CONSTRUCTION WORK TUTORIAL 

Introduction 
This tutorial is explaining about simplest way to build RC (Reinforced Concrete) building located in Doha, Qatar. This 
project is chosen as a sample for this tutorial because it is only small room and less material to use so that it becomes 
relatively  much  easier  to  understand  to  be  constructed  by  Civil  Engineer.  Some  requirements  are  prepared  to 
commence constructing this building which is given in the video list below: 

1st Tutorial : Short overview and Construction Stages (Structural Work) 
2nd Tutorial : Finish Stages (Architectural Work) 
3rd Tutorial : Step by Step Construction Schedule in Primavera P6 V16.2  
4th Tutorial : Step by Step Construction Design in STAAD.Pro V8i SS6 

Construction stage in the first tutorial was recorded in short video uploaded into Youtube, which is accessible through 
this address https://www.youtube.com/watch?v=eihemHVX3cU 

Any enquiries do not hesitate to email me at firdaus.yku@gmail.com 

1st Tutorial : Short overview and Construction Stages (Structural Work) 
1. Project schedule 

As the first step to understand this construction work, prior to begin this work, all major work items has to 
be put inside giant schedule including planned duration as a basic requirement to provide labour, material, 
equipment and cost. 

We are operating Oracle Primavera P6 V16.2 as project schedule software to breakdown all necessary works 
to be followed by field civil engineer. Besides explaining Primavara P6 in this tutorial, we also compare it with 
MS Project 2016 to whom is familiar working in MS Project only. 

Some main tasks in doing this project consist of Work Breakdown Structure (WBS) as a list below: 

1. Foundation 
2. Ground beam and slab 
3. RC (Reinforced Concrete) and Steel column 
4. Masonry / Concrete block 
5. Roof frame and sheet 
6. Finishes (Architectural and MEP Work) 

This simple building will be constructed following the schedule below: 

Firdaus.yku@gmail.com ‐ 1 
 
 
Firdaus.yku@gmail.com ‐ 2 
 
 

2. 3D View 
 
Expected final completion of this building can be seen in the figure below 

Top View 

Rear View 
 

Firdaus.yku@gmail.com ‐ 3 
 
 

3. Construction Stages 
Physically, main construction stages of RC/Steel structure are following sequence figures below: 

1. Soil Excavation for shallow foundation  2. Lean concrete and timber formwork for pad footing. 

3. Spacer is required to receive proper concrete cover  4. Reinforcement  bar  for  pad  footing  and  pedestal. 


at bottom side   Concrete  cover  shall  be  considered  following 
regulation. 

5. Strengthened formwork by adding some timbers to  6. Concrete pouring on the pad footing using Fc’35 MPa 
prevent any damages while using vibrator.  or C35/40 

Firdaus.yku@gmail.com ‐ 4 
 
7. Formwork  dismantling;  in  case  any  crack  or  8. Timber formwork is provided as a casing of concrete 
honeycomb  on  the  concrete  surface,  it  shall  be  pedestal  
either rectified by Sika/Fosroc grouting or concrete 
injection.  

9. Each footing has pedestal and it is ready now to be  10. After  backfilling  and  compaction,  each  footing  is 


backfilled by imported soil  connected  by  ground  beam.  Underneath  ground 
beam, we shall overlay compacted soil by polythene 
sheet and lean concrete. 

11. Reinforcement  bar  and  timber  formwork  are  12. Make  sure  that  all  formworks  have  been 
installed along ground beam line.  strengthened on both side (in the picture, formwork 
is strengthened one side only) 

Firdaus.yku@gmail.com ‐ 5 
 
13. One  day  after  concrete  pouring,  Formwork  can  be  14. Next step is to pour the concrete for column. Prior to 
dismantled; in case any crack or honeycomb on the  cast  it,  we  have  to  fabricate  timber  formwork 
concrete  surface,  it  shall  be  either  rectified  by  properly  and  fix  it  with  additional  support  for 
Sika/Fosroc grouting or concrete injection. Within 3  strengthening in order to reduce any damage while 
days,  this  fresh  concrete  must  be  cured  by  clean  using vibrator.  
water to maintain temperature and shrinkage effect 

15. One  day  after  concrete  pouring,  Formwork  can  be  16. While  fixing  steel  column  on  the  ground  beam  and 
dismantled; in case any crack or honeycomb on the  concrete column, we shall backfill and compact the 
concrete  surface,  it  shall  be  either  rectified  by  floor  area  as  per  requirement.  Base  plate  and  bolt 
Sika/Fosroc grouting or concrete injection. Within 3  fixing is not visible in this picture. It will be discussed 
days,  this  fresh  concrete  must  be  cured  by  clean  in the further topic. 
water to maintain temperature and shrinkage effect

 
17. Steel beam fixing and preparation for concrete floor  18. Final step is to install reinforcement bar (wiremesh) 
can be done in the same time. After compaction, we  for the concrete slab and concrete pouring as the last 
have  to  apply  polythene  sheet,  lean  concrete  and  stage of this structural work. Curing by water on the 
spacer to receive concrete cover for reinforcement  RC slab within 3 days is a must to be done to achieve 
bar (Wiremesh)  expected quality as per requirement.  