Académique Documents
Professionnel Documents
Culture Documents
Temperature. O F
1. High flow rate pump with recycle to storage tank. 1. Heat entire system including atomizer with steam,
2. Direct feed to atomizer as short as possible. hot water or a fuel oil, at the same temperature as that
3. Provisions for immediate flushing of lines and good needed for the waste fluidization.
drainage. 2. Feed waste into system and allow entire system, in-
4. Proper instrumentation and equipment for con- cluding recycle lines and tank, to fill up with waste
trolled heating of lines. at a controlled temperature level.
Air
I
I '
I
Mixer
I
I
I
- TANK
t o Burner
Heat - t raced
Insulated L i n e
INCINERATOR
Drhn
Drain
Figure 2. Waste piping system.
ATOMIZER LOCATION
A recent incinerator operation problem was determined
to be nozzle size and location. The nozzle type was correct
for the type of waste. It was an external atomizing type
using steam as the atomizing fluid (Figure 5 ) . The prob-
lems were the quantity of waste being injected through
each nozzle and the locations of these nozzles with respect
to the primary burner. As flow increases in a nozzle, the
nozzle flow design requires that the area must also in-
Figure 3. Sub-X incinerator. crease to maintain the velocities of the waste liquid and
248 November, 1985 Environmental Progress (Vol. 4, No. 4)
size of 125 p and the 10-gal/min nozzle form droplets with
a particle size of 300 p. Three 3.3-gaVmin nozzles will pro-
duce 610.7M droplets with a surface area of 300 cmi. The
single 10-gal/min nozzle produces 44.2M droplets with a
surface area of 125 cmz.With three 3.3-gal/min nozzles lo-
cated as shown in Figure 6, the heat transfer rate from the
high temperature products of combustion to the droplets
will be much more rapid than to the larger droplets from
the 10-gal/min nozzle and evaporation will be more rapid.
(Ratio is 2.4:l) [5].
The single 10-gal/min system was much less expensive
to install, but it did not produce the desired results. The
nozzle was also directed too close to the main flame,
quenching combustion from t h e main auxiliary fuel
HEATlNQ ZONES burner, adding to the problems of the incinerator.
Oxidation Air
DROP DIhYETER,pm
Important in the design of liquid waste incinerators is
the supply of combustion and secondary air and the injec-
tion point with respect to the wastes. Waste injected di-
rectly into a combustor is usually supplied with primary
air. The two streams are well mixed in the combustion pro-
cess (Figure 7). However, there are systems where waste is
injected directly into an incineration chamber. The oxy-
gen needed for combustion of the organics comes from ei-
ther excess air from the main burner (Figure 8) or as air
leakage, typical in rotary kilns. As a result, the organics are
being vaporized and superheated without the proper oxy-
gen for combustion. To properly oxidize a waste liquid, the
BURNlNQ TIME. msec. hydrocarbons should be in a gaseous state mixed with an
Figure 4. Droplet vs. burning time. excess of air or oxygen to promote rapid oxidation to COO
and H,O vapor. If oxygen is not available, the hydrocar-
bons will be pyrolyzed to CO, H2, and soot. Then, addi-
I
20
Wssl. Liquid
15
--.--c
Aur. Full
h.z" 10
w
Primsrr 0
Combustion
Air
T K
0 5
Figure 8. Aqueous waste incinerator without secondary air.
A U K . Fuel
I I I , 1 1 I I I I I
rn 400 500 600 700 a0 UK) m lsoo 1700
loo0 1100 1200 1300 1100 1 la00 1- zoo0 2100 2200
Furruco gar exit tomperoturr. C
Figure 12. Heat availability chart. Reproduced by permission of North American Mfg. Co., Cleveland, OH.
units that do, in fact, have quality design and controls. procedures. Systems that have overcome initial design and
With these improvements, users will now schedule pre- operating faults will go a long way in providing long term
ventive maintenance on the equipment, resulting in less operation in the process plant.
downtime [7, 8, 9, 101.
Systems that had been purchased on price alone have LITERATURE CITED
made second time users look closely at all costs, capital 1. Resource Conservation and Recovery Act. Standards for
and operating. For examples: a system priced at $1.4 x lo6 Owners and Operators of Waste Facilities: Incinerators.
was selected over one costing $1.2 x lo6(a $200,000 pre- 40CFR264, RCRA 3004, Jan. 25, 1981, Rev. July 21, 1982.
mium) based on the savings the user had projected would 2. Personal Communications with R. Johnson, Virginia Chemi-
result from lower maintenance. With a similar lower cost cal c o .
system, his past experience indicated that refractory main- 3. Personal Communications with American Cyanamid Co.,
tenance alone would result in an annual cost differential of Inc., Hannibal, Mich.
4. Santoleri, J. J. “Hazardous Liquid Waste Disposal: Incinera-
over $50,000. This did not include the fuel savings, nozzle tion -The Ultimate Solution.” National Conference on Haz-
replacement costs, downtime costs, etc [II]. ardous Wastes and Environmental Emergencies, ,March
It is extremely important in the installation of a new in- 12-14, 1984, Houston, Texas.
cinerator unit or in retrofitting an existing system to re- 5. Santoleri, J. J. “Spray Nozzle Selection,” Chemical Engineer-
view the experience of a particular design for the service ing Progress (Sept. 1974).
for which it will be used. In many cases, the purchaser 6. Monroe, E. S. “Incineration of Aqueous Wastes,” ASME Na-
does not question past experience and the final decision is tional Incineration Conference, May 1968.
based only on total installed costs and the manufacturer’s 7. Ready, D. F. and R. F. Schwab, Allied Chemical Corp., “In-
guarantee of performance. cineration Problems and How to Prevent Them,” Chemical
Engineering Progress (Oct. 1980).
With today’s high cost of fuel and labor, operating and 8. Olson, D. A. and R. J. Nebrbauer, Merck & Co., “Off-Gas In-
maintenance costs play a large role in the total annual cost cineration with Emissions Control,” Pharmaceutical Manu-
ofa system (Table 2). By ehecking on similar systems with facturers’ Association Spring Meeting, April 1983, Kalama-
reasonable operating experience a true bid evaluation can zoo, Mich.
be made. It is worth the time to visit installation sites and 9. Tipps, W. M. “Incinerating Cutting Oils and Similar Liquid
discuss operating problems with the owner and his plant Effluents Without Polluting the Air,” 23rd National Plant
personnel. This is most important as part of the bid review Engineering Conference, Jan. 1972, Philadelphia, Pa.
10. Bernadiner, M. N. et al. “Thermal Methods of Disposing of
TABLE2. COMPARISON OF TWO INCINERATION
SYSTEMS Industrial Waste Waters from Chemical Plants,”Int’Z. Chemi-
cal Eng. 13, No. 2, April 256-263 (1973).
Manufacturer A B 11. Personal Communications with E . Andreacola and G.
Irrgang, Trane Thermal.
Base Price (Equipment) $1,200 MM $1,400 M M
Annual Operating Costs Joseph J. Santoleri is a principal consultant, pro-
Fuel $2,700 M M $2.00 MM viding engineering services in the areas of com-
Power $50,000 $75,000 bustion, incineration, and heat transfer system de-
Caustic $160,000 $80,000 s i g n a n d a p p l i c a t i o n a t Four N i n e s , I n c. H e
received his B.S.M.E. a s well as his M.S.M.E. from
Maintenance $100,000 $50,000 Drexel University.
Total $3.01 MM $2,205 MM H e is a member of AIChE, ASME, American So-
Differentials ciety for Testing Materials, Air Pollution Control
Base Price +$200,000 Association, and t h e American Gas Association.
Operating Costs (Annual) +$805,000
Environmental Progress (Vol. 4, No. 4) November, 1985 251