Vous êtes sur la page 1sur 8

OIL PALM INDUSTRY ECONOMIC JOURNAL Vol.

13 (1)/MARCH 2013

Economic Feasibility Study


on Establishing an Oil Palm
Biogas Plant in Malaysia

Roslan Abas*; Ramli ABSTRACT


Abdullah* and Yahaya
Hawari* The processing of oil palm fresh fruit bunch (FFB) primarily for palm oil
results in the production of large amount of wastes, particularly in the form
of palm oil mill effluent (POME). Production of POME can be estimated
at almost three times the quantity of crude palm oil (CPO) produced. It
can pollute the environment through the production of biogas which can
be captured through a biogas-capturing system in a biogas plant. After
capturing, the biogas can be utilised either for fueling the mill boiler,
electricity generation, flaring or as cooking gas. This current study was
carried out with the objective of assessing the economics of establishing
an oil palm biogas plant based on the four different utilisation methods of
the biogas. The results indicate that utilising biogas for the boiler gives
higher economic returns compared with the other three options, given
certain conditions. This study finally concludes with some issues that
have an impact on any interested investor in a biogas project.

INTRODUCTION Resources and Environment


Ministry to finance projects aimed
During the Climate Change at reducing GHG emissions.
Summit (COP15) from 17-18 Some of the projects that are
December 2009 in Copenhagen, being financed are those related
Denmark, the Malaysian Prime to achieving energy efficiency and
Minister had announced that the exploiting renewable energy (RE)
country would voluntarily reduce sources, and they are mostly in the
emission intensity of greenhouse oil palm sector.
gas (CHG) emission by up to 40% The palm oil industry is the
based on 2005 levels by 2020 fourth largest component of the
(NRE, 2000). This reduction is national economy, covering a
an indication of Malaysia’s serious v al u e ch ai n s p an n i n g f ro m
commitment to combating climate upstream activities to downstream
change issues as stipulated in the processing. With limited land
National Green Technology Policy, available to continue the expansion
* Malaysian Palm Oil Board, launched by the Prime Minister on of oil palm plantations, the
6 Persiaran Institusi, 24 July 2009. Under this policy, a government desires to increase
Bandar Baru Bangi,
43000 Kajang, Selangor, Malaysia.
fund amounting to about RM 1.5 production efficiency and focus
E-mail: roslan@mpob.gov.my billion was allocated to the Natural on providing greater value-added

14
Economic Feasibility Study on Establishing an Oil Palm Biogas Plant in Malaysia

through downstream activities. development mechanism (CDM) capital expenditure (CAPEX)


One of the eight palm oil projects under the Kyoto Protocol. With and operational expenditure
under the National Key Economic that recognition, CDM-certified (OPEX), methane recovery rate
Area (NKEA) is to develop RE-producers such as biogas and retention time (MPOB, 2009).
gradually biogas facilities at all producers can issue Certified For example, CAPEX cost for
palm oil mills by 2020 to capture Emission Reduction (CER) units the covered lagoon method was
methane under Entry Point Project which can be sold later to buyers estimated to be lower at about RM
(EPP) 5. as stated under the Kyoto Protocol. 4 million than that for the closed
The palm oil industry has As POME has the potential tank system which was estimated
already embarked on green initia- to be the main source for future to cost between RM 7 and RM 8
tives to reduce carbon emissions, RE, the inclusion of methane million (Project Design Document
and now it has been enhanced trapping in the NKEA initiatives is Form, 2007). In contrast, CAPEX
through the implementation of the in the right direction. Among the for the closed tank was recently
NKEA projects. One of the initia- alternative sources of RE, such as estimated to be higher at between
tives includes trapping of biogas wind, solar and mini hydro, POME RM 10 and RM 12 million.
such as methane to generate elec- can be considered as having an In 2012, there were 429 mills
tricity for fuelling steam turbines. advantage over the others in terms in the country that processed
The inclusion of the palm oil sector of its quantity, consistency and about 92.3 million tonnes of fresh
under NKEA is to achieve a high availability as it is sourced from the fruit bunch (FFB) (MPOB, 2013).
income status nation by 2020. existing palm oil industry. As RE Most of the mills were located
Under EPP 5, all palm oil mills are has been included in the Malaysian in Peninsular Malaysia (248
mandated to build biogas facilities. Five-Fuel Policy since 2001, and mills or 58%), processing 51.6
This EPP is expected to generate is targeted to support 5.5% of million tonnes of FFB. Processing
2000 job opportunities, and will the total energy demand in 2015 operations produce a considerable
contribute about RM 2.9 billion (EPU, 2010), it is important to amount of organic waste in the
to gross national income while in- undertake a feasibility study on the form of POME. This gives rise to
curring an investment amounting establishment of a POME biogas a challenging task to the palm oil
to RM 2.8 billion (www.pemandu. plant. A feasibility study would industry of handling such a large
gov.my). As at December 2012, 57 assist investors in their decision- amount of organic waste. The
biogas facilities had been complet- making in whether to embark conventional method for handling
ed while 16 biogas facilities were on such biogas plant projects. this organic waste is by using a
under construction. At the same However, there is no available pond system in which anaerobic
time, 150 biogas facilities were information in the public domain digestion process takes place.
under planning (MPOB, 2012). regarding investment analysis on Anaerobic digestion is a natural
The palm oil industry produced developing such a plant which can process that occurs in the absence
18.7 million tonnes of crude serve as guidance to prospective of air and that releases biogas as
palm oil (CPO) in 2012 (MPOB, investors. the output. Production of biogas
2013). However, the production Therefore, the objective of this and its quality are dependent on
of such an amount of CPO resulted study is to assess the economics maintaining a delicate balance
in a larger amount of palm oil of establishing a biogas plant. For between the acid-forming and
mill effluent (POME), which is this purpose, the assessment will methanogenic bacteria in a digester
estimated at almost three times the be carried out on a palm oil biogas (Maizirwan et al., 2008). The
quantity of CPO produced (Vijaya plant with four possible forms of balancing process is done through
et al., 2008). POME can pollute usage of the biogas, namely, for the the control of several factors,
the environment if discharged mill boiler, electricity generation, including the type of substrate,
directly into the waterways due to flaring and as cooking gas. carbon nitrogen (C/N) ratio of the
its high chemical oxygen demand substrate, temperature, pH, organic
(COD) and biochemical oxygen LITERATURE REVIEW loading rate and the concentration
demand (BOD). Nevertheless, of solids in the digester charge.
palm oil mills are currently In Malaysia, there are two basic To calculate the monetary
practicing widely both aerobic methods of capturing methane gas returns to the producers of biogas,
and anaerobic pond systems to from POME, namely, by the covered the establishment cost together
reduce COD and BOD. Between lagoon and closed tank. Both with fixed and variable costs need
these two systems, the latter system methods have their advantages to be estimated. The information
has been recognised as a clean and disadvantages in terms of needed to calculate the total costs

15
OIL PALM INDUSTRY ECONOMIC JOURNAL Vol. 13 (1)/MARCH 2013

are capital, fuel, financing and In carrying out the analysis, Steven Based on the above scenario,
running costs (Stevens, 2007). The (2007) also showed that the the investment cost can vary. Due
capital cost is normally correlated payback period for most biomass to this, the study made several
positively with power output plants with a full 20-year lifetime assumptions in estimating the cost.
as measured by kiloWatt hours was 15 years, but for others it First, a palm oil mill will discharge
(kWhr), but the authors noted may be much shorter. Therefore, its POME directly into the tank,
that smaller combustion plants [of increasing the plant lifetime will eliminating the need to discharge
10-15 megaWatt (MW) capacity result in cost reduction, estimated POME into the pond first. It is also
range] could cost £2520 (RM at between 7% and 12%. Although further assumed that the plant will
17 3881) kWhr while a larger plant O&M is a smaller component of be using a new steel tank rather
(of 30-40 MW capacity range) the total costs, it still has an impact than refurbish an existing one.
could bring the figure down to because it is applicable over the full To estimate the economic
£1860 (RM 12 834) kWhr. This lifetime of the plant. It was noted feasibility of a biogas plant, the
scenario can best describe the that fuel costs represented a major study adopted a financial analysis
concept of economies of scale portion of the total costs, and even approach. This approach had been
where more output produce will more significantly during the later adopted by Stevens (2007), Project
result in a reduction in input cost. years of the plant, especially after Design Document Form (2007) and
The Sanwa Engineering the 15-year payback period. The National Technical Expert (2004).
Report (2006) estimated that the last two variables are efficiency The variables to be collected were
investment cost for a biogas facility and load factor that are very much mill capacity, FFB production,
from a 40 t/hr mill was RM 3.2 dependent on the technology POME production, percentage of
million with RM 0.3 million per adopted for the plant. An increase methane gas captured, tax rate,
annum for operating expenditure. in load factor and efficiency will CAPEX, OPEX and investment
For methane trapping using the lead to a reduction in cost. period. Other assumptions for this
continuously stirred tank reactor analysis included the following:
(CSTR) method, the investment METHODOLOGY • mill capacity was 60 t FFB per
cost was estimated at about RM 7.2 hour;
million with an annual operating It was observed that the cost • estimated volume of FFB
of establishing a biogas plant processed was 360 000 t FFB
cost of RM 0.2 million (Project
depends on whether a palm oil mill per year;
Design Document Form, 2007).
discharges its POME directly into • POME produced was 600 m3
In west Kalimantan, Indonesia, the
the tank, or into the pond first and per day;
investment cost for a biogas project
then into the tank. For the latter, • percentage of methane gas
from a 60 t/hr mill was around USD the tank may be smaller than for capture was estimated at 65%;
3.1 million (RM 10 million, RM the former because the mill may • operational cost was 5% of the
3.2=USD1) (National Technical not necessarily discharge all the capital expenditure;
Experts, 2004). From that total, POME into the tank at any one • tax holding on income for first
USD 2.9 million was for CAPEX time, but can keep some of it in five years of operation and 25%
and USD 0.12 million for OPEX. the pond. If the mill discharges its subsequently; and
Capital, operating and POME directly into the tank, it may • investment period was 16
maintenance costs of biogas require larger tank to accommodate years.
production and upgrading system all the POME produced by the mill.
vary significantly due to the Hence, the tank capacity can give The biogas plant was given
different technologies adopted as an impact on the cost because four different options to utilise
well as the scale of production clearly a larger tank can result in a the captured biogas, either for
(Maizirwan et al., 2008). To higher cost. running the boiler (Option A),
investigate the economic feasibility In addition, a palm oil mill may for electricity generation (Option
of the plant, the authors suggested either use an existing tank, already B), for flaring (Option C) and for
gathering relevant influencing built earlier on, due to space cooking gas (Option D). To utilise
parameters, such as payback limitation, or it may build a new the biogas, the plant had further
period, plant lifetime, discount rate, one. The existing tank, however, requirements, depending on the
construction cost, operation and needs to be refurbished before option or the purpose. These are
maintenance (O&M) costs, fuel use, which indeed can reduce the shown in Table 1.
and efficiency, and load factor, to investment cost compared with For each of the options in Table
be used in the simulation analyses. building a new tank. 1, the analysis further assumed

16
Economic Feasibility Study on Establishing an Oil Palm Biogas Plant in Malaysia

TABLE 1. ADDITIONAL ASSUMPTIONS USED IN THE SENSITIVITY ANALYSIS


Option Additional assumption Remarks
Option A – for a) Investment cost of the biogas plant is The biogas that is captured under this option is channeled
boiler between RM 19 and RM 20 million. to the biomass boiler for heat and energy purposes.
The boiler operates using a small amount of PKS and
b) Maximum sales of palm kernel shell mesocarp fibre estimated at around 10% and 25%
(PKS) and mesocarp fibre are 90% respectively. The remaining PKS and mesocarp fibre can
and 75% respectively of the total then be sold to other industries, such as cement industry.
productions. The investment amount for this option is expected to be
between RM 19 and RM 20 million. Income from sales
c) Continued use of the current boiler of PKS and mesocarp fibre is expected to repay part of
with no or minimal modification cost. the investment cost. To simplify the analysis, only PKS
price is changing while price for mesocarp fibre remain
at RM 50/t.

Option B – for a) Investment cost of the biogas plant is For this option, there is a need to have an additional
electricity between RM 23 and RM 24 million. investment due to the purchase of a gas engine and
generation the cost of connecting an electrical transmission cable
b) Installed capacity for producing between the mill generator and a TNB power sub-station.
electricity is less or equal to 4 MW. These investments result in an increase in cost amounting
to RM 20 million to RM 24 million. Hence, two additional
c) Cost of purification (fixed and variable variables were used in the sensitivity analysis, i.e. the
costs) is estimated at RM 1 million. length of the transmission cable and the tariff rate. The
distance of the electrical transmission cable connection
d) Transmission cable cost is estimated ranged between 10 and 30 km, while the tariff ranged
at RM 1 million/km. between RM 0.3184 and RM 0.4184 kWhr.

Option C – for a) Investment cost of the biogas plant is This option is the simplest form of utilising the biogas. In
flaring assumed to be at RM 19 million. fact, it is almost similar to option A where the investment
cost of biogas plant is also about RM 19 million. The
only form of revenue generated from this option is
from issuing Certified Emission Reduction (CER). For
sensitivity analysis, different rates of CER received were
tested, ranging from RM 15 to RM 25/t carbon credits.

Option D – for a) Investment cost of the biogas plant A bottling plant needs to be set up for this option The
cooking gas is RM 19 million while for investment investment cost of a bottling plant is estimated at RM 7
cost of the bottling gas plant is RM 7 million with a refill capacity of 60 000 gas cylinders per
million. year.

b) Retail price of a 14-kg gas cylinder is


RM 48 (RM 26.60 sales price and RM
21.40 government subsidy). Sales
price is 70% of the retail price.

c) Operational cost is 5% of the capital


expenditure for both plants.

d) Cost for purification (fixed and variable


costs) is estimated at RM 1 million.

that the plant was given another which are common indicators for Option A – Producing Biogas for
two sub-options, i.e. revenue assessing the economic feasibility the Boiler
without CER and revenue with of each option.
CER. Hence, there were eight The main influencing factor
scenarios representing all possible RESULTS AND DISCUSSION when utilising methane gas for
options as shown in Figure 1. running the boiler without CER
The analysis produced eco- To fully understand the economic is the price of palm kernel shell
nomic parameters, such as internal feasibility of the biogas project, a (PKS) in addition to income from
rate of return (IRR), payback pe- sensitivity analysis was carried out selling mesocarp fibre in which
riod and net present value (NPV), on each of the four options. its price was fixed at RM50/t.

17
OIL PALM INDUSTRY ECONOMIC JOURNAL Vol. 13 (1)/MARCH 2013

Options for utilising biogas

▼ ▼ ▼ ▼
Option A Option B Option C Option D
Boiler Electricity Flaring Cooking gas

▼ ▼ ▼ ▼
Result 1 Result 3 Result 5 Result 7
(without CER) (without CER) (without CER) (without CER)

Result 2 Result 4 Result 6 Result 8


(with CER) (with CER) (with CER) (with CER)

Note: CER - Certified Emission Reduction.

Figure 1. Four options for utilising biogas.

The estimated production of PKS value of IRR will correspondingly Option B – Producing Biogas for
and mesocarp fibre was 5% and increase to more than 20% and Electricity Generation
7% respectively from total FFB NPV to RM 28 769.
processed annually (Astimar et al., In summary, without applying For Option B, the sensitivity
2011). When the price of PKS is CER and letting the price of PKS analysis was carried out on three
RM 150/t, IRR is only about 0.78% range between RM 150 and RM variables, i.e. electricity tariff, CER
with a negative NPV. If price of 250/t, the simulation analysis value and distance of electrical
PKS increased to RM 200/t, it will shows that the IRR values will fall transmission cable between the
definitely improve IRR to 8.36% between 0.78% and 14.29%, NPV mill and a Tenaga Nasional Berhad
and NPV to RM 7355 (Table 2). from – RM 2639 to RM 16 769, and (TNB) power sub-station. Table 3 is
IRR, NPV and the payback period the payback period from seven to the result of the sensitivity analysis
will improve further if the price of 15 years, for capturing biogas for using varying rates of electricity
PKS rose to RM 250/t. the boiler. If the analysis included tariff and varying values of CER.
The contribution of CER is CER with values ranging from RM The current tariff rate for
also significant in improving the 15 to RM 25/t carbon, and coupled electricity (in 2013) for a project
feasibility. A combination of a with a price of PKS between RM approved by the government is
PKS price at RM 150/t and a price 150 and RM 250, IRR will be RM 0.3184 kWhr. At this rate,
of CER at RM 20 will give IRR between 6.57% and 20.66%, NPV without CER, an investment on
of 8.24% and NPV of RM 7433. between RM 4921 and RM 28 769, biogas for electricity generation
When the price of PKS increases to and the payback period between gives an IRR value of 2.59%, NPV
RM 250/t and CER to RM 25, the five and nine years. of RM 743 and a payback period

TABLE 2. SENSITIVITY ANALYSIS FOR PRODUCING BIOGAS FOR THE BOILER


PKS price With CER (RM Carbon/credit)
(RM/t) Parameter Without CER
RM 15 RM 20 RM 25
IRR (%) 0.78 6.57 8.24 9.85
150 NPV (RM) (2 639) 4 921 7 433 9 941
Payback 15 9 8 8
IRR (%) 8.36 12.54 14.01 15.45
200 NPV (RM) 7 355 14 339 16 487 19 355
Payback 8 7 6 6
IRR (%) 14.29 17.92 17.92 20.66
250 NPV (RM) 16 769 23 735 23 753 28 769
Payback 6 6 5 5
Note: IRR - internal rate of return; NPV - net present value; payback is calculated in years. PKS - palm
kernel shell. CER - Certified Emulsion Reduction.

18
Economic Feasibility Study on Establishing an Oil Palm Biogas Plant in Malaysia

TABLE 3. SENSITIVITY ANALYSIS FOR PRODUCING BIOGAS FOR ELECTRICITY GENERATION


Electricity tariff With CER (RM carbon/credit)
Parameter Without CER
(RM kWhr) RM 15 RM 20 RM 25
IRR (%) 2.59 6.00 7.28 8.51
0.3184 NPV (RM) (743) 5 803 8 456 11 087
Payback 13 10 8 8
IRR (%) 5.90 8.90 10.03 11.13
0.3684 NPV (RM) 5 540 11 927 14 438 16 946
Payback 10 8 8 7
IRR (%) 8.72 11.49 12.57 13.62
0.4184 NPV (RM) 11 397 7.787 20 295 22 803
Payback 8 7 7 6
Note: IRR = internal rate of return; NPV = net present value; payback is calculated in years; distance of transmission cable is
fixed at 10 km. CER – Certified Emulsion Reduction.

of 13 years. If the tariff rate were of RM 22 803, with a payback NPV of RM 5803 if the CER value
to increase by 5 sen to RM 0.3684 period of only six years. was RM 15.
kWhr, IRR will improve to 5.90%, Similar to tariff rate, the distance In summary, with CER, the
NPV to RM 3540 and the payback of electrical transmission cable minimum IRR value of 1.53% and
period reduced to 10 years. A from the mill to a TNB power sub- NPV of RM 3644 will result if the
further increase in tariff rate, e.g. by station can also influence revenue transmission line was 15 km, and
10 sen from the current tariff, and and return to investment of the CER was RM 15, while the highest
the investor will enjoy better IRR biogas plant. For the analysis, value of IRR (8.51%) and NPV of
of 8.72%, NPV of RM 11 397 and the costs for 5, 10 and 15 km of RM 11 087 will be achieved for a
a payback period of eight years. the transmission cable were set at 5 km distance between mill and
The contribution to revenue RM 5, RM 10 and RM 15 million, sub-station with CER at RM 25.
from CER is noticeable. At the respectively (Table 4).
current tariff rate of RM 0.3184 It was noticed that without Option C – Producing Biogas for
and a CER value of RM 15, the IRR CER, the IRR value will decrease Flaring
value will be 6.00% and NPV RM from 2.59% for 5 km to 1.69%
5803. If the CER value reached for 15 km of transmission cable. Table 5 shows the results of
RM 25, it will lead to IRR valued Increasing the distance between the feasibility study when biogas
at 8.51% and NPV at RM 11 087. the mill and the TNB sub-station is used for flaring. Without any
If both tariff and CER were to further will lead to a negative value activity that can generate income,
increase to RM 0.4148 kWhr and for NPV and smaller value of IRR. the project clearly indicates a
RM 25, respectively, the investment With CER, the return was much negative return of NPV at –RM
can yield IRR of 13.62% and NPV better with a IRR value of 6% and 27 783. Even with the revenue

TABLE 4. SENSITIVITY ANALYSIS FOR PRODUCING BIOGAS


FOR ELECTRICITY GENERATION
Distance With CER (RM carbon/credit)
(km) Parameter Without CER
RM 15 RM 20 RM 25
IRR (%) 2.59 6.00 7.28 8.51
5 NPV (RM) (743) 5 803 8 455 11 087
Payback 12 10 9 8
IRR (%) 0.20 3.61 4.78 5.92
10
NPV (RM) (5 743) 1 355 4 054 6 752
Payback 16 12 11 10
IRR (%) (1.69) 1.53 2.63 3.68
15
NPV (RM) (10 743) (3 644) (945) 1 752
Payback >16 14 10 12
Note: IRR = internal rate of return; NPV = net present value; payback is calculated in years; electricity tariff set at RM
0.3184 kWhr. CER – Certified Emulsion Reduction.

19
OIL PALM INDUSTRY ECONOMIC JOURNAL Vol. 13 (1)/MARCH 2013

generated from CER, this is still not Consistency Financial Aspect


sufficient to cover the investment
cost. The amount of methane The connection cost of the
generated is based on the electrical cable between the
Option D – Producing Biogas for assumption of 65% from the transformer at the mill and the
Cooking Gas biogas. The real amount could nearest TNB sub-station is still an
be less, especially during rain or issue. A connection cost of about
Under this option, an additional in the low cropping seasons. The RM 1 million/km is currently being
investment is needed to establish activity of microorganisms (which borne by the biogas producer. It
the gas refilling plant and to is crucial in ensuring productivity) has a significant impact on the total
purchase new gas cylinders (Table can also lead to inconsistencies investment cost. Another issue is
6). This additional investment in the amount of gas produced. being able to secure a loan from
is estimated at RM 7 million. Microorganisms are very sensitive commercial banks for a biogas
Without CER, the investment to drastic changes in temperature project. Not many commercial
indicates a negative return as the of POME. Less methane produced banks are willing to fund such
NPV value is -RM 24 294, and the will have an impact on the amount investments. The process for
payback period is more than 16 of electricity generated or the heat claiming CER is another issue
years. Even with a contribution produced. because the requirement to issue
from CER, the returns are still CER as well as to obtain payment
not sufficient because all the is quite rigid, coupled with the
Maintenance and Replacement
economic parameters indicate fluctuating CER price in the world
Costs
negative returns. market.

ISSUES The presence of hydrogen


Human Resource Management
sulphide (H2S) can cause corrosion
Of the various issues discussed to steel pipings and valves. This Establishment of a biogas plant
with the biogas players, some merit can lead to higher replacement as requires manpower either from
further deliberation for a clearer well as maintenance costs. Regular existing or new staff. If manpower
picture of the future prospects of monitoring is needed to maintain is obtained from the existing
the biogas industry. the safety of the biogas plant. staff, it means that there will be

TABLE 5. SENSITIVITY ANALYSIS FOR PRODUCING BIOGAS FOR FLARING


With CER (RM carbon/credit)
Parameter Without CER
RM 15 RM 20 RM 25
IRR (%) - - - -
NPV (RM) (27 783) (21 546) (19 310) (17 073)
Payback >16 >16 >16 >16
Note: IRR = internal rate of return; NPV = net present value; payback is calculated in years. CER –
Certified Emulsion Reduction.

TABLE 6. SENSITIVITY ANALYSIS FOR PRODUCING BIOGAS


FOR COOKING GAS
With CER (RM carbon/credit)
Parameter Without CER
RM 15 RM 20 RM 25
IRR (%) - (8.81) (6.02) (4.01)
NPV (RM) (24 294) (16 691) (13 993) (11 294)
Payback >16 >16 >16 >16
Note: IRR = internal rate of return; NPV = net present value; payback is calculated in years; refill
capacities of 200 cylinder per day x 25 days x 12 months = 60 000 gas cylinders per year.

Total price = consumer price of RM 26.60 + government subsidy of RM 21.42 = RM 48.02 per cylinder
of cooking gas.

Assuming producer sales price = 70% of total price = RM 33.61 per cylinder of cooking gas.

Plant refilling investment = RM 7 million.

20
Economic Feasibility Study on Establishing an Oil Palm Biogas Plant in Malaysia

a diversification of jobs and extra CER is crucial in increasing the cost of installing the electrical
responsibility for the staff. There investment return; thus, it is worth transmission cable needs to be
is also an increase in the training the effort of ensuring that it is resolved. This is important because
cost because a biogas plant needs successfully issued and paid for. To it has an impact on the investment
to be handled and supervised by this end, engaging an experienced costs as well as on returns, and
skilled personnel. In addition, consultant is important so that an helps in the decision-making
there is also a need to engage a investor gets the right CER price. process of would-be investors.
consultant who is responsible for The question of who should bear
project preparation, a baseline
study, and emission trading
which is one of the important REFERENCES
components for the success of
the biogas project. Selecting an
‘inexperienced’ consultant could ASTIMAR, A A; LOH, S K; LIM, W S and CHOO, Y M (2011). Business
result in an unfavourable outcome Opportunities in Palm Biomass for SME.
to the investment.
EPU (2010). Tenth Malaysian Plan 2011-2015. Economic Planning Unit.
CONCLUSION
MAIZIRWAN, M; SANY, I I and ERRY, Y T A (2008). Biogas Energy
The feasibility studies indicate Potential in Riau, Indonesia.
that utilising methane for the
boiler can result in higher returns MPOB (2009). Biogas Utilization in Palm Oil Mills. MPOB, Bangi.
compared with the other options.
The main reason is due to the total MPOB (2012). PEMANDU Progress Updates Report December 2012.
investment in utilising methane Unpublished.
for the boiler (RM 20.4 million –
without CER) which being at par MPOB (2013). Malaysian Oil Palm Statistics 2012. 32nd Edition. MPOB,
with flaring, but less than those Bangi.
for electricity generation (RM
23.2 million – without CER) and
NATIONAL TECHNICAL EXPERT (2004). Utilization of Biogas
cooking gas (RM 27.4 million –
Generated from the Anaerobic Treatment of Palm Oil Mills Effluent (POME)
without CER). The advantage is
as Indigenous Energy Source for Rural Energy Supply and Electrification.
from the sales revenues from PKS
Pre-feasibility study report.
(RM 4.4 million – without CER),
which is higher than the revenue
from electricity generation (RM NRE (2000). Malaysia-Second National Commnication to the UNFCCC.
3.2 million – without CER) and A publication by the Ministry of National Resources and Environment,
cooking gas (RM 2 million – Malaysia.
without CER).
Even though the revenue from PEMANDU (2012). www.pemandu.gov.my, accessed on 14 March 2012.
selling PKS in Option A (biogas
for boiler) is higher than for the PROJECT DESIGN DOCUMENT FORM (2007). Methane Capture and
other options, it is less consistent On-site Power Generation Project at Syarikat Cahaya Muda Perak (Oil Mill)
as compared with the revenue Sdn Bhd in Tapah, Perak. Version 1.4 04/11/2007.
from electricity generation and
cooking gas. This is because of SANWA ENGINEERING Co. Ltd (2006). Feasibility Study on Efficient
the fluctuating PKS price in the Methane Recovery and Heat Generation in Palm Oil Mill in Malaysia.
world market. In contrast, the Summary report.
selling price for electricity has
been fixed at RM 0.3184 kWhr (for STEVENS, A S N (2007). Economic Viability of Promising Biomass
projects approved in 2013), while Utilisation Technologies in the East of England. M. Sc., School of
cooking gas has been categorised Engineering, Cranfield University.
as a ‘price control product’ by the
government. This is where the VIJAYA, S; MA, A N; CHOO, Y M and NIK MERIAM, N S (2008). J. Oil
businesses need to make their own Palm Res. Vol. 20: 484-494
sound judgment.

21

Vous aimerez peut-être aussi