Académique Documents
Professionnel Documents
Culture Documents
Abstract
The Department of Transport and Main Roads is
replacing a large number of bearings along Brisbane’s
Riverside Expressway. The recently purchased bridge
jacking system is computer controlled and is capable
of accurately controlling up to twenty hydraulic jacks
during a lift. The previous system was manually
controlled and required a crew of people to monitor the
position of each hydraulic jack.
Introduction
To maintain and repair bridge bearings, bridge decks
Wayne Hansford must periodically be lifted from their supports. While
Project Manager (Structures), RoadTek Asset the Department of Transport and Main Roads (TMR)
Services have a small number of steel bridge structures, the vast
majority are manufactured from prestressed concrete to
a range of designs. Because concrete bridge structures
do not have the high degree of flexibility that steel
structures exhibit, it is important that when jacking a
concrete bridge deck, all jacks should lift uniformly
within close tolerances to avoid distortion and over-
stressing. When performing a lift, the number and size
of hydraulic jacks can vary and the load that each jack
is required to lift can also vary. This load variation
is due to a range of factors such as the physical deck
dimensions, the relative positioning of the jacks and if
unwanted restraints occur during lifting (for example,
snagging bolts, restraint angles, barrier rails and
debris).
45
In the past, operation of the hydraulic jacking systems
has been fairly rudimentary. The jacks have shared a
common source of high pressure hydraulic fluid (up
to 700bar) via a common distribution rail or manifold.
Because the pressure and flow requirements for each
jack are not uniform, the oil flow to each jack had to
be controlled manually, usually with a needle valve
in each jack’s supply line. Figure 1 shows a single
supply rail with a series of needle valves attached to
hoses connected to the jacks.
Figure 2. Monitoring the movement of the deck
and jack support
Improved method of control
The Technical Education and Innovation section
provided advice to Structures Division on a better
method of controlling the flow to each hydraulic
jack. In the manual mode, the needle valve seat at
a micro level is regulating/restricting the oil flow in
the fine gap between two parallel surfaces. From
past experiences and from an overall engineering
perspective, this method of flow control is not effective
at the very small flow levels which must be controlled
in this situation. The flows can become unstable.
Minor movements at the valve stem caused by hand
pressure can cause the flow to alter.
46
In addition to the orifice diameter, hydraulic
companies have information on oil flow through
a single orifice, but no information on the flows
through multiple orifices in series. A small research
project1 was initiated to gain an understanding of
what happens when orifice plates are used in series.
The hole in every alternate orifice plate was on centre
line, and orifice plates in-between had a hole offset
to the centreline. This arrangement was to reduce
the possibility of any dynamic effects of the oil. No
tests were undertaken to verify if this precaution was
justified.
1 The research project was performed in partnership with Mathers Hydraulics Pty Ltd
47
Up until this time, the bridge jacking work performed Computerised jacking system
by Structures Division was generally comprised of Based on the findings of the orifice research, tender
one-off bridge jackings on an ‘as required’ basis. documents were compiled by Technical Education
A very large program of sequential work had not and Innovation Branch on behalf of Structures and
occurred up until this time. Routine maintenance Metropolitan Divisions. Enerpac Australia (Actuant
checks on the Riverside Expressway (REX) revealed Australia Ltd) was successful in supplying the new
that of approximately 250 neoprene bearings and 750 computerised jacking system.
pot bearings, a large number required refurbishment or
replacement, and a program of maintenance work was The system is comprised of two separate hydraulic
proposed by Metropolitan Region. This large program powerpacks (with computers), each of which can
of works created the need to review how this lifting control up to ten jacks. The two systems can be used
operation was performed. independently, allowing the equipment to be used
on separate projects, or the two powerpacks can be
A brief revisit to the history of the REX may help put combined under the control of a single computer. The
the project into perspective. The contracts were let combined system can thus control and synchronise up
for the construction of the Riverside Expressway in to twenty jacks in a single lift.
1969 with work progressing from the Captain Cook
Bridge end toward the William Jolly Bridge. In 1974 The principal of operation of the computerised system
a section of the Riverside Expressway from Alice is to electronically monitor the relative movement of
Street to Ann Street was opened while the complete all girders being lifted, in relation to the supporting
2.7 km of expressway was opened to traffic at a headstock (fixed reference point). The system does
ceremony performed by His Excellency Air Marshal not monitor the displacement of the pistons inside the
Sir Colin Hannah, K.C.M.G., K.B.E., C.B., Governor jacks. By removing the measuring system away from
of Queensland, on the 22nd July, 1976 (1). Hence the the jacks and their supports, the support structure for
REX has provided thirty-four years of service under a jack may deflect under load while still maintaining
very high traffic flows. These neoprene bearings the accuracy of the lift. When setting up the initial lift
were some of the earliest bearings of their type on the parameters on the computer system, a tolerance band
network. must be nominated within which the displacements
of the bridge girders must fall. The control system
Because of the large number of lifts required for the switches off those jacks that would advance
REX and the importance of these lifts in terms of each beyond the nominated limits. The individual girder
being reliably carried out on a nominated night, an movements are measured to 0.1mm accuracy using
improved method of control during jacking operations string potentiometers as shown in Figure 4. These
was required. A decision was made to call tenders potentiometers not only allow the system to control
for a new computerised jacking system to replace the the movement of individual girders, but also control
current manual system. the tolerance between girders to 0.1mm. Close control
over the movement of each girder limits stressing of
the diaphragms.
48
The control of the jacks occurs in a digital manner
- control valves are either switched off or on. The
previous manually controlled system is equivalent to
an analogue system while this new system is a digital
system.
49
This new system is unlike other synchronised jacking
systems. The system was designed to incorporate up
to ten, 0.5mm orifice plates in each lift line. Initially
the system has been setup with five orifice plates and
five spacer plates. Although the powerpack has a
filtration system, the 0.5mm orifices are protected from
blockage by fine wire mesh screens. Foreign particles
can enter the system via the quick connect couplings if
these are not cleaned correctly. During lowering, the
orifice plates provide a resistance or back pressure that
assist the electronics to control the speed of descent.
Figures 6 & 7 are views of the hydraulic power pack
inside the vandal proof enclosure. The computer
system has a HMI (human machine interface) touch Figure 7. Main distribution rail and poppet valves
screen (Figure 8) for inputting system variables and for
monitoring the progress during a lift. The system has a
wireless card with its own IP address to enable remote
viewing of jacking operations via the internet, software
upgrades and real time diagnostics. An electronic
history of the jacking operation can be stored on a
USB memory stick.
50
Figure 9. Steel false work supporting system
The project commenced at the QUT end of the REX To correct this problem, the top surface of the
near the Captain Cook Bridge abutment. A system of replacement bearing (Figure 11) was capped with an
short steel beams above and below the headstock were epoxy paste (Sikadur® - 31 normal pot life). The
fastened together with high tensile steel bars to provide bearing was placed inside a split metal ring with an
a platform to support steel jacking beams either side over centre fastener clamped to the bearing
of the headstock. The steelwork was designed by (Figure 12). The metal ring allowed a uniform layer
consulting engineers, Parsons Brinckerhoff. of epoxy paste to be towelled onto the top side of the
bearing (Figure 13). To speed up curing during the
Initially it was thought that a large number of bearings winter months, the two epoxy components were
had failed prematurely because of bulging of the pre-warmed to approximately 29o C.
rubber between the separator plates (Figure 10). After
the first lift it was found that a contributing factor
toward the irregular bulging of the bearings was that
the upper and lower bearing mating surfaces were not
parallel.
Figure 10. Bulging of rubber between separator Figure 11. Replacement bearings
plates
51
Figure 14. Jacking operation prior to a lift
Additional features
An electronic pressure transducer is located in each
hydraulic jack pressure supply line. During the initial
setup, each jack’s lifting area is entered into the
system allowing the rated maximum lifting capacity
to be calculated. When the areas are multiplied by
the lifting pressure, the force exerted by each jack is
calculated and displayed. This feature allows a cross-
check to be made between each jack’s calculated load
and the actual working load exhibited during a lift. If
Figure 13. New bearings being capped with epoxy there are any significant differences between these load
paste figures, the jacking operation may be stopped either
manually or automatically (if this feature has been
selected during the initial system set-up).
52
Figure 15. Continuous span bridge being lifted
The final target displacement for each jack is also part The increased speed of raising and lowering allows
of the initial system set-up. In the majority of cases, valuable time to remove the old bearings and
the target lift height is common for all jacks. However, undertake any necessary technical repairs.
it is possible for every jack to have a different target
lift height. When the target lift height of a jack or In the past, undertaking a synchronous lift with twenty
group of jacks differ, the lifting (and lowering rate) individual jacks would have been an operation that
is proportioned so that all jacks reach their target lift would be approached with considerable trepidation
height at the same time. For example, in Figure 15 a because of its complexity. To date, the new jacking
continuous span bridge is being lifted. For an equal system has been used successfully eleven times on the
span bridge, the displacement of the left hand end set REX and three times on other QTMR bridge projects.
of jacks could be 50mm while the centre span could
be 25mm. This 2:1 ratio of displacements will be kept For readers interested in a practical demonstration of
constant throughout the jacking process. This will the system, the REX project has made a thirty minute
ensure that the bridge is kept straight thereby keeping video entitled, “Making Light of Heavy Work – REX
stress levels to a minimum. Bridge Jacking System, at 1 November 2010”. This
video CD is available on loan from the QTMR library.
Conclusion
The new jacking system has generated more control References
for the jacking operations of bridge decks. Operators
spend considerably less time worrying about lifting 1. Queensland Roads Vol 15, No 30. December 1976
the deck, allowing the focus to be on the bearing
replacement, particularly where it must be performed
between fixed time lines.
53