Académique Documents
Professionnel Documents
Culture Documents
In line with the mandate of the DPWH to secure the quality and safety of road
Department of Trade and Industry (DTI), for the guidance and compliance of all
concerned.
contractor regarding this matter that could cause safety problems, such
as:
E. Excavation that is not properly fenced and lighted during night time.
F. The contractor is liable for all road safety devices and arrangement on
the job site, this includes signage, lighting and other road safety devices
accountability for testing and acceptance lies fully with the contractor,
and to ensure that the tests comply with the standard specifications and
operations.
specifically adjacent to the existing road and properties, the utility experts
1.4. EXCAVATION
the site. The conveying and the disposal is within the authority of the
project engineer.
1.5. PAVEMENT
The stone shall be clean, hard & durable & shall be subject to
engineer’s satisfaction. Stones must have a thickness of not less than 150
mm and widths of not less than 1 & 1/2 times their respective thickness,
and lengths of not less than 1 & 1/2 times their respective widths.
1.8. ROAD MARKINGS
A. The project engineer should validate from the bill of quantities the
B. The project engineer should control the laboratory to assure that the
2. HIGHWAY PLANNING
information so that designers, reviewers, and the people can understand both
the existing conditions and project. It protects the existing highway system, and
to provide for its future needs by complete and integrated consideration of the
environmental issues. Plans also allow a contractor to construct the project and
management.
positions using various platforms, mostly aircrafts for studying the surface of
the Earth. It’s one of the most frequent, versatile and economical form of
taken from a low angle earth surface-aircraft are called low oblique
geometric properties.
unique angles.
4. HIGHWAY LOCATION
geometric features of highway design, the taking after surveys must make led
then afterward the need of the road may be concluded. In alignment and route
locations surveys have four principles these are: desk study, reconnaissance
deciding the alignment and route location. The role of the central line of
general, the purpose of alignment selection system is to find an area for the
new highway that will end result in the lowest total construction, land,
about the traffic desires and estimates its own characteristics as a road
skill that gives the basic details for the design, as well as the analysis for the
alternative route.
one or more corridor routes for a highway in some specific points that may
both time management and finance of this stage for highway location. First
step, collecting the data (terrain classifications, soil type and depth,
directness of the route and many more), location and maps relating to the
area. And the second step, visiting the site additional data.
the line for the final location survey. It is all about the study of one or more
suitable corridor highways. Paper location and alignment should show the
ties to existing maps to let the location party to mark the centerline.
affect the location of the route, the shape of the ground, the position of
the trees, bridges, power lines and many more. Practical routes are set
and collecting the additional data for the design of the drawings. The
final vertical and horizontal alignments were determined and the final
positions of the structures were located. In this survey, it will ensure that
5. BRIDGE LOCATION
The design and location of a bridge all depends upon traffic case. In
general, the bridge should be built to serve the traffic best, unless there are
other situation that are controlling. According to MS Troitsky is “bridge for the
Poor location and wrong sizes of the structure can make the bridge
geological concerns. All of this topic must be consider to ensure that the bridge
the site. Under this is preparation for site investigation and site works.
show up in the same location year after year, while the locations of
different years.
areas that are liable to being wet and may show problem areas
investigation and site survey. Borings are desirable for sites with
bedrock faces. Wet and unstable sites with clay and silt soils should
wildlife, and so forth. The more complex the site, the more
6.1. EMBANKMENT
The embankment is built to reinforce the other three layers of the road
up a large part of the total cost. Embankments can be made from almost
6.2. SUB-GRADE
give uniform support to the pavement. The sub-grade lies direct on the
6.3. BASE
The base is an intermixture of crushed rock. The base layer gives uniform
support to the road pavement. It allows water that enters any joints or cracks
and softening the sub-grade. The base layer lies direct on top of the sub-
The top layer is called the pavement. Its materials can either be Hot
Mix Asphalt (HMA) and Portland Cement Concrete (PCC). The pavement
itself can withstand bending, and distributes vehicle weights over a large
area.
6.5. SUB-DRAIN
The sub-drain collects water from the base and the sub-grade drains
that water into the ditch. The sub-drain lies alongside the pavement, base
Right of way is the area of land acquired and allocated for construct
and development of road along its alignment. The width of the right of
way is called land width and it depends upon the width of formation,
curves, drainage system and also on the importance of the road and
Road margins are the portion of the road beyond the carriageway
and on the roadway. The various elements in the road margins are parking
lane, frontage road, drive way, cycle track, footpath, guard rails and
embankment slope.
The frontage road may be run parallel to the pavement road and
isolated by separators.
customary bike lane. A cycle track is different from motor traffic and
6.8.5. FOOTPATH
Side slopes are the slopes provided of the side of earth work of the
road in embankment in cutting for its stability; side slopes in the road
cutting.
6.9. WIDTH OF PAVEMENT OR CARRIAGE WAY
Carriage way width is based on the width of traffic lane and number of lane
capacity of each lane. The lane width required is measured on the basic of
the width of vehicle and minimum side clearance required for safe drive.
6.10. SHOULDER
Shoulder are the portion of the road way between the outer edges of
carriage way & edges of top surface of embankment or inner edges of the
side drains in cutting. These are allocated along the road edge to use in an
station at the side of the shoulder would have a clearance of about 1.85m
6.11. KERBS
footpath.
7. WHY BUILD A ROAD?
leads to faster and better flow of transport services. These provide human
cities. Rural areas have different types of road to interconnect farm lands with
the city. There are different type of roads manufactured within a city main road,
boulevard, street and each type has its own prominence and condition.
Roads take farm products to market and children to school. Roads are
development and progression and bring important social benefits. They are vital
more areas and motivate economic and social progression. For those reasons,