Vous êtes sur la page 1sur 3

 T-Joint- Additional Zero degree probe regardless of thickness.

 L-Joint- Additional Zero degree probe when any member thickness 15mm and
above 15mm.
 T/L Joint-In accessible to carry out Normal probe scan for the detection of
lamellar tearing.
 As per BS standard Must Need to Scan Both side of Weld, (If access from one
side then it will change Non Hok), Half skip or Full Skip/Upper of Lower/ depend
on thickness, Weld with sealing run consider as both side weld
 Distance between two parallel weld less than 50mm, Detection of transverse
defect only,
 Corner Joint-MT Technique sheet 01
 Base On in UT worksheet when UT on fillet weld or out of 1714
 Single bevel Butt Weld (Full Pen)& 8mm PPBW,
 PPBW no need mansion in MT and VT
 Shear stud- Stud welding WW/RF=N/A, Material= Shear Stud, Weld Type=Stud
weld, Welding Process=Drawn Arc Stud Welding with ceramic ferrule
 Shear Stud: Visual Inspection carried out after strike and bend test on shear
stud, in accordance with C.O.P for SUOS 2011 Clause 14.3.7.3
 LOSF= Lac of sidewall fusion,
 Plug Weld= WW-N/A
 BS=DAC+14db, DAC+8db
 Chun Wo= Pipe Material-BS EN 10224:2002 Grade L275
 H-Beam, V-column
 BSEN 10210=Hollow structure (SHS, RHS), BSEN10219=CHS
 BS standard- VT-C-Acc
 Inaccessible to allow the flux pass in two direction at right angle to each other
 T-Joint –Minimum one member should be Plate
 Nozzle= Diameter of bracing should be equal to half or less than half of
diameter of chord
 Nodes
 Insufficient examination area
 Flare V Fillet, Through thickness is half of Weld width,
 Steel bar on plate use lap joint technique 02 for MT
 Cruciform Joint- Inaccessible carried out both side scanning
 Cruciform Joint write down one thickness only attaching members ,MAY be two,
In case heavy thickness could be 4 sites
 T-joint normally write down two thickness even one of that not accessible
 Partial Pen Less than 8mm issue Non Hok UT SUOS 2011
 Partial Penetration and full penetration (Drawing or worksheet either one
should clearly mention which is Full and Which is Partial
 Hollow section –Build-up section
 T-Joint, T-Joint, Single Vee, during formal Report,
 Hollow section to hollow section connection at corner Cross (Inside and outside
L should be fillet, and both side flush inaccessible area flush ground for UT)
 Cruciform means both side must be welded if one side welded and other side
section consider as T- Joint or corner
 SHS to SHS , OR RHS to RHS for approved operator consider as butt joint in plate,
butt joint in plate approved operator can to butt joint in SHS to SHS or RHS to
RHS
 If same day different operator with one set of report keep same examination
Level (UT-A or B)
 UT on steel lamination scan 10mm Diameter probe need 15 Minute per Meter
Square with 150mm per second speed
 Photo Resolution size minimum should be 480x640
 UT Technique EN ISO 2016-1 start use from 28 June 2016 \
 Partial Penetration above 6 OR 8 mm can issue HOK\
 T-Joint partial penetration need to scan from both side
 Stud welding MT-Non Hok, Fillet weld can HOK but not recommended
 Stud welding VT HOK, Crack detection only can add or not is depend on client
request
 1ST June start add DAC Calibration block in check list
 Shear Stud use SUOS if SUOS after Bend Test, if MTR use 5400 (ISO9934)
 Shear Stud fillet weld or Stud weld as per SUOS NVI/NRI
 Shear Stud as per 5400 if stud welding then No Crack for both MT, VT, if Fillet
Weld then NVI/NRI
 True Copy start on 24/10/2016 date of report, Stop from 16/5/2017 Date of
report
 T/L Joint fillet weld attachment member above 8mm need 0 degree scan if
accessible
 Not enough space scan (only probe area cannot issue report) Hok Report
 Cruciform rfgh SCAN .75 Skip Distance,
 Cruciform joint add all three base metal thickness
 Cruciform One side Butt other side Fillet weld consider to be T-joint

Vous aimerez peut-être aussi