Vous êtes sur la page 1sur 9

KSCE Journal of Civil Engineering (2011) 15(2):317-325 Structural Engineering

DOI 10.1007/s12205-011-0918-1
www.springer.com/12205

A Study On Dam Instrumentation Retrofitting


A. Melih Yanmaz* and Onur Ari**
Received July 1, 2009/Accepted May 11, 2010

···································································································································································································································

Abstract

Continuous monitoring and inspection of large dams would provide means for proper rehabilitative actions to be taken on time
which intend to maintain the desired safety throughout the physical life of dams. Comprehensive inspections can be carried out using
a number of instruments. An ideal dam instrumentation system should provide time-dependent information about critical parameters
so that possible future behaviour of the structure can be predicted. Numerous of the existing dams do not have adequate instruments
or current instrumentation systems may not be in good condition. By implementing the modern equipment to existing dams, the
uncertainty associated with the impacts of aging or unexpected severe external events will be reduced and possible remedial
measures can be taken accordingly. This paper addresses the concept of instrument retrofitting to an unmonitored structure,
Gokcekaya Dam, 159 m-high arch dam, Turkey, with reference to investigation of the current condition of the structure. The
deficiencies observed are listed and the corresponding rehabilitative measures are suggested. Finally, different alternatives of a new
instrumentation system are introduced and compared in monetary terms.
Keywords: dams, safety, instrumentation, rehabilitation, monitoring
···································································································································································································································

1. Introduction use of new types of instruments possible, which have greater


accuracy, and longer life with smaller dimensions. Moreover,
Many dams were designed and constructed during the last new instruments are equipped with their automated data loggers,
century using conventional procedures (DeMichele et al., 2005). which can lead to computer assisted evaluation of long-term be-
Therefore, the adequacy of such dams with respect to current haviour of the structure. Possible deficiencies should be moni-
conditions needs to be checked. On the contrary, new dams are tored either by direct or indirect measuring techniques. Charac-
designed using sophisticated approaches, which are normally teristics of items to be monitored should then be analyzed for
based on some simplifying assumptions. Validity of design as- determining the remedial actions to be taken. The extent and
sumptions and instantaneous status of safety of new dams can be degree of monitoring is decided during the design phase of a dam
assessed using some instruments installed in and around dams. with reference to the critical items that are likely to cause a hazard.
Unexpected behaviours may be observed throughout the physi- The type of dam, site characteristics, and the purpose of the
cal life of the structure due to the inability to model uncertainties project should also be considered. Time-dependent probabilistic
associated with extreme events, foundation conditions, material safety analyses should be carried out in order to ensure the desir-
properties as well as deficiencies in construction practices. With ed strength throughout the lifetime of dams. The critical items
sufficient data and experience gained from the behaviour of the should then be monitored constantly using the most appropriate
existing structure, challenging future designs can then be per- equipment in view of the performance of monitoring and economy.
formed. Although the required monitoring equipment would normally
Early dam examination practices consider only the visual in- differ from dam to dam, pore water pressure and seepage, body
spection, done by walking on dam body and checking the struc- and foundation movement, mass temperature, and seismic effects
tural integrity visually from inside of the galleries. Although this are mostly the parameters to be measured. Automated systems
method with an experienced examiner gives valuable informa- offset human-induced errors in measurements and monitor the
tion about the physical condition of dam body, more complex equipment continuously. They collect relevant inputs precisely
items, such as seepage, movement, and state of internal stresses and trigger possible warning messages.
cannot be determined without using proper equipment. With the As a dam gets aged, several deficiencies may occur i.e., con-
advancement in dam monitoring, a number of instruments have crete body deteriorates, drains may be clogged, grouts and cut-
been developed and used. Recent electronic technology made the off walls lose their effectiveness, contraction joints separate due

*Professor, Civil Engineering Department, Middle East Technical University, Ankara 06531, Turkey (Corresponding Author, E-mail: myanz@metu.edu.tr)
**Research Assistant, Civil Engineering Department, Middle East Technical University, Ankara 06531, Turkey (E-mail: oari@metu.edu.tr)

− 317 −
A. Melih Yanmaz and Onur Ari

to cyclic loading, and old instrumentation system may become ten weirs has also been equipped with an automatic gauge. Each
out of order. These adverse effects of aging bring the dam to a monolith has been instrumented with two piezometers. Three
more vulnerable condition against failure. In order to protect the direct and three inverted pendulums have been installed. Two
downstream, old dams should be rehabilitated. As a first step, the extensometers have also been introduced. In order to monitor the
current condition of the dam should be assessed properly. Fur- rotation of the monoliths, seven clinometer bases and one clin-
thermore, a number of instruments can be retrofitted to measure ometer have been added to the system. For monitoring contrac-
the critical parameters. Although retrofitted instruments cannot tion and expansion of the joints, 14 thermometers have been
give information about the events that have occurred before the installed to one of the monoliths. Finally, an automatic gauge has
installations, they provide a basis for assessing possible future been installed for reservoir level monitoring (ICOLD, 1992).
events. In the days of the design period of an existing dam, The initial instrumentation of Chandreja Dam (Spain) was set for
structural and geotechnical design techniques might have been measurement of drainage flow and uplift monitoring. The new
incapable of precise modelling. In order to ensure the validity of system has been proposed for further monitoring of uplift, sur-
assumptions made and the adequacy of the design, relevant data face movement, and joint movement. An array of piezometers has
may be obtained from the retrofitted instruments. The aim of this been installed under the buttresses. Angular collimation targets
paper is to illustrate the application of dam instrumentation re- have been introduced for horizontal movement monitoring and
trofitting to an existing dam, Gokcekaya Dam, Turkey. Various an array of jointmeters has been implemented for monitoring the
alternatives have been generated in terms of monetary units. relative movements of joints (ICOLD, 1992). Seeuferegg Dam
(Switzerland) is located in the Alps. Existing monitoring system
2. Literature Survey consisting of a direct pendulum and seepage rate monitoring
weirs was supplemented with additional direct and inverted
This section introduces some case studies on dam instrument- pendulums. A new geodetic network has been provided for sur-
ation retrofitting practices. The facing of the Morávka Dam in face monitoring. A number of standpipe piezometers have also
Czech Republic has been rehabilitated, drainage system has been been installed for uplift pressure monitoring (ICOLD, 1992).
improved and the monitoring system has been upgraded by auto- After 1971 San Fernando Earthquake, vertical contraction joints
matic monitoring and data transfer (Kratochvíl and Glac, 2006). of Pacoima Dam (USA) have been opened resulting in horizontal
Surface monitoring system and pendulum have been automated cracks. Due to the movement of plates, a slight rotation of the
for Talvacchia Dam in Italy and additional equipment, monitor- dam body has also been noticed. No instrumentation had been
ing dynamic and seismic responses, have been installed (ICOLD, provided for the dam initially. After rehabilitation, extensometers
1992). Dam leakage and surface movement of Baitone Dam have been installed in abutments. A total of 20 piezometers were
(Italy) have been monitored periodically. The existing monitor- provided to monitor the uplift pressures. An inclinometer, an array
ing system has been supplemented with one inverted pendulum, of accelerometers, and a number of thermometers have also been
three piezometers, and an automated data acquisition system installed at various locations on dam body (ICOLD, 1992).
(ICOLD, 1992). Marunuma Dam in Japan experienced severe
cracking due to freezing and thawing. Increased leakage has 3. Case Study
been observed from the joints. The dam has been equipped with
strain and joint monitoring instruments. Based on detailed 3.1. General
inspections, the deck has been covered with a new concrete slab. Gokcekaya Dam, located on Sakarya River, 60 km northeast of
New stress, strain and joint movement monitoring equipment Eskisehir province, Turkey, generates electricity. It is an arch
have been implemented (ICOLD, 1992). Kohmyo-Ike Dam dam, which was constructed during the period 1967-1972. A
(Japan) was subject to extensive seepage during the period of 60 descriptive sketch of it is shown in Fig. 1. The dam is 159 m high
years. After intensive analyses, the upstream face has been from the foundation, 115 m high from the thalweg and it has a
covered with silty clay and new piezometers and weirs have been crest length of 479.7 m (including thrust blocks). Its crest width
installed. The measurements verified decrease in seepage after is 8 m. A concrete volume of 650,000 m3 was used in the
this rehabilitation (ICOLD, 1992). Upper Huia Dam in New construction of the body. The reservoir lake has a surface area of
Zealand had uplifting problems. New piezometers were installed 20 km2 with maximum volume of 910 million m3. The hydro-
to constantly monitor the pore water pressures beneath the dam. electric power plant has three units with an installed capacity of
By using the automated system, the measured pore water pres- 278.4 MW. The spillway of Gokcekaya Dam, 62 m long, has
sure data gave invaluable information about the effectiveness of been constructed in a neighbouring valley as a separate structure
the cut-off wall and the necessary remedial actions were then on the right side of the dam. Three radial gates are supported by
implemented on that basis (Ahmed-Zeki et al., 2000). A new two intermediary piers. The energy dissipater of the spillway is
monitoring system has been designed for Compuerto Dam (Spain) of a deflector bucket type. Detailed information on basin hydro-
with some rehabilitative actions. Grout curtains have been logy and site characteristics can be found in Ari (2008). There
extended and all existing drains have been cleaned and bored. were two important fault lines at the dam site, which directly
Weirs have been installed to monitor the seepage rate. One of the affected the body construction. Treatments of these faults were

− 318 − KSCE Journal of Civil Engineering


A Study On Dam Instrumentation Retrofitting

this section. The remaining economical life of Gokcekaya Dam


is roughly estimated to be around 40 years (Ari, 2008). Due to
lack of routine inspection and necessary repair works, the
expected safety performance of Gokcekaya Dam was assumed
to be reduced. So it is essential to perform some rehabilitative
works. To this end, monitoring the performance of the structure
by modern retrofitted instruments is of utmost importance. In
order to be consistent on rehabilitative and instrumental recom-
mendations, not only the present situation, but also some impor-
tant past events should be taken into account. The dam has
experienced a major problem of leakage of some mud flow from
the sluiceway drainage system in August 1983. It clouded almost
one-third of the downstream reach to brownish colour. One week
after this event, a new mud flow had been started from various
drain holes in the floor of the main gallery. The situation of the
dam was inspected by a team who observed mud flow coming
from some drain holes, mud residue on the stairs of the inspec-
tion gallery, and opening of some contraction joints around drain
holes. The drain canals were observed to be clogged and no
measurement for seepage was available. Furthermore, they also
noticed that stress-strain monitoring equipment were out of order
(Tanriverdi et al., 1983). The mud observed in galleries and in
Fig. 1. Characteristic Sections of Gokcekaya Dam (Not to scale) drain holes was of clay origin, containing some organic materials
with light-brown colour. Physical and chemical studies on both
the mud found in drain holes and the material taken from the
completed by removing the debris up to a predefined level and reservoir bottom showed identical properties. So the origin of the
then filling the fault by concrete (DSI, 1974). mud was assumed to belong to the reservoir bottom. Because of
The authors visited Gokcekaya Dam site to be informed on the lack of maintenance, the residues of the mud are still observable
current conditions. Several deficiencies observed throughout the in drain holes in the gallery, which may lead to pore water pres-
site visit are summarized below. sure built-up by increasing the uplift pressure at the foundation
a) Traces of leaked water from the contraction joints, some level.
calcium deposits, and some diagonal cracks and openings were The dam has 17 weirs which are located in a sectioned manner
noticed on the walls and ceilings of the galleries. Leakage from in order to get an idea in case of an abnormal behaviour. However,
contraction joints can be evaluated as a sign of joint movement. most of them are inoperable. Therefore, they should be renewed.
b) A relatively large leakage has been noticed along one of the A number of standpipe piezometers mounted around the right
contraction joints on the downstream face of the dam at the same thrust block are assumed to monitor seepage due to the right fault
axis as one of the faults. line. There exist eleven piezometers in that group. In addition to
c) At the entrance of the gallery from the power plant access, a those on the right thrust block, five standpipe piezometers also
crack was observed on the base of the gallery, perpendicular to exist around the spillway. After detailed studies on the past
the dam axis, which may result from the differential settlement readings of these standpipe piezometers, four wells at the left
due to foundation movement. thrust block have been selected to be retrofitted with reference to
d) On the right abutment around the right thrust block, eleven their location and condition. In Gokcekaya Dam, many joints
drain wells exist, which have been used as standpipe piezo- experienced significant leakage due to the relative movement
meters. One of them is out of order due to a subsidence, whereas between blocks. The condition of joints should then be inspected
the other three had no water, possibly due to clogging. and repaired urgently. Jointmeters had been embedded to the
e) The chute and the deflector bucket sections of the spillway concrete mass during construction phase but almost all of them
were heavily covered by plants, which would significantly decre- are out of order. Main problems observed at the dam site and the
ase the capacity of the spillway during operation. The local corresponding rehabilitative actions to be taken have been
authorities stated that the gates have not been opened since 1982. summarized in Table 1.
It is, now, suspicious that whether or not the gates can operate
properly during a possible subsequent flood. 3.3. Instrumentation Retrofitting
Instrument application design of a dam requires extensive
3.2. Rehabilitative Recommendations structural, hydraulic and geotechnical analysis, prediction of
Some remedial actions for dam rehabilitation are introduced in weak zones, determination of best-suited instruments, cost

Vol. 15, No. 2 / February 2011 − 319 −


A. Melih Yanmaz and Onur Ari

Table 1. Rehabilitation Program Table 2. Unit Prices of Instruments (IIC, 2007)


Problems Unit price per item
Rehabilitative action required Equipment Type
identified at (€ )
• Cleaning channels and weirs VW Piezometer 400.00

Drain holes
• Re-drilling of drain holes, if necessary V-Notch Weir and Automatic VW Readout Unit 2,145.00
and weirs • Possible additional foundation grouting based on Automatic VW Weir Readout Unit 1,915.00
chemical analysis of the materials removed from
drain holes Parshall Flume and Automatic VW Readout Unit 2,350.00

• Cleaning the cracks and expanded joints Surface-mount VW Jointmeter 550.00

• Filling cracks and joints with urethane sealant for Accelerometer 11,253.00
Cracks and
watertightness Surface-mount Clinometer (Tiltmeter) 895.00
joints
• Filling cracks and joints with epoxy resin injection Extensometer 980.00
for structural bonding
Instrument Cable 4.90 /m
• Removing the accumulated debris and plants from
spillway face Cable Carrier Tray 26.00 /m
Spillway and
gate mechanism
• Repairing concrete damages Multiplexer 4,425.00
• Inspecting and repairing spillway gates and operat- Data Logger 15,104.00
ing mechanism
Software 16,300.00
Common Triggering Unit and Data Recorder for
23,788.00
optimization, and experience. For existing dams, however, some accelerometers
of the relevant information may be missing as in the case of Handheld Data Readout 5,627.00
Gokcekaya Dam. It has been believed that after some time, the
items, such as concrete temperature, are stable in terms of
measured values and further monitoring may not be required. achieved by considering several items, such as types of instru-
Recent studies showed that aging of dams results in more ments, installation locations, the cable lengths to data logger
damage than expected. In order to monitor and predict faulty from the individual instrument, required cable sag, and the length
elements and conduct repair works, it is necessary to install of the tray carrying cable. The multiplexers and data loggers are
modern and precise equipment to an old dam. In the following located at the entrance of the gallery from the hydroelectric
sections, the alternatives of instrument retrofitting will be power plant for access ease. Furthermore, all length calculations
discussed for Gokcekaya Dam. The proposed basic instruments have been completed accordingly. The required sag of the cables
are piezometers, automated weirs, surface jointmeters, surface has been chosen as 15% of the total length of cable (USBR
clinometers, borehole extensometers and strong motion accelero- 1987). The complete price list of all proposed instruments is
meters. All equipment is to be planned considering a central given in European currency unit (EUR) with reference to IIC
automated data acquisition system in order to obtain precise (2007) in Table 2.
results, free of human induced errors. The calculations have been After computing the details and the quantity of the individual

Table 3. Cost Computations


Monitoring item Option Ci (€ ) Cc (€ ) Cca (€ ) Ct (€ )
1 14,000.00 32,848.11 13,925.60 60,773.71
Piezometer 2 12,400.00 24,821.61 11,390.60 48,612.21
3 6,400.00 13,081.65 11,390.60 30,872.25
1 25,850.00 8,739.32 16,265.60 50,854.92
Seepage
2 21,065.00 8,739.32 16,265.60 46,069.92
1 35,750.00 49,595.33 23,821.20 109,166.53
Joint movement
2 18,700.00 27,363.00 12,430.60 58,493.60
1 17,005.00 18,629.31 17,758.00 53,392.31
Rotation (tilt)
2 2,685.00 2,163.84 7,397.00 12,245.84
Foundation movement - 13,720.00 12,069.61 5,570.24 31,359.85
1 57,547.00 4,194.13 11,499.80 73,240.93
Earthquake acceleration
2 35,041.00 1,052.62 4,856.80 40,950.42

− 320 − KSCE Journal of Civil Engineering


A Study On Dam Instrumentation Retrofitting

instrument items, cabling, cable tray and instrument costs have Option 3, the piezometers on the existing right drain holes are
been determined and total costs of each option are attained by discarded as in Option 2. Moreover, unlike the previous options,
summing them up as shown in Table 3 in which Ci, Cc, Cca, and only one piezometer for two cantilevers is utilized. So the canti-
Ct stand for cost of instrument, cost of cable, cost of carrier, and levers with even numbers are equipped with piezometers. These
total cost, respectively. cost-cutting actions reduce the total number of instruments to 16.
The costs of three piezometer options in Euros are compared
3.3.1. Piezometer Options according to their total costs in Table 3.
In Gokcekaya Dam, three options for piezometer applications
are proposed. Although uplift is less critical in arch dams, 3.3.2. Seepage Monitoring Options
Gokcekaya Dam has been observed to have some problems After evaluating past reading logs for seepage measurements,
related with the seepage and uplift reducing facilities. In order to it is clear that neither the monitoring has been properly scheduled
monitor possible deficiencies, installation of a new pore water nor the readings had the required precision. By evaluating the
pressure monitoring system would be beneficial. A definition condition of the existing weirs, those that need to be instru-
sketch is presented in Fig. 2 to demonstrate the instrumentation mented have been determined. For seepage measurement, two
configuration for piezometers. In Option 1, the total number of options are suggested. In Option 1, the existing weirs are proposed
required vibrating wire piezometers are determined as 35. On the to be replaced by Parshall flumes because of less maintenance
right thrust block, TR-2 and TR-3 (See Fig. 2) are selected and and smaller headlosses. The selected Parshall flumes in this
one of their drain holes is considered to be utilized for piezo- option should also be automated by vibrating wire weir gauges in
meter installation. Similarly, TL-2 to TL-5, on the left thrust order to fully adapt to automated data logging system. They are
block, are chosen to be monitored. Since this option concentrates planned to be installed to the place of the existing weirs. So the
on the amount of data gathered, all cantilevers from 0 to 24 are weirs should be cut from the base of the canal to install Parshall
equipped with piezometers to monitor the change of pore water flumes. Like the piezometers, cables have been routed to the
pressure between the sequential blocks. In this option, the exist- ceiling of the gallery and then carried via cable carrier trays to
ing standpipe piezometer holes on the right abutment are also the multiplexer units. Option 2 suggests repairing and cleaning
evaluated. of the existing weirs. Afterwards, by using the vibrating wire
By considering their condition and location, wells 149, 147, weir gauges, the existing weirs can be equipped and monitored
145 and 143 are added to the monitoring system by installing continuously by data logger device. For cable routing, similar
piezometers. In the computations, the average depth, where approach as that of Option 1 is applied. Table 3 gives the costs of
piezometers are embedded, is taken as 10 m. The possible costs two seepage monitoring options.
of drilling and backfilling are ignored. In Option 2, the existing
right abutment drain holes are excluded because of the consistent 3.3.3. Joint Movement Monitoring Options
results of manual well reading up to date and the closeness of the Gokcekaya Dam consists of 25 cantilevers and 10 thrust
piezometers on blocks, TR-2, TR-3, and cantilever 0. The other blocks. During the construction, several embedded jointmeters
installations in the dam body are taken as the same as Option 1. had been installed along the contraction joints. However, almost
The total number of instruments in this option is 31. The Option all of them are out of order and past readouts are not available.
3 is suggested as a lower-cost alternative to Options 1 and 2. In Furthermore, the readout ports have been out of order due to

Fig. 2. Definition Sketch for Piezometer Arrangement

Vol. 15, No. 2 / February 2011 − 321 −


A. Melih Yanmaz and Onur Ari

heavy corrosion. In addition to those, a horizontal joint opening are proposed for this dam with reference to the gallery layout.
and leakage has been observed on cantilever 1 and several Option 1 recommends installing surface-mount clinometers over
leakages on vertical joints inside the gallery have been observed. the three sections inside the gallery and onto the downstream
After extensive studies on dam projects, some repair works and face. The dam body is first divided into two and the location of
subsequent instrument retrofitting are recommended. Two options the first group of clinometers is determined as cantilever 11. In
for instrument retrofitting are suggested. In Option 1, every joint this central section, 9 clinometers are proposed with a vertical
along the inspection gallery is equipped with two surface-mount spacing of 20 m. The other sections are selected as cantilevers 4
jointmeters. One jointmeter is proposed for the downstream side, and 21. Each section is equipped with 5 clinometers. Option 2
whereas the other one is for the upstream side of the same joint suggests installing only three clinometers inside the galleries of
as seen in Fig. 3. above sections in order to reduce the cabling and equipment
The reason behind this layout is that the hydraulic loading on costs. It is obvious that the data gathered from this option are
an arch dam creates either tension or compression on the limited. Table 3 gives costs of two rotation monitoring options.
different zones of the shell and two jointmeters on both faces
help to monitor the movement precisely. Moreover, after the 3.3.5. Earthquake Acceleration Monitoring Options
repair works on the leaking joint on cantilever 1, the downstream Gokcekaya Dam is placed in the third earthquake zone on the
face of the horizontal joint is suggested to be instrumented with Ankara - Eskisehir province border. However, the dam site is
surface-mount jointmeters in order to verify the performance of only 30 km far from the first earthquake zone and 80 km from
the repair works done. It is computed that 65 surface-mount Duzce, the epicentre of the 12 November 1999 Earthquake with
jointmeters are required in this option. Cables are conveyed a magnitude of 7.2. Gupta (2002) investigated possible sources
along the ceiling of the gallery by cable trays and a total length of of earthquakes in dam environments. His results covering more
10.12 km of cable is required. Option 2 suggests a more econo- than 90 earthquakes indicated that these earthquakes were
mical layout than Option 1 by proper placement of 34 surface- triggered by reservoirs with the recorded largest event at Koyna
mount jointmeters. In this option, a contraction joint is equipped Dam reservoir, India, in 1967 having a magnitude of 6.3. Gupta
with only one surface-mount jointmeter on either downstream or (2002) also stated that the depth and the volume of the reservoir
upstream face. If a joint is monitored on its downstream face, the are the most important factors in reservoir induced seismicity.
neighbouring joints are instrumented on the upstream face as One of the recent studies implied that reservoir induced earthquakes
shown in Fig. 3. This layout has created an alternating plan and have been occurring over 44 years in Koyna region (Gupta et al.,
thus reduced the required number of instruments. As a result of 2007). Considering the left and right faults at the foundation and
having fewer instruments, the total length of cables is reduced to closeness to the North Anatolian Fault Line, Gokcekaya Dam
5.59 km. Table 3 presents the costs of two joint movement site can be considered as a seismically active region. Moreover,
monitoring options. the depth and the volume of the reservoir dictate that this dam is
prone to reservoir induced seismicity.
3.3.4. Rotation (Tilt) Monitoring Options Earthquake performance and behaviour under seismic loading
In Gokcekaya Dam, no pendulums had been installed during can only be evaluated with proper measurement of earthquake
the construction. Furthermore, no vertical shafts had been pro- acceleration. That is why Gokcekaya Dam needs to be equipped
vided. Installation of surface-mount clinometers is planned for with strong motion accelerometers. Strong motion accelerometers
rotation monitoring. Two options of surface-mount clinometers have not been monitored by automated data loggers like the
other instruments. So they require a common triggering unit and
a recorder. Common triggering unit activates the strong motion
accelerometer at a time, in case it senses any earthquake (Sezgin,
2008). In Gokcekaya Dam, two options are suggested for installing
strong motion accelerometers. In Option 1, three accelerometers
are recommended. Two accelerometers are proposed to be placed
on the dam body and the remaining one to the left abutment as a
free-field accelerometer. A typical distance for free-field accelero-
meter in dam applications is defined as twice the height of
concrete dams and half of this value if the modulus of elasticity
of foundation is equal to or greater than the modulus of elasticity
of the dam concrete (Darbre, 1995). The first accelerometer is
placed to the dam-foundation interface at cantilever 10, whereas
the second one is placed on its crest. The third accelerometer is
installed as a free-field accelerometer, 300 m from the left
Fig. 3. Definition Sketch for Jointmeter Arrangement (A part of the abutment. Option 2 is suggested as consisting one accelerometer
gallery) which is placed on the crest of cantilever 10. No matter which

− 322 − KSCE Journal of Civil Engineering


A Study On Dam Instrumentation Retrofitting

Table 4. Total Costs of Alternatives


Alternative Option Code ni nm Cic (€ ) Ca (€ ) Ct (€ )
1 P1 A1 W1 J1 T1 E 147 18 378,788.24 111,054.00 504,842.24
2 P1 A1 W1 J1 T2 E 131 16 337,641.77 102,204.00 454,845.77
3 P1 A1 W1 J2 T1 E 116 15 328,115.31 97,779.00 440,894.31
4 P1 A1 W1 J2 T2 E 100 13 286,968.84 88,929.00 390,897.84
5 P1 A1 W2 J1 T1 E 147 18 374,003.24 111,054.00 500,057.24
6 P1 A1 W2 J1 T2 E 131 16 332,856.77 102,204.00 450,060.77
7 P1 A1 W2 J2 T1 E 116 15 323,330.31 97,779.00 436,109.31
8 P1 A1 W2 J2 T2 E 100 13 282,183.84 88,929.00 386,112.84
9 P1 A2 W1 J1 T1 E 145 18 346,497.73 111,054.00 472,551.73
10 P1 A2 W1 J1 T2 E 129 16 305,351.26 102,204.00 422,555.26
11 P1 A2 W1 J2 T1 E 114 15 295,824.80 97,779.00 408,603.80
12 P1 A2 W1 J2 T2 E 98 13 254,678.33 88,929.00 358,607.33
13 P1 A2 W2 J1 T1 E 145 18 341,712.73 111,054.00 467,766.73
14 P1 A2 W2 J1 T2 E 129 16 300,566.26 102,204.00 417,770.26
15 P1 A2 W2 J2 T1 E 114 15 291,039.80 97,779.00 403,818.80
16 P1 A2 W2 J2 T2 E 98 13 249,893.33 88,929.00 353,822.33
17 P2 A1 W1 J1 T1 E 143 18 366,626.75 111,054.00 492,680.75
18 P2 A1 W1 J1 T2 E 127 16 325,480.28 102,204.00 442,684.28
19 P2 A1 W1 J2 T1 E 112 14 315,953.82 93,354.00 424,307.82
20 P2 A1 W1 J2 T2 E 96 12 274,807.35 84,504.00 374,311.35
21 P2 A1 W2 J1 T1 E 143 18 361,841.75 111,054.00 487,895.75
22 P2 A1 W2 J1 T2 E 127 16 320,695.28 102,204.00 437,899.28
23 P2 A1 W2 J2 T1 E 112 14 311,168.82 93,354.00 419,522.82
24 P2 A1 W2 J2 T2 E 96 12 270,022.35 84,504.00 369,526.35
25 P2 A2 W1 J1 T1 E 141 18 334,336.23 111,054.00 460,390.23
26 P2 A2 W1 J1 T2 E 125 16 293,189.76 102,204.00 410,393.76
27 P2 A2 W1 J2 T1 E 110 14 283,663.30 93,354.00 392,017.30
28 P2 A2 W1 J2 T2 E 94 12 242,516.83 84,504.00 342,020.83
29 P2 A2 W2 J1 T1 E 141 18 329,551.23 111,054.00 455,605.23
30 P2 A2 W2 J1 T2 E 125 16 288,404.76 102,204.00 405,608.76
31 P2 A2 W2 J2 T1 E 110 14 278,878.30 93,354.00 387,232.30
32 P2 A2 W2 J2 T2 E 94 12 237,731.83 84,504.00 337,235.83
33 P3 A1 W1 J1 T1 E 128 16 348,886.79 102,204.00 466,090.79
34 P3 A1 W1 J1 T2 E 112 14 307,740.32 93,354.00 416,094.32
35 P3 A1 W1 J2 T1 E 97 12 298,213.86 84,504.00 397,717.86
36 P3 A1 W1 J2 T2 E 81 10 257,067.39 75,654.00 347,721.39
37 P3 A1 W2 J1 T1 E 128 16 344,101.79 102,204.00 461,305.79
38 P3 A1 W2 J1 T2 E 112 14 302,955.32 93,354.00 411,309.32
39 P3 A1 W2 J2 T1 E 97 12 293,428.86 84,504.00 392,932.86
40 P3 A1 W2 J2 T2 E 81 10 252,282.39 75,654.00 342,936.39
41 P3 A2 W1 J1 T1 E 126 16 316,596.27 102,204.00 433,800.27
42 P3 A2 W1 J1 T2 E 110 14 275,449.80 93,354.00 383,803.80
43 P3 A2 W1 J2 T1 E 95 12 265,923.35 84,504.00 365,427.35
44 P3 A2 W1 J2 T2 E 79 10 224,776.88 75,654.00 315,430.88
45 P3 A2 W2 J1 T1 E 126 16 311,811.27 102,204.00 429,015.27
46 P3 A2 W2 J1 T2 E 110 14 270,664.80 93,354.00 379,018.80
47 P3 A2 W2 J2 T1 E 95 12 261,138.35 84,504.00 360,642.35
48 P3 A2 W2 J2 T2 E 79 10 219,991.88 75,654.00 310,645.88

Vol. 15, No. 2 / February 2011 − 323 −


A. Melih Yanmaz and Onur Ari

option is selected, the required number of common triggering tion, maintenance, installation, and workmanship costs are almost
units and data recorder is only one. In Table 3, the costs of two the same for all alternatives, these cost items are omitted.
earthquake acceleration monitoring options are presented. A proper decision-making for the selection of a suitable instru-
mentation system is based on consideration of the achievement
3.3.6. Foundation Movement Monitoring to be expected in reduction of future risks as a result of imple-
Foundation of Gokcekaya Dam had been equipped with Carlson mentation of the proposed instrument retrofitting and rehabilita-
type foundation deformation meters at several places during the tive actions to be taken. Therefore, the net benefit of such a
construction. Despite of being a sound system for foundation retrofitting project would be the difference between the failure
monitoring in the past, foundation deformation meters are inad- cost of the dam and the total cost of instrumentation and rehabili-
equate compared to vibrating-wire extensometers. To this end, tative actions. The cost of failure of Gokcekaya Dam cannot be
replacement of existing foundation deformation meters with determined since all relevant information covering the dam site
borehole extensometers is proposed. In order to be consistent and downstream failure possibilities of all types of properties is
with the dam design and to reduce the retrofitting costs by not available. However, it is quite clear that this cost is much
elimination of extensive foundation drilling, existing boreholes greater than the initial investment cost of such a dam, which was
used for foundation deformation meters are planned to be 52.9 million U.S. Dollars as of 1967 prices (EMO, 1967). This
equipped with extensometers. cost is converted to 2008 prices (FTF, 2008) to obtain $288.71
million. The instrumentation cost is about 1% of the total project
3.4. Evaluation of Alternatives cost (USBR, 1987), which comprises approximately $2.89 million.
Table 4 presents possible 48 combinations with three options When compared to the highest-cost alternative, this value is
for pore water pressure monitoring; two options for seepage more than 4 times the cost of retrofitted instruments to be
monitoring, joint movement monitoring, rotation monitoring, proposed for Gokcekaya Dam. Since instrumentation retrofitting
earthquake acceleration monitoring, and finally one option for cost is much smaller than the initial investment cost and dam
foundation movement monitoring. In Table 4, ni and nm stand for failure cost, selection of a reasonable alternative may be
number of instruments and number of multiplexers, respectively, governed by the performance expectation from the monitoring
whereas Cic and Ca are instrument and cable cost and automation system. The alternative having the highest ability to monitor dam
cost, respectively. Options are designated by two-character performance may then be selected. To this end, it is recommend-
codes. The first character defines the instrument group as P for ed to choose either alternative 1 or 5 since they have maximum
piezometers, W for seepage monitoring, J for joint movement number of instruments with the desired performance for moni-
monitoring, T for rotation (tilt) monitoring, A for earthquake toring the critical parameters.
acceleration monitoring, and E for foundation monitoring. The
second character identifies the aforementioned option numbers. 3.5. Further Instrumentation
The total numbers of instruments in alternatives are also pre- Recent developments in electronic technology lead to the
sented in Table 4. The highest and lowest numbers of instru- production of high accuracy GPS devices, especially in elevation
ments are 147 and 79, respectively. Total number of instruments calculations. These advanced GPS units can be used on dams for
is used to determine the required number of multiplexers, which surface monitoring. Together with the body and foundation
are used to increase the number of instruments to be monitored movement monitoring, surface monitoring will give the behaviour
by automated data acquisition system. For every 8 instruments of the dam body precisely. In Gokcekaya Dam, the surface
including temperature sensors, one multiplexer should be added monuments for conventional geodetic measurements, such as
to the automated data acquisition system. triangulation, are in good condition but the lack of routine
The aforementioned calculations made the computation of the measuring make these monuments obsolete. The initial cost of
automation cost possible, which consists of the required number installing such a GPS system for surface monitoring would be
of multiplexers, a data logger device, and software. The costs of high but the automatic data collection and processing abilities of
these items are also given in Table 1. After determination of the system would remove the necessity for skilled operators.
instrument and automation cost, total costs of alternatives are Temperature monitoring is vital, especially during concrete
computed and presented considering the combinations of pouring. After some time, the variation of concrete temperature
different options. A constant cost of 15,000 € has been added to stabilizes. Joint movements in concrete dams can also be correl-
the alternatives in order to represent the cost of portable data ated with temperature changes. Therefore, the mass concrete
logger which should be available in all automated systems for should be monitored throughout the life of the dam. In Gokcekaya
determining the possible faults and the cost of some additional Dam, thermistors had been placed during construction in order to
consumables, such as cable splicing kits. The highest total cost of monitor dehydration temperature. However, the present condi-
the proposed system is then determined as 504,842.24 € and the tions of these sensors are not known and a comprehensive survey
most economical alternative has a cost of 310,645.88 € . Total is needed to check their operability. Almost all types of modern
costs of all alternatives are presented in Table 4. Cost computa- instruments are equipped with temperature sensors. However,
tions are carried out considering initial costs only. As the opera- additional ones can be added to the proposed system. As a final

− 324 − KSCE Journal of Civil Engineering


A Study On Dam Instrumentation Retrofitting

recommendation, accurate reservoir water level measurement is Turkey.


recommended with a vibrating-wire water level gauge. Darbre, G. R. (1995). “Strong-motion instrumentation of dams.”
Earthquake Eng. and Structural Dynamics, Vol. 24, No. 8, pp. 1101-
1111.
4. Conclusions De Michele, C., Salvadori, G., Canossi, M., Petaccia, A., and Rosso, R.
(2005). “Bivariate statistical approach to check adequacy of dam
Instrument retrofitting requires installation of modern equip- spillway.” J. Hydr. Engrg., ASCE, Vol. 10, No. 1, pp. 50-57.
ment to old dams in order to assess the destructive effects of DSI (1974). Gokcekaya Dam with photos, State Hydraulic Works,
aging and thus take the necessary corrective actions on time. In Ankara (in Turkish).
this paper, Gokcekaya Dam, Turkey, has been considered in a EMO (Chamber of Electrical Engineers) (1967). Electrical Engi-
case study to demonstrate instrument retrofitting. First, numerous neering, EMO, Vol. 127, Ankara, Turkey (in Turkish).
deficiencies on the dam body and appurtenant structures have FTF (Financial Trend Forecaster) (2008). Inflation Rate Calculator.
From http://inflationdata.com/Inflation/Inflation_Calculators/Inflation_
been identified. Then, these evidences were interpreted. After
Rate_Calculator.asp
evaluation of results, a number of rehabilitative repair works and Gupta, H. K. (2002). “A review of recent studies of triggered
a modern dam monitoring system have been proposed with cost earthquakes by artificial water reservoirs with special emphasis on
analysis of different alternatives, which are formed by the com- earthquakes in Koyna, India.” Earth-Science Reviews, Vol. 58, No.
bination of various options for different types of instruments. 3, pp. 279-310.
Cabling costs were found to be of the order of instrument costs. Gupta, H., Shashidhar, D., Pereira, M., Mandal, P., Purhachandra Rao,
The highest-cost belongs to Alternative 1 (504,842.24 €), whereas N., Kousalya, M., Satyanarayana, H. V. S., and Dimri, V. P. (2007).
Alternative 48 has the lowest cost (310,645.88 € ). It should be “Earthquake forecast appears feasible at Koyna, India.” National
Geophysical Research Institute, No. 93, pp. 843-848.
noted that these alternatives consist only of the initial instrument-
ICOLD (International Commission on Large Dams) (1992). Improve-
ation costs. The costs of rehabilitative measures as well as repair, ment of existing dam monitoring, Bulletin 87, ICOLD, Paris.
maintenance, installation, and workmanship costs should also be IIC (IIC-GrupoEP) (2007). Unit price list for material supply, from
added to these values to determine the overall costs. Since the http://www.iic-grupoep.com.
cost of instrumentation retrofitting is normally much smaller Kratochvíl, D. and Glac, F. (2006). “Prevention of seepage and mod-
than the failure cost of a dam, the reduction in future risks as a ernization of monitoring system on the Morávka Dam.” Twenty-
result of implementation of a retrofitting system would highlight Second International Congress on Large Dams, Barcelona, pp. 135-
the benefits to be gained. 144.
Sezgin, Ö. I· . (2008). An evaluation study on instrumentation system of
Cindere Dam, MSc Thesis, Middle East Technical University,
References Ankara, Turkey.
Tanriverdi, I· ., Karadayl, N., Solakoglu, Ö., and Kucur, T. (1983).
Ahmed-Zeki, A. S., Logan, N., McQuarrie, W., and Jaduram, R. (2000). Investigation of sediment-laden flow from drain holes of Gokcekaya
“Monitoring the cut-off wall performance of Upper Huia Dam.” Dam, Unpublished Report, Turkish State Hydraulic Works, Ankara
Massachusetts: Geo-Institute Specialty Conference, Amherst, pp. (in Turkish).
212-227. USBR (1987). Embankment dam instrumentation manual, USBR, U.S.,
Ari, O. (2008). A study on dam instrumentation retrofitting: Gokcekaya Goverment Printing Office Washington, D.C.
Dam, MSc Thesis, Middle East Technical University, Ankara,

Vol. 15, No. 2 / February 2011 − 325 −

Vous aimerez peut-être aussi