Académique Documents
Professionnel Documents
Culture Documents
(“JIGCC”) Project
Jazan Integrated DOCUMENT CHEC-JIGCC6IK-82-HV-
Gasification NUMBER MST-0001
Method Statement of HVAC
Combined Cycle
(JIGCC) Project REVISION A00
ISSUED BY CHEC ISSUED DATE 28 TH
Sep, 2016 PAGE 2 / 21
Table of Contents:
Contents Page No.
01. PURPOSE 04
02. SCOPE 04
03. REFERENCES 04
03.1 SAUDI ARAMCO ENGINEERING STANDARDS 04
03.2 JOB SPECIFICATION 05
03.3 INDUSTRY CODES 05
04. RESPONSIBILITIES 05
05. HANDLING, STORAGE AND PRESERVATION 06
06. WORK PROCEDURE 07
6.1 INSPECTION OF MATERIALS PRIOR TO
INSTALLATION FOR EQUIPMENT: 07
6.1.1 FOR DUCTING AND PIPING: 07
6.2 HVAC DUCTWORK 08
6.2.1 DUCT INSTALLATION 08
6.2.2 DUCT LEAKAGE TEST 09
6.2.3 DUCT INSULATION 10
6.2.4 AIR GRILLES, REGISTER & DIFFUSER
INSTALLATION 11
6.3 REFRIGERANT PIPING INSTALLATION 11
6.3.1 FABRICATION AND INSTALLATION 12
6.3.2 JOINTS & FITTINGS ASSEMBLY 12
6.3.3 BRAZING PROCEDURE OF JOINTS & FITTINGS 12
6.3.4 COOLING AND CLEANING 13
6.3.5 LEAK TESTING OF REFRIGERANT PIPINGS 13
6.3.6 SYSTEM VACUUM / EVACUATION OF SYSTEM 14
6.3.7 INSULATION OF REFRIGERANT PIPING 14
Jazan Integrated Gasification Combined Cycle
(“JIGCC”) Project
Jazan Integrated DOCUMENT CHEC-JIGCC6IK-82-HV-
Gasification NUMBER MST-0001
Method Statement of HVAC
Combined Cycle
(JIGCC) Project REVISION A00
ISSUED BY CHEC ISSUED DATE 28 TH
Sep, 2016 PAGE 3 / 21
1. PURPOSE
To ensure the Material delivery, storage handling, installation, testing and air
balancing is carried out safely and in accordance with good working practices, as
per Saudi Aramco Job Specifications and HVAC vendor manufacturer’s
recommendation. This procedure is intended to provide general application
guidance and establish controls during preparation and installation of all HVAC
and other related parts at various locations at the area of Jazan Integrated
Gasification Combined Cycle (JIGCC) Project -EPC No. 06 in Kingdom of
Saudi Arabia.
2. SCOPE
2.1 This covers procedures for inspection during installation of all HVAC System
Components such as Air Handling Unit, Air Cooled Condensing Unit,
Exhaust Fans, Variable Air Volumes, Electric Duct Heaters, Mini-Split Units,
DDCs, Metal Ducts, Duct Accessories such as Volume Dampers, Fire
Dampers, Back draft Dampers, Air Terminal Devices, Hangers and Supports
and Duct Insulations, Refrigerant Copper Piping’s and all its accessories.
2.2 This procedure shall be used in conjunctions with applicable manufacturer’s
installation and Maintenance instruction manuals.
3. REFERENCES
4. RESPONSIBILITIES
4.1 The HVAC Engineer shall be responsible for carrying out the work
procedure and ensures that installation is carried out in accordance with
project specifications and manufacturer’s instruction. He shall see to it that
all equipment’s be handled carefully during transport, handling, storage and
protected from any damage before and after installation.
4.2 The Quality Control Engineer shall be responsible for conducting work
surveillance and inspection duties to make sure that an efficient recording of
Jazan Integrated Gasification Combined Cycle
(“JIGCC”) Project
Jazan Integrated DOCUMENT CHEC-JIGCC6IK-82-HV-
Gasification NUMBER MST-0001
Method Statement of HVAC
Combined Cycle
(JIGCC) Project REVISION A00
ISSUED BY CHEC ISSUED DATE 28 TH
Sep, 2016 PAGE 6 / 21
(2) Be sure that the proper method of rigging is used, with straps or slings
or spreader bars for protection during lifting.
(3) Refer to rigging instructions on unit manual if provided.
5.6 POSITIONING OF HVAC EQUIPMENT
All equipment shall be checked in accordance with equipment schedule and
drawings.
(1) Locate the equipment into concrete foundation pad.
(2) Make sure anti-vibration pads in place. Check installation and alignment
of equipment’s.
(3) Provide clearance around and above the unit to provide minimum
distance from combustible materials, proper airflow, and service
access.
(4) The contractor shall ensure that all HVAC equipment and duct
accessories shall be handled, stored and preserved in accordance with
manufacturer’s recommendation.
6. WORK PROCEDURE
6.1 INSPECTION OF MATERIALS PRIOR TO INSTALLATION FOR
EQUIPMENT:
(1) Inspect unit for transportation damage. If damage to the unit is found, report
the nature of this damage immediately to the vendor / supplier.
(2) Check the unit name plate to determine if the unit is correct for the intended
application.
(3) Check to be sure that the refrigerant charge has been retained during
shipment. Assemble and fix the forms to the correct position.
(4) Check the dimension to conform to the required size of pipe openings and
embedment’s, subject to the tolerances prescribed in the project
specification.
(1) All ducting and piping materials shall be checked in accordance with the
drawings, specification, code and standards.
(2) Duct and piping work shall be checked for any obstruction or dirt.
(3) Dampers, fans, and duct accessories shall be checked for damage
and proper operation.
(4) All materials shall be inspected to ensure that it is an approved item.
(5) Prior to field fabrication and assembling materials (ducts & accessories,
refrigerant pipes, fittings, elbows, and etc.) shall be checked against the
relevant shop drawings for construction and material approval documents.
(6) Shop inspection shall be performed before field installation in
accordance with inspection and test plan (ITP) regarding the following
items: Dimension, reinforcement, sealing, insulation and cleaning.
(7) Field inspection shall be performed in accordance with inspection and
test plan (ITP) regarding the following items: Duct location, support,
dampers & access door, flexible duct hose, diffuser, grilles and register.
Test Procedure:
(1) Ensure that all ductworks to be tested are properly installed, cleaned and
free from obstruction.
(2) Open all volume dampers and cover all openings by poly-ethylene plastic.
(3) Identify and mark the unsealed holes and seal it with approved sealant.
(4) Repeat the procedure once the repair is done.
(7) Attach corner clip and tie up aluminum foil faced fiberglass roll mat or
board firmly by aluminum band.
(8) Insulate around flange joints complete with foil vapor barrier.
(9) Apply foil tape between duct insulation vapor barrier.
(10)Close openings of duct with vinyl preventing from dust ingression.
(11)Unless otherwise specified, all finished air duct shall be externally
insulated or as per design specification.
Hard drawn copper tube shall not be bent by any means. Care is to be taken
during brazing the excess heat is not used. All copper pipes may only be cut by
pipe cutting wheels. No flame cutting or hacksaw work will be permitted. No
water quenching will be permitted.
(3) Sweeping the flame around the tube in short strokes at right angles to the
axis of the tube.
(4) Keep the flame in motion and not remain on any one point long enough
to damage the tube.
(5) Heat uniformly, sweeping the flame alternately from fitting to the tube
until the flux becomes quiet.
(6) Apply the filler metal at a point where the tube enters the socket of the
fitting, when the proper temperature is reached, the filler metal will flow
readily into the space between the tube and fitting socket, drawn in by the
natural force of capillary action.
(7) For joining copper tube to solder refrigerant control valves such as;
expansion valve or solenoid valves, disassemble and remove the o-rings
and internal diaphragms before brazing.
refrigerant system). This testing method is intended for suction and liquid
line only.
(6) System leak testing, evacuation, dehydration, and charging with
refrigerant shall conform.
(7) Test piping with either a halide torch electronic detector or soap solution.
(8) After the system is found to be without leaks, release the pressure after
inspection.
6.4.1 MECHANICAL
(1) Check the HVAC equipment’s as per design.
(2) Check the location of HVAC equipment’s as per the drawings.
(3) Make sure anti-vibration pads in place also check installation and
alignment of HVAC equipment’s.
(4) Ensure that the HVAC equipment’s are clean both inside and outside.
(5) Check air filter type and installation.
(6) Check motor and fan pulleys are aligned properly.
(7) Verify that fan sheaves are aligned and belts are properly tensioned.
(8) Check ducting connection to fresh air is done correctly as well as for
supply and return.
(9) Check motorized volume dampers and fire dampers are mechanically
functional.
(10)Check refrigerant pipe connections and control accessories are installed.
(11)Verify that condensate connection is installed as per instruction.
(12)Ensure that all service valves such as; Suction, Discharge and Liquid line
service are fully opened prior to run.
(13)Energize compressor crankcase heater at least 24 hours prior to initial
start up.
6.4.2 ELECTRICAL
Jazan Integrated Gasification Combined Cycle
(“JIGCC”) Project
Jazan Integrated DOCUMENT CHEC-JIGCC6IK-82-HV-
Gasification NUMBER MST-0001
Method Statement of HVAC
Combined Cycle
(JIGCC) Project REVISION A00
ISSUED BY CHEC ISSUED DATE 28 TH
Sep, 2016 PAGE 16 / 21
(1) Electrical supply shall be isolated prior to initial running of the motor.
(2) Check all power and control wiring completed in detail as per circuit
diagram, including equipment grounding.
(3) All power cable shall be megger before initial start up of the motor.
(4) All connections shall be tightened on terminals.
(5) Check fuse ratings, circuit breakers, contactors are conformed to
manufacturer equipment name plate.
(6) Perform insulation and continuity test on motors.
(7) Starter overloads set correctly in relation to motor name plate full load
current.
(8) Check voltage imbalance on each phase as per manufacturer
recommendation.
(9) Before initial run of motors, control logic and starter operation shall be
tested.
(10)Actuate only the control phase and check the control operation, alarm
interlocks are properly working as per instrument normal operation
sequence.
7.2 PERSONNEL
NO. DESCRIPTION REMARK
Jazan Integrated Gasification Combined Cycle
(“JIGCC”) Project
Jazan Integrated DOCUMENT CHEC-JIGCC6IK-82-HV-
Gasification NUMBER MST-0001
Method Statement of HVAC
Combined Cycle
(JIGCC) Project REVISION A00
ISSUED BY CHEC ISSUED DATE 28 TH
Sep, 2016 PAGE 20 / 21
9. ATTACHMENT
9.1 HVAC Drawings – A61-K- VA-746701-001-00
9.2 HVAC Drawings – A61-K- VA-746719-001-00
9.3 HVAC Drawings – A61-K- VA-746720-001-00
B
A
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
B
A
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 2 3 4 5 6 7 8 9
C
B
A
1 2 3 4
C
B
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9