Académique Documents
Professionnel Documents
Culture Documents
E2-E3: CIVIL
CHAPTER-12
BSNL CONTRACT CLAUSES
Clause 1
Performance
Guarantee
Clause – 1A
Deduct at 5% or 10%( as per above) of the Gross Amount of each running bill till
the sum along with the sum already deposited as EMD, will amount to S.D. of
10% of the tender value of the work
All Compensations or other payments which are due, may be deducted from SD.
A notice shall be issued, if the part of SD is reduced to make good the deficit
within 10 days.
Clause 1 not applicable if tender amount < Rs. 15 lacs and 1A applicable with
S.D. recovery @ 10 %.
Clause 2
If the Contractor fails to meet milestones [as per Cl. 5] then with-held money
from his bills automatically without any notice to contractor. It can be released if
later-on contractor picks up the progress.
Levey Compensation
EE( C ) tender amount upto Rs.6lakhs.
SE (C) without SW, tender amount above Rs.6lakhs upto Rs50 lakhs. SE with SW
above Rs.6Lakhs upto 70 Lakhs PCE/CE:-For all works tender amount above
Rs.50Lakhs /Rs.70 Lakhs as the case may be.
Clause 2A
Bonus
Eligibility
For works costing Rs. 10 Lakhs and above.
Applicable only when so provided in ―Schedule F‖ by the NIT authority.
Completes the work ahead of the scheduled completion time.
Amount : @ 1 % per month computed on per day basis.
Maximum: 5% of the tendered value.
To be paid along with final bill only after completion of work.
Authority: Decision of the C.E. regarding quantum of bonus shall be final and
binding.
Provided: always that Bonus shall be applicable only when so provided in
Schedule ‗F‘.
Clause 3
If the contractor fails to pay the required sum within 30 days, the E-in-C shall
have the right to sale any or all of the contractor‘s unused materials,
constructional plant, implements, etc.
Important Points
The final notice shall be got approved from Tender Accepting Authority before
serving to contractor.
Whether the date for completion has or has not elapsed, Action under clause-3 can
be taken up.
On recession, E-in-C shall have powers to carry out the balance work by any
means at the risk and cost of the contractor
Clause 4
In case in which any of the powers conferred upon the Engineer-in-charge by
clause 3 thereof, shall have become exercisable and the same are not exercised,
the non exercise thereof, shall not constitute a waiver of any of the conditions
hereof and such powers shall notwithstanding be exercisable in the event of any
future case of default by the contractor and liability of the contractor for
compensation shall remain unaffected.
Clause 5
The time allowed for execution of the works or the extended time shall be the
essence of the contract.
If the contractor fails to commence by the stipulated DOS, forfeit the PG and the
EMD.
To ensure good progress, the Contractor shall carryout the work as per mile
stones stipulated in clause 5.6.
If the Estimated Cost is more than 10 Lakhs, The contractor shall submit a time
and progress chart for each milestone and get it approved by the E-in-C.
Cl 5.5 Non-application by the contractor for EOT shall not be a bar for giving fair
and reasonable extension.
The authority mentioned in Schedule ‗F‘ may give EOT and reschedule the
milestones. It shall be communicated to the Contractor by the E-in-C within 3
months of such request from the contractor.
The EOT can be issued without any application from the contractor.
1 1/8th (Of the 1/4th (Of the whole 1% of the tendered value of work will
whole work) work) be withheld for failure of each
milestone from Running payments.
2 3/8th 1/2th
3 3/4th 3/4th
4 Full Full
Clause 6
Measurements of Work Done
All measurements and levels shall be taken jointly and shall be signed and dated
by the E-in-C and the contractor(s) or his/their representative in token of their
acceptance. ‗3‘ days notice shall be given to contractor & If the contractor does
not remain present at the time of Measurements and…..fails to countersign or to
record objection within a week from the date of the measurement, then….. such
measurements recorded in his absence by the Engineer-in-Charge or his
representative shall be deemed to be accepted by the Contractor.
The contractor shall give not less than seven day‘s notice before covering up and
will not cover the work without consent of the Engineer-in-Charge.
In case of Items not covered by specs, measurements be taken as per:
*BIS (Bureau of INDIAN Standard) or if its is not available then as per mutual
consent
Clause 7
Payment on Intermediate Certificate
to be regarded as Advances
No payment shall be made for work of E/cost Rs.20000 or less till after the whole
of the work has been completed and certificate of completion given.
For works of E/cost over Rs. 20,000,R/A bills shall be submitted by the contractor
(in triplicate) on or before the date of every month, fixed for the same by the
Engineer-in-Charge.
In the event of the failure of the contractor to submit the bills, E-in-C shall
prepare bills & in such a case no claims whatsoever due to delays on payment
including that of interest shall be payable to the contractor.
The amount admissible will as far as possible be paid by 10th working day after
the day of presentation of the bill by the Contractor to the Engineer-in-Charge or
his S.D.E. and in 15 days for works outside the headquarter.
Clause 8
Completion Certificate
& Completion Plans
Within 10 days of the completion of the work, the contractor shall give notice of
such completion and within 30 days the E-in-C shall inspect the work and if there
is no defect in the work, shall furnish the contractor with a final certificate of
completion, otherwise a provisional certificate of physical completion indicating
defects shall be issued.
Work not to be said complete till all defects complete & rubbish removed.
Clause 8A
• Contractor to Keep Site Clean
In case of repairs and maintenance works, the splashes and dropping from white
washing, colour-washing, painting etc, on walls, floor, windows etc. shall be
removed and the surface cleaned simultaneously with the completion of these
items of work in the individual rooms. In case the contractor fails to comply then
E-in-C can get this work done at the cost of the contractor after 10 days notice to
the contractor.
Clause 8B
Completion Plans to be
Submitted by the Contractor
The Contractor shall within 1 month of the date of completion of the work
submit:-
Completion plans for Electrical works.
Completion plans of internal and external sanitary, water supply and drainage
installations showing all lines/fixtures etc in the manner specified by the E-in-C.
The Contractor shall also arrange statutory inspection and certification of the
aforesaid installations by local authorities in conformity with the bylaws.
Failure to do so then E-IN-C shall get the above done at the cost of contractor.
Clause 9
Payment of Bills
The contractor shall submit the final bill within 1 month of the date of the final
certificate of completion furnished by the E-in-C. No claims after that.
Payments of undisputed items will be made within the period as below, reckoned
from the date of receipt of the bill by the E-in-C, complete with account of
materials issued by the BSNL and dismantled materials:
i) If the Tendered value is upto Rs.5 Lakhs: 3 months
ii) If the Tendered value is more than Rs.5 lakhs: 6 months
Clause 9A
Payment of Contractor’s Bill to Banks
Payments due to the contractor may, if so desired by him, be made to his bank
instead of direct to him provided that the contractor furnishes to the Engineer-in-
Charge necessary documents
Clause 10
Cement & Steel:-
The contractor shall submit every month statement of cement, reinforcement steel
and PVC Pipes procured, consumed and balance at site, supported by complete
calculations I/C total consumption and certified balance (diameter/ section-wise in
case of reinforcement steel) and resulting variations and reasons thereof.
Clause 10 A
(1)Materials to be provided by the Contractor:-
The contractor shall, at his own expense, provide all materials, required for the
works for testing.
The E-IN-C shall within 30 days intimate to the Contractor whether samples are
approved by him or not.
(2)The contractor shall bear all charges and cost of testing.
Clause 10 B
Secured Advance on Non-perishable Materials:-
(i)To be paid as already work being done No secured advance, shall be paid on
high-risk materials such as ordinary glass, sand, petrol, diesel etc.
(ii) Mobilisation advance not exceeding 5 % of the estimated cost put to tender or
5% of tender value whichever is less may be given.( But E/cost should be 2 Crore
& above.)
Clause 10 C :-
Payment due to Increase/ Decrease in Prices/Wages after receipt of Tender for the
work:-
If the prices of materials and/or wages of labour required for execution of work
increases, the contractor shall be compensated for such increase as per provisions
of this clause and the amount of contract shall be accordingly be varied subject to
the condition that no such compensation shall be payable if the stipulated period
of completion is 18(Eighteen) months or less. Provided always that the provisions
of the clause 10CA & 10 D shall not be applicable for contracts where provisions
of this clause are applicable but in cases where provisions of this clause are not
applicable, the provisions of clause 10 CA & 10 D hereinafter shall be applicable.
Clause 10(CA) :-
As per this clause after submission of tender if prices of cement and/or steel
reinforcement bars increases beyond the prices prevailing at the time of the last
stipulated date of receipt of tenders for the work then the amount of the contract
shall accordingly be varied and provided further that any such variation shall be
affected for stipulated period of contract including the justified period extended
under clause-5 of the contract without any action under clause-2 subject to the
condition that no such compensation shall be payable for the work for which
stipulated period of completion is 03 months or less.
Clause 10 D:-
Payments on account of increase in Wages due to Statutory Order(s).:-
(1) For Contracts with stipulated time of completion less than 18 months, if after
submission of the tender, the wages of labour increases as a direct result of the
coming into force of any fresh law or statutory rule or order.
And such increase exceeds ten per cent of the wages prevailing at the time of the
last stipulated date for receipt of the tenders i/c extensions if any for the work
and the contractor thereupon necessarily and properly pays in respect of labour
engaged on the work such increased wages, the reimbursement shall be made only
on the excess over 10 % .
(2)Provided that any such increase in the opinion of the S.E. (whose decision shall
be final and binding on the contractor) is not attributable to any delay on the part
of the contractor.
(3)No reimbursement shall be payable if such increase has become operative after
the contract or extended date of completion of the work.
(5)Also the contractor shall, within a reasonable time of his becoming aware of
any alteration in the wages of labour, gives notice for the same.
Clause 11
Works to be executed in accordance with Specifications, Drawings, Orders
etc.
The contractor shall execute the whole and every part of the work in strict
accordance with the specifications, design, drawings and instructions by the
Engineer – in – Charge.
Clasue-12
Deviations, Variations Extent and Pricing Provisions
The E-in-C shall have power to make alteration, omission, additions, or
substitutions for the original specifications, drawings, designs and instructions
that may appear to him to be necessary or advisable during the progress of the
work .
Contractor shall be bound to carry out the work in accordance with any
instructions given to him in writing signed by the E-in-C.
He has to carry out on the same conditions in all respects including price on
which he agreed to do the main work except as hereafter provided.
The time period shall be extended due to increase in cost over the tendered
value, if requested by the contractor, as follows:
(i) In the proportion of extra work plus
(ii) 25% of the time calculated above or any other period which is decided
by Competent Authority i.e.
(iii) 1.25x (A/B)xT
(iv) A= cost of additional work.
(v) B= Tendered amount
(vi) T = time for completion of work
Cl 12.2
(if the deviation limits of the contract are exceeded):-
In case of contract items, substituted items, contract cum substituted items or
additional items which individually exceeds the deviation limits in the contract,
the contractor shall within 15 days claim revision of the rates, supported by proper
analysis.
In the event of the contractor failing to claim within 15 days, the E-in-C shall
make payment at the rates as specified in the Schedule of Quantities or those
already determined under sub-paras (i) to (ii) of condition 12.1.2 for the quantities
in excess of the deviation limit.
Cl 12.4
The E-in-C shall intimate to the contractor the sanctioned rates of items falling
under the sub–clauses 12.1.2(i) to (ii) above within 3 months of written orders to
carry out the work
And in case item falling under sub-clauses 12.1.2 (ii) and clauses 12.2, within 3
months of intimation of rate claimed by the contractor.
Cl 12.3—provisions of 12.2 applies to decrease in rates also & ENC after giving
notice & considering reply of contractor will revise the rates as per reduced
market rates.[ Try to do it within 3 months of reply from the contractor].
Under no circumstances the contractor shall suspend the work on the plea of non-
settlement of rates or disputes in the rates of the items falling under the above
clauses.
Deviated Items
Deviation means deviation in quantities of items in agreement.
JTO/SDE are responsible to assess the anticipated deviation and to initiate
Deviation Item Statement.
They shall allow the execution of deviated items only after prior approval of
competent authority.
Deviations, even though they are as per Modifications in drawings made by the
Architects, cannot be done without prior approval of Technical Sanctioning
Authority.
AO/Auditor to be responsible to bring to the notice of EE about items whose qty
has exceeded agreement qty when bill is received in EE‘s office.
Extra/Substitute Items
Extra Items – Completely new and in addition to (not a replacement) the items in
contract.
Substituted Items – In lieu of already provided with partial modification in items
of work in the contract.
No extra/sub item should be executed without prior approval of the TSA.
In case of works TS by SDE/EE, the E.I./Substituted items not to exceed 30% of
agmt amount and beyond 30% approval of next higher authority reqd.
Clause 13
Foreclosure of Contract
(i) Foreclosure of contract due to abandonment or reduction in scope of
work.
(ii) The contractor shall have no claim for payment or compensation for
reduction in scope of work; changes in drawings, specifications, designs or
any alternations as desired by Engineer –in- Charge.
(iii) Even in case work is abandoned, this clause is applicable - thus no
compensation payable.
Clause 14
Suspension of Work
It could be either due to default of contractor or due to for reasons other than this
then specific provisons exists in the clause for the same.
Clause 15
Inspection and supervision of work
Work open to inspection by QA/CTE etc & contractor to be present for receiving
instructions.
Clause 16
Rectification of defects
(i) If either E-in-C or the Sr. DDG(BW) or QA or CTE finds that any
work has not been executed properly as per contract, the contractor
shall (which shall be intimated to contractor within six months of the
completion of the work not withstanding that the same may have been
passed, certified and paid for) forthwith rectify the work.
(ii) If contractor fails, then get it done at his risk & cost & decision of E-
in-C will be final & binding.
(iii) Proviosn of acceptance of item at Reduced rates is also there in this
clause.
Clause 17
(i) Contractor liable for damages, defects during maintenance period.
(ii) Six months Maintenance period for works costing up to 15.00 Lakh
except road works.
(iii) For works costing more than 15.00 Lakh maintenance period shall be
:-
a) If any damage happens to the work while in progress from any cause
or any faults appear in the work within 12 months after a certificate
final, the contractor shall make the same good at his own expense.
b) The S.D. shall not be refunded before the expiry of 12 months after
the issue of the certificate final or otherwise, of completion of work, or
till the final bill has been prepared and passed whichever is later.
Clause 18
Contractor to Supply Tools and Plants etc.
Clause 18A
Recovery of Compensation Paid to Workman
Clause 18B
Ensuring Payment & Amenities to Workers, If Contractor Fails
Clause 19
Labour Laws Compliance by Contractor
Clause 21
Work Not to be Sublet, Action in Case of Insolvency
Work not to be sublet by the contractor.
Contractor cannot sublet the work or appoint agent for the work by General
Power of Attorney without written approval of Engineer –in-Charge.
Clause 22
Changes in Constitution of Firm to be Intimated in Advance.
Clause-25
Settlement of Disputes & Arbitration
What is a Dispute?
If the contractor considers that he is entitled to any extra payment over and above
the amounts admitted to pay by the BSNL.
If the contractor wants to dispute the validity of any recoveries made or proposed
to be made from the contract.
Conciliation Proceedings
(i) Conciliatory Authority-CE for his NIT.SE for his NIT & for NIT of
EE/SDE
(ii) The party initiating conciliation shall send to the other party a written
invitation to conciliate.
(iii) Conciliation proceedings shall commence when the other party accepts in
writing the invitation to conciliate.
(iv) If the other party rejects the invitation, or does not reply within 30 days,
there will be no Conciliation Proceedings.
(v) Settlement agreement [ it has same effect as of arbitral award] shall be
drawn, if both parties are agreeing to settle the dispute as per formulated
terms of Conciliator.
(vi) If a settlement does not appear possible, the Conciliator, after consultation
with the parties shall terminate the Proceedings.
(vii) On failure of CP, the party, which initiated the Conciliation shall, within a
30 days of termination give a notice to the Chief Engineer for appointment
of arbitrator.
Arbitration Proceedings
1. The party invoking arbitration shall give a list of disputes with amounts
claimed in respect of each dispute along-with the notice for appointment
of arbitrator.
2. The CE shall appoint a sole arbitrator.
3. The arbitration shall be conducted in accordance with the provisions of
the A & C Act 1996.
4. The arbitrator shall adjudicate on only such disputes which are referred
to him by the appointing authority.
5. Arbitrator shall give separate award against each claim referred to him.
6. The arbitrator shall give reasons for the award for each dispute referred
to him.
7. If any fees are payable to the arbitrator these shall be paid equally by
both the parties.
Clause 28
Action where no Specifications are Specified
Action in works where specifications are not specified then follow this sequence:
o BIS.
o Manufacturer‘s specs
o District specs
o As per direction of E-IN-C
Lien and withholding of contractor‘s payments in respect of sum due from the
contractor as per this clause.
Clause 31
Water and Power Supply:-
Contractors shall make his own arrangement for water and power supply and
nothing extra shall be paid.
Clause 31 A
Departmental Water/Power Supply
If Departmental water supply is given for Work:
1% water charges on gross amount of work done shall be recovered.
Contractor to make own arrangement for laying of pipe line as required
from source of supply of water.
Similarly contractor to install sub meter and extend power supply from
tapping point & cost will be recovered from his bills.
Clause 36
Employment of Technical Staff and
Employees
1) More than Rs. 5.0 lacks but less - Diploma in Civil Engg.
than Rs. 10.00 lacks.
Contractor before commencement of work shall give the Name, Age, Experience,
Qualification, Address, and Certificates for Engineers/Technical staff employed
for the work. If contractor himself is a qualified engineer-not necessary to
employ site engineer.
Clause 37:-
Levy / Taxes Payable by Contractor
1) Sales Tax and any other taxes on materials shall be paid by Contractor.
2) The contractor shall pay royalty and obtain necessary permits for supply
of sand, stone, kankar (aggregate) etc. from local authorities.
Clause 38
1. Reimbursement of Levy/ Taxes, if levied after last date of receipt of
Tender
2. If contractor actually pays & intimates within 30 days of their
implementation
3. Decision of SE is Final
Clause 42
Recovery for Inadequate Consumption Of Materials---
As per Schedule ´F´
Clause 42:-
Return of Material & for Excess Materials
Store materials issued to contractor (cement, steel etc. ) have to be
returned by the contractor after completion of work.
Cement:
For works not more than Rs. 5.0 lacs - 3% minus
For works more than Rs.5.0 lacs - 2% minus
In case of steel 3% wastage due to cutting into pieces is (on plus side) allowed for
calculating theoretical quantities.
For the balance materials, if not returned by the contractor, recovery at the
rate specified in schedule F is made.
Clause 45
Release of S.D. after Labour Clearance
Contractor produces a clearance certificate from the Labour Officer. If no
complaint is pending, on record till after 3 months after the completion of the
work and/or no communication is received from the Labour Officer to this effect
till six months after the date of completion, it will be deemed to have received
the clearance certificate and the Security Deposit will be released if otherwise
due
Clause-46
Insurance
Main Provisions
1. The Contractor shall at his own cost take insurance in the joint names of the
BSNL and the contractor.
Questions:-
1. What are the provisions of clause-2 of the contract about levy of
compensation? Briefly discuss powers of various authorities about levy of
compensation under clause-2 of the contract.
2. What are the circumstances under which work can be rescinded/
determined under clause-3 of contract? What are the provisions about
forfeiture of various deposits of the contractor under the contract?
3. Briefly discuss about provisions made for, under clause-10 for payment of
escalation to contractor for increase in wages/prices of material/cement &
steel.
4. Please detail the provisions made under clause-12 for deviation and extra
items. Please list out the steps and order as to how the rates of
extra/substituted items are derived?
5. Clause-13 of the contract relates to which actions under the contract?
Please elaborate.
6. Briefly discuss about clause-25 of the General conditions of contract
regarding conciliation and arbitration proceedings.
7. What are the penalties which can be imposed on the agency under clause-
36 for non employment of technical staff and employees by the
contractor?
8. Briefly discuss recovery provisions for cement and steel under clause-42
for inadequate consumption?
9. What are the various insurance covers which a contractor should get done
before the start of work? Please mention the relevant clause also. In case
of failure by the contractor, what are the remedial measures?
10. What are the provisions made under clause-6 about measurement of
works? What are the notices and time periods under this clause for
satisfactory performance of tasks?