1. briefing conduct by project manager about;
i. Preparation of floods to avoid landslide at hill construction site-the precaution is
to make drain, plant grass at side of hill, and faster the process of work before
rainy season.
2. Supervise worker that herbicides at barriers area to maintain the barriers.
3. Maintain reflective rope barriers and substitute old reflective rope barriers.
4. Observe excavator making a drain at side of construction to avoid overflow water to the
road.
5. Located new jersey barriers and reflective rope at dangerous corner.
1. Follow traffic management officer flying drone to see and record video at new location.
2. Observing and maintaining barriers that fall down.
3. Observing and maintaining reflective rope that slack
4. Place barrier at dangerous corner to avoid accident happens.
5. Observe excavator digging a drain.
6. Break for jumaat pray.
7. Help SHO failing a report.
1. Observing and maintaining barriers and reflective rope that fall and slack.
2. Supervise worker that herbicides grass at barriers.
3. Ask worker to spray barriers with company name to avoid stealing barriers.
1. Observing and maintaining barriers that fall and reflective rope that slack.
2. Follow traffic management officer flying drone to see new area.
3. Ask worker to herbicides grass at jersey barriers to maintaining the barriers.
4. Supervise worker spray company name at barriers to avoid stealing barriers.
1. Observing and maintaining barriers that fall and the reflective rope that slack.
2. Supervise 700m double line road marking by sub-contractor.
i. This area is the hardest because have many corner and the road on the hill.
ii. I have to use 4 flat man to control public car.
iii. Emergency transport like ambulance make the flat man have to insure the
ambulance can move faster.
3. Help SHO failing new format of checklist and permit to work.
1. Observing and maintaining barriers that fall and reflective rope that slack.
2. Toolbox meeting to worker conduct by SHO and SSS.
3. Senior site supervisor giving me a task that to insure all flat man at borrow pit at the place
where lorries out and in
4. Supervise worker spray company name at barriers.
1. Observing and maintaining barriers that fall and reflective rope that slack.
2. Senior site supervisor giving me a task that to insure all flat man at borrow pit at the
place where lorries out and in
3. Supervise sub-contractor installing road guard rail.
4. Supervise worker spray company name at barriers to avoid stealing barriers.