Vous êtes sur la page 1sur 11

OTC 18561

Comparison and Advantages of Underbalanced and Managed-Pressure Drilling


Techniques: When Should Each Be Applied?
Kent Ostroot, Sara Shayegi, Derrick Lewis, and Randy Lovorn, SPE, Halliburton Energy Services

Copyright 2007, Offshore Technology Conference


Introduction
There is some debate in the industry as to what constitutes
This paper was prepared for presentation at the 2007 Offshore Technology Conference held in
Houston, Texas, U.S.A., 30 April –3 May 2007. MPD and UBD and whether one is a subset of the other.
This paper was selected for presentation by an OTC Program Committee following review of
While all drilling can be considered a form of “managed
information contained in an abstract submitted by the author(s). Contents of the paper, as pressure drilling,” since the pressure must be controlled or
presented, have not been reviewed by the Offshore Technology Conference and are subject to
correction by the author(s). The material, as presented, does not necessarily reflect any “managed” for safe drilling, the industry has adopted this
position of the Offshore Technology Conference or its officers. Electronic reproduction,
distribution, or storage of any part of this paper for commercial purposes without the written
terminology to specify certain drilling practices different from
consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print conventional overbalanced drilling.
is restricted to an abstract of not more than 300 words; illustrations may not be copied. The
abstract must contain conspicuous acknowledgment of where and by whom the paper was The IADC has defined managed pressure drilling as “an
presented. adaptive drilling process used to precisely control the annular
profile throughout the wellbore.” MPD objectives are to
Abstract ascertain the downhole-pressure environmental limits and to
The difficulties often experienced in drilling a well using manage the annular pressure profile accordingly.1 An
conventional overbalanced drilling have led to increased underbalanced drilling operation is described as “an operation
consideration of under-balanced (UBD) and managed-pressure in which the hydrostatic head of a drilling fluid is intentionally
drilling (MPD) techniques. Under-balanced drilling designed to be lower than the pressure in the formations being
techniques were initially adopted to provide solutions to drilled.2”
drilling problems, but it soon became evident that this For the purposes of this paper, the difference between
technique could also minimize reservoir damage. In spite of UBD and MPD is that for UBD, the target bottomhole
its many benefits, UBD has not been embraced by the industry circulating pressure is maintained below the reservoir or pore
as readily as would have been expected. Equipment-rental pressure throughout the openhole section, while for MPD, the
costs and limitations on application of the techniques offshore, target bottomhole circulating pressure is designed to be at or a
either due to regulations limiting hydrocarbon flaring or little above the pore pressure throughout the openhole section.
formation instability, are often cited as the reasons for its slow There are some exceptions such as when there are several
acceptance. As an intermediary mitigation, MPD was formation pressures in the openhole section; however, the
developed. objective in MPD is primarily to preclude influx from the
Each technique has its place, and which solution is formation while drilling, while the opposite is the case with
applicable depends on the problems faced. MPD cannot UBD.
match UBD in terms of minimizing formation damage,
allowing characterization of the reservoir, or identifying UBD and MPD Comparison
productive zones that were not evident when drilled MPD and UBD are both focused on controlling bottomhole
overbalanced; but when the objective is simply to mitigate circulating pressure during drilling; however, the two methods
drilling problems, MPD can often be as effective as UBD and differ technically in how this is accomplished. Whereas MPD
is more economically feasible. MPD is also preferable where is designed to maintain bottomhole pressure slightly above or
1) wellbore instability is a concern, 2) when there are safety equal to the reservoir pore pressure (i.e. overbalanced or at
concerns due to high H2S release rates, or 3) when there are balanced drilling), UBD is designed to ensure that bottomhole
regulations prohibiting flaring or production while drilling. pressure (BHP) is always below the reservoir pore pressure
This paper will help to identify the situations appropriate (i.e. underbalanced drilling), so that it will induce formation
for each technique and the benefits that can be expected. fluid influx into the wellbore, and subsequently, to the surface.
Differences between the two techniques concerning equipment A comparison of the two methods can be performed by
requirements and the potential for reservoir characterization considering the objectives for the project, the equipment
will be analyzed also. Results from UBD and MPD case requirements, and potential benefits/risks of each method.
histories will be used to qualify the results from these With regards to design objectives, it has been established
operations. that MPD is employed primarily to solve drilling-related
problems, although some reservoir benefits also may be
achieved. This is not surprising, since any effort to decrease
2 OTC 18561

the degree of overbalance, and thus, the impact of drilling To summarize, two of the primary reasons for selecting
fluid on a formation usually will have some positive reservoir MPD over UBD are 1) wellbore instability concerns during
benefits. UBD, on the other hand, has long been employed to UBD, and 2) the desire to reduce equipment requirements to
solve both drilling-related and reservoir-related problems.3,4 improve cost efficiency. However, basing the decision on just
The primary difference, therefore, between UBD and MPD these criteria ignores the possibility that significant reservoir
concerns the degree of resolution attainable with each method benefits also could be realized with UBD and that equipment
for both the drilling-related and reservoir/production-related requirements really depend on the reservoir to be drilled, since
problems. in some cases, MPD may require an almost equivalent setup as
MPD is often seen as easier to apply compared with full UBD.
UBD operations. Often, in non-reservoir sections, MPD
design requirements may determine that a simpler equipment Reservoir Benefits
package will satisfy safety considerations for the well, and The reservoir-related or production-related benefits of UBD
therefore, the day rate would be reduced compared to going all (and to a much lesser extent, MPD) are significant when
the way to full underbalance. Another consideration is that in compared with conventional overbalanced drilling (OBD).
UBD, if there is multi-phase flow, the gas phase interferes Primarily, these benefits are seen through higher productivity
with certain logging-tool measurements, which typically of UBD wells.
would not present a problem in an MPD operation. In fact, reduction in damage to the reservoir compared
As has been described, equipment requirements for both with conventional OBD of some MPD wells only recently
operations vary considerably, depending on the design have been recognized in the industry. UBD, on the other hand,
parameters of the project. In many instances, the same has a long history of having proven that it has the capability to
equipment setup is necessary for UBD as well as MPD maximize well productivity, thereby ensuring higher sustained
methods. The distinguishing feature in the difference in production rates compared to conventional wells. Historically,
equipment setup is that smaller-sized separation equipment many wells that have been classified as UBD have in fact been
could be used for the MPD setup, as large fluid influx would MPD where some portion of the drilling was underbalanced;
not be expected during drilling. Additionally, due to the fact however, overbalanced conditions occurred often or were used
that wellhead pressure changes are used to control MPD for completing a well drilled underbalanced. This had the
operations, some level of automation of the surface system is effect of reducing or even eliminating any productivity gains
needed for quick, uninterrupted reaction to changes in from UBD, thereby giving the false impression in many
downhole conditions. This type of automation could be instances that UBD had little or no impact on reduction of
required to enhance UBD operations as well. formation damage and improved productivity.
Comparison of the benefits of the two methods will be High productivity wells in a reservoir means that a
described separately in terms of the drilling-related as well as minimum amount of pressure drawdown is required to meet
reservoir/production-related benefits. field production targets. This helps maximize hydrocarbon
recovery from the reservoir by lowering the abandonment
Drilling Benefits pressure. Even with extended period of exploitation of the
Historically, the major reason for companies to explore reservoir, the undamaged well outperforms the damaged wells
alternative drilling techniques such as UBD and MPD has in terms of recoverable reserves.
been the incapability to drill the well using conventional The incremental benefit of UBD wells as a function of
overbalanced drilling (OBD) methods. Drilling problems that wellbore skin factor has shown that in the short term, there is
have driven the use of UBD or MPD techniques in the past not a significant difference in the cumulative production from
have included: wells with much lower skin factors because of constraints with
• the need to minimize or eliminate formation damage surface handling facilities, etc.5 These differences increase in
• small formation pressure/fracture gradient window the intermediate term, and then, begin to decline. Thus, an
• desire to minimize well cost by: MPD well that is designed to reduce reservoir damage to some
1. minimizing fluid losses residual value (other than full cleanup to zero skin) will
2. eliminating differential sticking ultimately under-perform a UBD well with a skin factor of
• increase the rate of penetration zero.
• extend bit life, etc. One additional reservoir benefit of UBD compared to
• increase safety in drilling operations. MPD is its capability to allow comprehensive evaluations
It is important to mention here that while UBD has the during drilling to be conducted. Due to deliberate suppression
potential to eliminate formation damage, MPD only has the of reservoir influx during MPD, identification of productive
potential to reduce it compared to conventional overbalanced intervals as well as determination of some petrophysical
drilling. Nonetheless, residual damage in the near-wellbore properties, these productive zones cannot be evaluated
area after drilling is still likely. Residual formation damage of directly. We note that the use of logging-while-drilling (LWD)
an MPD well can be as high as that of a conventionally-drilled and measurement-while-drilling (MWD) tools provide the
overbalanced well. means for determining some reservoir properties directly.
Additionally, both UBD and MPD have the potential to However, it is only a properly executed UBD job that has been
reduce drilling fluid costs significantly through the use of designed for reservoir fluid inflow, which provides a platform
cheaper, lighter fluid systems and elimination or significant for full evaluation of reservoir parameters, including the
reduction of mud losses. presence of possible nearby boundaries during drilling.
OTC 18561 3

To be able to perform this evaluation, an adequate data evaluated should also include the potential for stuck pipe,
acquisition system is essential. Different UBD and MPD hard-rock drilling, and possible rate of penetration (ROP)
setups, as discussed in the equipment section, will determine improvement, lost circulation problems, presence of sour gas
the amount of data that it is possible to obtain from the and operational feasibility. Preliminary wellbore-hydraulics
operation, and it is important early on in a project to determine modeling is performed to determine the operational feasibility;
the objectives of the operation and the types of analyses i.e., if underbalanced (UB) conditions are possible and if it can
sought. Different reservoir properties can be obtained with be maintained throughout the entire hole section while
UBD and MPD; the zone-by-zone characterization with UBD maintaining adequate hole cleaning and satisfying the
is only possible with systems with adequate bottomhole target downhole motor limits. If there are multiple candidates,
pressure control, separation, metering, and data-acquisition characteristics of each of these would be compared, and an
systems. initial ranking would be performed. The wells would be
For performing reservoir characterization while drilling ranked according to the key variables that would have the
underbalanced, more data will be required, and typically, a highest potential for success and the least chance of risk.
minimum number of channels capable of capturing all surface Once it has been concluded that a particular prospect is a
data are required where the additional data from the drilling candidate or is ranked high among a group of prospects, then
rig, bottomhole pressure, temperature, gamma ray and the optimal UB technique would be selected. Next, an
resistivity, and mudlogging information is transferred to the evaluation of the potential production improvement will be
data acquisition system via another method such as a Wellsite investigated. Reservoir properties play the most important role
Information Transfer Specification (WITS) system. in the success of UBD, since reservoir modeling will
The total data-management software systems vary for determine how much formation production might be expected
different service providers, and these typically can display at while drilling UB. Different scenarios are modeled, the results
least the minimum data such as the pressures, which include of which are used in both the detailed wellbore-hydraulics
wellhead pressure (WHP), stand pipe pressure (SPP), and flow modeling and the economics evaluation.
bottomhole pressure while drilling (PWD) if used in the If there are multiple candidates that have been evaluated in
operation, gas and liquid rates injected and produced, depths, detail, a final comparison is performed, and the potential
torque, WOB, and pit volumes required to control the impact of benefits and limitations of applying UBD are
operation safely. This basic data would be available in an compared so that the best candidate can be selected.
MPD operation or an underbalanced operation where reservoir UBD technology is not the solution to all problems, and
characterization is not needed. If reservoir characterization is project success depends on correct determination of the wells
required for underbalanced drilling or control, and automation where the technology is most applicable. The importance of
is sought for a managed-pressure operation, then total data- this evaluation will be seen if the well objectives primarily
management software would be required to provide the focus on solving drilling solutions, since MPD might prove to
capability to integrate all worksite well information from be a more economical solution.
whatever source for real-time display and data manipulation at The final qualification for an underbalanced candidate
the rig site, and optionally, in the client’s office. depends on the economic evaluation, which approximates the
A system for reservoir characterization in UBD or possible cost difference between UBD, MPD and conventional
automated control for MPD would require capability to OB drilling. It is here that the quantified productivity
monitor all pressure, temperature, levels, and flow-rate improvement becomes an important factor. At this time, other
information normally associated with the surface separation technologies such as stimulation are compared with the
package. Additionally, wellbore hydraulics and reservoir possible results from underbalanced drilling. In Fig. 1, an
behavior simulation would be required for a complete process. example is shown in which the economics for a well where
The reservoir characterization system would also require UBD, MPD are considered as alternatives to conventional
capability to accept, manage, store, and display bottomhole, drilling are compared. This example is based on actual data
mud logging, and rig-site data and integrate it for ease of from a field where MPD as well as conventional drilling was
analysis and interpretation. performed, and UBD was being evaluated to see if the
potential production gain would outweigh the added cost of
Candidate Selection / Economics achieving full-underbalanced conditions and maintaining them
Proper candidate selection is critical to the success of both throughout the drilling and completion phase. The costs used
UBD and MPD projects. It is essential that the main project are based on the actual applied formation evaluation (AFE)
objectives are identified at the beginning of the project to not for the MPD and offset conventional wells with similar
only ensure that they can be achieved, but also to determine geometries and depths. The AFE for the UBD well is
which technique; i.e., UBD or MPD, is most appropriate for estimated based on typical costs for UBD services in this area.
the candidate well or reservoir. The drilling report for each well was used to determine the
The candidate selection process consists of analyzing nonproductive time (NPT) due to drilling problems as well as
geomechanical and petrophysical information to determine to estimate mud losses, number of bit runs required, and ROP.
whether or not a particular well and/or reservoir is a potential These were taken into account in formulating the economics
candidate by evaluating some of the main reservoir and case for each scenario. For the UBD well, the improved
wellbore characteristics. These would include the type of productivity was based on the reservoir properties and logs
formation damage in the well and the possible effect that UBD showing productive formation. The number of bits, ROP, NPT
would have on its mitigation and wellbore stability. The info time for the UBD well was taken to be the same as for the
4 OTC 18561

MPD well. The production with UBD was more than 4 times and data acquisition system able to accurately measure and
that from the OBD well, which had skin damage. Production capture all required data. Many equipment setups are possible,
starts when the reservoir section is being drilled, since it is and best practices should always drive the design of the
assumed that production is sent to facilities. For MPD, the system to appropriately handle the well potential safely. This
production improvement was twice that from the well drilled is one key point that at times has been ignored in some
conventionally. This meant that the UBD case became the instances to the detriment of the safety of the operation.
best option (as shown in Fig. 1) when the improved A typical UBD setup for primarily addressing drilling
productivity was taken into consideration. For the UBD problems would include at minimum a rotating control device
scenario, the net revenue is 21% higher than the one for OBD, (RCD) plus a choke and open or closed surface separation
and “break even” is reached much earlier than in the MPD or system. If the reservoir is very depleted, then an upstream gas
OBD scenarios, because of the additional benefit of early and generation and/or compression system would be required. If
higher production. The net revenue for MPD is about 5% the objective of the UBD operation is reservoir focused,
higher than the one from conventional. If little or no additional metering, a geologic sampler for continuous
improvement in production occurred with UBD to balance its reservoir description, and a 3-phase or 4-phase fluid-
additional cost and only its drilling benefits were considered, separation system typically would be used with an adequate
then MPD was the best option from an economics standpoint. data-acquisition system to capture all the surface, rig and
This would be the scenario where the primary objective is to bottomhole data.
address drilling problems and reduce NPT, and the costs Surface equipment used in the industry for what is now
associated with mud losses, where the section drilled is not termed “managed pressure drilling” can also vary widely. The
productive or the reservoir is of marginal quality with low equipment can vary from a simple wellhead rotating-control
productivity capability or damage has been found not to be an device tied to rig flow lines to comprehensive UBD-type
issue. equipment. Note that as reservoir fluids are not intended at the
MPD can be applied at the surface or in intermediate surface, some MPD operations do not use a separation unit.
and/or reservoir well sections and all wells types as is the case However, it is important to remember that in MPD operations,
for UBD, however, adequate consideration of the application as with any overbalanced operation, it might be necessary to
as well as the equipment requirements are critical, as in some control “influx” if underbalanced techniques are applied, and
cases, MPD may not be capable of solving the drilling therefore, it will be necessary to have contingency and well-
problems encountered. An example of this situation might be control plans in place to handle such a contingency.
when the fracture pressure is too close to the pore pressure or This is especially true when there are different pressure
when there are variations in pore and fracture pressures in regimes that may be encountered, and the area is unknown. At
different intervals within the same open hole. These cases times, a separation package is required to handle influx safely
may require the design to consider underbalance in some or to minimize time spent on conventional well control during
sections while overbalance in others in order to drill the well an MPD operation. When designing the system, safety and
economically and successfully. drilling efficiency must be addressed adequately.
In some cases, when UBD cannot be applied because it is For the most basic MPD operation, the equipment needed
not technically and/or economically feasible (such as when the will include a rotating control device, which is tied into the
wellbore may not be stable or the risk of high release rates of flow lines of the drilling rig. Any influx from the reservoir
sour gas on surface is possible), MPD could be the best will be treated like a kick in conventional drilling, and well
solution. control operations will be initiated.
Where downhole pressure control is desired, both a
Surface Equipment Requirements rotating control device and a dedicated manual or automated
Key components of a surface equipment package for choke system is required. As previously mentioned, any
underbalanced drilling can include: reservoir fluid influx is treated as a kick, and conventional
• wellhead rotating control device or RCD well-control operations are initiated with the kick being
• downstream choke-manifold system circulated out often using the rig’s kick control system as with
• open or closed fluid-handling systems including conventional overbalanced drilling operations.
downstream fluid-separation package – 3-phase or 4- When the margins between the pore pressure and fracture
phase separation system gradient are narrow, the system can benefit from an automated
• upstream gas generation and fluid compression/ control system. In this case, the equipment required in
injection systems addition to the RCD and an automated choke system would be
• geologic sampler. a method to meter the fluids in and out, bottomhole and
Note that these equipment systems typically come with surface pressures, and a control system that would have
auxiliary flow lines, emergency shutdown (ESD) systems, different levels of complexity. Full automation of the choke
pumps, metering devices, data-acquisition systems, holding manifold system means that bottomhole pressures (BHP) can
tanks, mud pits, flare stacks, etc. be strictly controlled so that losses and kicks are minimized
Several equipment setups can be derived from a during drilling. Since any reservoir-fluid influx is treated as a
combination of these key equipment components – from kick, well control operations are used to circulate the kick out
simple to the most complex. The full package would include through the rig’s kick-control system. With an automated
all the equipment mentioned above plus a high end metering choke and control system where very careful monitoring of
flow into and out of the reservoir is performed, any kick will
OTC 18561 5

be detected very early, and often, it can be circulated out the project plan while drilling the first well from full UBD
without initiating full kick-control procedures, since the mode to MPD mode in order to avoid thinning out the mud
volume may be on the scale of trip gas, depending on the system, and thereby, increasing surface backpressure
sensitivity of the system; however, this degree of automation requirements. By balancing the formation pressure throughout
has yet to be fully implemented. As experience grows, and the the last part of the well, further thinning of the rather
optimum equipment, metering, detection, and control methods expensive K-Formate brine was avoided. The liner was run
are put in place and tested further, reliance might be placed on and cemented successfully at balance, allowing access to
automation. However, these systems will need redundancy drilling the reservoir overbalanced.
methodology and personnel supervision with safety Based on the lessons learned from the first well, it was
contingencies in place to ensure safe drilling operations. planned to drill the cap rock in the second well in balanced
If there is a high possibility of formation influx, it might be conditions. The work scope was expanded, however, to
more efficient to add a surface-separation package. The need include drilling the reservoir section at balanced pressure and
for a downstream, fluid-separation system assumes that there to test the feasibility of this technology. The reservoir is very
is the potential for fluid influx from the reservoir during productive with high permeability, and near-wellbore damage
drilling due to several reasons; i.e., very narrow or inverse was not thought to be a significant consideration.
pore pressure/fracture gradients, intervals with different pore Additionally, it was expected that there would be the potential
pressures, or an extremely high-permeability reservoir, all for depleted reservoir zones in conjunction with prolific
with the potential for high production that could overwhelm a reservoir sections; therefore, MPD appeared to be a better
rig’s gas-buster system. In this case, an adequate separation solution than UBD.
system should be used to optimize the drilling of these This well also became a test case, since if MPD proved
formations, since it will be possible to circulate kicks with the viable, then this would pave the way for drilling more
separation package with added safety procedures and fluid challenging reservoirs in the field with this technology. The
handling systems. Thus, the reservoir influx will be processed first section through the cap rock was drilled successfully in
and handled safely by this pressurized separation package. two runs with the K-Formate drilling fluid and a targeted
However, if at all possible, the well will be kept in an bottomhole pressure. The openhole was then sealed off with a
overbalanced condition, and influx will be treated as a risk that 7-in. liner and cemented at balance similar to the first well.
can be neutralized with the pre-planned presence of a surface When drilling the 6-in. hole with the K-Formate brine, it
separation package for handling of any effluents. became apparent that the formation was becoming
If the formations are depleted, then, an upstream gas- increasingly unstable. This created problems cleaning the hole
generation and fluid-compression/injection system may be properly with the limited flow rate available. Hole conditions
needed to obtain the lower degree of overbalance needed to deteriorated with time, and pack-off situations occurred.
stay within the pore and fracture pressures through the Ultimately, it was decided to plug and abandon the first
depleted reservoir sections. The need for the gas-generation section and drill a new sidetrack. It was suspected that the
and/or compression system is always dictated by the reservoir mud might be creating the problems, and it was decided to use
pressure and the available drilling-mud system. a proven oil-based mud (OBM) system. The openhole
sidetrack with a motor assembly was used to enable higher-
MPD Case History – Offshore angle doglegs, and the hole condition seemed stable during
To address the severe lost-circulation problems being faced by this period. Drilling at balanced conditions proceeded. At this
the operators in this offshore North Sea field, underbalanced time, no further problems were experienced, and the
drilling was implemented initially.6 This was one possible remainder of the reservoir section was drilled uneventfully at
solution for meeting the challenges of drilling through the balanced conditions.
highly fractured caprock to get to the reservoir. The operators In Fig. 2, the result of manual choke control on the last
of this field had experienced severe pressure control and lost- part of the well using Barite-weighted 1.45sg OBM can be
circulation problems, and these had resulted in the suspension seen. The pressure envelope for the reservoir drilling was
of several wells during attempts to access the reservoir targets. fairly large in this case; therefore, auto choke control was not
Drilling these wells with conventional means was not possible critical. The bottomhole equivalent circulating densities
because of the small margin between pore pressure and (ECDs) varied up to 0.05 sg (10 bar) with manual operation of
fracture gradient. The primary issues needing resolution for the hydraulically actuated, remote-controlled chokes. It was
this project, therefore, were drilling problems. determined that for tighter margins, an automated choke-
In the first well, a clear Potassium (K)-Formate brine was control system would be required.
used with a sufficiently high density to minimize surface The implementation of MPD technology allowed the
pressure and the risk of hole collapse. While drilling the well operator to drill previously abandoned wells, which could not
underbalanced, it was found that the produced fluid was be drilled with conventional means. It was found that full
primarily water. This was a problem since continuing to drill UBD was not needed to address the drilling problems and that
underbalanced with a controlled influx would add more water drilling balanced or slightly overbalanced was the best option
to the active water-based drilling fluid system effectively for overcoming the problems encountered in reaching the
decreasing the K-Formate concentration and mud weight. It target depths, both through the caprock as well as through the
was decided to drill the remainder of the well at balance to reservoir section. The success of the drilling of these wells
minimize formation influx, which would eliminate produced has enabled the following best practices to be established:
water and preserve the drilling-fluid properties. This changed
6 OTC 18561

1. Cost effective solids-weighted mud, both water and oil- and the formation is much more consolidated. The hole
based types, were verified to be viable. sections range from 10,000 to 20,000 ft TVD.
2. Choke control was verified to be within acceptable limits The main objectives for this project were to design a
for this application. For projects where the difference flexible drilling system to cover the wide range of pressures
between fracture gradient and pore pressure is small, an (pressure gradients from 2 to 8.34 ppg) to minimize the
automated choke-control option should be considered. amount of overbalance because of the low margin between the
3. Based on the lessons-learned, shut down activation and pore and fracture pressures and to reduce or eliminate
potential plugging of chokes has now been implemented problems such as differential sticking and lost circulation.
as a preventative measure to automatically shut off the Moreover, MPD was implemented to precisely manage the
mud pumps This feature has been incorporated in the bottomhole pressure to reduce fluid and solids invasion to the
design for future wells to prevent fracturing the formation and to prevent hydrocarbon and H2S production to
formation in such an instance. surface.
4. In rapidly changing project conditions, it is vital to Some of the challenges included designing a stable drilling
conduct a detailed review of all systems in order to avoid fluid for the expected depths and high temperatures,
incompatibility issues with drilling fluid ― a situation implementation of H2S monitoring and control, and reservoir-
that could cause problems both downhole and on pressure uncertainty and hole instability that were due to
surface. mechanical stresses and not chemical sensitivity.
Since the initial plan in this project was for underbalanced Complete reservoir sections were drilled using MPD
drilling, a pressurized separation vessel was part of the techniques in wells with known reservoir pressures. If
equipment setup. This added flexibility to decision making, reservoir pressure was unknown, the wells were drilled with
especially at this stage where there were many unknowns. an 8.34-ppg drilling fluid until fractures were encountered;
The use of this equipment was invaluable for starting up these consequently, fluid loss was detected, and reservoir pressure
MPD operations in an area where all reservoir parameters are was estimated from the static fluid level. Then, MPD
not known. Its use has provided many design requirements operations were designed and implemented using this
that can be optimized for future MPD operations in the same calculated reservoir pressure.
field. Two fluid systems were designed to cover the entire range
of pressures ― a recyclable high-temperature foam system for
MPD Case History – Onshore the 2.0 to 5.0 ppg range and a nitrified-fluid system for the 4.0
In the previous field case, it was shown that MPD was adopted to 8.34 ppg range. Both fluid systems were interchangeable,
after it was found to satisfy the requirements and objectives of since the same polymers at different concentrations were used
the project better than UBD, which originally had been and easily could be controlled to mix the base fluid and the
implemented. In contrast, one of the main conclusions noted chemical injection to generate and break the foam.
for this case history is that even though MPD resulted in Control of the bottomhole pressure (BHP) was based on
successfully overcoming the drilling problems, UBD should precise selection of critical operation parameters such as
be attempted in several future wells to evaluate the injection flow rates, fluid properties, and chemical injection
productivity gains that could be made by avoiding formation control. During MPD operations, important variables were
damage. measured, recorded, and displayed at the rigsite and/or
MPD was applied in this multi-well project in Southern transmitted to other locations, allowing engineers to monitor
Mexico to drill a deep, depleted, fractured, and the ongoing operations and make adjustments to the main
compartmentalized reservoir with widely variable pore operational parameters in order to satisfy the target BHP. This
pressures that were creating significant challenges during the was required to closely and accurately control the BHP. The
drilling process as described by Miller et al.7 The case history degree of overbalance or underbalance would be determined
described here used an equipment the full MPD equipment by precise measurement of net losses and gains of both liquid
setup including: RCD, manual choke-manifold system, ling and gas.
systems including downstream fluid-separation package – 3- In two wells, two different sections with different reservoir
phase separation system, upstream gas generation and fluid pressures in the same pay zone were identified, and fluid
compression/ injection systems and geologic sampler as seen losses could not be maintained at the initial minimum
in Fig. 3. Although offset wells were also drilled using MPD requirement, increasing from 5 to 30 bbls/hr. Therefore, some
techniques, the actual reservoir pressures were found to be hydrocarbon production was handled at surface using a
much lower in these wells and represented greater drilling separate closed-tank system.
challenges. The successful implementation of MPD in this project
Since wells in this area present varying hole conditions, included results such as improvement of the process from
two primary zones have been distinguished: North and South. lessons learned while drilling very challenging hole sections
The wells in the north area are more highly fractured due to with changing hole conditions; increased rate of penetration
their proximity to a salt dome; the reservoir is more (ROP) (although it was controlled to avoid hole cleaning
compartmentalized, the reservoir pressures are much lower problems); and drilling times were approximately 50% less for
(from 2.9 to 5.9 ppg), and additionally, there is a weak sections where MPD was implemented when compared with
transition zone causing wellbore instability problems. In the other OBD wells in the area. When the wells were brought on
south area, the reservoir pressures are higher (4.8 to 7 ppg), for production, the clean up times for these wells were also
reduced by about 15%.
OTC 18561 7

MPD proved to be an effective solution for the drilling determined that micro fractures were also contributing to the
problems the operator was facing, and at the same time, it production in these zones, and skin damage was prevalent in
showed some of the potential benefits of UBD resulting from the smaller fractures in the network that contributed flow to
the improvements in production. Because of these successes, the larger fractures and openhole in the near wellbore area. In
this technique is being evaluated for future implementation in the next wells, the project implementation included guards
a fully underbalanced mode. against going overbalanced, and therefore, it was possible to
maintain underbalanced conditions from start through
UBD Case History completion. No skin damage was observed, and higher
When a severe loss zone prevented conventional drilling from productivity was achieved, although all wells were very much
accessing the reservoir in several onshore wells, UBD was more prolific than the offset wells. From analysis of the near
implemented to 1) solve drilling problems by maintaining wellbore damage created for the first underbalanced well, it
underbalanced pressure control to minimize losses while could be seen that some productivity was lost, and even
drilling to total depth (TD), and 2), to minimize reservoir though some of the damage cleaned up with production,
damage and evaluate productivity of different intervals. residual skin damage remained. Should MPD have been
This application required high-end data acquisition, using employed, it is probable that the same amount of damage
both pressure-while-drilling gauges and additional downhole would have resulted; however, it is likely that the amount of
memory gauges for controlling BHP. In some wells, two types damage would have been higher since balanced or
of gas meters were used to allow constant monitoring of the overbalanced conditions would have been maintained through
gas rate. Data were transmitted via satellite to the service most of the drilling, and as with the offset wells, stimulation
company’s reservoir evaluation center where analysis was might have been required.
carried out in real time and included conducting of periodic The production improvement seen with underbalanced
flow tests and pressure build-ups in some wells. drilling showed a ~10-fold increase over the sustained offset
Other wells drilled in the area generally produced in the overbalanced well rates and a 5-fold increase compared to the
range of 8-12 MMScf/d after some type of stimulation best stimulated well in this and offset fields.
treatment. The area is highly faulted, and these faults can Another important advantage gained was the opportunity
form sealing barriers although sufficient data were not yet for the reservoir characterization that only UBD allows.
available to confirm that this possibility existed. It was To determine the reservoir characteristics while drilling in
thought that the reservoir was still close to the original these UBD wells, a full UBD package as described previously
reservoir pressure, although there was the potential for varying with the high-end data acquisition system was required. It was
pressures, if multiple compartments were to be traversed. possible to have both a PWD as well as additional downhole
Drilling underbalanced in these sandstone and fractured memory gages for downhole bottomhole pressure, which
carbonates proved to be successful. It was possible to drill allowed verification of this very important parameter.
into the reservoir section without any losses. Additionally, in several of the wells, two different types of gas
Savings resulted from several sources when UBD was meters, which allowed for verification and cross-check of the
compared with the conventionally drilled wells. These gas rate at all times, were used. The acquired data were sent
included a reduction in nonproductive time (NPT), bit runs, via a satellite transmission system to the service company’s
number of bits used, savings on mud, and stimulation costs. reservoir evaluation center, where the analysis of the data was
NPT from conventional overbalanced drilling resulted in time carried out in real time. Periodic flow tests, and for some
spent controlling the well and dealing with stuck pipe. wells, pressure build-ups were conducted along with the
Additionally, there were savings in bit runs where typically 6 normal analysis of the data acquired while drilling ahead.
to 8 bits were required when drilling overbalanced in this Throughout the drilling of the underbalanced well, the rate
interval. During underbalanced drilling, only 2 to 3 bits were and pressure data were analyzed, and the formation properties
used for the high-compressive-strength rock. determined. In Fig. 4, an excerpt from the data that had been
What makes this project extraordinary is the production normalized is shown. The bottomhole pressure, actual
improvement seen in the underbalanced wells. This measured rate, and calculated predicted rate using proprietary
improvement would probably not have been seen if the wells underbalanced analytical software is shown. As a result of the
had been drilled MPD, since the formation was found to be capability to provide continuous analysis, it was seen that after
very sensitive to damage, even with limited short periods of a period of overbalance, some reservoir impairment was
overbalance as experienced in the first UBD well. sustained, although with continued production, some of this
Since the primary objective was to address drilling damage was cleaned up. It was determined that multiple
problems when first implementing UBD, the project plan did primary zones were actually responsible for the production
not require maintaining underbalanced conditions at all times seen, one of which had not been productive previously when
through to completion. In fact, during trips and sometimes at drilling had been overbalanced. In fact, it had been
connections, the system experienced periods of overbalance. completely overlooked!
When evaluating the data using the UBD simulator, it was
found that these periods of overbalance resulted in some skin Conclusions
damage. This was contrary to what had been previously Underbalanced and managed pressure drilling are not new
assumed in the industry, namely that a highly fractured technologies, however their potential has yet to be fully
carbonate could suffer much damage due to the high realized by the industry.
conductivity. Although macro fractures were present, it was
8 OTC 18561

MPD and UBD both address drilling problems and reduce When determining which technique should be applied, the
non-productive time by minimizing losses and differential benefits and limitations of each technique should be both
sticking as well as the time associated with well control events qualitatively and quantitatively considered, and a decision to
typically associated with conventional overbalanced drilling. “do what’s best for the well” should be reached depending on
Reservoirs benefiting most from UBD are those formations the merits of each technique.
prone to damage. These can include all types of formations,
although significant benefits have been seen in naturally- Acknowledgments
fractured reservoirs by minimizing any damage to the micro- The authors wish to thank the management of Halliburton
fractures, and identifying fracture swarms. In addition, it has Energy Services, Inc. for their support in the preparation and
been seen that UBD allows comprehensive reservoir presentation of this paper and Carolyn Williams and Nancy
characterization while drilling, which may help reduce time Woods for comprehensive editing and review.
and cost associated with conventional methods of gathering
and analyzing well-test data. In some cases, the data collected References
has led to the discovery of previously unseen zones. 1. Alberta Energy Utilities Board Interim Directive 94-03,
In view of these benefits, the industry has been slow to “Underbalanced Drilling”, July 1994.
adopt UBD in some of the regions with high equipment rental 2. Schmeigel, K.:“UBD Techniques Optimize Performance”, Harts
costs, regulatory limitations offshore, and unstable formations E&P, October 2005.
3. Benesch, J.M. and Nor, N.: “Optimization of Big-Bore HTHP
such as in the Gulf of Mexico. Additionally, UBD has not Wells to Exploit a Low Pressure Reservoir in Indonesia,” paper
shown the anticipated productivity benefits due to practices in SPE 87171 presented at the 2004 SPE/IADC Drilling
the industry that have allowed periods of overbalance to take Conference, Dallas, TX, Mar. 2-4.
place, which have been documented to cause formation 4. Ansah, J., Shayegi, S., and Ibrahim, E.: “Maximizing Reservoir
damage. Often, a well performs very well during Potential using Enhanced Analytical Techniques with
underbalanced drilling until an overbalanced event or a trip Underbalanced Drilling,” paper SPE 90196 presented at the
occurs, when in many cases, the well is overbalanced to pull 2004 SPE Annual Technical Conference and Exhibition,
out or is at the completion phase. There are several techniques Houston, TX, Sept. 26-29
5. Finley, D., Shayegi, S., Ansah, J., and Gil, I.: “Reservoir
available to keep the well underbalanced or at-balance during
Knowledge and Drilling – Benefits Comparison for
the entire drilling and completion process ― yet these have Underbalanced and Managed Pressure Drilling Operations,”
not yet been fully adopted by the industry. Further paper SPE/IADC 104465 presented at the 2006 SPE/IADC
development and implementation of these methods is needed Indian Drilling Technology Conference and Exhibition,
for them to become standard practice. Mumbai, India, 16-18 October.
Another difficulty seen in the industry is that UBD is often 6. Tonnessen, T., Larsen, B., and Ronneberg, A.,: “Underbalanced
viewed as complex and costly. By addressing the concerns Equipment meets Challenges in MPD Applications Offshore
stated above specifically, MPD has emerged as an Norway,” Drilling Contractor, March/April 2006.
intermediary solution between full underbalanced drilling and 7. Miller, A., Boyce, G., Moheno, L., Arellano, J., Murillo, J.,
Aguilar, M., Lopez, A., Moreno, A., Perez, C.: “Innovative
conventional overbalanced drilling to mitigate drilling
MPD Techniques Improve Drilling Success in Mexico” paper
problems. SPE 104030 presented at the 2006 First International Oil
The industry has now embraced MPD more fully Conference and Exhibition in Mexico, Cancun, Aug. 31 - Sept.
compared to full UBD, since it is often easier; however, it is 2.
important to remember that each of these techniques has its
place. MPD cannot match UBD in terms of minimizing
formation damage and enhanced production resulting in SI Metric Conversion Factors
improved overall well value. Additionally, UBD allows °F (°F - 32)/1.8 =°C
characterization of the reservoir, which has yet to reach full ft x 3.048* E - 01 = m
exploitation by the subsurface engineers. in x 2.54* E + 00 = cm
On the other hand, when the objective is to mitigate psi x 6.894 757 E + 00 = kPa
drilling problems, MPD can often be less costly than gal x 3.785 412 E - 03 = m3
maintaining full UBD to attain these drilling objectives due to ft x 3.048* E - 01 = m
reduced equipment requirements. MPD is also preferable bbl x 1.589 873 E - 01 = m3
where wellbore instability could be a concern during UBD or
when there are regulations on flaring or producing while *Conversion factor is exact.
drilling.

RTRETM is a trademark of the Halliburton Company


OTC 18561 9

UBD

MBD

OBD

Fig. 1 ― Comparison of Net Revenue vs. time considering revenue generated from production for UBD, MPD, and OBD.

40 1.75
U/S Choke Pressure
39
ECD reprocessed Recorded 1.74
38 ECD WITS RT
1.73
37
36 1.72
35
1.71
34
1.7
33
32 1.69
S.G. Equivalent
Pressure (bar)

31
1.68
30
1.67
29
28 1.66
27
1.65
26
1.64
25
24 1.63
23
1.62
22
1.61
21
20 1.6
00:00:00 02:09:36 04:19:12 06:28:48 08:38:24 10:48:00 12:57:36 15:07:12 17:16:48 19:26:24 21:36:00 23:45:36
Time July 6, 2005

Fig. 2 ― Real time and memory BHP VS Choke pressure for MPD offshore field case.
10 OTC 18561

Fig. 3 ―Equipment rigged up at location for MPD onshore field case.


OTC 18561 11

Bottom Hole Pressure


Interpreted Reservoir Pressure
Production Rate

Pressure
Measured Rate

Calculated/Predicted Rate

04-10 15:36 04-10 20:36 04-11 01:36 04-11 06:36

Fig. 4 ― UBD RTRE analysis showing predicted and measured rate along with measured bottomhole pressure.

Vous aimerez peut-être aussi