Académique Documents
Professionnel Documents
Culture Documents
steelwise
Directly Welded Flange FR Moment Connections
As illustrated in Figure 12-4, a directly welded flange FR moment connection
of a shear connection CHOOSING
Make your non-seismic moment connections and complete-joint-penetration (CJP) groove welds, whic
connect the top and bottom flanges of the supported beam to the supporting colum
better with these helpful
in Figuretips. THE
12-4b, the stiffener MOMENT
extends beyond the toe of the column flange to elim
effects of triaxial stresses.
BY RYAN CURTIS, P.E., AND
KEITH GRUBB, S.E., P.E.
steelwise
(a) strong-axis connection schematic (b) weak-axis connection schematic (c) strong-axis connection schematic
with bolted flange plates. with bolted flange plates. with welded flange plates
(weak-axis version not pictured.)
Shim top or Shim top or bottom as required
bottom as required Shim top or bottom
as required
Check column for stiffener and Check column for stiffener and Check column for stiffener andCONSIDERATIONS
8–18 DESIGN
doubler requirements doubler requirements doubler requirements
(a)2Column
Figure flange
(adapted from support, bolted
Figure 12.2 flange
in the 14thplates the flux, although auxiliary(c)
edition Steel Construction Manual). Column
material can flange support,
be clamped to the welded flange
member to pl
provide
➤
NOVEMBER 2015
steelwise
A Word about the Code of Standard Practice moment connections invariably involve design, not just
This article presupposes that the engineer is selecting selection and completion. Clearly this is consistent with
either Option 1 (connections designed by the Engineer what is stated in the Code and its Commentary:
of Record) or Option 3 (connection design work dele- “The intent of this method is that the steel detailer
gated to a licensed engineer working for the fabricator) will select the connection materials and configuration
as given in Section 3.1.2 of the AISC Code of Standard from referenced tables or complete the specific con-
Practice. There is also an Option 2 (basic connections nection configuration (e.g., dimensions, edge distances,
left to be selected and completed by and experienced and bolt spacing) based upon the connection details
steel detailer). that are shown in the structural design drawings…It is
One trend we noticed when talking to fabricators was not the intent that this method be used when the prac-
a high proportion of fabricators noting that Option 2 is tice of engineering is required.”
not used for moment connections. This makes sense Download the complete AISC Code of Standard Prac-
because Option 2 does not allow for design work, and tice for free at www.aisc.org/specifications.
Including forces on the drawings also helps determine if costs—unless the end reactions are shown on the drawings for
columns require reinforcing. Sometimes, increasing the col- every moment connection.
umn size by a few pounds per foot can eliminate the need for Finally, remember to ask a fabricator for his/her advice
column reinforcing. when you encounter special situations. Even if they end up
Also, it’s never a good idea to overlook the cost implications not being the actual fabricator, your project will benefit from
of these two vague (and far too common) drawing notes: their expertise. ■
➤ “provide column stiffeners and doublers as required”
➤ “detail for the maximum moment capacity of the beam” For additional tips for designing moment connections, check out the
If Option 3 is the connection design option of choice, June 2009 Modern Steel article “In the Moment” by Victor Shneur
these phrases will most certainly lead to lots of fabricator (available at www.modernsteel.com).
and detailer head-scratching and RFIs—not to mention extra