ID Task Name Duration Start Finish Predecessors

Planned % Actual % 04 Feb '18 11 Feb '18 18 Feb '18 25 Feb '18 04 Mar '18
complete complete T S M W F S T T S M W F S T T S M
1 RM Building Alembic 28 days Mon 05-02-18
Sun 04-03-18 100% 60%
2 Phase -1 28 days Mon 05-02-18
Sun 04-03-18 100% 60%
3 Foundation 24 days Mon 05-02-18
Wed 28-02-18 100% 88%
4 Pad Footing 9 days Tue 13-02-18
Wed 21-02-18 100% 100%
5 Excavation 4 days Tue 13-02-18
Fri 16-02-18
31FS+1 day100% 100%
6 rubble soiling 4 days Wed 14-02-18
Sat 17-02-18
5SS+1 day100% 100%
7 PCC 3 days Fri 16-02-18
Sun 18-02-18
6SS+2 days100% 100%
8 Rebaring 2 days Sun 18-02-18
Mon 19-02-18
7SS+2 days100% 100%
9 Reinforcement Laying 2 days Mon 19-02-18
Tue 20-02-18
8SS+1 day100% 100%
10 Shuttering 2 days Tue 20-02-18
Wed 21-02-18
9SS+1 day100% 100%
11 Concreting 1 day Wed 21-02-18
Wed 21-02-18
10SS+1 day100% 100%
12 Column (14 nos) 6 days Thu 22-02-18
Tue 27-02-18 100% 71%
13 Chipping of plaster (14 Nos) 3 days Thu 22-02-18
Sat 24-02-18
11 100% 100%
14 Fabrication of column (14 Nos)
4 days Fri 23-02-18
Mon 26-02-18
13SS+1 day100% 80%
15 Shuttering 4 days Sat 24-02-18
Tue 27-02-18
14SS+1 day100% 50%
16 Concreting 2 days Sat 24-02-18
Sun 25-02-18
15SS 100% 50%
17 Ground Beam 17 days Mon 12-02-18
Wed 28-02-18 100% 68%
18 Excavation 2 days Mon 12-02-18
Tue 13-02-18
31 100% 100%
19 Pcc 1 day Wed 14-02-18
Wed 14-02-18
18 100% 100%
20 Brick Masonary 3 days Thu 15-02-18
Sat 17-02-18
19 100% 100%
21 Rebaring/Welding 2 days Sun 18-02-18
Mon 19-02-18
20 100% 70%
22 reinforcement Laying 3 days Mon 19-02-18
Wed 21-02-18
21SS+1 day100% 60%
23 Shuttering 2 days Tue 20-02-18
Wed 21-02-18
22SS+1 day100% 40%
24 Concreting 1 day Thu 22-02-18
Thu 22-02-18
23 100% 40%
25 back filling & compaction 3 days Sat 24-02-18
Mon 26-02-18
24FS+1 day100% 45%
26 Floor PCC 1 day Wed 28-02-18
Wed 28-02-18
25FS+1 day100% 50%
27 Lift 3 & 4 7 days Mon 05-02-18
Sun 11-02-18 100% 100%
28 Rebaring 3 days Mon 05-02-18
Wed 07-02-18 100% 100%
29 Reinforcement Laying 4 days Tue 06-02-18
Fri 09-02-18
28SS+1 day100% 100%
30 Shuttering 4 days Wed 07-02-18
Sat 10-02-18
29SS+1 day100% 100%
31 Concreting 4 days Thu 08-02-18
Sun 11-02-18
30SS+1 day100% 100%
32 Lift 1 & 2 7 days Thu 08-02-18
Wed 14-02-18 100% 100%
33 Rebaring 3 days Thu 08-02-18
Sat 10-02-18
28SS+3 days
100% 100%
34 Reinforcement Laying 4 days Fri Mon 33SS+1 100% 100%
09-02-18 12-02-18 day
35 Shuttering 4 days Sat 10-02-18
Tue 13-02-18
34SS+1 day100% 100%
36 Concreting 4 days Sun 11-02-18
Wed 14-02-18
35SS+1 day100% 100%
37 Staircase 11 days Tue 06-02-18
Fri 16-02-18 100% 87%
38 PCC 1 day Tue 06-02-18
Tue 06-02-18
28SS+1 day100% 100%
39 Reinforcement Laying 6 days Wed Mon 38 100% 100%
07-02-18 12-02-18
40 Shuttering 7 days Fri 09-02-18
Thu 15-02-18
39SS+2 days
100% 80%
41 Concreting 5 days Mon 12-02-18
Fri 16-02-18
40SS+3 days
100% 80%
42 Ground floor Works 17 days Mon 12-02-18
Wed 28-02-18 100% 45%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: Project3 PCC working 1 Split External Tasks Inactive Summary Manual Summary Progress
Date: Tue 06-03-18
Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Name Duration Start Finish Predecessors
Planned % Actual % 04 Feb '18 11 Feb '18 18 Feb '18 25 Feb '18 04 Mar '18
complete complete T S M W F S T T S M W F S T T S M
43 Column 3 days Mon 26-02-18
Wed 28-02-18 100% 0%
44 Shuttering (6nos) 3 days Mon 26-02-18
Wed 28-02-18
16 100% 0%
45 Concreting (6nos) 3 days Mon 26-02-18
Wed 28-02-18
44SS 100% 0%
46 Lift 3 & 4 7 days Mon 12-02-18
Sun 18-02-18 100% 95%
47 Rebaring 3 days Mon 12-02-18
Wed 14-02-18
31 100% 95%
48 Reinforcement Laying 4 days Tue 13-02-18
Fri 16-02-18
47SS+1 day100% 95%
49 Shuttering 4 days Wed 14-02-18
Sat 17-02-18
48SS+1 day100% 95%
50 Concreting 4 days Thu 15-02-18
Sun 18-02-18
49SS+1 day100% 95%
51 Lift 1 & 2 7 days Thu 15-02-18
Wed 21-02-18 100% 69%
52 Rebaring 3 days Thu 15-02-18
Sat 17-02-18
36 100% 80%
53 Reinforcement Laying 4 days Fri 16-02-18
Mon 19-02-18
52SS+1 day100% 80%
54 Shuttering 4 days Sat 17-02-18
Tue 20-02-18
53SS+1 day100% 60%
55 Concreting 4 days Sun 18-02-18
Wed 21-02-18
54SS+1 day100% 60%
56 Staircase 9 days Sat 17-02-18
Sun 25-02-18 100% 0%
57 Shuttering 7 days Sat 17-02-18
Fri 23-02-18
41 100% 0%
58 Reinforcement Laying 6 days Mon 19-02-18
Sat 24-02-18
57SS+2 days
100% 0%
59 Concreting 5 days Wed 21-02-18
Sun 25-02-18
58SS+2 days
100% 0%
60 Block Masonary 5 days Thu 15-02-18
Mon 19-02-18 100% 90%
61 Internal Plaster 6 days Tue 20-02-18
Sun 25-02-18
60 100% 0%
62 1st Floor Works 18 days Thu 15-02-18
Sun 04-03-18 100% 22%
63 Column 5 days Thu 15-02-18
Mon 19-02-18 100% 87%
64 Chipping of Plaster (6nos) 1 day Thu 15-02-18
Thu 15-02-18
60SS 100% 100%
65 Fabrication (6nos) 2 days Fri 16-02-18
Sat 17-02-18
64 100% 100%
66 Shuttering (6nos) 3 days Sat 17-02-18
Mon 19-02-18
65SS+1 day100% 80%
67 Concreting (6nos) 3 days Sat 17-02-18
Mon 19-02-18
66SS 100% 80%
68 Lift 3 & 4 7 days Mon 19-02-18
Sun 25-02-18 100% 0%
69 Rebaring 3 days Mon 19-02-18
Wed 21-02-18
50 100% 0%
70 Reinforcement Laying 4 days Tue 20-02-18
Fri 23-02-18
69SS+1 day100% 0%
71 Shuttering 4 days Wed 21-02-18
Sat 24-02-18
70SS+1 day100% 0%
72 Concreting 4 days Thu 22-02-18
Sun 25-02-18
71SS+1 day100% 0%
73 Lift 1 & 2 7 days Thu 22-02-18
Wed 28-02-18 100% 0%
74 Rebaring 3 days Thu 22-02-18
Sat 24-02-18
55 100% 0%
75 Reinforcement Laying 4 days Fri 23-02-18
Mon 26-02-18
74SS+1 day100% 0%
76 Shuttering 4 days Sat 24-02-18
Tue 27-02-18
75SS+1 day100% 0%
77 Concreting 4 days Sun 25-02-18
Wed 28-02-18
76SS+1 day100% 0%
78 Staircase 7 days Mon 26-02-18
Sun 04-03-18 100% 0%
79 Shuttering 7 days Mon 26-02-18
Sun 04-03-18
61 100% 0%
80 Block Masonary 5 days Tue 20-02-18
Sat 24-02-18
60 100% 90%
81 Internal Plaster 6 days Sun 25-02-18
Fri 02-03-18
80 100% 0%
82 2nd Floor Works 14 days Fri 16-02-18
Thu 01-03-18 100% 81%
83 Column 5 days Fri 16-02-18
Tue 20-02-18 100% 87%
84 Chipping of plaster (6 nos) 1 day Fri 16-02-18
Fri 16-02-18
64 100% 100%
85 Fabrication (6nos) 2 days Sat 17-02-18
Sun 18-02-18
84SS+1 day100% 100%
86 Shuttering (6nos) 3 days Sun 18-02-18
Tue 20-02-18
85SS+1 day100% 80%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: Project3 PCC working 1 Split External Tasks Inactive Summary Manual Summary Progress
Date: Tue 06-03-18
Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task Name Duration Start Finish Predecessors
Planned % Actual % 04 Feb '18 11 Feb '18 18 Feb '18 25 Feb '18 04 Mar '18
complete complete T S M W F S T T S M W F S T T S M
87 Concreting (6nos) 3 days Sun 18-02-18
Tue 20-02-18
86SS 100% 80%
88 Block Masonary 5 days Sun 25-02-18
Thu 01-03-18
80 100% 70%
89 3rd Floor Works 20 days Sat 10-02-18
Thu 01-03-18 100% 64%
90 Column 9 days Sat 10-02-18
Sun 18-02-18 100% 100%
91 Rebaring 3 days Sat 10-02-18
Mon 12-02-18 100% 100%
92 Reinforcement Laying 4 days Sun 11-02-18
Wed 14-02-18
91SS+1 day100% 100%
93 Shuttering 7 days Sat 10-02-18
Fri 16-02-18
92SS-1 day100% 100%
94 Concreting 7 days Mon 12-02-18
Sun 18-02-18
93SS+2 days
100% 100%
95 Beam 13 days Sat 17-02-18
Thu 01-03-18 100% 55%
96 Shuttering 9 days Sat 17-02-18
Sun 25-02-18
94SS+5 days
100% 80%
97 Reinforcement Laying 8 days Tue 20-02-18
Tue 27-02-18
96SS+3 days
100% 40%
98 Concreting 2 days Wed 28-02-18
Thu 01-03-18
97 100% 0%
99 Slab 12 days Sun 18-02-18
Thu 01-03-18 100% 33%
100 Shuttering 9 days Sun 18-02-18
Mon 26-02-18
96SS+1 day100% 65%
101 Reinforcement Laying 7 days Wed 21-02-18
Tue 27-02-18
100SS+3 days
100% 0%
102 Concreting 2 days Wed 28-02-18
Thu 01-03-18
101 100% 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: Project3 PCC working 1 Split External Tasks Inactive Summary Manual Summary Progress
Date: Tue 06-03-18
Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 3