Académique Documents
Professionnel Documents
Culture Documents
BY
JULY 2012
ii
DEDICATION
iii
ACKNOWLEDGEMENT
All adoration and appreciation goes to God Almighty for his endless mercy,
favour, provision, guidance and protection. I appreciate the financial, moral
and spiritual support of my parents and siblings; it is immeasurable. Special
thanks to all my friends especially Obafemi Ajayi, Wale Adekola, Uzor,
Tunde Ibiyemi, Fikayo Abogunrin, Babatunde Oni and Rotimi Lawal who
helped me in the course of this project. God will bless, keep, guide and
protect you all.
iv
TABLE OF CONTENT
Page
Title Page i
Certification ii
Dedication iii
Acknowledgement iv
Table of Content v
List of Figures ix
Abstract x
1.0 Introduction 1
2.4 Screens 14
2.10.1 Nomographs 21
vi
2.13.4 Coding and numbering 24
2.14 Project Cost Estimation 25
2.14.1 Preliminary estimates 25
2.14.2 Cost per function 25
2.14.3 Unit area cost 25
2.15 Market Survey 26
3.2.1 Loading 31
5.1 Conclusion 51
5.2 Recommendation 51
vii
LIST OF TABLES
viii
LIST OF FIGURES
x
CHAPTER ONE
INTRODUCTION
1.1 Introduction
1
1.2 Statement of the Problem
The C-channel structural steel has been in use for over five years and it
will be most appropriate to completely replace it with a culvert. This will
provide a long lasting solution to the accessibility limitations been
experienced presently by the communities. A twin-cell reinforced
concrete box culvert with material able to withstand erosion and channel
the flow effectively is required. The box culvert will be made of
reinforced concrete. This will provide a structure that will stand the test
of time, improve accessibility of both vehicular and pedestrian traffic and
provide optimal conveyance of the channel flow.
LITERATURE REVIEW
A culvert is a short, closed conduit that conveys storm water runoff under
an embankment usually a roadway. The primary purpose of a culvert is to
convey surface water but if properly designed may also be used to restrict
flow and reduce downstream peak flows. In addition to the hydraulic
function, a culvert must also support the embankment and or roadway
and protect traffic and adjacent property from flood hazards.
Box culverts are reinforced concrete closed rigid frames which must
support vertical earth loads, truck loads and lateral earth pressure. They
may be either single or multi-cells. Culverts come in many shapes and
sizes: round, elliptical, flat-bottomed, pear-shaped and box. They vary
from the small drainage culverts found on highways and driveways to
large diameter structures on significant waterways or supporting large
water control works. The latter can comprise large engineering projects.
There are three primary materials that culverts are made out of. These are
steel, precast concrete and polymer. They can also be built as a hybrid
between steel and concrete. For example an open-bottom corrugated steel
structure on concrete footings or a corrugated steel structure with a
concrete "collar" around the ends. Precast circular concrete pipe culverts
are the most common in Nigeria. They differ in diameter but are usually
made to span a metre length. Grooves are incorporated at the ends to
allow for easy connection. Precast circular pipes are durable and it is
preferred to box culvert because of its ease of construction.
6
Culvert pipe is used in construction to guide drainage water. It is often
used in situations where water overflow need to be handled. By
definition, a culvert is a mechanism that directs water. For instance
municipal sewage systems in America use culvert pipe not only to deal
with sewage, but to direct overflow water when it is raining. The culvert
pipe directs the water to reservoirs that are used to hold the water until it
can evaporate, or be further drained into natural water reservoirs like
lakes. In Nigeria, culverts are mostly used to provide accessibility where
a road spans across a river channel.
In modern times, culverts are built out of pipe and hence referred to as
culvert pipe. The larger municipal culverts are created out of concrete
which allow for high mass flow, longevity and reduced cost. Segments of
concrete culvert pipe are seen in construction areas. The segments are
premade in a factory and are transported to the construction location.
Older culvert pipe whether it is corroded or that is not large enough is
often replaced and can be very expensive because it requires shutting
down the drainage, digging up the old pipe, and burying new pipe.
Because of this, new neighborhoods are planned to allow for expansion
and built with high quality concrete culvert pipe.
7
The material the culvert pipe is made of can differ depending on the
application. Ancient culverts were crafted out of earth or stone. The three
most common materials that culverts are made out of are steel, precast
concrete, and polymer. Culvert pipes made out of steel are either designed
for durability and longevity, or are used for pressurized water. Steel
piping can handle excess pressure and high mass flow rates better than
concrete. However it is also much more expensive and hard to transport.
PolyVinylChloride (PVC) is also a common choice for culvert piping. It
is fairly inexpensive and has a major advantage of being slightly
malleable. This means that as the earth settles, the pipe can give a little
bend before breaking.
Concrete pipe is brittle and will simply break if the surround earth moves
too much. PVC is more expensive than concrete and less than steel.
However large diameter PVC pipes are not feasible. The applications for
culvert piping are numerous. Any situation where water impedes
construction generally utilizes culvert piping. Without them our cities
would flood, or roads would wash away, and our water supply wouldn’t
exist. Culvert piping allows water to pass naturally under buildings,
bridges, and roads. These are easily recognizable as storm drains. Culvert
pipes are a staple of civil engineering and help humans build magnificent
cities by overcoming the obstacles of nature.
8
2.2 Types of Box Culverts
2.2.1 Full box
Full boxes consist of a complete box culvert cell integrally cast. This type
of unit provides maximum onsite construction savings by eliminating the
need to pour an insitu base. Moulds can be changed to make portals and
ducts.
9
Fig. 2.2 Portal and base box culvert
10
2.2.4 Twin cell structure
This unit is commonly formed by installing two individual units side by
side. A twin cell installation for culverts provides additional flow capacity
which may be required for larger streams.
11
the most hydraulic efficient structure which means for a given discharge,
the area of flow is minimal. Therefore, it helps to save the cost of extra
linings required for the choice of box culverts.
12
2.3.2 Best hydraulic section
for cross-sectional area larger than about 5m2 owing to the following
reasons (Engineeringcivil.com, 2012):
13
If a choice has to be made between a single-cell box culvert and smaller
multiple pipes, it is better to select single-cell box culvert because of the
lower risk of blockage when compared with smaller size of multiple
pipes. In addition, the hydraulic performance of a single-cell box culvert
is better than multiple pipes system because of the larger hydraulic radius
associated with the box culvert for a given cross-sectional area.
2.4 Screens
However, screens are not always placed at culvert inlet and they should
be determined case by case. For trash or security screens installed in
place, it would inevitably trap floating debris and rubbish. Unless they are
14
regularly removed, it would eventually lead to rise in upstream water
level leading to local flooding. For new culvert, there is a trend that the
use of trash screens is declining. Trash screens are only placed in culvert
inlet where there is a high risk of blockage history. Instead the need of
trash screen can be eliminated by adopting the following design features:
If the depth of a box girder bridge exceeds 1/6 or 1/5 of the bridge width,
then it is recommended to be designed as a single cell box girder bridge.
However, if the bridge depth is smaller than 1/6 of the bridge width, then
a twin-cell or multiple cell is a better choice. However, for wider bridges
with small depths, the number of cells should be minimized because there
is not much improvement in transverse load distribution when the number
of cells of box girder is increased to three or more.
15
1. Inlet Control – Inlet control occurs when the culvert barrel is
capable of conveying more flow than the inlet will accept. This
typically happens when a culvert is operating on a steep slope. The
control section of a culvert is located just inside the entrance.
Critical depth occurs at or near this location, and the flow regime
immediately downstream is supercritical.
16
2. Outlet Control – Outlet control flow occurs when the culvert
section is not capable of conveying as much flow as the inlet
opening will accept. The control section for outlet control flow in a
culvert is located at the barrel exit or further downstream. Either
subcritical or pressure flow exists in the culvert barrel under these
conditions. Proper culvert design and analysis requires checking
for both inlet and outlet control to determine which will govern
particular culvert designs.
17
2.7 Appurtenant Structures
In order to integrate an improved inlet into a culvert system, several
appurtenant structures are required. These structures include circular to
square transition sections, wingwalls, headwalls and aprons.
19
2.8 Loads on Culverts
The load on the top of a box or pipe culvert according to Reynolds and
Steedman, (1999) includes the weights of the earth and the top slab and
the imposed load. Where a trench has been excavated in firm ground for
the construction of a culvert and the depth from the surface of the ground
to the roof of the culvert exceeds, say, three times the width of the
culvert, it may be assumed that the maximum earth pressure on the
culvert is that due to a depth of earth equal to three times the width of the
culvert.
20
4. A triangularly distributed horizontal pressure on each wall due to
the increase in earth pressure in the height of the culvert.
5. A uniformly distributed horizontal pressure on each wall due to
pressure from the earth and any surcharge above the level of the
roof of the culvert.
6. The internal horizontal and possibly vertical pressures from water
in the culvert.
2.10.1 Nomographs
The use of nomographs requires a trial and error solution. The solution is
quite easy and provides reliable designs for many applications. It should
be remembered that velocity, hydrograph routing, roadway overtopping,
21
and outlet scour require additional and separate computations beyond
what can be obtained from the nomographs.
23
measured on site or admeasurement where the actual quantities are
calculated from records. There are five sections in the Bill of Quantities
(Okeola, 2012). These are:
Preamble
List of Principal Quantities
Daywork Schedule
Work Items (divided into parts)
Grand Summary
2.13.2 Preamble
The Preamble is an extremely important section of the Bill of Quantities
and is the potentially vital source of information to the estimator. If any
other Methods of Measurement have been used in the preparation of the
Bill of Quantities, the fact should be recorded there.
2.13.3 Preliminaries
The preliminaries section of the bill of quantities is the engineer or QS’s
introduction to the contract. The section provides information on the
location, size, and complexity of the project and gives details of the
conditions of contract under which the project is to be implemented. For
preliminaries an amount of N500,000 was allocated for site clearance,
provision of an alternate linkage, diversion of water and site preparation
for the culvert.
24
2.14 Project Cost Estimation
2.14.1 Preliminary estimates
There are many approaches to preliminary estimates of proposed projects.
They all use some measures of gross unit costs from recently completed
construction works which are updated by the use of factors which
recognizes cost differences as a result of time frame, location or any
peculiarities of the work that is being estimated. However in general the
estimating structure comprises:
1. Dividing the project into small elements so as to allow a single rate
or unit cost to be applied to each element
2. Extending the quantities and rates to determine a cost for each
element
3. Summing the resulting elemental costs and
4. Applying indirect costs to give a complete estimate.
30
2.14.2 Cost per function
The estimate is based on historic data per unit of use. For example the
cost per vehicle in a park or per 100 books in a library.
Market survey was carried out in Ibadan, the project location to determine
the price of reinforcement and concrete materials. The price obtained
indicated that a tonne of 10mm, 16mm and 20mm high yield steel was
N165,000 and consist of 134pieces, 52pieces and 33pieces respectively of
11.5m length. Each bar of Y10 was N1250, Y16 was N3200 and Y20 was
N5000. Casting rate per cubic metre of 1:2:4 mix ratio was N30,000 and
1:3:6 mix ratio was N27,000 per cubic metre (YK consultants, 2012).
26
CHAPTER THREE
METHODOLOGY
Different methods for flood estimation have been developed. They may
be divided into three categories:
Analysis of flow data
Regionalized flood formulae
Runoff modeling
square kilometers.
The rational method assumes that:
27
1. The design storm produces a uniform rainfall intensity over the
entire catchment
2. The relationship between rainfall intensity and rate of runoff is
constant for a particular catchment
3. The flood peak at the catchment exit occurs at the time when the
whole catchment contributes
4. The coefficient C is constant and independent of rainfall intensity.
C = CT + CS + CV
(3.2)
where:
CT = coefficient of topography
CS = coefficient of soil permeability
CV = vegetation type
28
Table 3.1 Runoff coefficient for rational method
Runoff coefficient C = CT + CS + CV
Rainfall intensity (I) modeled by Salami and Sule (2009) indicate that
very intense storms are of short duration and are rare and of low
probability. Storms of long duration tend to be less intense and extremely
long storms, supplying large amounts of rains are also rare. This is the
reason why we need to quantify the relationships between intensity,
duration and frequency. Three parameters of interest in connection with
rainfall are intensity, duration and frequency. A formula expressing the
relationship between rainfall intensity, duration and frequency takes the
form given in equation 3.3 (Salami and Sule, 2009).
b
i aT (3.3)
tc
where:
i = the intensity (mm/hr)
T = frequency or recurrence interval (years)
t = duration (hr),
a, b, c = locality constants.
29
Table 3.2 Rainfall intensity model developed for towns in Nigeria
Town Intensity Town Intensity
T 0.70 T 0.44
Maiduguri i 11.17 Osogbo i 19.97
t 0.34 t 0.42
Sokoto i 11.95 T 0.60 Ibadan i 28.61 T 0.19
t
t0.45 0.62
T 0.51 T 0.46
Makurdi i 16.43 Ilorin i 22.00
t 0.62 t 0.40
Yola i 8.37 T 1.05 Ikeja i 18.50 T 0.66
t
t 0.10 0.19
1000 S
where:
T
c time of concentration in hours
L
length of main stream (km)
mm
S average slope of main stream ( )
3.2.1 Loading
As for the bridges, dead and imposed loads are considered. The imposed
load considered are 30-units of HB loading. Water, hydrostatic and earth
pressures are also considered. The dead loads include the self weight of
the structures and the surcharge loads from the fill materials.
31
HYDROLOGIC ANALYSIS
32
REFERENCES CALCULATION OUTPUT
Rainfall intensity
Using rational method of flood estimation,
CIA
Q
Equation 3.1
p 3.6
Bent (1996)
Qp 0.278C I A
where C = coefficient of runof
I = intensity of rainfall
A = catchment area
S 1280 960
3500
= 0.0914
= 9.14%
0.8735002 0.385
Equation 3.2 T
TC 2hrs
Bent (1996)
C 10000.0914
TC 89.27 1hr 30min
Table 3.1
Runof coefficient
C CT CS CV
CT 0.08
where CS 0.08 C 0.37
CV 0.21
C 0.37
33
REFERENCES CALCULATION OUTPUT
Equation 3.1 From rational method, Qp 0.278C I A
for Ibadan is of the form
Table 3.2 T 0.19
QP1 0.2780.3760.163.25
QP1 20.11m3 s
20.11m3 s
QP2 0.2780.3739.153.25
13.09m3 s QP2 13.09m3 s
QP3 0.2780.3730.443.25
10.18m3 s
QP3 10.18 m3 s
QP 4 0.2780.3725.473.25
QP 4 8.52 m3 s
8.52 m3 s
QP5 0.2780.3722.183.25
QP 5 7.42 m3 s
7.42m3 s
34
REFERENCES CALCULATION OUTPUT
Utilizing the discharge Qp for 2hr period as the
Salami worst flood
(2012)
Q p 13.09 m3 s
Note : 1 ft 0.3048 m
Channel width 4m
Channel height 2m
Q 462.26
Ratio of discharge to width :W 13.12
Hw
W 35.23
From the inlet control nomograph (Fig. A-12)
Hw
D 0.88
Chart 8 Hw = 1.75m
Therefore, Hw = 0.88 x 6.56f = 5.77 f
35
STRUCTURAL DESIGN
36
DESIGN INFORMATION
Engineer:
Client:Lagelu Local Government, Oyo state. Afolabi, A. O.
1. BS8110 The structural use of concrete, part 1&3
2. BS 5440 Steel, Concrete and Composite Bridges.
3. Reinforced concrete designer’s handbook by Relevant building and
Reynolds and Steedman. design codes
4. Steel designers manual.
30units of HB loading at 2.5KN/wheel = General loading
2
75KN Slab imposed load = 4.8KN/ m conditions
Exposure condition
Severe (external and internal)
Characteristic strength
2
– Main bars fy=460N/mm
2
– Distribution bars = fy=460N/mm Material data
Characteristic strength of Concrete fcu = 25
2
N/mm Concrete cover = 40mm
2
Self weight of concrete = 24KN/mm Other relevant
All dimensions shown in the drawings are in (mm) informations
37
REFERENCES CALCULATION OUTPUT
A B C
200
2000 mm
200
1900 mm 1900 mm
200mm 200mm 200mm
Dead load :
slab own weight = 0.2 24 4.8 KN m GK 4.8 KN m
Assumption
w = 246.72KN/m
RA 2100 mm RB 2100 mm RC
38
REFERENCES CALCULATION OUTPUT
FEM
Oyenuga wl 2
(2008) M AB 12
2
M 246.722.1
AB 12
M AB 90.67KNm
wl 2
M 90.67KNm
BA 12
wl 2
M BC 12 90.67KNm
wl 2
M 90.67KNm
CB 12
2.1
2.1R 246.722.1
A 2
Shf R AL )
(M M
B
AB
90.67 0
ShA 259.06 302.24KN
2.1 ShB 215.88KN
0 90.67
Sh 259.06
B 215.88KN
2.1 ShC
ShC 302.24KN 302.24KN
BS 8002 1 sin
Clause 2.2.4 Active pressure (k)
1 sin
30, and k 0.33
Pr essure against wall A
P2.4 18 0.33 2.4 14.26 KN m
Wall weight 0.20 24 4.8 KN m
2.1PA 246.72 2.11.05
90.67 PA 302.23KN
1.4(4.8 14.26)
Total load on wall A 302.23 2
5
A 304.90KN
39
REFERENCES CALCULATION OUTPUT
2
wl
Oyenuga moment
12
(2008) w weight from top slab wall weight
w 246.72 26.68 273.40KN / m
273.4 22
M
12
M 91.14KNm M 91.14KNm
Middle wall B
M 246.72 2.11.05
b
2.1
M b 259.06 KN m2
1.4(4.8 0)
Load on wall 259.06
25
MOMENT
M wl 2
12
w weight of top slab(wall weight pressure)
w 259.73 1.4(4.8
0) w 266.45 KNm
M 266.45 22
12
M 88.82 KNm
Bottom Slab
40
REFERENCES CALCULATION OUTPUT
2
FEM wl
Oyenuga 12
(2008) 273.6 2.12 100.55KNm
12
reaction at ABC
2.1
2.10A 273.6 2.1 2
A 287.28KN
Shearforce at A
M M
SFA R AB L BA
AB SFA 329.58KN
88.82 0
287.38 329.58KN
2.1
M M
SFB R BCL CB
BC
0 88.82
287.38 244.99KN
2.1 SFB 244.99KN
CASE TWO
Assuming the culvert is full and flowing at
maximum of 2m, worst loading condition becomes:
Top Slab
water load 2101.6 32 KN m
lessthan slab weight 5.38 KN m
Total load 26.62 KN m
2
FEM wl
Oyenuga 12
(2008) 26.62 2.12
FEM 9.78 KN
m 12
reaction
2.1
2.1R 26.622.1
A 2
RA 27.95KN
RA RC
RC 27.95KN
Rc 27.95KN
41
REFERENCES CALCULATION OUTPUT
M M
SFA R AB L BA
AB
9.78 0 SFA 32.61KN
27.95 32.61KN
2.1
0 9.78 SFB 23.29KN
SFB 27.95 23.29KN 2.1
WALL
Consider wall due to water pressure only
At top of top slab = 2101.6 32
At bottom of bottom slab= 2.4 10 1.6 38.4 KN m
wl 2
Moment on wall =
12
Oyenuga 38.4 2.42
(2008) M
18.43KNm 12
4.4m
wl 2
FEM
AB 12
2
44.51 2.1 16.36KNm
12
wl 2
FEM
BA 12 M BA 16.36KNm
44.51 2.12 16.36KNm
12
wl 2
FEM BC 12
42
REFERENCES CALCULATION OUTPUT
wl 2
FEM
CB 12
44.51 2.12 16.36KNm
12
Midspan moment AB BC M CB 8.18 KNm
16.36 (16.36 0)
2
8.18 KNm
VA VB VC
VA 46.74KN
2 .1
VA 47.51 2 46.74KN
M M
SFA V AB L BA
AB
16.36 0 SFA 54.53KN
46.74 54.53KN
2.1
00
SFB 46.74 46.74KN
SFB 46.74KN
2.1
16.36 0
SFC 46.74 54.53KN SFC 54.53KN
2.1
Wall A = Wall C
Maximum shear force = 304.90 KN
Maximum moment = 91.14 KNm
Wall B
Maximum shear force = 259.73 KN
Maximum moment = 88.82 KNm
Bottom Slab
Support moment = 100.55 KNm
Max shear force = 329.58 KN
43
REFERENCES CALCULATION OUTPUT
k
leverarm factor (la ) 0.5 0.25 0 .9
l
a 0.5 0.25 0.1612
0.9
la 0.7663
M
Area of steel required ( ASR )
0.95 f y la d
A 90.67 106
SR
0.95 460 0.7663152
A 1761.54mm2
SR
44
REFERENCES CALCULATION OUTPUT
Deflection check
BS 8110 477 fs 2
M f 0.55 M
(1997) 120 0.9
2
Table 3.1.1 bd
A
fs 2 SR
fy
3 ASP
fs 2 1761.54 460
3 1800
fs 300.11
477 300.11
M f 0.55 6
90.67 10
120 0.9
2
1000 152
M f 0.86
Limiting value M f sdf
0.86 26 22.24
span
Actual value
effective depth
2100
152 13.82
Since Limit value actualvalue,
Deflection is satisfied
Design Of Wall
Wall A = Wall C
Moment = 91.14 KNm
Shear force = 304.90 KN
BS 8110
M
Part 1
k fcu bh2
(1985)
clause 91.14 106
3.4.4.4 k 251000 2002 0.091
N 304.90 103
0.6098
fcu bh 251000 200
From graph,
d 152 0.76
H 200
Area of steel 0.0026 fcu bh
From the graph of d/H = 0.8
2.0
chart between 0.4 – 0.5 curve
45
REFERENCES CALCULATION OUTPUT
BS 8110 M
Part 1 k fcu bd 2
(1985) 100.55 106
k
Clause 25 1000 1522
3.4.4.4 k 0.1741
k
leverarm factor (la ) 0.5 0.25
0.9
la 0.5 0.25 0.1741
0.9
l
a 0.7378
M
Area of steel required (ASR )
0.95 f y la d
6
A 100.55 10
SR 0.95 460 0.7267 152
A 2051.72mm2
SR
46
REFERENCES CALCULATION OUTPUT
Deflection check
BS 8110 477 fs
(1997) M f 0.55 M 2
120 0.9
Table 3.1.1 bd 2
A
2 SR
fs fy
3 ASP
fs 2 2051.72 460 301.05
3 2090
477 301.05 M f 0.829
M f 0.55 100.55 10 3
120 0.9 2
1000 150
M f 0.829
Limiting value M f sdf
0.829 26 21.56
span
Actual value effective depth
2100
152 13.82
Since Limit value actual value,
Deflection is satisfied
SUMMARY
Top Slab
Main bar = Y20 @ 175mm c/c spacing,
distribution bar = Y10 @ 300mm c/c spacing
Wall
Y16 bars @ 150mm spacing
distribution bar = Y10 @ 300mm c/c spacing
Bottom Slab
Main bar = Y20 @ 150mm c/c spacing,
distribution bar = Y10 @ 300mm c/c spacing
47
CHAPTER FOUR
RESULT AND DISCUSSION
4.1 Computation of Concrete Volume and Cost
Top slab
Volume = b h l
= 4.4 0.2 5 4.4m 3
Walls (3nos)
Volume = b h l
= 0.2 2 5 2m3
Volume = 3 2 6m3
Bottom slab
Volume = b h l
Headwall (2nos)
Volume = b h l
= 4.4 0.15 0.15 2 0.198m3
Number of bars = length 1
spacing of bars
Bar length = actual length – 2(cover) + 2(return length)
total
length
Cost of bar = 1 amount per piece of Ymm bar
11.5m
48
4.3 Bar Bending Schedule
Top slab
02 Y20 1 30 4300
4300
Top slab
02 Y20 1 30 4100
4100
50
50
Distribution
Y10 1 108 4950 4950
Bars
49
4.4 Bill of Engineering Measurements and Evaluation (BEME)
1 20mm dia. high yield steel for top 666.67 kg 165 110,000
slab
20mm dia. high yield steel for
2
757.58 kg 165 125,000
bottom slab
3 16mm dia. high yield steel for
788.46 kg 165 131,200
walls
4 10mm dia. high yield steel for
373.13 kg 165 62,500
distribution.
D SUB TOTAL 431,700
EXCAVATION AND FORMWORK
1 Excavate for culvert base not
10 m 2,200 22,200
2 exceeding 0.75m depth
Sawn formwork for culvert 56 m2 850 40,800
SUB TOTAL 63,000
Add 5% contigency 49,257
50
CHAPTER FIVE
CONCLUSION AND RECOMMENDATION
5.1 Conclusion
Based on the analysis and the design of the culvert, it can be deduced that
a culvert is a suitable and feasible solution to the accessibility problem of
Yawiri community. This is in terms of minimum cost of construction,
ease of maintenance and durability. Also, based on this designed culvert,
efficient conveyance of the storm-water runoff will be achieved which
will eliminate the occurrence of flooding especially during rainfall.
5.2 Recommendation
51
REFERENCES
Bent T. (1998) Highway and Traffic Engineering in developing countries.
E & FN Spon, London, UK.
52
Knox County Storm Water Management Manual, Tennessee, USA
Volume 2 Technical Guidance (http://www.knoxcounty.org: accessed on
12th March, 2012).
54
Slab Detailing
5000 mm
A A
4400 mm
30Y20 02 - 175B
16Y10 02 - 300B
Fig. A-1 Top slab reinforcement detail
5000 mm
A A
4400 mm
34Y20 01 - 150B
16Y10 01 - 300B
Fig. A-2 Bottom slab reinforcement detail
55
Reinforcement Detailing
Main bars Y-20 @ 175mm c/c spacing Distribution bars Y-10 @ 300mm c/c spacing
A B C
57
Fig. A-7 Reinforcement arrangement in the culvert
60