Académique Documents
Professionnel Documents
Culture Documents
Objectives are the ends towards which the activities of a project are
directed. A project has clearly defined (specific objectives). It is
focused on end result. Project exists when the objectives have been
achieved. Hence the first step in any project is to define the objective.
We define the project objective in order to:
Goals are purpose and mission for initiating a project which is set at
the start of project. It is the specification of what is hoped to be
achieved at the end of the project which allows stakeholders to
specify the target then work towards their own objectives. Goal
should clearly state what the project will deliver. Goal setting takes
time, energy and dialogue.
a. Initiation Phase
b. Planning Phase
c. Engineering and Design Phase
d. Implementation Phase
e. Termination Phase
Resources /Risk
Resources
Risk
Start End
Initiation Planning Engineering and Implement Termination
design ation
Fig: 2.1is the simple example that might have been used around the
time Gantt charts were invented
The Bar chart suffers from some disadvantages which limits its
usefulness:
1. There may be physical limit to the size of the bar chart, which
may limit the size of the project that can be planned with this
technique or only major activities are shown. Hence, it is not
useful for large and complex projects.
2. There are some activities of a project which are taken up
concurrently, while there are others which can be taken up
Example 2.1
Activity Duration
(weeks)
A 2
B 4
C 2
D 4
E 6
F 4
G 5
H 4
Draw the bar chart and find out the completion time of the project.
Solution
Activity/week 1 2 3 4 5 6 7 8 9 10 11 12 13
A
B
C
D
E
F
G
H
Though the two methods are conceptually similar except for certain
minor differences, they were developed independently in USA.
Layout
Excavation of foundation
Construction of wall Layout
Concreting i1 2j
Construction of roofing
Wiring and electrification
Plastering and paining work
2. Activity Duration
Layout
11 2
2
(4 days)
4. Event (Node):
1 22 3
Generally, the name of the activity (Or symbol of the activity is) is
indicated above the arrow while the duration of the activity is
indicated below the arrow.
11 2 3
5. Dummy activity
A 2
Dummy
1
B 3
A B
4 5 8
Dummy
D
C
6 7 9
i
ti-j j
i ti-j j
2
4 5
1
3
F
B
A 2 5
1
Er. Santosh Kr.Shrestha Er. Ishwar Adhikari
D E G
4
18
A C 5
F
1 2 B
3
G
D E
4
5. There should be only one arrow for an activity, i.e. number of
arrows should be equal to number of activities.
6. There shall not be unnecessary dummy activities in the
network. Dummy activity shall be introduced only when it is
absolutely necessary and without which the network diagram
cannot be completed.
Skip numbering:
Example 2.2:
Draw a network with the following details. Number the events using
Fulkerson’s rule
4 D B G
5 E C G
6 F C -
7 G D, E -
Solution: D
B 3 5
G
A 2 E
1
C
F
6
4
Example 2.3
B 3
5
A Dummy F
1 2 C
Er. Santosh Kr.Shrestha Er. Ishwar Adhikari
21
E
4 6
Activity on Node (AON):
B (2)
3 5
G (4)
E (6)
A (4)
1 2 C (5)
F (1)
6
4
Event 1 2 3 4 5 6
No.
Early 0 0+4 = 4 4+2 = 6 4+5= 9 6+3= 9 15 + 4 =19
Event
time 9+6 = 15 9+1 = 10
Late 4-4=0 12-2=10 15-3=12 19-1=18 19-4=15 19
Event
Time 9-5=4 15-6=9
Thus in the above network, Events 1, 2, 4, 5 & 6 have both the times
(early event time and late event times) are equal.
The free time available for the activity is called ‘Float’ or ‘Slack’. An
activity has four types of floats.
All the floats are equal to zero for critical activities. Critical path is
that path connecting activities having Total Float Equal to Zero.
A
i j
D
E-I L-I E-J L-J
event time of event I. Similarly, E-J is the early event time of event J
and L-J is the late event time of event J.
TF
Ind-F
6 15 15
In the above example: D (3)
3 5
0 B (2)
4 12
G (4)
1 A (4)
2 C (5) 9
E (6)
19
0 4 F (1)
4 6 19
3 C 5 4 9 4 9 0 0 0 0 Critical
4 D 3 6 9 12 15 6 6 0 0
5 E 6 9 15 9 15 0 0 0 0 Critical
6 F 1 8 10 18 19 9 9 9 0
7 G 4 15 19 15 19 0 0 0 0 Critical
6. Determine the latest start and finish times for each task. LFT is
equal to the Latest occurrence time of the head event and LST = LFT
– D.
7. Determine slack/ float for each task using difference between latest
and earliest start times.
8. Find tasks with zero slack. These are critical tasks lying on the
critical path.
Example2.3
9 I 5 G,H J
10 J 3 I -
Solution
19 20
3 8 E (1) 8
G (5)
2
8 12 25 33 42
A (3) J (9)
0 C (4) I (8)
F (7)
4 5 6 9 10 11
1
12 25 33
8 42
0 B (8)
3 7 H (6)
D (2)
SN 8
Activity 8Duration EST EFT 19
LST 19
LFT TF FF Ind Inf Remark
1 A 3 0 3 5 8 3 0 5 3
2 B 8 0 8 0 8 0 0 0 0 Critical
3 C 4 8 12 8 12 0 0 0 0 Critical
4 D 2 8 10 17 19 9 9 9 0
5 E 1 3 4 19 20 16 15 16 1
6 F 7 12 19 12 19 0 0 0 0 Critical
7 G 5 19 24 20 25 1 1 0 0
8 H 6 19 25 19 25 0 0 0 0 Critical
9 I 8 25 33 25 33 0 0 0 0 Critical
10 J 9 33 42 33 42 0 0 0 0 critical
The critical path is shown by the dark arrow line which is 1-3-4-5-6-7-9-10-11
The critical activities are B,C,F,H,I,J
The project duration is 42 weeks.
Project manager would be interested in completing the project at the minimum possible time but it is not
entirely in his hand to do so. There are many factors, both internal and external to the organizations which
have influence on the completion time of each activity in the project. Thus, there is an element of
uncertainty in deciding upon the completion time of each activity and consequently the estimated project
completion time. It is a probabilistic approach for estimating the duration of an activity and event oriented
network diagram. PERT is used in the completely newly developed project such as Research and design,
new industries product design and there may not be record of past experiences in the particular field.
PERT system is preferred for those projects in which correct time determination for various activities
cannot be made.
PERT uses three time estimates for each activity with a view to overcome uncertainty in time estimates.
a) Optimistic time estimate (to): It is the shortest possible time in which an activity can be
completed under ideal conditions. In arriving at the optimistic time estimate, it is assumed that
everything is favorable in completing the activity in the shortest possible time.
b) Pessimistic time estimate (tp): It is the maximum possible time it would take to complete an
activity under worst conditions. In arriving at the pessimistic time, it is assumed that everything is
unfavorable for completing the activity in time and every possible delay and difficult situation is
encountered.
c) Most likely time estimates (tm): It lies between optimistic and pessimistic time estimates. It is
the time in which an activity can be completed under normal conditions. In arriving at the most
likely time, it is assumed that conditions are neither favorable nor unfavorable, but normal.
The supervisor or the foreman who is in direct charge of an activity is asked to estimate the three time
estimates taking into account, favorable, unfavorable, and normal conditions. In assuming unfavorable
conditions, extremely unfavorable situations such as floods, fires, earthquakes, labour strikes etc. are
excluded.
Expected time estimate (te): PERT assumes that the optimistic time (to) and the pessimistic time (tp) are
equally likely to occur while the most likely time (tm) is four times more likely to occur than the others.
Hence for arriving at the expected time (te) we use following formula
te =
To arrive at this formula we must assume some functional form of the activity time as shown in the figure
below. It was observed that beta distribution suits well for the purpose and hence same was accepted as a
mathematical model for arriving at the mean (te). The formula is a linear approximation to +of4tbeta
m + tp
distribution whose accuracy is considered reasonably sufficient.
6
After having arrived at the expected time (te) for each activity, the critical path is found out by making
forward pass computation and backward pass computation as in CPM. Variance in activity times:
Consider the following two time estimates.
Activity to tm tp
te =
A 3 4 5 4
B 2 3 10 4
For the activities A & B the expected time arrived at is the same. However as seen, the difference
between to and tp is more for activity B than for activity A. Thus, though the estimated expected time (t e)
is the same for both the activities, there is greater extent of uncertainty in the same estimate for activity B.
Thus the reliability of the expected time (te) depend upon the variability of two time estimates to and tp.
1. Variance and
2. Standard deviation.
PERT uses the following simplified formula for arriving at the variance and standard deviation of
activity times.
Variance (ϑ ) =
CPM originated from construction project where as PERT is originated from R & D projects. Both CPM
and PERT share same approach for constructing the project network and for determining the critical path
of the network. However there are some basic differences between CPM and PERT.
SN CPM PERT
1 Time estimates are Time estimates are probabilistic
deterministic so use single with uncertainty in activity
time estimate for activity duration so use three time
duration. estimates
2 Activity oriented network Event oriented network diagram
diagram
3 Focused on time cost trade Focused on time only; no cost
off
4 More suitable for simple More suitable for new and
and repetitive projects like complex projects like research
construction and development.
5 Easy to maintain. Costly to maintain
It is an attempt to reduce peak resources requirement and smooth out period to period assignments within
the constraints of project duration. A project manager often comes across mismatch between the
availability of resources and the requirement of resources. This means that there are surplus resources
available on someday and there is deficit of resource on some other days. It will be uneconomical to
permanently employ personnel to satisfy peak time requirements since there will be under utilization of
personnel to many days. Hence only less number of personnel than peak time requirement during peak
time can be handled by hiring on casual basis. Since the personnel requirement varies from day to day, the
project manager should plan properly in such a way that optimum utilization of available personnel is
achieved. Thus the objective of project manager in such a situation is to level as far as possible the
demand for resources throughout the project execution time keeping in view that project completion time
does not exceeds.
Resource leveling is the process that ensures resource demand does not exceed resource availability. The
ideal scenario would be a buildup of resource usage at the beginning of the project and a reduction at the
end of the project. However, the approach to resource leveling will also depend on whether resources are
dedicated to a particular project or shared across several projects and whether there is a need to keep all
resources fully utilized. We will begin by analyzing the issues involved in resource leveling for a situation
where a bar chart has been used as the primary planning technique for a simple project. The reason for
this is that resource leveling must be considered within a time framework and bar charts are drawn to a
time scale while networks are not. Examine Figure 2.4 shown on the previous page. In this figure, the
time-scale for the activities comprising the project is shown in a bar chart, which also shows resource
requirements for one particular resource unit. An examination of the bar chart and its associated resource
chart in Figure 2.4 shows that improvements can be made to the level of resource requirements by:
However, there are problems with using the simple bar chart as a tool for resource leveling. For example,
we do not have any information about the interdependency of tasks. Therefore, if we delay a task by
starting later than originally planned or by extending the duration of the task, we cannot evaluate the exact
impact this will have on the overall project. Referring to Figure 2.4 again, if we assume that the maximum
amount of resource availability is 14 units, then we have a problem in week 2 because 18 units of
resources are required in that week. In order to reduce the resource demand in week 2, we may have to
extend Activity A into week 3 (if this is possible) and spread the resource demand over three weeks, or
delay the commencement of Activity B. However, the exact impact of these changes on the overall
project duration cannot be easily determined.
Another issue is that the critical path(s) cannot be easily determined, although we may be able to deduce
which activities are critical by inspection. Clearly, if we do not wish to extend the overall duration of the
project we must avoid extending or delaying activities which are on the critical path. Finally, the
availability of slack or float is not clear. Knowing this is important because it is this attribute that can be
utilized to adjust our resource requirements.
Resource leveling can be accomplished more easily if resource requirements to complete an activity are
expressed in terms of hours or days required. The definition of resource requirements using such units of
measure can help us determine if an activity should be completed in a short time through the use of many
resources or over a longer period of time through the use of fewer resources. In practice, however, there is
a limit to the number of resources that can be deployed and, therefore, a limit to the amount by which any
activity duration can be shortened. We will now examine situations where networks are used as the
primary planning method. Generally, there are two approaches to leveling and smoothing the resources
required:
Time-limited resource considerations: In this case emphasis will be placed on completing the
project within a specified time. This time will usually have been determined by network analysis.
Adjustments in the timing of any activity, and the resources required at a given time, must be
undertaken within the float (slack) available. Obviously there can be no adjustment of activities
which are on the critical path.
Resource-limited resource considerations: In this case the project must be completed with the
resources available even if this means extending the project duration. If the total resource demand
exceeds the resource availability at any time then some of the activities must be delayed until
there is sufficient resource availability.
For both of the above approaches, information concerning the earliest and the latest start times and slack
will be used to level resources.
Monitoring
Monitoring is collecting, recording and reporting information concerning all aspects of project
performances that the project managers or others in the organization wish to know. Monitoring is primary
aimed at tracking and improving project implementation. It is a continuous process.
Evaluation
Evaluation is an objective and systematic judgmental process for determining relevance, efficiency
effectiveness and impact of project performance. It is done to improve project implementation and to
improve future project planning and decision making.
Monitoring is usually an ongoing activity throughout the life of the project whereas evaluation is periodic.
It is undertaken at certain time such as mid-term or/and termination of the project.
Controlling
Controlling is the management function of comparing the actual achievements with the planned ones at
every stage and taking necessary action, if required, to ensure the attainment of the planned goals. It
includes three step processes – measuring, evaluating and correcting - which are defined as follow.
Measuring: Determining through formal and informal reports the degree to which the progress
towards objective is being made
Evaluating: Determining cause of and possible ways to act upon significant deviations from planned
performances
Thus controlling ensures that - “Right things are done in right time in right manner”.
During planning stage, various resources are planned based upon the analysis made for time and cost,
such plans in most of the cases cannot be precise and correct since each project is unique on its own.
Planning of new projects cannot be considered as wholly true and infallible (never failing). In fact
planning is an intelligent guess. However if the project is left on its own, there is every chance that
estimated resources will fall short and project requirement will go on increasing as the project proceed for
implementation. Therefore appropriate control system is necessary which will detect such occurrence and
allow opportunity to take corrective actions to bring the project back on track. Project Control System is a
process or mechanism for continuing regular monitoring and controlling of a project. It serves two major
functions. They are:
The project control cycle begins with the initial project plan.
Item1: Project plan includes a budget, schedule and other planning information such as staffing and
administrative procedures. It identifies the resources such as equipment, people and materials that are
needed at job site.
Item 2: The project plan is used to initiate the field operations. The field supervisors are responsible for
the productive utilization of resources.
Item 3: It represents the impact of external factors such as labor strike, vandalism, bad weather or other
events that are difficult to predict and affect the field operations.
The arrow between field operation and cost/schedule engineers block represents the processing of the
actual information from the field.
Item 4: The cost/schedule engineer block represents the coordination of data from the field and
comparison with the initial plan. The technical people who established the initial work plan are
responsible for recommending the adjustment to plans based on their analysis of actual field operations.
Item 5: It represents the permanent storage of information for use by the company in future job planning.
The arrow between the cost/schedule engineers and project manager block represents the distribution
(spreading) of status reports to the project team. For the reporting process to be useful, it must deliver
accurate information to the right people on time. The reports should also be sorted to indicate the more
important activities first with key variances noted.
Initiate plan
Adjust plan as Work
needed Plan (1)
Project
manager (6)
Use
Outside input to
External factors Field
com
(3) operation
pare
(2)
to
actu
al
data
Actual field data
Cost/Schedule
Analyze, Engineers (4)
recommend
action Historical data
base (5)
The arrow from the project manager back to field operation represents the completion of project control
cycle. Management has made a decision and final instructions are now being given to the field.
Adjustment may be made in a project plan, or the instruction may be continue on as originally scheduled.
For these instructions to be effective, they must be delivered soon enough to be smoothly implemented.
The project control cycle is a feedback loop providing all the participants with a measure as to the success
of their past decision.
Feedback is the process of extracting information from the output level and then feeding it back to the
input. Hence the results of the execution process are feedback. In the perfect world, the tangible results
of the execution process i.e. output / performance can be estimated accurately.
Input Output
PROCESS
Feedback
Once the resources and the control strategy are fixed, the planning process will give the exact output such
as exact cost, exact time of completion etc. However, in a project there may be unpredictable events that
act on the process as disturbances i.e. in these cases the feedback control system is necessary. In
feedback control system, direct variance is obtained by subtracting plan data from implementation data to
be given a positive or negative variance. It can be used to show differences between actual progress and
planned target, the resources use against estimated quantities or budget.
In feedback control system, information about the results of the activity is fed back to the persons who are
the actors themselves. In a system control, the communication network is set up in such a way that
information about deviations is at once transmitted to the person, who can take the corrective actions such
as adjustment on resources. Hence the control process of the project can be supported by introducing
elements of feedback control theory. A perfect leader should develop a system for performance revision,
and at each revision control action is taken.
Cost control may be broadly defined as the process of controlling the expenditure in a project at all stages
from its inception through its development. Cost control means controlling changes to project budget.
Cost control is equally important to all firms, regardless of size. Small firms generally have tighter
monitory control, mainly because they have fewer project and the risks of failure of project are high.
Unlike this, larger firms usually have several projects and even if one project fails, they have the luxury to
spread project losses over several projects. So, larger firms may have less sophisticated control
techniques.
Graphical presentation of Earned Value Analysis (EVA) Fig3.7: Earned Value Analysis
CV
identified. Any deviation from
the activity S-curve is reported
SV
BCWP
immediately acted upon.
Cost
It is the budgeted amount of cost for work scheduled to be accomplished plus the amount of level of effort
or apportioned effort scheduled to be accomplished in a given time period. In simple term, BCWS is the
value of work that should have been done at a given point of time i.e. expected expenditure at given point
of time (review date).
It is the budgeted amount of cost for completed work, plus budgeted level of effort or apportioned effort.
This is sometimes referred to as "Earned Value". In simple term, BCWP is the value of work done at a
point of time.
It is the amount reported as actually expended in completing the work accomplished within a given time
period. In simple term, ACWP is the actual cost of work done at a point of time.
These costs (BCWS, BCWP, ACWP) can be applied to any level of the work break down structure (i.e.
program, project, task, subtask, work package) for work that is completed Using these definitions, the
following variance definition can be obtained:
If it is 0, you are right on budget. If it is negative, you are over budget. If it is positive, you are under
budget.
If it is 0, you are right on schedule. If it is negative, you are behind schedule. If it is positive, you are
ahead of schedule.
Capital structure, some time known as financial plan (Capital plan or financial plan) refers to the
composition (makeup) of long-term sources of funds, such as debentures, long-term debt, preference
share capital, and equity share capital including reserve and surplus. Some companies do not plan their
capital structure and it develops as a result of the financial decision taken by the financial manager
without any formal planning. Such companies may prosper in short term, but ultimately will face
considerable difficulties in raising funds to finance their activities. With unplanned capital structure,
organization may also fail to economies the use of their funds. Consequently, it is being increasingly
realized that an organization should plan its capital structure to maximize the use of funds and to be able
to adapt more easily to the changing conditions.
Budgetary control is a process of comparing the actual performance with budgeted performance and
taking an action to correct the budget variance. It helps in comparing the actual result with the
corresponding budget data to know the actual cause of differences. It can also be defined as: "The process
which keeps the actual standard as nearly as possible to the predetermined standards by strict
supervision". The purpose of budgetary control is to provide benchmark for controlling performance of
managers, subordinates by comparing actual performance with the budgeted performance and taking
actions to correct the budget variances.
To provide benchmark for controlling performance of managers and their subordinates by comparing
actual performance with the budgeted performance and taking actions to correct the budget
variances.
To provide timely information to managers on facts related to:
To helps utilize resources in the best possible for maximizing the output
To provides basis for revising financial policies
1. Realistic plans are prepared to provide direction to carry out business operations.
2. Actual performance for each area of responsibility is measured. Generally, the accounting system
is used to measure actual performance in financial terms.
3. Actual performance is compared with the budgeted performance to identify significant deviation.
4. Feedback mechanism is prepared to inform the management about deviations from budgets
5. Corrective action is taken to ensure the future performance is in accordance with budgets (plans).
Some corrective action may involve motivating people to implement policies, modifying certain
policies, etc.
Capital budgeting decision is the investment decisions of a firm. It may be defined as the firms' decision
to invest its current funds most efficiently in long term activities in anticipation of an expected flow of
future benefit over a series of years. The long term activities are those activities which affects firms'
operations beyond the one year period.