk Ten
3.90 2.10 65%
Tas k El even
1.50 4.50 25%
Ta sk Twel ve
1.50 3.50 30% Ta s k Thi rte en

4.00 4.00 50% Ta s k Fourteen

4.00 6.00 40% Ta sk Fifteen

3.85 7.15 35% Ta sk Sixteen

1.65 9.35 15% Tas k Seventeen


Tas k Seventeen

Key: Calculate

These cells will be automatical


inputs on other cells.
Use this number for the Minimum Bound of the Horizontal Axis to set the beginning of the chart.

8/4/16 8/9/16 8/14/16 8/19/16 8/24/16 8/29/16 9/3/16


Calculated Cell Manual Entry Cell

cells will be automatically calculated based on the These cells require manual input so the calculated
s on other cells. cells have data to work with.
g of the chart.

8/29/16 9/3/16
Task Name Start Date End Date Duration Start Date in Number Form 43132.00 Use this number for the Minimum Bound of the Horizontal Axis to set the beginning of the chart.

Develop timeline, Build log data 2/1/2018 2/6/2018 5


2/1/18 2/21/18 3/13/18 4/2/18 4/22/18 5/12/18 6/1/18 6/21/18 7/11/18
Introductory Research & Propose Perfortion Interval 2/4/2018 2/7/2018 3
Develop timeline, Build log data
Prepare 1st Presentation 2/7/2018 2/15/2018 8
Introductory Research & Propose Perfortion Interval
Research for Literature Review 2/10/2018 3/13/2018 31
Prepare 1st Presentation
1st Presentation - Introduction 2/22/2018 2/23/2018 1 Research for Literature Review
Analyze logs - Lithology, Sw, Reserve Determination 2/24/2018 3/26/2018 30 1st Presentation - Introduction
Prepare Literature Review Presentation/Report 3/10/2018 3/19/2018 9 Analyze logs - Lithology, Sw, Reserve Determination
Project Writeup 3/10/2018 6/29/2018 111 Prepare Literature Review Presentation/Report
2nd Presentation - Literature Review 3/22/2018 3/23/2018 1 Project Writeup
2nd Presentation - Literature Review
Design of Perforation Program 4/2/2018 4/16/2018 14
Design of Perforation Program
Semester Ends 4/19/2018 5/14/2018 25
Semester Ends
Design of Sand Control (optional) 4/19/2018 4/30/2018 11
Design of Sand Control (optional)
Design of Completion Program 5/1/2018 5/22/2018 21
Design of Completion Program
Design of Artifical Lift Program 5/23/2018 6/6/2018 14 Design of Artifical Lift Program
Project Economics/Sensitivity Analysis 6/6/2018 6/23/2018 17 Project Economics/Sensitivity Analysis
Proof Read 6/30/2018 7/8/2018 8 Proof Read
Prepare Final Report 7/8/2018 7/12/2018 4 Prepare Final Report
Prepare Final Presentation 7/12/2018 7/20/2018 8 Prepare Final Presentation
Final Presentation
Final Presentation 7/22/2018 7/23/2018 1

43306.00

Key: Calculated Cell Manual Entry Cell

These cells will be automatically calculated based on the These cells require manual input so the calculated cells
inputs on other cells. have data to work with.

Vous aimerez peut-être aussi