Vous êtes sur la page 1sur 1

Document Transmittal

PROJECT NO. LOT 2


SOUTH DHAHRAN WATER PROJECT-WWTP
From:
Consortium of: Aziz Company for Contracting and Industrial Investment
& Passavant Energy and Environment
To:
Mr. Jari Lukkarila,
Acting Project Manager,
ILF-Tecon & Partners Engineering PSC
Date: Feb. 26, 2018
Document Transmittal No: 0245
Dear Sir,
Attached to this Transmittal Note, we submit the Drawing/Document(s) listed below. Please acknowledge
the receipt by a return e-mail, reporting any shortages, if any.

DRW. / DOC. Submission Status


Item Rev Drawing / Document Title Remarks
No Date *
1 LOT2-SUB-010 00 26.02.2018 AMAR Pre-Qualification for Civil Works - IFA

*Status Index Attached Document(s) are delivered by


IFI For Information Hand
IFA For Approval X Mail
IAB As Built Airmail
AFC Approved for Construction Express Courier
Electronic File
E-mail X

Best Regards,

Mohamed Hany
Project Manager
In behalf of Aziz-Passavant Consortium