Vous êtes sur la page 1sur 12

AUTCON-01758; No of Pages 12

Automation in Construction xxx (2014) xxx–xxx

Contents lists available at ScienceDirect

Automation in Construction
journal homepage: www.elsevier.com/locate/autcon

Building Information Modeling (BIM) application framework: The


process of expanding from 3D to computable nD
Lieyun Ding a, Ying Zhou a,b,⁎, Burcu Akinci b
a
School of Civil Engineering & Mechanics, Huazhong University of Science & Technology, Wuhan 430074, China
b
Civil & Environmental Engineering, Carnegie Mellon University, Pittsburgh 15213, USA

a r t i c l e i n f o a b s t r a c t

Article history: The utilization of Building Information Modeling (BIM) has been growing significantly and translating into the
Received 20 September 2013 support of various tasks within the construction industry. In relation to such a growth, many approaches that
Received in revised form 19 March 2014 leverage dimensions of information stored in BIM model are being developed. Through this, it is possible to
Accepted 14 April 2014
allow all stakeholders to retrieve and generate information from the same model, enabling them to work
Available online xxxx
cohesively. To identify gaps of existing work and evaluate new studies in this area, a BIM application framework
Keywords:
is developed and discussed in this paper. Such a framework gives an overview of BIM applications in the
BIM construction industry. A literature review, within this framework, has been conducted and the result reveals a re-
3D search gap for BIM applications in the project domains of quality, safety and environmental management. A com-
nD putable multi-dimensional (nD) model is difficult to establish in these areas because with continuously changing
Computable conditions, the decision making rules for evaluating whether an individual component is considered good
Modeling quality, or whether a construction site is safe, also vary as the construction progresses. A process of expanding
from 3D to computable nD models, specifically, a possible way to integrate safety, quality and carbon emission
variables into BIM during the construction phase of a project is explained in this paper. As examples, the process-
es of utilizing nD models on real construction sites are described. It is believed to benefit the industry by provid-
ing a computable BIM and enabling all project participants to extract any information required for decision
making. Finally, the framework is used to identify areas to extend BIM research.
© 2014 Elsevier B.V. All rights reserved.

1. Introduction point for practitioners to better understand how BIM can be applied
on their projects.
Many researchers have evaluated the effectiveness of Building Infor- From a previous research review, it is seen that utilization of BIM in
mation Modeling (BIM) applications within different educational or in- the construction industry can help practitioners by improving visualiza-
dustrial settings [1]. In addition, many practitioners have acknowledged tion, communication and integration in construction operations [11].
the potential benefits of this new technology, such as Sacks et al. [2], However, some practitioners still hesitate to adopt these innovative
Chen et al. [3] and others [4,5]. To date, BIM is accepted as a process tools [12]. Some surveys have been conducted to evaluate the extent
and corresponding technology to improve the efficiency and effective- and benefits of applying BIM in the construction industry in different
ness of delivering a project from inception to operation/maintenance countries [13–16]. According to the survey conducted by Young, archi-
[6]. In the last decade, BIM has received a considerable amount of atten- tectural/engineering/construction (A/E/C) participants did not identify
tion by researchers. A number of case studies have been published that much value in using BIM [12]. Therefore, a framework is needed to un-
show useful BIM implementations on actual construction projects. In derstand the clusters of work and less focused areas to push the re-
The BIM Handbook, 10 case studies have been thoroughly explained search on and utilization of BIM throughout the life-cycle of facilities
[7]. In addition, Hartmann and Fischer proposed to use 3D/4D models for multiple stakeholders. A well-rounded BIM application framework
for design review from the perspective of constructability [8]. Rüppel might give the practitioners a broader view of the use of BIM applica-
and Schatz designed a BIM-based game for fire evacuation simulations tions to support construction project management and help them to
[9]. Zhou and Ding presented a 4D visualization technology for safety better understand the benefits of implementing BIM on their projects.
management [10]. Case studies such as these have served as a starting Formulating a comprehensive framework provides an opportunity
for the researchers to identify future BIM research and implementation
⁎ Corresponding author at: Huazhong University of Science and Technology, Wuhan
directions and it would enable application of these sophisticated
430074, China; visiting scholar at Carnegie Mellon University, Pittsburgh 15213, USA. technologies in the whole life-cycle of projects [17,18]. This paper
E-mail addresses: ying_zhou@mail.hust.edu.cn, yingzhou@andrew.cmu.edu (Y. Zhou). offers a starting point for the development of such a framework. It

http://dx.doi.org/10.1016/j.autcon.2014.04.009
0926-5805/© 2014 Elsevier B.V. All rights reserved.

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009
2 L. Ding et al. / Automation in Construction xxx (2014) xxx–xxx

presents a framework of BIM applications generated from past project extension of BIM [32,39]. Although some have tried to differentiate nD
implementations of BIM. The framework would guide research efforts, from BIM [40], most research has agreed that BIM represents the utiliza-
which will enhance communications, share understanding and knowl- tion of nD models to simulate the planning, design, construction and
edge growth among all the academic researchers and industry practi- operation of a facility [39,41].
tioners, and integrate relevant concepts into a descriptive or predictive Application of BIM can be described as a process that expands 3D
model. A thorough literature review has been conducted to validate data into an nD information model, which allows dynamic and virtual
the framework and identify the current research gap. The process of analysis of scheduling [42–45], costing [46,47], stability [48,49], sustain-
how BIM applications expand from 3D to nD, specifically referring ability [50,51], maintainability [52], evacuation simulation [9,53] and
to quality, safety and environmental management in this paper, is safety [54] to name a few. This nD model provides a database allowing
described. all stakeholders to retrieve needed information through the same sys-
Such a framework would guide practitioners to applications of this tem, which allows them to work cohesively and efficiently during the
new technology and show researchers where the development of whole project life-cycle. Therefore, to be useful to academic researchers
deeper knowledge and better tools is needed. In addition, the main chal- and industry practitioners, a BIM application framework must contain
lenges of implementing BIM applications with potential solutions are three parts: all project management domains (examples are listed
explained. The authors hope that this paper will inspire further develop- above in italics), all stakeholders, and across the whole project life-
ment of the research framework and guide future research into BIM cycle. The three parts of the framework are defined in the following
applications. sections (Sections 3 and 4).

2. Terms and definitions


3. BIM application framework
Building Information Modeling (BIM) is defined as “a digital repre-
sentation of the physical and functional characteristics of a facility. A 3.1. Overview
BIM is a shared knowledge resource for information about a facility
forming a reliable basis for decisions during its life-cycle; defined as This section introduces the proposed BIM application framework, a
existing from earliest conception to demolition [19].” research and delivery map of existing research and implementation
Many terms related to BIM have been adopted by researchers, such projects which identify interrelationships between project domains
as virtual design and construction (VDC) and multi-dimensional (nD) and requirements for further knowledge acquisition. This proposed
modeling. Table 1 lists some of the widely used terms in both research BIM application framework targets stakeholders to better understand
and industry studies and shows a summary of them by application the current state of BIM applications and future BIM implementation
domain. requirements.
A BIM model is different from traditional 3D CAD models in which A BIM framework must be comprehensive enough to address all rel-
3D CAD only describes a facility with independent 3D views, such as evant BIM domains and implementation challenges as well as to present
plans, sections and elevations. If one of those views is modified, the key issues of project management in a systematic manner. On the basis
others must be updated accordingly. Further, data in 3D CAD drawings of the definition of BIM, this application framework consists of three
are only graphical entities, such as lines, arcs and circles. On the parts: 1) project domains listed, 2) stakeholders and 3) phases of the
contrary, a BIM integrates semantically rich information related to the project life-cycle. These are shown as the three axes in Fig. 1.
facility, including all geometric and functional properties during the A particular research can be put in this framework using one of these
whole life cycle in a collection of “smart objects” [20]. For example, a six options: 1) single BIM application within a single organization
valve or tube module within a BIM would also include its functional through a single project phase; 2) single application within multiple or-
and performance properties, such as material, supplier, maintenance ganizations through a single phase; 3) single application within multi-
requirements, cost and delivery time, in a semantically rich way. Each ple organizations through multiple phases; 4) multiple applications
component is a “smart object” with all associated parameters stored in within a single organization through a single project phase; 5) multiple
it. The information of the properties can be accessed when needed by applications within a single organization through multiple project
any stakeholder. This important feature of BIM allows stakeholder phases and 6) multiple applications within multiple organizations
access to information and combinations of information to which they through multiple phases.
have never before easy access. For example, as shown in Fig. 2, “a1a2a3a4” represents the utilization
As for other terms, virtual reality (VR) provides a tool which allows a of BIM for safety management from the owner's perspective, while
user to experience a computer-generated simulation of a real or imag- “b1b2b3b4” represents the utilization of BIM for cost management from
ined environment [21–23]. 4D modeling utilizes BIM for project time the perspective of different stakeholders, which are, in this case, the
allocation and construction sequence scheduling simulations while owner, the contractors and the supervisors, also known as owner's
VDC is becoming a more accepted industry term to explain the use of representatives. The “c1c2c3c4, d1d2d3d4” area represents the utilization
BIM to design and construct a project [37]. of BIM for design review during the planning and design phases by
In terms of nD modeling, some researchers use nD to describe the different stakeholders. In this framework, application of BIM in the
different maturity levels of BIM [38]. Some researchers define nD as an construction industry can have 6 different levels based on the project

Table 1
Differences between widely used terms and BIM.

Sample terms Information can be retrieved Design review Performance simulation Virtual simulation of Management of site Maintain facility Reference
from 3D building elements construction process constraints operations

3D CAD √ [20,21]
Virtual reality (VR) √ √ [21–24]
4D modeling √ √ √ [25–28]
VDC √ √ √ √ √ [29–31]
nD modeling √ √ √ √ √ √ [32,33,39]
BIM √ √ √ √ √ √ [7,97]

Other related terms: Integrated project delivery [34], computer integrated construction [35], building product models [36].

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009
L. Ding et al. / Automation in Construction xxx (2014) xxx–xxx 3

Fig. 1. BIM application framework.

management tasks that are aimed for, the project stakeholders that are May 2013, are considered as recent work. In total, there are 135 papers.
involved in and the different phases that BIM is used in. This time-frame does not cover the early stages of BIM research in the
built environment, but is extensive enough to identify the emerging
3.2. Current research within BIM framework research and development for BIM. The key words for searching are
“Building information modeling”, “Building information model” and
Recently, there has been a large quantity of work in BIM. It is “BIM”. As the purpose of this paper is to focus on the implementation
necessary to comprehensively review recent significant BIM work in of BIM, those articles that concentrated solely on BIM concepts or IT
its application. The main objectives of this review are to: 1) validate techniques rather than BIM applications in the built environment are
the framework proposed in Section 3.1; 2) reveal research gaps; and not included.
3) try to evaluate future research and development trends. Within the 135 papers, the current research can be categorized into
The selected papers are from leading built environment journals in the following groups: 1) some explained and advanced the industry
the information technology research area. The searched journals are foundation class (IFC) data schema [55–57]; 2) some explored how in-
Automation in Construction, ASCE Journal of Computing in Civil Engineer- formation is exchanged among different environments [58,59]; 3) some
ing, Advanced Engineering Informatics and Journal of Information Technol- proposed approaches to extract information from complex BIM models
ogy in Construction. The articles, published from 2006 to as current as [60–62]; 4) some tried to evaluate the benefits [4,30,63] and identify the

Fig. 2. Geometric interpretation of BIM application framework.

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009
4 L. Ding et al. / Automation in Construction xxx (2014) xxx–xxx

Fig. 3. (a) Percentage of BIM publications from the viewpoint of project management domain; (b) percentage of BIM publications from the viewpoint of project life cycle.

challenges [64] of BIM; and 5) some started to establish a BIM frame- Since performance and functionality of a facility can be analyzed
work for different purposes [97,40,65,66]. In terms of the BIM imple- based on 3D models, 3D based applications can be applied in the design
mentation studies, Fig. 3 depicts the percentages of BIM research phase and operations phase. For example, energy consumption, facility
articles within the framework presented in the above sections. In performance and evacuation procedures can be simulated and evaluat-
some research, other techniques such as Augmented Reality (AR) ed before the facility is constructed. The results of these assessments can
[67–69], Radio Frequency Identification (RFID) [70,71], Laser Scanning help architects improve design proposals. In addition, after the facility
[72,73] and Geographic Information System (GIS) [74–76] are proposed has been constructed, the information stored within 3D models can be
to be combined with BIM to assist in quality inspection, data acquisition used for operations management, and maintenance plans can be auto-
and other functions. matically generated from the previously entered “smart objects” in the
The percentages of different research articles from the viewpoint of shop instructions for each component. From the previous research re-
the project management domain and project life cycle are shown in view, it is known that 3D based applications such as design review are
Fig. 3. Papers that focus on multiple domains for multiple phases are the most common studies in this early stage of nD application research
counted under each relevant category. From the literature study, few [91]. Much research has been conducted into 3D applications, specifical-
authors mentioned for whom their system/products were designed or ly in the design review, evacuation simulation, energy performance and
what stakeholders would benefit from the research [77,78,88]. As the facility management domains.
requirements for different stakeholders are not the same, it might be However, 4D models are needed to depict, visualize and analyze the
easier to get the industry to implement the research products on real constantly changing variables that occur as the construction phase pro-
construction sites if the authors addressed the benefits to specific users. ceeds. As 4D models provide virtual visualization of the construction
It is not surprising that design review has the highest percentage of process, BIM applications for the construction management, specifically
research articles published. The reason might be because design is the the schedule, cost, quality, and safety control, should be based on 4D
longest-standing application of BIM and feedback of design-related models.
BIM activities is in relatively high frequency [79]. However, BIM re- Time, cost and quality have been the basic criteria for project success
search articles for the construction phase are rapidly catching up to [92] while safety and environmental impact gained a lot of concerns in
the pace for the design phase. Also, schedule management articles are recent years [93]. In some research, quality, safety and environmental
tied for second place for specific domain articles. At least partially, impact are proposed to be important aspects in construction manage-
these results are because the benefits of BIM applications in the design ment as establishing a risk free work place and reducing environmental
phase have captured so much attention from researchers and practi- pollution are vital for a successful project [94]. It can be seen from Fig. 3
tioners in the built environment, that many of them have begun to ex- that there is a BIM related research gap for the project domains of qual-
tend the application area of BIM to the construction phase [77]. ity, safety and carbon emissions. In comparison to other domains, few
Table 2 lists all the references to papers that belong in this category. research studies have has been conducted so far in these domains. The
Within the articles focused on the construction phase, safety manage- reason might be that these project domains are more complicated to
ment, quality management and low carbon emission research are a quantify than cost management and schedule control. For the schedul-
relatively low percentage in research literature. ing and cost management domains, it is easy to retrieve and compare
Based on the review of the literature, BIM applications can be the actual data to the planned schedule and project budget, and man-
classified into two categories which are listed in Table 3: 1) 3D based agers are constantly updated with this information. However, because
applications and 2) 4D (3D models plus schedule) based applications. of continuously changing conditions, the standards or decision making
rules, for evaluating whether an individual component is considered
good quality or whether a construction site is safe, vary as the construc-
Table 2 tion progresses. In addition, another reason might be that the main pur-
Papers on the BIM for schedule management during construction phase. pose, for the stakeholders of a construction project, is to gain economic
Classification criteria (from the viewpoint of BIM References profits. Speeding up the progress and saving costs are the most impor-
application framework) tant issues for them. Therefore, establishing the 4D/5D models to man-
Construction phase Schedule management Designer [80,81] age scheduling and costs was the first developmental priority. However,
Supervisor [81–87] with economic and cultural progress, “people-first value” is gaining
Contractor [70,76,78,81–83,85–88] publicity. Gaining economic profits is no longer the only goal of project
Owner [70,81–88] management, as much public attention is being paid to the environment
Operator
and to safety/security.

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009
L. Ding et al. / Automation in Construction xxx (2014) xxx–xxx 5

Table 3
Example categories of prior work on BIM applications.

Project domain Related literature Information integrated Required information


environment

Design review [87,89,90] 3D Geometric data, spatial features, component type, specifications
Evacuation simulation [9,53] 3D Geometric data, spatial features, component type, specifications, social psychological and social
organizational characteristics of the occupants
Energy performance [50,51] 3D Geometric data, spatial features, component type, material information, geographical coordinates
Facility management [52] 3D Geometric data, spatial features, component type, operation specifications
Schedule management [42–45] 4D Geometric data, spatial features, construction schedule plan
Cost management [46,47] 4D Geometric data, spatial features, component type specifications, construction schedule plan,
quantities of component, unit price information

BIM applications have just begun to quantify and objectively analyze 4. BIM application examples
the quality and safety control project domains. A time-space collision
detection model was proposed to optimize a construction plan [95, 4.1. Quality management based on 4D
96]. The structural health of construction components was analyzed
by integrating a 3D BIM model with engineering simulation software Quality management plays a crucial role in the construction indus-
[49]. Previous research provided a qualitative method to combine a try. Difficulties in quality management are primarily caused by the fol-
BIM model with safety or quality information. Limited research has lowing: 1) Quality inspection items for individual components are
been conducted to establish a computable safety/quality BIM model scattered in different national, industrial and urban code guidelines
from the perspective of using mathematics to work out the degree of [98]. Site workers are not usually well-educated people [99]. The neces-
safety or quality status as is possible with cost management and sched- sity of referring to a series of different code books leads to on-site
uling. As the degree of safety or quality status varies with the construc- misunderstanding of quality control standards; 2) Ignorance of the im-
tion moving forward, a computable BIM-based safety or quality control portance of tracking the behavior of on-site personnel making it is diffi-
model is difficult to establish. cult to determine who is responsible for quality accidents; and 3) Most
It has been acknowledged that BIM was used for its 3D visual data at of the existing methods of quality control focus on the completed com-
first, and was then expanded to nD applications [97]. The key challenge ponents, but quality failures occur due to the process of construction
of this expansion is the method to establish the nD model and identify [100].
the types of information that need to be integrated into the 3D model The key process of building a 4D based quality management model is
to accomplish different purposes. The following sections discuss the to establish the POP (product–organization–process) model based on
process of developing computable and 4D based BIM applications for BIM. This is totally different from the cost management model. For
the quality, safety and carbon emission project management domains cost management, once the unit price is linked with the corresponding
as a start point. components and activities, the actual cost and planned cost can be easily

Fig. 4. A hierarchical structure of the product information in a bridge project.

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009
6 L. Ding et al. / Automation in Construction xxx (2014) xxx–xxx

Fig. 5. Inspection items for “monolithic cast-in-place reinforced concrete beam”.

calculated. However, in quality management, such a calculated model information, organization information and process information within
cannot be directly established. A POP model including the quality status one model, specifically referring to a BIM model in this research.
of individual components, the responsible organization, and the quality Product information is defined in this research as a hierarchical struc-
inspection process should be built into a quality management model in ture of the products/elements for different kinds of construction projects.
the construction industry. For example, this hierarchical structure has been established for a bridge
The POP model is proposed to complement 3D product models with project in this research. The monolithic cast-in-place reinforced concrete
process and organization models to support both design and construc- beam can be subdivided into individual elements, see Fig. 4.
tion [101]. This idea is suitable to solve the quality management As discussed before, for each element, the inspection items are
problem in the construction industry because it integrates the product scattered in different national, industrial and urban code guidelines.

Fig. 6. An example of the relationships between “product” and “organization”.

3D Module Activities Quality Checklist 4D-based Quality model


Guidelines

responsible person
concerned

Inspection results

Quality status

Fig. 7. 4D-based quality model of a construction project.

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009
L. Ding et al. / Automation in Construction xxx (2014) xxx–xxx 7

Table 5
Value of severity of consequences Cf.
Quality
Inspection Items Level Guess value Description

The first level 0.0–0.2 The risk severity is extremely small


The second level 0.2–0.4 The risk severity is little
The third level 0.4–0.6 The risk severity is medium
The fourth level 0.6–0.8 The risk severity is high
The fifth level 0.8–1.0 The risk severity is extremely high

BIM component
risk and the affected area shift frequently as activities get executed.
Therefore, safety needs to be controlled from the perspective of both
time and space and, therefore, on the basis of a 4D management tool.
Fig. 8. An example of a BIM component and its related quality inspection items. (For inter- The principle of safety management based on a 4D BIM application is
pretation of the references to color in this figure, the reader is referred to the web version
illustrated below.
of this article.)
The construction sequence of foundation pit construction using the
open cut method includes: 1) Constructing the earth-retaining struc-
Therefore, the inspection items must be evaluated/confirmed by ture; 2) dewatering; 3) excavation of the 1st layer; 4) steel bracing of
measurement against all related codes/guidelines. An example is given the 1st layer; 5) excavation of the 2nd layer; 6) steel bracing of the
in Fig. 5. 2nd layer; 7) excavation of the 3rd layer; 8) steel bracing of the 3rd
For organization information, all stakeholders are responsible for the layer; 9) base plate dredging; 10) base plate setting; 11) steel bracing
quality of construction. For example, in Fig. 6, the responsibilities of stripping of the 3rd layer; 12) median plate; 13) stripping of the 2nd
different participants with regard to the inspection items of a bridge layer; 14) loft plate setting; and 15) stripping of the 1st layer.
product are shown. In Fig. 6, if a block is shaded, it means that the The main safety risks existing in this construction process can be
corresponding stakeholder has responsibilities for the relevant inspec- classified into the following types: 1) retaining pile collapse; 2) land-
tion item. Relationships between “product” and “organization” can be slide hazard in excavation procedures; 3) bracing structure deformation
established by collating the scattered codes/guidelines. in excavation procedures; 4) water inrushing; 5) damage to adjacent
The process of 4D quality information modeling is shown in Fig. 7. buildings; 6) seepage caused by fractured retaining piles; 7) bottom
The 4D-based application is the information carrier for both schedule heave caused by artesian water; and 8) crane operation failures.
and quality information. All national, industrial and urban code guide- Usually, different types of safety risks exist at the same time during
lines regarding one inspection item are integrated as text-based the construction process. Therefore, it is necessary to analyze how
through the BIM application. Then, real-time quality status information different risks combine in foundation pit excavation procedures.
can be continuously displayed within a 4D BIM application. A quality According to the Guideline of Risk Management for Construction of
checklist for each activity can be provided during the 4D simulation. Subway and Underground Works, published by Ministry of Construction
For each component, its related activities and quality checklist can be re- of the People's Republic of China, risk analysis should be evaluated for
trieved at just the right time during construction, see Fig. 8. Therefore, two issues: the probability of occurrence and severity of consequences
the official construction codes/standards can be populated in a BIM for [102]. Therefore, in this research, a method based on dependability is
reference data. Once the inspection data is retrieved, the status of each used to evaluate different types of risks.
component can be generated by comparing actual quality inspection Risk degree r is defined to represent the risk level. Pf stands for
data with the standards. The color of a component reflects the status the probability of consequences and Cf stands for the severity of
of this quality inspection item: Unconstructed (gray), under construc- consequences.
tion (purple), constructed, but not yet inspected (green), inspection
failed (red), and inspection passed (blue). Because a POP model has Therefore; r ¼ 1−ð1−P f Þð1−C f Þ ¼ P f þ C f −P f C f : ð1Þ
been established, not only the quality status of each element can be
continuously retrieved from the model, but also, the responsible stake- The value of Pf and Cf can be retrieved and calculated by the expert
holders can instantly know when quality standards are not met, and investigation method. According to the rules established in Tables 4 to
therefore, they have the opportunity to take immediate corrective 6, an example of the risk level of each activity in foundation pit excava-
action. The results of this corrective action can be traced through the tion using the open cut method is detailed in Table 7. The initial data
model as well. was retrieved by expert investigation. Furthermore, the relationship
among an activity, its main risks, and the affected components/area
4.2. Safety management based on 4D can be established, which is shown in Table 8. Therefore, the safety
risk evolvement pattern can be displayed based on a 4D model, see
The risk level on construction projects rises and falls continuously Fig. 9. It can be used as a dashboard to assist site workers in deciding
during the whole construction process. For example, the safety risk dur- which structural elements are unstable and what behaviors should be
ing excavation of the foundation pit is always high, but drops dramati-
cally after base plate construction is completed. In other words, the
Table 6
Value of risk level r.

Table 4 Level Estimated Color-coded Description


value
Value of risk probability Pf.
The first level 0-0.2 The risk can be ignored
Level Guess value Description The second level 0.2-0.25 The risk level is low, but needs some attention
The risk level is acceptable, but needs to be
The first level 0.0–0.2 The risk possibility is extremely small The third level 0.25-0.3
monitored
The second level 0.2–0.4 The risk possibility is little
The risk level is not acceptable, and some action
The third level 0.4–0.6 The risk possibility is medium The fourth level 0.3-0.35
should be taken to prevent accidents
The fourth level 0.6–0.8 The risk possibility is high
The risk level is not acceptable, and construction
The fifth level 0.8–1.0 The risk possibility is extremely high The fifth level 0.35-1
work should be suspended

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009
8 L. Ding et al. / Automation in Construction xxx (2014) xxx–xxx

Table 7
Risk level of each activity in foundation pit construction using open cut method.
Construction Risk Earth- Dewatering Excavation Steel Excavation Steel Excavation Steel Base plate Base Steel Median Stripping Loft Stripping
sequences level r retaining of the 1st bracing of the 2nd bracing of the 3rd bracing dredging plate bracing plate of the 2nd plate of the 1st
structure layer of the 1st layer of the 2nd layer of the 3rd stripping layer layer
layer layer layer of the 3rd
Main risks layer

Retaining pile
collapse 0.492 0.019 0.074 0.056 0.056 0.074 0.074 0.093 0.093 0.093 0.093 0.074 0.074 0.056 0.056 0.019

Landslide
hazard in
excavation 0.479 0.025 0.100 0.075 0.075 0.100 0.100 0.125 0.125 0.125 0.025 0.025 0.025 0.025 0.025 0.025
procedures

Bracing
structure
deformation in
the excavation 0.472 0.020 0.039 0.039 0.078 0.078 0.078 0.098 0.078 0.098 0.098 0.078 0.078 0.059 0.059 0.020
procedures

Water
in rushing 0.531 0.026 0.051 0.077 0.077 0.103 0.103 0.128 0.128 0.128 0.051 0.026 0.026 0.026 0.026 0.026

Damage to
adjacent 0.525 0.054 0.071 0.054 0.054 0.071 0.071 0.089 0.089 0.089 0.089 0.071 0.071 0.054 0.054 0.018
buildings

Seepage
caused by
fractured 0.571 0.263 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.053
retaining piles

Bottom heave
caused by 0.637 0.026 0.053 0.079 0.079 0.105 0.105 0.132 0.132 0.132 0.026 0.026 0.026 0.026 0.026 0.026
artesian water

Crane
operation 0.439 0.094 0.038 0.057 0.075 0.057 0.075 0.057 0.075 0.057 0.075 0.075 0.057 0.075 0.057 0.075
failures

Risk level of each


activity 0.281 0.248 0.256 0.283 0.335 0.344 0.405 0.404 0.405 0.258 0.216 0.208 0.189 0.180 0.133

Corresponding color Yellow Blue Yellow Yellow Orange Orange Red Red Red Yellow Blue Blue Green Green Green

avoided in the current state. Site workers have previously had little in- caused great concern. Dynamic calculation of carbon emissions dur-
formation to improve their real-time, on-the-spot decision making, ing the construction process can be realized based with a 4D BIM
but now, it is possible to have continuous, real-time visual warnings of application.
danger to consider. Carbon sources during the construction process can be classified into
three categories: 1) Caused by building materials and construction
4.3. 4D computational model for carbon emissions waste, 2) directly caused by the fuel consumed by construction machin-
ery and equipment, such as diesel and gasoline; and 3) caused by elec-
In the global context of climate change, facility construction causes tricity, referring to the power consumed by construction machinery and
a large amount of energy consumption [103]. Carbon emissions have equipment. Carbon emissions of various building materials contribute

Table 8
Main risks and affected components/areas with the construction sequences.

Activities Main risks Affected components/areas

Earth-retaining structure ⑥, ⑧ Retaining piles, areas around the hoisting equipment


Dewatering ②, ⑤ Retaining piles, neighboring area and buildings
Excavation of the 1st layer All risks at this stage Refer to the adjacent activities
are extremely low
Steel bracing of the 1st layer ⑧ Steel bracing structures, areas around the hoisting equipment
Excavation of the 2nd layer ②, ③, ④, ⑤, ⑦ Retaining piles, longitudinal slope, steel bracing structures, bottom of the foundation, neighboring area and buildings
Steel bracing of the 2nd layer ②, ③, ④, ⑤, ⑦, ⑧ Retaining piles, longitudinal slope, steel bracing structures, bottom of the foundation, neighboring area and buildings,
areas around the hoisting equipment
Excavation of the 3rd layer ②, ③, ④, ⑤, ⑦ Retaining piles, longitudinal slope, steel bracing structures, bottom of the foundation, neighboring area and buildings
Steel bracing of the 3rd layer ②, ③, ④, ⑤, ⑦, ⑧ Retaining piles, longitudinal slope, steel bracing structures, bottom of the foundation, neighboring area and buildings,
areas around the hoisting equipment
Base plate dredging ①, ②, ③, ④, ⑤, ⑦ Retaining piles, longitudinal slope, steel bracing structures, bottom of the foundation, neighboring area and buildings
Base plate ①, ③, ⑤, ⑧ Retaining piles, steel bracing structures, neighboring area and buildings, areas around the hoisting equipment
Steel bracing stripping of the ①, ③, ⑤, ⑧ Retaining piles, steel bracing structures, neighboring area and buildings, areas around the hoisting equipment
3rd layer
Median plate ①, ③, ⑤ Retaining piles, steel bracing structures, neighboring area and buildings
Stripping of the 2nd layer ⑧ areas around the hoisting equipment
Loft plate All risks at this stage Refer to the adjacent activities
are extremely low
Stripping of the 1st layer ⑧ areas around the hoisting equipment

① retaining pile collapse; ② landslide hazard in excavation procedures; ③ bracing structure deformation in the excavation procedures; ④ water inrushing; ⑤ damage to adjacent
buildings; ⑥ seepage caused by fractured retaining piles; ⑦ bottom heave caused by artesian water; ⑧ crane operation failures.

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009
L. Ding et al. / Automation in Construction xxx (2014) xxx–xxx 9

Fig. 9. Dashboard for safety control during foundation pit excavation processes.

the most to total carbon emissions in the construction stage [104]. and construction plan. Consumed material information can then be re-
Formula (2) provides an approach to calculate the total carbon emis- trieved from the construction site as used. Meanwhile, the data source
sions of building materials [105]. for carbon emissions per one unit of building material can be acquired
from International Panel on Climate Change (IPCC) or local standards
E8¼ Ep þ Et þ Ec þ Eo þ Er such as Building for Environmental and Economic Sustainability
X
> Ep ¼
> Q mi α i ; carbon emissions of the comsumed building materials (BEES) developed by the National Institute of Standards and Technology
>
>
>
> in the USA. Therefore, the carbon emission curve can be generated as
>
> X
at the raw material production stage
>
>
> Et ¼
> Q mi Lti ε i ; carbon emissions of the comsumed building
the construction process moves forward. In addition, this method can
>
>
>
> be used to evaluate and optimize different construction methods by
>
> materials at the material transportation stage
>
> X comparing the total carbon emissions of current and alternate methods.
>
> E ¼ Q η ;
>
> c mi i carbon emissions of the comsumed building materials
>
>
>
> at the construction stage of buildings
>
> X
>
> Eo ¼
>
> Q mi Y i μ i ; carbon emissions of the comsumed building 5. Conclusion and future work
>
>
>
> materials at the operation stage of buildings
>
> X
>
> This paper proposes a framework for BIM applications in the
>
> E r ¼ Q mi i i ; carbon emissions of the comsumed building
ω λ
>
>
>
> materials at the waste recycling stage construction industry. Using this framework, it is possible to classify
>
>
< existing research projects into to six categories based on the project
Q mi ¼ the consumption amount of material i ð2Þ
> management tasks that are aimed for, the project stakeholders that
>
> α ¼ the unit emission coefficient of material i
>
>
i are involved in and the different phases that BIM is used in. Such a
>
> Lti ¼ the transportation distance to the construction site of material i
>
> framework could possibly help in understanding the landscape of the
>
>
> εi ¼ the unit carbon emission coefficient of unit distance of the
> existing work and identifying gaps in the prior research. Classifying
>
>
>
>
>
> corresponding transportation means existing research studies using this framework, we have identified
>
>
> ηi ¼ the unit carbon emission coefficient of material i at the
> that relatively few research projects have been conducted for the
>
>
>
> project domains of quality, safety and carbon emissions. The paper has
>
> construction stage
>
> described approaches to quantify and analyze quality, safety, and
>
> Y ¼ the service life of material i
>
> i
>
> carbon emissions using BIM on real construction projects.
>
> μ i ¼ the annual unit coefficient of carbon emissions of material i
>
> In most past projects, funds were invested into the creation of 3D/4D
>
> ωi ¼ the recycling ratio of material i
>
> models for only one application in one domain or one phase. Further
>
>
>
> λ ¼ the unit carbon emission coefficient of different recycling research is needed to explore how the same or upgraded 3D/4D models
>
: i
methods: can be easily upgraded to manage multiple domains. Additionally, from
the literature review, some of the main challenges for implementing
This method of building a 4D computational model for carbon emis- BIM applications are generating the 3D models, retrieving the job site
sions is illustrated in Fig. 10. When using this method, the required 4D environmental information and updating actual data from the job site,
BIM application can be produced with the existing design drawings within the 3D models, as the construction process moves forward

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009
10 L. Ding et al. / Automation in Construction xxx (2014) xxx–xxx

3D Module 1 Activities 2 Consumed materials

Carbon emission - time curve during the construction process 3 The amount of carbon emissions of a specific material
roofworks
Major Structure
decorations

Ground Foundation

1 +2 + 3

Fig. 10. Computational model for carbon emissions based on 4D.

[106]. Integration of BIM applications with other techniques is regarded [18] Timo Hartmann, Ju Gao, Martin Fischer, Areas of application for 3D and 4D models
on construction project, J. Constr. Eng. Manag. 134 (2008) 776–785.
as an effective way to address some of these problems.
[19] National building information model standard project committee, http://www.
Laser scanning and image processing might be used to generate 3D buildingsmartalliance.org/index.php/nbims/faq/ .
models [107–109] while augmented reality could be used to retrieve [20] Salman Azhar, Abid Nadeem, Johnny Y.N. Mok, Brian H.Y. Leung, Building informa-
tion modeling (BIM): a new paradigm for visual interactive modeling and simula-
actual environmental information from the job site [84,110-111]. As
tion for construction projects, First International Conference on Construction in
for collecting job site data, one approach is to use RFID. The data ac- Developing Countries (ICCIDC-I) “Advancing and Integrating Construction Educa-
quired by RFID could be quickly transferred into the 4D BIM application tion, Research & Practice”, Karachi, Pakistan, August 4–5 2008.
which changes the display appearance of the corresponding module [21] J. Whyte, N. Bouchlaghem, A. Thorpe, R. McCaffer, From CAD to virtual reality:
modelling approaches; data exchange and interactive 3D building design tools,
[70]. Also, integration of RFID and BIM can be utilized for safety monitor- Autom. Constr. 10 (2000) 43–55.
ing during construction, which is another method of using a BIM [22] N. Bouchlaghem, A. Thorpe, I.G. Liyange, Virtual Reality Applications in the UK's
application for safety management. Construction Industry, CIB W78 Construction on the Information Highway, Bled,
June 10–12 1996.
[23] K.H. El-Ammari, Visualization, Data Sharing and Interoperability Issues in Model-
References based Facilities Management Systems, Concordia University, 2006.
[24] J. Goulding, W. Nadim, P. Petridis, et al., Construction industry offsite production: a
[1] Forest Petersona, Timo Hartmannb, Renate Fruchtera, Martin Fischer, Teaching virtual reality interactive training environment prototype [J], Adv. Eng. Inform. 26
construction project management with BIM support: experience and lessons (1) (2012) 103–116.
learned, Autom. Constr. 20 (2011) 115–125. [25] Bonsang Koo, Martin Fischer, Feasibility study of 4D CAD in commercial construc-
[2] R. Sacks, L. Koskela, B. Dave, R. Owen, Interaction of lean and building information tion, J. Constr. Eng. Manag., ASCE 126 (4) (2000) 251–260.
modeling in construction, J. Constr. Eng. Manag. 136 (9) (2010) 968–980. [26] M. Fischer, Introduction to 4D research, (Available from) http://www.stanford.
[3] C. Chen, H. Dib, G. Lasker, Benefits of implementing building information modeling edu/group/4D/ 2001 (accessed May 02, 2013).
for healthcare facility commissioning, J. Comput. Civ. Eng. (2011) 578–585. [27] Burcu Akinci, Martin Fischer, 4D WorkPlanner; a prototype system for automated
[4] Kristen Barlish, Kenneth Sullivan, How to measure the benefits of BIM — a case time-space conflicts analysis, Proceedings of the ICCCBE-VIII, Stanford, California,
study approach, Autom. Constr. 24 (2012) 149–159. ASCE, August 14–17 2000, pp. 740–751.
[5] R. Solnosky, Current status of BIM benefits, challenges, and the future potential for [28] V. Benjaoran, S. Bhokha, An integrated safety management with construction
the structural discipline, Structures Congress 2013, 2013, pp. 849–859. management using 4D CAD model, J. Saf. Sci. 48 (3) (2010) 395–403.
[6] R. Volk, J. Stengel, F. Schultmann, Building Information Modeling (BIM) for existing [29] M. Fischer, J. Kunz, Virtual Design and Construction: Themes, Case Studies and
buildings-Literature review and future needs, Autom. Constr. 38 (2014) 109–127. Implementation Suggestions, Center for Integrated Facility Engineering, Stanford
[7] C. Eastman, P. Teicholz, R. Sacks, K. Liston, BIM Handbook: A Guide to Building University, California, USA, 2005.
Information Modeling for Owners, Managers, Designers, Engineers and Contrac- [30] A. Khanzode, M. Fischer, D. Reed, Benefits and lessons learned of implementing
tors, Wiley, New York, 2008. building virtual design and construction (VDC) technologies for coordination of
[8] T. Hartmann, M. Fischer, Supporting the constructability review with 3D/4D mechanical, electrical, and plumbing (MEP) systems on a large healthcare project,
models, Build. Res. Inf. 35 (1) (2007) 70–80. IT Con. 13 (2008) 324–342 (Special Issue Case studies of BIM use: http://www.
[9] Uwe Rüppel, Kristian Schatz, Designing a BIM-based serious game for fire safety itcon.org/2008/22 ).
evacuation simulations, Adv. Eng. Inform. 25 (2011) 600–611. [31] P. Yee, M. Fischer, C. Kam, Prospective validation of virtual design and construction
[10] Y. Zhou, L.Y. Ding, L.J. Chen, Application of 4D visualization technology for safety methods, ITcon 18 (2013) 214–239 (http://www.itcon.org/2013/11 ).
management in metro construction, Autom. Constr. 34 (2013) 25–36. [32] G. Aound, A. Lee, S. Wu, From 3D to nD modelling, (Special Issue From 3D to nD
[11] Jungjun Park, Byungil Kim, Changyoon Kim, Hyoungkwan Kim, 3D/4D CAD appli- modelling) ITcon 10 (2005) 15–16 (http://www.itcon.org/2005/2 ).
cability for life-cycle facility management, J. Comput. Civ. Eng. 25 (2011) 129–138. [33] Changfeng Fu, Ghassan Aouad, Angela Lee, Amanda Mashall-Ponting, Song Wu, IFC
[12] N.W. Young Jr., S.A. Jones, H.M. Berstein, J.E. Gudgel, The business value of BIM: model viewer to support nD model application, Autom. Constr. 15 (2006)
getting building information modeling to the bottom line premier, Smart Market 178–185.
Rep., , McGraw-Hill Construction, New York, 2009. [34] AIA, Integrated project delivery: a guide, AIA California Council, (Available from:)
[13] AIA, AIA firm survey: the business of architecture, American Institute of Architects, http://www.aia.org/groups/aia/documents/pdf/aiab083423.pdf 2007 (accessed
Information Technology Chapter, 2006. 67–75. January 31, 2013).
[14] Patrick C. Suermann, Raja R.A. Issa, Evaluating industry perceptions of building [35] Stefan Boddy, Yacine Rezgui, Grahame Cooper, Matthew Wetherill, “Computer
information modeling (BIM) impact on construction, J. Inf. Technol. Constr. 14 integrated construction: a review and proposals for future direction”, Adv. Eng.
(2009) 574–594. Softw. 38 (10) (2007) 677–687.
[15] BIM SmartMarket Report McGraw-Hill Construction Research and Analytics, 34 [36] C. Eastman, Building Product Models: Computer Environments Supporting Design
Crosby Drive, Suite 201, Bedford, MA 01730, 2009. and Construction, CRC Press LLC, Florida, USA, 1999.
[16] National BIM report, building information modeling the national BIM library, NBS, [37] P.E. Will Ikerd, Who's Using BIM? Trends and drivers affecting structural engineers,
http://www.thenbs.com/topics/bim/articles/nbsNationalBimSurvey_2012.asp (available from:) http://www.tpm.com/component/content/article/1-latest-news/
2012 (Accessed May 02 2013). 620-whos-using-bim (accessed January 16, 2013).
[17] P. Barrett, Construction management pull for 4D CAD, Proceeding of Construction [38] Seyed Meysam Khoshnava, Alireza Ahankoob, Christopher Preece, Raheleh
Congress VI, ASCE, Reston, Va, 2000, pp. 977–983. Rostami, “Potential application of BIM in construction dispute and conflict”.

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009
L. Ding et al. / Automation in Construction xxx (2014) xxx–xxx 11

Management in Construction Research Association (MiCRA)Postgraduate Confer- [69] K. Yeh, M. Tsai, S. Kang, On-site building information retrieval by using projection-
ence., 178–184. based augmented reality, J. Comput. Civ. Eng. 26 (3) (2012) 342–355.
[39] A. Lee, S. Wu, A. Marshall-Ponting, G. Aouad, R. Cooper, J.H.M. Tah, C. Abbott, P.S. [70] Haiyan Xie, Wei Shi, Raja R.A. Issa, Using RFID and real-time virtual reality simula-
Barrett, nD Modelling Road Map: A Vision for nD-enabled Construction Report, tion for optimization in steel construction, ITcon 16 (2011) 291–308.
University of Salford, 2005. [71] Ali Motamedi, Rakesh Saini, Amin Hammad, Bo Zhu, Role-based access to facilities
[40] Bilal Succar, “Building information modeling framework: a research and delivery lifecycle information on RFID tags, Adv. Eng. Inform. 25 (3) (August 2011) 559–568.
foundation for industry stakeholders”, Autom. Constr. 18 (2009) 357–375. [72] Pingbo Tang, Daniel Huber, Burcu Akinci, Robert Lipman, Alan Lytle, Automatic re-
[41] S. Azhar, M. Hein, B. Sketo, “Building information modeling (BIM): benefits, risks construction of as-built building information models from laser-scanned point
and challenges”, Proceedings of the 44th ASC Annual Conference, Auburn, clouds: a review of related techniques, Autom. Constr. 19 (7) (November 2010)
Alabama, April 2–5, 2008, 2008. 829–843.
[42] B. Koo, M. Fischer, Feasibility study of 4D CAD in commercial construction, J. Constr. [73] Frédéric Bosché, Plane-based registration of construction laser scans with 3D/4D
Eng. Manag. 126 (4) (2000) 251–260. building models, Adv. Eng. Inform. 26 (1) (January 2012) 90–102.
[43] Z. Mallasi, Dynamic quantification and analysis of the construction workspace [74] Javier Irizarry, Ebrahim P. Karan, Farzad Jalaei, Integrating BIM and GIS to improve
congestion utilising 4D visualization, Autom. Constr. 15 (5) (2006) 640–655. the visual monitoring of construction supply chain management, Autom. Constr.
[44] J.H. Kang, S.D. Anderson, M.J. Clayton, Empirical study on the merit of web-based 31 (May 2013) 241–254, http://dx.doi.org/10.1016/j.autcon.2012.12.005.
4D visualization in collaborative construction planning and scheduling, J. Constr. [75] M. Castro, J. Sánchez, C. Vaquero, L. Iglesias, R. Rodríguez-Solano, Automated GIS-
Eng. Manag. 133 (6) (2007) 447–461. based system for speed estimation and highway safety evaluation, J. Comput. Civ.
[45] N. Dawood, E. Sriprasert, Z. Mallasi, B. Hobbs, Development of an integrated infor- Eng. 22 (5) (2008) 325–331.
mation resource base for 4D/VR construction processes simulation, Autom. Constr. [76] Javier Irizarry, Ebrahim P. Karan, Optimizing location of tower cranes on construc-
12 (2) (2003) 123–131. tion sites through GIS and BIM integration, ITcon 17 (2012) 351–366.
[46] Ma Zhiliang, Wei Zhenhua, Wu. Song, Lou Zhe, Application and extension of the IFC [77] Richard Davies, Chris Harty, Implementing ‘site BIM’: a case study of ICT innovation
standard in construction cost estimating for tendering in China, Autom. Constr. 20 on a large hospital project, Autom. Constr. 30 (March 2013) 15–24.
(2011) 196–204. [78] S. Ergan, B. Akinci, Automated approach for developing integrated model-based
[47] Nobuyoshi Yabuki, Tomoaki Shitani, A management system for cut and fill earth- project histories to support estimation of activity production rates, J. Comput.
works based on 4D CAD and EVMS, International Conference on Computing in Civ. Eng. 26 (3) (2012) 309–318.
Civil Engineering, 2005, http://dx.doi.org/10.1061/40794(179)152. [79] BIM SmartMarket Report McGraw-Hill Construction the business value of BIM in
[48] R. Sacks, R. Barak, Impact of three-dimensional parametric modeling of building on North America, multi-year trend analysis and user ratings (2007–2012).
productivity in structural engineering practice, Autom. Constr. 17 (4) (2008) [80] K. Ku, S. Pollalis, M. Fischer, D. Shelden, 3D model-based collaboration in design de-
439–449. velopment and construction of complex shaped buildings, ITcon 13 (2008)
[49] Z.Z. Hu, J.P. Zhang, BIM- and 4D-based integrated solution of analysis and manage- 258–285 (Special Issue Case studies of BIM use http://www.itcon.org/2008/19 ).
ment for conflicts and structural safety problems during construction: 2. Develop- [81] Nenad Čuš Babič, Peter Podbreznik, Danijel Rebolj, Integrating resource production
ment and site trials, Autom. Constr. (2010), http://dx.doi.org/10.1016/j.autcon. and construction using BIM, Autom. Constr. 19 (5) (August 2010) 539–543.
2010.09.014. [82] M. Golparvar‐Fard, F. Pena‐Mora, and Savarese, Automated progress monitoring
[50] G. Augenbroe, J. Hensen, Simulation for better building design, Build. Environ. 39 using unordered daily construction photographs and IFC‐based building informa-
(8–9) (2004) 865–871. tion models S, Journal of Computing in Civil Engineering. http://dx.doi.org/10.
[51] Arno Schlueter, Frank Thesseling, Building information model based energy/exergy 1061/(ASCE)CP.1943-5487.0000205 .
performance assessment in early design stages, Autom. Constr. 18 (2009) [83] V. Bansal, M. Pal, Generating, evaluating, and visualizing construction schedule
153–163. with geographic information systems, J. Comput. Civ. Eng. 22 (4) (2008) 233–242.
[52] Ibrahim Motawa, Abdulkareem Almarshad, A knowledge-based BIM system for [84] M. Golparvar-Fard, F. Pena-Mora, C. Arboleda, S. Lee, Visualization of construction
building maintenance, Autom. Constr. 29 (2013) 173–182. progress monitoring with 4D simulation model overlaid on time-lapsed photo-
[53] Weilin Shen, Qiping Shen, Quanbin Sun, Building information modeling-based user graphs, J. Comput. Civ. Eng. 23 (6) (2009) 391–404.
activity simulation and evaluation method for improving designer–user communi- [85] Emad Elbeltagi, Mahmoud Dawood, Integrated visualized time control system for
cations, Autom. Constr. 21 (2012) 148–160. repetitive construction projects, Autom. Constr. 20 (7) (November 2011) 940–953.
[54] D. Chantawit, B.H.W. Hadicusumo, C. Charoenngam, 4D CAD-safety: visualizing [86] Samir El-Omari, Osama Moselhi, Integrating automated data acquisition technolo-
project scheduling and safety planning, Constr. Innov. 5 (2005) 99–114. gies for progress reporting of construction projects, Autom. Constr. 20 (6) (October
[55] M. Venugopal, C.M. Eastman, R. Sacks, J. Teizer, Semantics of model views for 2011) 699–705.
information exchanges using the industry foundation class schema, Adv. Eng. In- [87] Jin-Kook Lee, Jaemin Lee, Yeon-suk Jeong, Hugo Sheward, Paola Sanguinetti, Sherif
form. 26 (2) (April 2012) 411–428. Abdelmohsen, Charles M. Eastman, Development of space database for automated
[56] T. Pazlar, Z. Turk, Interoperability in practice: geometric data exchance using building design review systems, Autom. Constr. 24 (July 2012) 203–212.
the IFC standard, ITcon 13 (2008) 362–380 (Special Issue Case studies of [88] Seungjun Roh, Zeeshan Aziz, Feniosky Pena-Mora, An object-based 3D walk-
BIM use). through model for interior construction progress monitoring, Autom. Constr. 20
[57] Mikael Laakso, Arto Kiviniemi, The IFC standard — a review of history, develop- (1) (January 2011) 66–75.
ment, and standardization, ITcon 17 (2012) 134–161. [89] Mads Bendixen, Christian Koch, Negotiating visualization in briefings and design,
[58] Y.-S. Jeong, C.M. Eastman, R. Sacks, I. Kaner, Benchmark tests for BIM data Build. Res. Inf. 35 (1) (2007) 42–53.
exchanges of precast concrete, Autom. Constr. 18 (4) (July 2009) 469–484. [90] C. Eastman, Jae-min Lee, Yeon-suk Jeong, Jin-kook Lee, Automatic rule-based
[59] Alan Redmond, Alan Hore, Mustafa Alshawi, Roger West, Exploring how informa- checking of building designs, Autom. Constr. 18 (2009) 1011–1033.
tion exchanges can be enhanced through Cloud BIM, Autom. Constr. 24 (July 2012) [91] R. Sacks, M. Radosavljevic, R. Barak, Requirements for building information model-
175–183. ling based lean production management systems for construction, Autom. Constr.
[60] L. Zhang, R.R.A. Issa, Ontology-based partial building information model extraction, 19 (2010) 641–655.
J. Comput. Civ. Eng. 27 (6) (2012) 576–584. [92] Albert P.C. Chan, Ada P.L. Chan, Key performance indicators for measuring
[61] M. Nepal, S. Staub-French, R. Pottinger, J. Zhang, Ontology-based feature modeling construction success, Benchmarking: Int. J. 11 (2) (2004) 203–221.
for construction information extraction from a building information model, J. [93] Frank Harris, Ronald McCaffer, Modern Construction Management, Wiley.com,
Comput. Civ. Eng. (Aug. 14 2012), http://dx.doi.org/10.1061/(ASCE)CP.1943- 2013.
5487.0000230. [94] E. Koehn, N. Datta, Quality, environmental, and health and safety management sys-
[62] Madhav Prasad Nepal, Sheryl Staub-French, Rachel Pottinger, April Webster, tems for construction engineering, J. Constr. Eng. Manag. 129 (5) (2003) 562–569.
Querying a building information model for construction-specific spatial informa- [95] Burcu Akinci, Martin Fischer, Raymond Levitt, Robert Carlson, Formalization and au-
tion, Adv. Eng. Inform. 26 (4) (October 2012) 904–923, http://dx.doi.org/10. tomation of time–space conflict analysis, J. Comput. Civ. Eng., ASCE 16 (2) (2002).
1016/j.aei.2012.08.003. [96] V. Bansal, Use of GIS and topology in the identification and resolution of space
[63] N. Hassan Ibrahim, Reviewing the evidence: use of digital collaboration technolo- conflicts, J. Comput. Civ. Eng. 25 (2) (2011) 159–171.
gies in major building and infrastructure projects, ITcon 18 (2013) 40–63. [97] Youngsoo Jung, Mihee Joo, Building information modelling (BIM) framework for
[64] Alastair Watson, Digital buildings — challenges and opportunities, Adv. Eng. practical implementation, Autom. Constr. 20 (2011) 126–133.
Inform. 25 (4) (October 2011) 573–581. [98] Chris Gordon, Burcu Akinci, James H. Garrett, Characterization and search of
[65] Tomo Cerovsek, A review and outlook for a ‘building information model’ (BIM): a construction inspection plan spaces developed using a component-based planning
multi-standpoint framework for technological development, Adv. Eng. Inform. 25 approach, Journal of Computing in Civil Engineering, ASCE, 23(4), 211–220.
(2) (April 2011) 224–244. [99] R.M. Choudhry, D. Fang, Why operatives engage in unsafe work behavior: investi-
[66] Atul Porwal, Kasun N. Hewage, Building information modeling (BIM) partnering gating factors on construction sites, Saf. Sci. 46 (4) (April 2008) 566–584.
framework for public construction projects, Autom. Constr. 31 (May 2013) [100] Jens J. Dahlgaard, Su Mi Dahlgaard-Park, Lean Production, Six Sigma Quality, TQM
204–214. and Company Culture, The TQM Magazine, 2006. 263–281.
[67] Yi Jiao, Shaohua Zhang, Yongkui Li, Yinghui Wang, BaoMing Yang, Towards cloud [101] Calvin Kam, Martin Fischer, Capitalizing on early project decision-making opportu-
augmented reality for construction application by BIM and SNS integration, nities to improve facility design, construction, and life-cycle performance-POP,
Autom. Constr. (October 29 2012), http://dx.doi.org/10.1016/j.autcon.2012.09. PM4D, and decision dashboard approaches, Autom. Constr. 13 (1) (2004) 53–65.
018 (Available online). [102] Ministry of Construction of the People's Republic of China, Guideline of Risk
[68] Chan-Sik Park, Do-Yeop Lee, Oh-Seong Kwon, Xiangyu Wang, A framework for Management for Construction of Subway and Underground Works [M], China
proactive construction defect management using BIM, augmented reality and Architecture & Building Press, Beijing, 2007.
ontology-based data collection template, Autom. Constr. (22 October 2012), [103] Luis Pérez-Lombard, José Ortiz, Christine Pout, A review on buildings energy con-
http://dx.doi.org/10.1016/j.autcon.2012.09.010 (Available online). sumption information, Energy Build. 40 (3) (2008) 394–398.

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009
12 L. Ding et al. / Automation in Construction xxx (2014) xxx–xxx

[104] Xiaolv Zhou, “Circular economy and China construction waste management”, [109] B. Akinci, F. Boukamp, C. Gordon, D. Huber, C. Lyons, K. Park, “A formalism for uti-
Constr. Econ. 6 (2005) 14–16. lization of sensor systems and integrated project models for active construction
[105] B. Li, F.F. Fu, H. Zhong, H.B. Luo, Research on the computational model for carbon emis- quality control”, Autom. Constr. 15 (2006) 124–138.
sions in building construction stage based on BIM, Struct. Surv. 30 (5) (2012) [110] Xiangyu Wanga, Phillip S. Dunston, Compatibility issues in Augmented Reality sys-
411–425. tems for AEC: an experimental prototype study, Autom. Constr. 15 (2006)
[106] Salman Azhar, Building information modeling (BIM): trends, benefits, risks, and 314–326.
challenges for the AEC industry, Leadership Manage. Eng. 11(3), 241–252. [111] S.A. Talmaki, S. Dong, V.R. Kamat, Geospatial databases and augmented reality vi-
[107] B. Giel, R.A. Issa, Using laser scanning to access the accuracy of as-built BIM, Journal sualization for improving safety in urban excavation operations, Proc., Construc-
of Computing in Civil Engineering, Proceedings of the 2011 ASCE International tion Research Congress 2010: Innovation for Reshaping Construction Practice,
Workshop on Computing in, Civil Engineering, 2011, pp. 665–672. ASCE, Reston, VA, 2010, pp. 91–101
[108] Xuesong Liu, Matineh Eybpoosh, Burcu Akinci, Developing As-built Building Infor-
mation Model Using Construction Process History Captured by a Laser Scanner and
a Camera, Construction Research Congress, 2012. 1232–1241.

Please cite this article as: L. Ding, et al., Building Information Modeling (BIM) application framework: The process of expanding from 3D to
computable nD, Automation in Construction (2014), http://dx.doi.org/10.1016/j.autcon.2014.04.009

Vous aimerez peut-être aussi