02.00.00 EXPLANACIONES
COMPACTACION DE SUB BASE EN PISOS m2 1,217.39 6.66 8,107.82
BASE COMPACTADA EN PISOS PRIMER NIVEL m2 1,217.39 26.71 32,516.49
COSTO DIRECTO
GASTOS GENERALES 10.00%
UTILIDADES 10.00%
IGV 19.00%
SON: UN MILLON TRESCIENTOS CINCUENTA Y UN MIL QUINIENTOS OCHENTA 71/100 nuevos soles
PRESUPUESTO
TOTAL
6,476.08
40,624.30
65,318.89
12,611.25
33,209.74
874,288.93
1,032,529.19
103,252.92
1,135,782.11
215,798.60
=============
1,351,580.71