Académique Documents
Professionnel Documents
Culture Documents
Lecturer – U Myint Oo
Presented by
Eaint Yadanar Khin (ME.CM - 2)
Yoon Mone Mone Khin (ME.CM - 3)
Than Zaw Htike (ME.CM - 4)
Moe Hein Kyaw (Dip.CM – 1)
Shar Lae Win (Dip.CM - 3)
Htet Wai Yee Aung (Dip.CM - 4)
(1) Introduction
Contracts and agreements are customized according to our clients’ needs and specific
requests. To help clients navigate the legal issues that arise throughout the multiple stages of
their business life cycle. To prepare a good contract, we must know the legal laws that are
applicable laws. Laws are related with everyone. Legal is the applicable law that are very useful
in every business especially in construction business. There are many types of contracts – among
them, lump sum contract is the common contract. In this assignment, we selected the lump sum
contract that is between the main contractor and the developer. In construction industry, the
following eight contract types are so far practiced:
1. Lump Sum Contract,
2. Bill of Quantities or Unit Rate Contract,
3. Cost Plus Fixed Fee Contract,
4. Cost Plus Percentage of Cost Contract,
5. Item Rate or Schedule of Rates Contract,
6. Labor Contract,
7. Hybrid Contract and
8. Special Contract
Lump Sum Contract: when the project or tender price is determined and quoted as a total
sum of money without individual ratings to execute the whole of the works and / or services
according to the drawings and specifications, it is called a Lump Sum Contract. It is difficult to
administer changes and amendments but experiences of similar projects are used as a basis to
this effect, Works or services are checked based on the specifications, the conditions of contract
or terms of reference and drawings if any for acceptance and closing of accounts and Payments
are agreed at different stages of works or services. A Lump Sum Contract is more suitable for
works of smaller in size and where the contracting parties have prior experience of similar
project. But it is not advisable for projects with considerable uncertainties such as; difficult sub
surface situation, unusual projects, maintenance projects, etc. a Lump Sum Contract mainly
includes Contract Agreement, Conditions of Contract, Drawings and Technical Specifications.
When we prepare the contract, legal concerns are also one thing that are considered in
the contract. Therefore, in the form of contract – we must need to write the problems
encountered in the construction industry since we prepare the contract. Among these problems,
especially legal has many disputes, claims and so on. Legal system refers to a procedure or
process for interpreting and enforcing the law. It elaborates the rights and responsibilities in a
variety of ways. Three major legal systems of the world consist of civil law, common law and
religious law. Jury system is a legal system for determining the facts at issue in a law suit. Tax
system is a legal system for assessing and collecting taxes. Electoral system is a legal system for
making democratic choices. Legal tender is currency that cannot legally be refused in payment of
debt.
(2) Objective
❖ To understand the legal concerns between the main contractor and developer
❖ To understand the practices of contracts that are fully aware in construction industry
❖ To understand the legal issues that are associated with the construction industry
(3) Possible Disputes in Construction and Resolution Method
Incomplete contract documents invariably lead to claims from contractors for extension of time
and additional compensation. When owners have tight budgets or are reluctant to pay more for a project, a
dispute results. The dispute leads to further increased costs, frequently with associated legal costs.
(3.7)Construction Defects
During the course of construction, the owner may identify work that is not in conformance with
the plans/specifications. If the contractor/subcontractor does not agree with the owner's assertion of that
defective construction, a dispute arises. Typically, both the general contract and subcontracts allow the
owner and general contractor, respectively, to order the removal and replacement or repair of the
allegedly defective work. Assuming the contractor/subcontractor complies, it will have a claim against the
owner at the conclusion of the project if the contractor/subcontractor had conformed to the plans and
specifications.
(3.8)Dispute Resolution Methods
Discussion of construction disputes from the legal perspective would not be completed without a
discussion of the various types of dispute resolution methods.
(3.8.1)Termination
Termination, whether by the owner or the contractor, is the ultimate “dispute.” Typically, contract
provisions allow the owner to terminate the contractor for cause if the contractor:
(1) fails to supply properly skilled workers or proper materials;
(2) fails to make payments to subcontractors;
(3) disregards laws, statutes, ordinances, codes, rules, and regulations; or
(4) substantially breaches the contract documents.
The contractor, whether provided in the contract or not, can terminate if the owner is in material breach of
any of its contractual obligations, the most prevalent of which is failure to pay.
(3.8.2)Mediation
Whether it's during the course of construction (less frequent) or after the project is complete,
mediation is arguably the most satisfying of dispute resolution method. It can occur as early in the process
as the parties are able to organize mediation and identify/schedule a mutually agreeable mediator.
However, mediation is typically most successful after the parties, their attorneys, and the consultants have
had an opportunity to review the other side's project files and prepare whatever impact/delay analysis may
be necessary. Because mediations are nonbinding, they involve a neutral mediator understanding each
side's position/settlement appetite and then bringing the parties together in settlement.
(3.8.3)Arbitration
Arbitration was the favored form of dispute resolution in the construction industry, at least when
the owner was able to dictate the form of dispute resolution. The theory was that arbitration was both
speedy and economical because the parties and arbitrators scheduled it at their convenience. Unless the
parties otherwise agreed, there was no discovery or jury as there is in litigation, and no appeal. Finally,
the arbitration panel was comprised of individuals knowledgeable in the construction industry.
(3.8.4)Litigation
Litigation is dispute resolution in the courts, where all parties are subject to all of the forms of
discovery, such as interrogatories, requests for admission, document production demands, and
depositions. The parties then have a trial, either by a court alone or by jury. If the parties are dissatisfied
with the results, they have an appeal as a matter of right. Historically, litigation has a reputation for being
a long, expensive process. That's one key reason why arbitrations came into vogue on construction
disputes.
(3.8.5)Government Claims Procedures
In the public sector, there are often requirements that contractors must first file a government
claim and even go through an administrative hearing procedure before they can proceed to arbitrate or
litigate their claims.
(3.8.6)Reading the Contract before Executing
Lastly, there is no substitute for reading each contract very carefully before signing it. Beyond
the obvious problems of errors and inaccurate information that creep into negotiated contracts, careful
review may reveal additional risks, improperly allocated risks, and other issues. No agreement is perfect,
but vigilant contract review is one of the most crucial steps in the risk management process
4. Permits Problems
4.6Performance Bond
The Government and private sector require performance bonds and payment bonds for
projects to protect the tax payer’s investment.
Common performance and payments bonds for government projects consist of building
bridges and roads, although it can comprehend much more than only those two categories. If the
contractor does not complete the project specified in the contract the surety bonding company
will either pay for the completion of the project or hire a contracting firm to complete the project.
A performance bond will protect the owner against possible losses in a case a contractor
fails to perform or is unable to deliver the project as per established and the contract provisions.
Sometimes the contractor defaults or declares himself in bankruptcy, and then in those situations,
the surety is responsible for compensating the owner for the losses. Such compensation is
defined as the amount covered under the performance bond.
Payment from the performance bond is available only to the project/property owner and
no one else can make claims against it.
In order for a performance bond to be effective, the contract must be specific about the
work to be done and because of this, a contractor cannot be held accountable for vague
descriptions that are open to interpretation.
5. Environmental Risks of Construction
Based on the Environmental Conservation Law 2012, the following are the high level of
awareness and commitment with regard to protecting the environment among owner, contractors
and others involved in the construction industry.
Owners may impose liquidated damages for delays in project turnover. When the owner
assesses liquidated damages, the cost can be crippling to a contractor, especially if the owner is
retaining funds or withholding progress payments. A contractor should negotiate with the owner
if delays arise. Some states have pro-contractor laws that provide a remedy for untimely
payments from an owner. Knowing the state’s contractor protection laws is key to managing a
project when delays arise.
A thorough negotiation of owner or contractor-caused delays can address costs for owner
acceleration or suspension, workforce supplementation, mobilization or escalation costs, weather
or other delays. If problems arise early in the project, a contractor can hire an independent expert
to assess schedule delays and begin building the claim for additional compensation. Force
majeure clauses can protect a contractor in the event of unforeseen delays, but in some locales,
performing a project in snow, rain or heat may be reasonable job conditions.
General contractors spend a great deal of their time balancing costs on their projects. To
ensure profitability, they must control material, labor, and overhead costs while continually
receiving payment from clients. The task is difficult and a number of factors affect a contractor’s
ability to do this. One such factor is the varying costs of materials and labor. If fuel or building
materials cost the same when you bid the project as it does halfway through the project that
would be excellent. Unfortunately, that’s seldom the case, especially in our fluid economy.
The contractor’s primary tool for combating this is the escalation clause. An escalation
clause is a provision in a contract that calls for adjustments in fees, wages, or other payments to
account for fluctuations in the costs of raw materials or labor. This clause shifts the burdens for
increasing materials and labor costs from the contractor to the client. It’s an important clause to
include in your contract, so it’s helpful to have an Orlando construction lawyer review your
contract before submittal.
Escalation clauses can apply to any cost that is subject to fluctuation based on market
conditions. However, escalation clauses are most commonly seen in conjunction with fuel, steel,
and asphalt costs.
Fuel costs: If you follow the news, you know that oil prices fluctuate regularly and over the
course of a year, there can be sharp increases and decreases. Escalation clauses are designed to
protect contractors from those changes.
Steel costs: An escalation clause can be used here to adjust to fluctuations in the steel cost
adjustment index.
Asphalt: Escalation clauses apply to fluctuations of asphalt cement based on average price in a
geographic area.
It’s important to note in each case that escalation clauses are meant to protect contractors from
sharp increases that are beyond the normal fluctuation of market prices.
In the construction industry, legal concerns are also important in the contract. The
construction is also related with the legal, so it is also written in the contract. In lump sum
contract, the contractor mostly has the responsibility but there also has the indirect loss for the
developer. For example, if the project can be damaged because of the equipment that is borrowed
by the main contractor, so the main contractor has the responsibility but the developer has the
indirect loss, eg. the project must be delayed. Therefore, we must write the protection ways for
the problems and risks in the contract before we start the construction. If the risks are
encountered although written the protection ways in the contract, we use the system of risk
management. First, identified the risks - the all reasons that can be negative impacts are defined
as the risks. Second, we analysis the risks – how much the degree of impact, how to eliminate the
risks and the best result is the zero impact. Third, we must prepare the medication measures by
planning the risk control measures. In legal concerns, if the equipment is needed to be used – the
equipment is maintained and running good condition – these facts are also included in the
contract. The certified company can be also called the third party test this equipment then give
the approval and certificate for this equipment that is safe for use. If there have an accident – if
the company buys the insurance, compensation will be okay for this equipment but people are in
accident, there has very complicated legal issues in it. Therefore, also write down how to protect
legally these accidents in the contract. In lump sum contract, the most responsible person is the
contractor but there has indirect loss for the developer.
References
❖ Lecture from Sir U Myint Oo
❖ Sources from Internet