Port Scheduling
1 Problem Statement
Scheduling bulk mineral ports is a complex and important task for Australia. We have some of the
busiest bulk mineral ports in the world. Ships arrive at the port to pick up a set of stockpiles. The
aim is to delay the ships the least amount of time possible from when they arrive.
The stockpiles are stored on pads, which are very long. Here we consider the simple example of a
single long pad. The stockpiles are stacked onto the pads over time, as trains bring in the materials
for the stockpile. In this simple model we will just assume a stacking time for each stockpile and
otherwise not worry about stacking. The pad causes a packing problem, we have to reserve space
on the pad for a stockpile from the moment we start stacking to the moment it is fully reclaimed.
Two stockpiles cant co-exist in space time.
The critical issue is the reclaiming of the stockpile from the pad to load it onto the ship. We
will schedule the reclaimers.
pad
rail 1
rail 2
Reclaimers run on rails beside the pads. There can be multiple parallel rails, and multiple
reclaimers on each rail. Reclaimers on the same rail can not pass each other, they have to stay in
the same order. Reclaimers on separate rails are free to move past each other.
When a ship arrives in berth we can start reclaiming its stockpiles. The reclaimer has to be
at the westernmost end of the stockpile to reclaims the material, once finished it can move to the
next task. The time to reclaim is given by the size of the stockpile. The reclaimer takes time to
get to the stockpile to begin the reclaim.
The assignment is broken into stages though each of them uses the same input data format.
1
int: nr; % number of reclaimers
% number of rails = nr for stages A,B,C,D,E
% number of rails = (nr + 1) div 2 for stage F
set of int: RECLAIMER = 1..nr;
bool: stageF;
For the purposes of this stage we only are interested in the stockpile data. You can assume the
stageF parameter is false (until stage F).
The critical decisions that need to be made are: for each stockpile the position of its western
most end on the pad, when it is started to stack, and when it is started to reclaim. In later stages a
critical decision will be which reclaimer is used for each stockpile, but for this stage this can always
be set to 1.
A stockpile occupies a position on the pad from its westend to its eastend = westend + size. It
occupies a time on the pad from its stacking start time to the end of its reclaiming time. No two
stockpiles can overlap in both time and position (but note that a stockpile could be in position 0..4
and another in position 4..8 at the same time and this is not an overlap, or on the pad from time
0..10, and then another stockpile in the same position from time 10..14 and this is not an overlap).
We assume that stacking a stockpile requires stack time times its size in time units, and
stacking must be finished before reclaiming begins. The dwell time of the stockpile is the period in
between when stacking ends and reclaiming begins.
Reclaiming a stockpile requires reclaim time times its size.
Output of the plan should be of the form
2
westend = array of positions of westend ;
eastend = array of positions of eastend ;
stack = array of stacking start times ;
endstack = array of stacking end times ;
reclaim = array of reclaiming start times ;
finish = array of reclaiming end times ;
which = array of which reclaimers used ;
3
1.6 Stage F: Rail Constraints
In reality usually there are two reclaimers per rail line, and they cannot cross.
Add constraints in your model so that the two reclaimers on rail i numbered 2i − 1 and 2i for
i ∈ 1..nr div 2 remain so the western one 2i − 1 is never east of the eastern one 2i. Note they can
legitimately be in the same position (this is for simplicity, its not very real). Note that if there are
an odd number of reclaimers the last reclaimer is on its own rail and has no further constraints.
1.7 Visualization
In order to help you visualize the results of the schedule we provide a program: portschedule draw.cpp
which will take the output of the model and plot it. For example for the input data
nr = 2;
stageF = true;
ns = 7;
nsh = 4;
size = [4, 8, 2, 5, 4, 3, 3];
ship = [1,2,3,1,4,2,3];
maxtime = 200;
arrival = [ 0, 0, 20, 40 ];
len = 12;
stack_time = 4;
reclaim_time = 3;
reclaim_speed = 1;
gives a solution
westend = [0, 0, 4, 0, 8, 6, 8];
eastend = [4, 8, 6, 5, 12, 9, 11];
stack = [0, 29, 0, 85, 21, 0, 52];
endstack = [16, 61, 8, 105, 37, 12, 64];
reclaim = [16, 61, 23, 105, 40, 12, 128];
finish = [28, 85, 29, 120, 52, 21, 137];
which = [1, 1, 2, 1, 2, 2, 1];
The plot for this solution is shown in Figure 1 which shows for each the stockpile the stacking
time, the dwell time the reclaiming time, and the path of each reclaimer in its reclaiming tasks.
Note how the reclaimer 2 stays east (above) reclaimer 1, and we can see delays caused by moving
the reclaimers. Be aware that sometimes the visualization can show a crossing which does not need
to be there since it simply connects the reclaim jobs in order. The grader will detect when the
crossing must occur and flag an error (for stage F).
2 Instructions
Edit portschedule.mzn to solve the optimization problem described above. Your portschedule.mzn
implementation can be tested on the data files provided. In the MiniZincIDE use the play icon to
test your model locally. At the command line use,
mzn-gecode ./portschedule.mzn ./data/<inputFileName>
4
12
5
10
6
Pad position
2
4
1 4
2
0
0 20 40 60 80 100 120 140
Time
R_1 R_2
Figure 1: Pad diagram showing stacking, dwell, and reclaiming for each stockpile, as well as the
path of the reclaimers.
to test locally. In both cases, your model is compiled with MiniZinc and then solved with the
GECODE solver.
Resources You will find several problem instances in the data directory provided with the hand-
out.
Handin From the MiniZinc IDE, the coursera icon can be used to submit assignment for grading.
From the command line, submit.py is used for submission. In both cases, follow the instructions to
apply your MiniZinc model(s) on the various assignment parts. You can submit multiple times and
your grade will be the best of all submissions.1 It may take several minutes before your assignment
is graded; please be patient. You can track the status of your submission on the programming
assignments section of the course website.
1
Problem submissions can be graded an unlimited number of times. However, there is a limit on grading of model
submissions.
5
3 Technical Requirements
For completing the assignment you will need MiniZinc 2.0.x and the GECODE 4.4.x solver. Both of
these are included in the bundled version of the MiniZinc IDE 0.9.9 (http://www.minizinc.org).
To submit the assignment from the command line, you will need to have Python 2.7.x installed.