MODULE 2

EXERCISE:
WORK BREAKDOWN STRUCTURE (WBS)

Instructions: Read the case study and complete the work breakdown structure following the instructions in
the PM4R Guide. The following activities do not have an established order, but represent the work that the
Haiti project must complete. There are 38 activities in components 1, 2 and 3; among them are products and
work packages. Your objective is to complete the WBS on the next page, making sure that each task is in the
appropriate area. The WBS already includes some elements to help you complete the exercise. Remember to
put the result of the activities in the WBS, not the activity itself. For example, the result of activity 11 “Install 30
kitchen units” is: “30 kitchen units installed”; that is what you put in the WBS, the result, not the action.

Nº Task Description Nº Task Description Nº Task Description Nº Task Description

Set up furniture for


1 Build 30 schools 4 Build 30 schools 7 Equip 30 schools 10
30 classrooms
Install cafeteria
Hire construction Build 30 green Install 30 kitchen
2 5 8 furniture for 11
companies spaces units
30 schools
Purchase
Prepare 30 plots Build 30
3 6 9 equipment and 12 Install 30 libraries
of land playgrounds
furniture

1 Project Management for Development


Nº Task Description Nº Task Description Nº Task Description Nº Task Description

Deliver training Hire the development


Install 300
13 20 material for 300 27 of 300 school packa- 34 Complete project
computers
teachers ges for teachers
Hire maintenance Conduct training Design 300 school
Perform
14 service for 30 21 events for 300 28 packages for 35
evaluations
schools teachers teachers
Hire maintenance Produce and
Develop and deliver
service for green deliver 9,000 Hire consultant
15 22 29 300 school packages 36
spaces in 30 school packages for evaluations
for teachers
schools for students
Hire the
Hire equipment developing of Design Perform internal
16 maintenance for 23 9,000 school 30 communication 37 and external
30 schools packages for campaign audits
students
Hire communication
Hire structure Design 9,000
company to design Hire consultant
17 maintenance for 24 school packages 31 38
television and radio for audits
30 schools for students
campaign
Develop and
Disseminate
Train 300 deliver 9,000
18 25 32 communication
teachers school packages
campaign
for students
Hire company to
Produce and
disseminate 200
Hire training for deliver 300 school
19 26 33 TV spots and 5,000
300 teachers packages for
minutes in radio
teachers
spots

2 Project Management for Development


Goal
Improve the Provision and Quality of Educational Services at the Preschool and Primary Levels
Components

Component 1: Component 2:

Provide Quality Infrastructure Improve Education Quality


30 new schools operating that meet building Trained teachers impart new knowledge in the classroom
codes and design guidelines with new educational materials

1.1 1.2 1.3 2.1 2.2 2.3


9,000 school
Product

30 schools with packages 300 school packages


maintenance for students for teachers produced
contracts produced and and delivered
delivered

1.1.1 1.2.1 1.3.1 2.1.1 2.2.1 2.3.1

1.1.2 1.2.2 1.3.2 2.1.2 2.2.2 2.3.2


Maintenance Training
Work Packages

equipment for material for


30 schools 300 teachers
hired delivered

1.1.3 1.2.3 1.3.3 2.1.3 2.2.3 2.3.3


Furniture for 300 school packages
300 classrooms for teachers developed
set up and delivered

1.1.4 1.2.4

3 Project Management for Development


1.1.5 1.2.5
30
playgrounds
built

1.2.6
Goal

Improve the Provision and Quality of Educational Services at the Preschool and Primary Levels

Component 3: Component 4:
Components

Support and acceptance for the project Successful project management


A communication campaign is developed The project is managed and evaluations and audits are carried out
to be disseminated and achieve project
acceptance.

3.1 3.2 4.1 4.2 4.3


Product

Communication
Project
campaign
completed
disseminated

3.1.1 3.2.1 4.2.1 4.3.1


Work packages

Communication
company to design Consultant for
television and radio audits hired
campaign hired

4 Project Management for Development