Académique Documents
Professionnel Documents
Culture Documents
A Concession gives a concessionaire the long term right to use all utility assets
conferred on the concessionaire, including responsibility for operations and some
investment. Asset ownership remains with the authority and the authority is
typically responsible for replacement of larger assets. Assets revert to the
authority at the end of the concession period, including assets purchased by the
concessionaire. In a concession the concessionaire typically obtains most of its
revenues directly from the consumer and so it has a direct relationship with the
consumer. A concession covers an entire infrastructure system (so may include
the concessionaire taking over existing assets as well as building and operating
new assets). The concessionaire will pay a concession fee to the authority which
will usually be ring-fenced and put towards asset replacement and expansion. A
concession is a specific term in civil law countries. To make it confusing, in
common law countries, projects that are more closely described as BOT projects
are called concessions.
A Build Operate Transfer (BOT) Project is typically used to develop a discrete
asset rather than a whole network and is generally entirely new or greenfield in
nature (although refurbishment may be involved). In a BOT Project the project
company or operator generally obtains its revenues through a fee charged to the
utility/ government rather than tariffs charged to consumers. In common law
countries a number of projects are called concessions, such as toll road projects,
which are new build and have a number of similarities to BOTs .
In a Design-Build-Operate (DBO) Project the public sector owns and finances the
construction of new assets. The private sector designs, builds and operates the
assets to meet certain agreed outputs. The documentation for a DBO is typically
simpler than a BOT or Concession as there are no financing documents and will
typically consist of a turnkey construction contract plus an operating contract, or
a section added to the turnkey contract covering operations. The Operator is
taking no or minimal financing risk on the capital and will typically be paid a sum
for the design-build of the plant, payable in instalments on completion of
construction milestones, and then an operating fee for the operating period. The
operator is responsible for the design and the construction as well as operations
and so if parts need to be replaced during the operations period prior to its
assumed life span the operator is likely to be responsible for replacement.
This section looks in greater detail at Concessions and BOT Projects. It also
looks at Off-Take/ Power Purchase Agreements, Input Supply/ Bulk Supply
Agreements and Implementation Agreements which are used extensively in
relation to BOT Projects involving power plants.
This section does not address the complex array of finance documents typically
found in a Concession or BOT Project.
back to top
Key Features
Concessions
A concession gives a private concessionaire responsibility not only for
operation and maintenance of the assets but also for financing and
managing all required investment.
The concessionaire takes risk for the condition of the assets and for
investment.
A concession may be granted in relation to existing assets, an existing
utility, or for extensive rehabilitation and extension of an existing asset
(although often new build projects are called concessions).
A concession is typically for a period of 25 to 30 years (i.e., long enough at
least to fully amortize major initial investments).
Asset ownership typically rests with the awarding authority and all rights in
respect to those assets revert to the awarding authority at the end of the
concession.
General public is usually the customer and main source of revenue for the
concessionaire.
Often the concessionaire will be operating the existing assets from the
outset of the concession - and so there will be immediate cashflow
available to pay concessionaire, set aside for investment, service debt, etc.
Unlike many management contracts, concessions are focused on outputs -
i.e., the delivery of a service in accordance with performance standards.
There is less focus on inputs - i.e., the concessionaire is left to determine
how to achieve agreed performance standards, although there may be
some requirements regarding frequency of asset renewal and consultation
with the awarding authority or regulator on such key features as
maintenance and renewal of assets, increase in capacity and asset
replacement towards the end of the concession term.
Some infrastructure services are deemed to be essential, and some are
monopolies. Limits will probably be placed on the concessionaire – by law,
through the contract or through regulation – on tariff levels. The
concessionaire will need assurances that it will be able to finance its
obligations and still maintain a profitable rate of return and so appropriate
safeguards will need to be included in the project or in legislation. It will
also need to know that the tariffs will be affordable and so will need to do
due diligence on customers.
In many countries there are sectors where the total collection of tariffs
does not cover the cost of operation of the assets let alone further
investment. In these cases, a clear basis of alternative cost recovery will
need be set out in the concession, whether from general subsidies, from
taxation or from loans from government or other sources.
The concept of a "concession" was first developed in France. As
with affermages, the framework for the concession is set out in the law and
the contract contains provisions specific to the project. Emphasis is placed
in the law on the public nature of the arrangement (because the
concessionaire has a direct relationship with the consumer) and
safeguards are enshrined in the law to protect the consumer. Similar legal
frameworks have been incorporated into civil law systems elsewhere.
Under French law the concessionaire has the obligation to provide
continuity of services (“la continuité du service public”), to treat all
consumers equally (“l’égalité des usagers”) and to adapt the service
according to changing needs ("l’adaptation du service"). In return, the
concessionaire is protected against new concessions which would
adversely affect the rights of the concessionaire. It is therefore important
when considering concessions in civil law systems to understand what
rights are already embodied in the law.
Within the context of common law systems, the closest comparable legal
structure is the BOT, which is typically for the purpose of constructing a
facility or system.
back to top
BOT Projects
In a BOT project, the public sector grantor grants to a private company the
right to develop and operate a facility or system for a certain period (the
"Project Period"), in what would otherwise be a public sector project.
Usually a discrete, greenfield new build project.
Operator finances, owns and constructs the facility or system and operates
it commercially for the project period, after which the facility is transferred
to the authority.
BOT is the typical structure for project finance. As it relates to new build,
there is no revenue stream from the outset. Lenders are therefore anxious
to ensure that project assets are ring-fenced within the operating project
company and that all risks associated with the project are assumed and
passed on to the appropriate actor. The operator is also prohibited from
carrying out other activities. The operator is therefore usually a special
purpose vehicle.
The revenues are often obtained from a single "offtake purchaser" such as
a utility or government, who purchases project output from the project
company (this is different from a pure concession where output is sold
directly to consumers and end users). In the power sector, this will take the
form of a Power Purchase Agreement. For more, see Power Purchase
Agreements. There is likely to be a minimum payment that is required to
be paid by the offtaker, provided that the operator can demonstrate that
the facility can deliver the service (availability payment) as well as a
volumetric payment for quantities delivered above that level.
Project company obtains financing for the project, and procures the design
and construction of the works and operates the facility during the
concession period.
Project company is a special purpose vehicle, its shareholders will often
include companies with construction and/or operation experience, and with
input supply and offtake purchase capabilities. It is also essential to include
shareholders with experience in the management of the appropriate type
of projects, such as working with diverse and multicultural partners, given
the particular risks specific to these aspects of a BOT project. The offtake
purchaser/ utility will be anxious to ensure that the key shareholders
remain in the project company for a period of time as the project is likely to
have been awarded to it on the basis of their expertise and financial
stability.
Project company will co-ordinate the construction and operation of the
project in accordance with the requirements of the concession agreement.
The off-taker will want to know the identity of the construction sub-
contractor and the operator.
The project company (and the lenders) in a power project will be anxious
to ensure it has a secure affordable source of fuel. It will often enter into a
bulk supply agreement for fuel, and the supplier may be the same entity as
the power purchaser under the Power Purchase Agreement, namely the
state power company. For examples, click on Fuel Supply/Bulk Supply
Agreements. Power is also the main operating cost for a water or
wastewater treatment plant and so operators will need certainty as to cost
and source of power.
The revenues generated from the operation phase are intended to cover
operating costs, maintenance, repayment of debt principal (which
represents a significant portion of development and construction costs),
financing costs (including interest and fees), and a return for the
shareholders of the special purpose company.
Lenders provide non-recourse or limited recourse financing and will,
therefore, bear any residual risk along with the project company and its
shareholders.
The project company is assuming a lot of risk. It is anxious to ensure that
those risks that stay with the grantor are protected. It is common for a
project company to require some form of guarantee from the government
and/ or, particularly in the case of power projects, commitments from the
government which are incorporated into an Implementation Agreements.
In order to minimize such residual risk (as the lenders will only want, as far
as possible, to bear a limited portion of the commercial risk of the project)
the lenders will insist on passing the project company risk to the other
project participants through contracts, such as a construction contract, an
operation and maintenance contract
back to top
Contractual Structure
The chart below shows the contractual structure of a typical BOT Project or
Concession, including the lending agreements, the shareholder's agreement
between the Project company shareholders and the subcontracts of the
operating contract and the construction contract, which will typically be between
the Project company and a member of the project company consortium.
Each project will involve some variation of this contractual structure depending
on its particular requirements: not all BOT projects will require a guaranteed
supply of input, therefore a fuel/ input supply agreement may not be necessary.
The payment stream may be in part or completely through tariffs from the general
public, rather than from an offtake purchaser.
back to top
Examples
Water and Sanitation
Energy and Power
Power Purchase Agreements (PPAs)
Fuel Supply/Bulk Supply Agreements
Implementation Agreements
Land Lease
Transport
Solid Waste
back to top
BOT (build–operate–transfer)[edit]
BOT finds extensive application in infrastructure projects and in public–
private partnership. In the BOT framework a third party, for example the
public administration, delegates to a private sector entity to design and
build infrastructure and to operate and maintain these facilities for a certain
period. During this period the private party has the responsibility to raise
the finance for the project and is entitled to retain all revenues generated by
the project and is the owner of the regarded facilities. The facility will be
then transferred to the public administration at the end of the concession
agreement,[4] without any remuneration of the private entity involved. Some
or even all of the following different parties could be involved in any BOT
project:
BOT model
BOOT (build–own–operate–transfer)[edit]
A BOOT structure differs from BOT in that the private entity owns the
works. During the concession period the private company owns and
operates the facility with the prime goal to recover the costs of investment
and maintenance while trying to achieve higher margin on project. The
specific characteristics of BOOT make it suitable for infrastructure projects
like highways, roads mass transit, railway transport and power generation
and as such they have political importance for the social welfare but are not
attractive for other types of private investments. BOOT & BOT are methods
which find very extensive application in countries which desire ownership
transfer and operations including. Some advantages of BOOT projects are:
BOO (build–own–operate)[edit]
.... In a BOO project ownership of the project remains usually with the
project company for example a mobile phone network. Therefore, the
private company gets the benefits of any residual value of the project. This
framework is used when the physical life of the project coincides with the
concession period. A BOO scheme involves large amounts of finance and
long payback period. Some examples of BOO projects come from the
water treatment plants. This facilities run by private companies process raw
water, provided by the public sector entity, into filtered water, which is after
returned to the public sector utility to deliver to the customers.[10]
BLT (build–lease–transfer)[edit]
Under BLT a private entity builds a complete project and leases it to the
government. On this way the control over the project is transferred from the
project owner to a lessee. In other words, the ownership remains by
the shareholders but operation purposes are leased. After the expiry of
the leasing the ownership of the asset and the operational responsibility are
transferred to the government at a previously agreed price. For foreign
investors taking into account the country risk BLT provides good conditions
because the project company maintains the property rights while
avoiding operational risk.
DBFO (design–build–finance–operate)[edit]
Design–build–finance–operate is a project delivery method very similar to
BOOT except that there is no actual ownership transfer. Moreover, the
contractor assumes the risk of financing till the end of the contract period.
The owner then assumes the responsibility for maintenance and operation.
Some disadvantages of DBFO are the difficulty with long term relationships
and the threat of possible future political changes which may not agree with
prior commitments.This model is extensively used in specific infrastructure
projects such as toll roads. The private construction company is
responsible for the design and construction of a piece of infrastructure for
the government, which is the true owner. Moreover, the private entity has
the responsibility to raise finance during the construction and the
exploitation period. The cash flows serve to repay the investment and
reward its shareholders. They end up in form of periodical payment to the
government for the use of the infrastructure. The government has the
advantage that it remains the owner of the facility and at the same time
avoids direct payment from the users. Additionally, the government
succeeds to avoid getting into debt and to spread out the cost for the road
over the years of exploitation.[11]
DBOT (design–build–operate–transfer)[edit]
This funding option is common when the client has no knowledge of what
the project entails. Hence he contracts the project to a company to design,
build, operate and then transfer it. Examples of such projects are refinery
constructions. [12]
DCMF (design–construct–manage–finance)[edit]
Some examples for the DCMF model are the prisons or the public
hospitals. A private entity is built to design, construct, manage, and finance
a facility, based on the specifications of the government. Project cash flows
result from the government's payment for the rent of the facility. In the case
of the hospitals, the government has the ownership over the facility and has
the price and quality control. The same financial model could be applied on
other projects such as prisons. Therefore, this model could be interpreted
as a mean to avoid new indebtedness of public finance.
1. Outsourcing
Contracting a set of tasks to a service company in India. We
talked in depth with three companies about a specific project. As
we discussed this in detail, it became clear to us that though the
service companies would be able to provide expertise to do this
and complete the task, our investment would be too high. Due to
the high engineering content of our technology, there would be a
delay while we trained their engineers to do the task. Moreover,
the contractors couldn’t guarantee us access to the same
engineers we had trained for subsequent projects. This made
outsourcing a difficult choice as we might lose the value we
created in the training process. Also, since IP is the core of
Tensilica, its protection is a major concern. For this reason we
chose not to outsource certain projects.
2. Set up a subsidiary
This is a very of attractive choice, since it addresses the concerns
of IP protection as well as the training investment. However, it
comes with an initial investment in infrastructure and organization
overhead, which we deemed to be too high for the scale of
operation we contemplated. Since we are an IP company, with no
silicon tapeouts, testing or manufacturing, we don’t need a large
number of employees. It would be adequate to have about 15
engineers during the first year. So, though a subsidiary was an
eventual goal, we searched for a model that wouldn’t have a large
up-front investment.
3. Acquisition
This choice has the very real advantage of bringing in a team that
already exists. As is clear now, building up a well-qualified
engineering team in India is a difficult and long task. We explored
this option in detail, but eventually determined that no prospect
was found that met our needs in terms of engineering expertise,
location and cost.
4. Build-Operate-Transfer
This was our eventual choice. We decided to hire and build a
team dedicated to Tensilica projects in partnership with a
company in India that had domain knowledge, local infrastructure
and expertise. We chose eInfochips to be our Indian partner and
are working with them to build a team in Pune and operate it
under their aegis for about a year and a half. The transfer to
Tensilica occurs when there is a “critical mass of engineers to
justify the cost overhead of infrastructure and additional services.
There are some concerns with this model, of course. Will we have
the freedom and flexibility to inculcate Tensilica culture and
values into this team? Also, we have seen that recruiting is
potentially harder into this model than directly into a subsidiary
might have been. There are risks associated with events in the
future too. Will the transfer occur smoothly and on time? Will all
the employees transfer over, or will some want to stay on at
eInfochips?
Over time other tasks have been added. They share the major
attributes of supplemental work and include aspects of
development and testing.
Third, name brand matters a lot. This is a very important but often
overlooked point. Tensilica isn’t a well-known, large multinational
company. It’s well-known, for its size, in California, but it’s hardly
known in India. Engineers need to be able to explain to their
parents, spouses and neighbors who they work for — and the
name needs to be instantly recognized. This is true also of
eInfochips. Though the company has been in India for about 10
years, it has only recently expanded to Pune and isn’t a large
company.
4. Recruiting is hard!
Closing a candidate and ensuring that he or she shows up is
harder still.
Public-Private Partnerships
That’s why companies such as RWL Water are leveraging public-
private partnerships to construct public water facilities. One option
with many benefits is known as build, finance, operate, and
transfer (BOT). A BOT is a long-term contract that allows the
client to purchase a service for the life of the contract. The client
is responsible only for buying the service. At the end of the
contract, the facility is transferred to the client at no cost.
Projects ideally suited to BOT are government-driven ones in
which a substantial public benefit has been identified. This
contractual option can be applied any public facility,
including water treatment and sanitation facilities. The World Bank
explains:
A Build Operate Transfer (BOT) Project is typically used to develop a
discrete asset rather than a whole network and is generally entirely
new or greenfield in nature (although refurbishment may be involved).
In a BOT Project the project company or operator generally obtains its
revenues through a fee charged to the utility/government rather than
tariffs charged to consumers. In common law countries a number of
projects are called concessions, such as toll road projects, which are
new build and have a number of similarities to BOTs.
Through BOT, cities that might have otherwise forgone building
new, state-of-the-art water treatment or desalination facilities can
now ensure local residents have the safe water supplies they
need for years to come.
Government Entities
A variety of agencies and organizations are typically involved in
BOT projects since the involvement of a municipal,
state/provincial, or federal agency is required. Precise
requirements vary, based on national laws. When a project is not
fully funded by these entities, a remaining investment by
commercial or investment banks may be needed.
BOT contractual arrangements do not necessarily reduce the cost
associated with the providing service to the end user, Tramer
said. Most importantly, the service can be provided efficiently and
with little risk to the off-taker.
The primary benefit associated with BOT is that it enables
construction of essential water facilities, whether water treatment
plants or desalination facilities that provide communities with
fresh, potable water. BOTs eliminate the need for public sector
agencies to find funding, which can be an obstacle to responding
quickly to water-related emergencies.
BOT vs. BOOT. To address such situations, outsourcing planners have learned from
project financing the structures for “build-operate-transfer” (“BOT”) and “build-own-
operate-transfer” (“BOOT”) models. They are essentially identical.
Common Elements: In each case, the enterprise customer gets access to
technology, expertise, knowledge and operating capital. In each model, the service
provider assembles the people, the processes and the technology and then
provides services as an outsourcer under the classic outsourcing model. At the
agreed time, the service provider transfers the service delivery operation (including
infrastructure) to the enterprise customer.
BOOT: In the BOOT model, the enterprise customer also gets the benefit of the
service provider’s financing of the capital expenses necessary to start a new service
center or service delivery platform. In a pure BOOT, the service provider owns and
finances the infrastructure in addition to managing it for a fee.
BOT: In the BOT model, the enterprise customer provides the financing for the new
infrastructure. In a pure BOT, the service provider does not own the infrastructure
but is a concessionaire entitled to manage it for a fee that covers its operating
expenses.
Time Lapse Scenario. Thus, where the enterprise customer wants help in building its
own captive, the BOT or BOOT model provides a legal structure for the supplier to build
and, for a time, manage the entire service delivery center before assigning it to the
customer. This model reflects traditional project financing for building transportation
infrastructure – such as highways, airports, bridges, tunnels and ports – for
governments. In the public sector, BOT relationships are sometime called “public-
private partnerships.” [LINK TO THAT PAGE = SEE BELOW]
Accounting. An essential element of BOT is its cost accounting. The cost structure for
BOT involves amortization of capital investment. The pricing structure will reflect this
amortization if the service provider owns any physical assets, license agreements or
real property used for service delivery.
Advantages. The BOT and BOOT models offer several advantages to the enterprise
customer. It saves:
time because the service provider is presumably more expert at assembling the
infrastructure and obtaining local regulatory consents;
money (and maybe market share) because the benefits of the new infrastructure
can be enjoyed sooner;
effort because the service provider is performing the effort, presumably at lower
salaries.
Disadvantages. The BOT and BOOT models have certain drawbacks for the enterprise
customer.
Additional costs are incurred to pay a profit to the service provider for the value of its
know-how and time in assembling the service delivery infrastructure.
Tie-in effects arise, since the enterprise customer commits to work with the
particular service provider (as in any class outsourcing model) and cannot escape
for low switching costs until the service provider’s investment is amortized or
recaptured.
Inflexibility results from the enterprise customer’s commitment to purchase the
infrastructure, whether up front, by imputed self-amortizing “mortgage” payments or
at the end. This ties up the enterprise customer’s capital and credit, unless the
enterprise customer can structure the financial risk so that the service provider
retains ownership until the customer exercises, in effect, a call option to acquire the
service center infrastructure.
Build–operate–transfer (BOT) is a well-established solution
used in the engineering and construction industries for
building different types of infrastructure (e.g. railways,
highways, power plants). In recent years, BOT has
increasingly been adopted by companies in the service
industry as a mode for entering foreign markets. BOT in
service offshoring (SO) is characterised by a number of
significant peculiarities (e.g. different numbers of involved
parties, fee methods, lengths of the concession period),
which may call into question the possibility of extending
existing findings that relate to infrastructure projects. The
aims of this work are as follows: to collect and systematise
existing knowledge on engineering and construction BOT
projects; to highlight – through an exploratory case study –
how these results could be applied to BOT in SO; and to shed
light on the factors affecting the choice between different
entry modes (including BOT).
Procurement arrangements
2. Which are the most common procurement
arrangements if the main parties are local? Are these
arrangements different if some or all of the main parties
are international contractors or consultants?
Generally, if both the parties are Indian, the usual arrangement is
an item rate contract, with some of the material supplied by the
employer or purchase on a "star rate" basis. However, where the
contract is subject to international competitive bidding, an
increasing number of contracts are shifting from item rate to an
engineering, procurement and construction (EPC) basis.
Additionally, some contracts utilise EPC with public private
partnership (PPP) models, for example, build-operate-transfer
(BOT) and build-own-operate-transfer (BOOT). Many road
construction projects are given on a BOT basis, where toll
collection is used as the basis for recovering costs (see Question
4).
Transaction structures
3. What transaction structures and corporate vehicles are
most commonly used in both local and international
projects?
Local projects
In local projects, most of the contracts are given to an Indian
entity. In smaller projects, special purpose vehicles (SPVs) or joint
ventures (JVs) are not common. The funding is usually supplied
entirely by the employer.
International projects
In projects involving international competitive bidding, particularly
where foreign lenders are involved (for example, the Asian
Development Bank (ADB) and the Japan International Co-
operation Agency (JICA)), the preferred structures are JVs or
SPVs.
The form of JV typically utilised in India is an unincorporated JV,
referred to as an "association of persons". An "association of
persons" is recognised by the Income Tax Act 1961. It enables
various parties to combine their qualification requirements and
skills without actually having to start or incorporate a SPV.
However, for build-operate-transfer (BOT) projects, the preferred
structures involve setting up of an SPV. In some projects,
incorporation of a SPV is required by the employer. Typically, in
these projects, the SPV does not carry out all of the work and
subcontracts some of the work (either to their own principals or to
other subcontractors).
In many large projects (for example, airport projects), the SPVs
are set up by the developers with the government entity and in
turn subcontract the entire construction work to an EPC contractor
(who further subcontracts specialised work). Most large projects
involve international competitive bidding.
Finance
4. How are projects financed? How do arrangements
differ for major international projects?
In the past, funding for most projects in India was supplied by the
employer, who only engaged contractors on an item rate basis.
The employer also funded the supply of building materials (for
example, cement and steel).
However, this structure has undergone a substantial change and,
for both item rate and engineering, procurement and construction
(EPC) contracts, most of the funding is currently from government
entities who either receive budgetary allocation or loans from
foreign lenders. Many government entities like the National
Highways Authority of India (NHAI) can also issue bonds,
including tax free bonds, to raise financing.
In build-operate-transfer (BOT), build-own-operate-transfer
(BOOT) projects and projects with developers, both debt and
equity funding is used. One of the recent issues with this model
has been that in many projects (particularly road projects), even
after the construction phase is over, the contractor or the SPV
was not permitted to sell the equity. As a result, more complex
arrangements were not entered into and only an escrow
arrangement was worked out in which all toll collection and other
earnings would be deposited. The NHAI has also tried annuities-
based projects where the bidders bid based on amount they want
from the NHAI (or will pay to the NHAI). This takes care of viability
funding and the government is seriously considering using this
arrangement in other infrastructure projects.
Contractual issues
Contractors' risks
7. What risks are typically allocated to the contractor?
How are these risks offset or managed?
In more typical item rate contracts, the employer bears the risk of
a change in law (including taxes and compensation for inflation,
providing land and the design). The contractor is subject to most
other risks. Typically, the contractor is entitled to full extension of
time for events which are beyond the contractor's control and
which lead to delays to the project.
However, in a large number of government contracts, a
substantial number of delaying events (even if they are beyond
the contractor's power) are the basis of extension of time, but
prolongation costs are prohibited by contractual clauses. Delay in
land acquisition is a common cause for delays to such projects.
Adverse geological occurrences and site encumbrances are also
causes which often lead to disputes. In many cases, environment
approval or court orders relating to improper environmental
impact analysis have also led to delays. Stoppage of work due to
local issues is also a cause of a number of arbitrations. This is
because, even where there are provisions for compensation, the
employer is not always willing to compensate the contractor, often
suggesting that these issues should have been discovered by the
contractor during the pre-bidding inspection. In fact, land
acquisition and site encumbrances, along with geological
occurrences are often the bone of contention as far as the risk for
the same is concerned. Even if the employer is otherwise happy
to grant time extension for this, he will be reluctant to do so if the
contract links prolongation costs to the grant of a time extension.
Excluding liability
8. How can liability be excluded or restricted under local
law?
The Indian Contract Act 1872 has provisions for determining the
liability in the case of defaults by the contracting parties. Parties
are also free to contract and can agree to impose liability on one
or the other party. Many contracts include exclusion of liability
clauses. Typically, the courts would enforce these exclusion
clauses. However, in certain cases if enforcement of a particular
exclusion clause causes extreme hardship, the courts have
declined to enforce the terms or declined to enforce it in the facts
of the case. Many clauses that limit the liability of the employer
are also read down or read strictly against the employer.
Caps on liability
9. Do the parties usually agree a cap on liability? If yes,
how is this usually fixed? What liabilities, if any, are
typically not capped?
Section 73 of the Indian Contract Act 1872 addresses damages.
Under this section, damages which are to be awarded to the non-
defaulting parties, must be actual damages. Punitive damages
are not permitted under Indian law. However, parties are free to
agree to liquidated damages, if they are genuine pre-estimates of
likely loss. These become the ceiling on the amount payable but
what is liable to be paid is only the actual loss.
Additionally, liquidated damages can be awarded when there are
genuine pre-estimates of likely loss and it is for the non-defaulting
party to show that these are not genuine loss or are excessive or
penal in nature. Essentially, Indian law does not permit penal
damages or damages which are in terrorem. Indian law only
contemplates damages which put the non-defaulting party back in
the position that he would be, but for the breach or damages
causing event. Therefore, Indian law allows damages that are
compensatory and not punitive. If liquidated damages are
stipulated, the party in breach must pay the same. However, in
the event the party in breach declines to do so, the arbitrators or
the court will have to decide if the sum stipulated is a genuine pre-
estimate of likely damages or is punitive in nature. If liquidated
damages are in the punitive in nature then the arbitrator or the
court will only award what is reasonable or actual loss caused.
However, the determination of actual loss cannot exceed the
liquidated damages specified.
Most contracts do have liquidated damage clauses for delay in
work. However, other liabilities are not always capped.
Force majeure
10. Are force majeure exclusions available and
enforceable?
Force majeure clauses are available and are enforceable under
Indian law. Force majeure is normally a defined term in most
contracts and the consequences set out.
Material delays
11. What contractual provisions are typically negotiated
to cover material delays to the project?
Most major contracts in India are those granted by the
government or governmental agencies. These contain clauses for
extension of time as well as prolongation costs. While the
provision for extension of time is generally very wide, provisions
for prolongation costs are restricted. However, most of these
clauses are non-negotiable and parties must bid, based on the
provisions as provided.
Subcontracts in such projects (which would be between private
parties) also have similar terms. However, all other private
contracts will have negotiated term to cover delays to the projects.
The Indian Contract Act 1872 has detailed provisions which apply
even where a standard-form contract (for example FIDIC
Conditions of Contract) is adopted, the clauses relating to liability,
time extension, prolongation costs and liquidated damages, as
well as unencumbered possession of site are typically modified by
the employer to limit its own liability. These have been the subject
matter of a large number of disputes. In private contracts there is
scope for negotiating these clauses. As a result, disputes are not
as common.
Material variations
12. What contractual provisions are typically negotiated
to cover variations to the works?
Most agreements contain a clause for variation. Typically, in all
contracts, whether item rate or an engineer, produce and
construct (EPC), the variation clause provides for variations
instructed by the employer or variations suggested by the
contractor and approved by the employer. This is in line with most
standard-form contracts.
In either case, the employer typically seeks a cost and work
method proposal from the contractor and will approve the
variation and its cost based on these proposals. In item rate
contracts, additional work is only paid at the rate already agreed
upon. In the event no rate is agreed upon for any additional work,
rates are calculated either based on the contractual rate or based
on break-up of cost submitted by the contractor and approved by
the engineer or the employer.
In EPC contracts where there are no individual rates, the contract
often provides for submission of the break-up rates in a sealed
cover that is used in case of any additional work or dispute in
regard to the contract. However, normally, whenever a variation is
proposed, the contractor must give a proposal which is then
accepted or rejected by the employer. Typically, if the variation is
suggested by the employer, the contractor will be asked to
provide a proposal including a modified design along with a cost-
breakup and an updated time schedule. This variation will then be
verified and approved along with appropriate modifications and
will then become part of the schedule of works.
The contractor can also suggest a variation in design or in the
work method or in materials used. This proposal must also be
approved and priced by the employer and then implemented. It is
important to note that usually the employer will appoint an
engineer for the project who will deal with these issues, of
instructing variations, appraisal and pricing of proposals and
finally approving them. At the same time, it is seen that in many
projects, many variations are verbally conveyed on a day-to-day
basis, including redesign and change of method by the engineer
on site, while the work is taking place. These are frequently by
mutual understanding but fail to be conveyed in writing. This lack
of written instructions can cause difficulties at the payment stage
as it is possible to dispute whether a variation was indeed
approved or not and whether it must be reimbursed or not.
Other negotiated provisions
13. What other contractual provisions are usually heavily
negotiated by the parties?
Most large contracts are awarded by the government or
government agencies based on international competitive bids.
Therefore, clauses of these contracts are not easily negotiated.
Many contracts which are based on international standard-form
contracts (for example, the FIDIC Conditions of Contract), with
some modifications, typically tend to favour the employer. It is
difficult for the bidders or even the successful contractor to
negotiate any of the terms. However, parties do seek and get
clarifications relating to some of the clauses before the bid
submission date and some times even manage to have some of
the clauses amended. However, this is rare.
However, private contracts between, for example, a developer or
a special purpose vehicle (SPV) with a contractor or
subcontractors are typically negotiated. However, even in these
contracts, the scope for negotiation is not very large and the
employer tends to retain their contract forms. Additionally,
contracts with subcontracts can be on a back-to-back basis.
The following are some of the clauses that can be negotiated:
Price.
Escalation clauses.
Changes in law.
Liability for site encumbrances.
Geological occurrences.
Unforeseeable conditions.
However, radical changes are rarely achieved. After the lowest
bidder is found, there is also a tendency to further negotiate the
price. Terms and requirements for attaining financial closure
and/or conditions precedent to the commencement of contract are
also sometimes negotiated.
The Central Vigilance Commission (CVC) has now tried to put a
stop to this practice. Under the CVC Guidelines, the bid
documents must clearly specify criteria to be adopted for
evaluation purposes.
For the two bid system, the CVC Guidelines specify that techno-
commercial negotiations can be conducted with all the bidders to
clarify the deviations regarding tender specifications and
requirements. After bringing the acceptable offers on a common
platform, all the commercial terms and conditions and technical
specifications, must be frozen. If some changes are made in
terms and conditions or technical specifications, the bidders may
be given a fair chance to revise their price bids accordingly. The
distribution of work, if considered necessary, must be done in a
fair and transparent manner.
Subcontractors
17. How do the parties typically manage their
relationships with subcontractors?
Subcontracts are awarded by the contractor according the
structure of the contract. If the whole works can be divided into
packages, the subcontracts are then awarded accordingly for
different packages. These can also be awarded according to the
different specialised jobs or activities to be carried out during the
works.
Subcontractors can either be nominated by the employer, or they
can be proposed by the contractor according to the pre-
qualifications set by the main contract and approved by the
independent engineer or employer. Typically, the nature of the
subcontracts will depend on the nature of the main contract and
they will often be back-to-back with the main contract.
The subcontractor has no privity directly with the principal
employer. However, it is the subcontractor will often try to claim
against the principal employer, particularly if there is no arbitration
clause. In any event, the subcontractor can apply to a court (even
if there is an arbitration clause) to stop payment by the employer
to the contractor for dues of the subcontractor. However, such
orders are passed only in very rare cases where there are no
disputed questions of fact. After the subcontractor has a decree in
his favour, he can attach amounts payable by the employer to the
contractors.
Where there are nominated subcontractors, the question of
liability between the employer and contractor and subcontractor
becomes more complicated.
Licensing
18. What licences and other consents must contractors
and construction professionals have to carry out local
construction work? Are there any specific licensing
requirements for international contractors and
construction professionals?
There are no specific licences and consents required for
construction professionals to work in India. However, a foreign
company working in India must register itself under the
Companies Act 2013 and act under the foreign direct investment
(FDI) guidelines.
19. What licences and other consents must a project
obtain?
A large number of licences and permits are required for a
construction project. Typically, the responsibility of obtaining the
consents is divided between the employer and contractor. The
employer typically obtains permission relating to zoning laws and
environment laws, among others. The contractor must obtain all
permissions necessary for carrying out the works. Additionally,
various registrations are required for taxation purposes.
Projects insurance
20. What types of insurance must be maintained by law?
Are other non-compulsory types of insurance maintained
under contract?
There are no types of insurance that are specifically required by
law for a construction project. However, a construction project
usually has insurance requirements, which are often taken jointly
by the employer or by the employer and contractor. Advance
losses and profit insurance is not common in India.
Labour laws
21. Are there any labour law requirements for hiring (local
and foreign) workers?
India has a large number of labour laws. Many of these laws are
also state specific. Workers are also often hired from labour
contractors and can be engaged as contract labour except in
certain industries (not connected with construction law) where
contract labour is prohibited.
If the workers are hired as permanent employees there are strict
rules for retrenchment and retrenchment compensation. Foreign
workers must have the necessary visas and work permits and the
payment to them must comply with the requirements of the
Reserve Bank of India (RBI).
Environmental issues
25. Which local laws regulate projects' effects on the
environment?
There are a number of environment laws which govern
construction projects. Most of these laws are central or federal,
including:
The Air (Prevention and Control of Pollution) Act 1981, as
amended in 1987. The Air Act was introduced to provide for the
prevention, control and abatement of air pollution in India.
The Water (Prevention and Control of Pollution) Act
1974. Water Act was introduced to provide for the prevention
and control of water pollution and the maintaining or restoring of
wholesomeness of water. Under section 19 (3) of the said Act
the State Government may, by notification in the Official
Gazette:
alter any water pollution prevention and control area, whether
by way of extension or reduction; or
define a new water pollution, prevention and control area, in
which may be merged one or more water pollution, prevention
and control areas, or any part or parts of that area.
The Environment Protection Act. The Environment Protection
Act was introduced for protection and improvement of
environment and prevention of hazards to human beings, other
living creatures, plants and property. The purpose of the
Environment Protection Act is:
to co-ordinate the activities of the various regulatory agencies
already in existence;
to create an authority or authorities with adequate powers for
environmental protection;
to regulate the discharge of environmental pollutants and the
handling of hazardous substances; and
speedy response in the event of accidents threatening
environment and punishment to those who endanger human
environment, safety and health.
The Explosives Act 1884. The Explosives Act was introduced
to regulate the manufacture possession, use and sale of
explosives.
There are other regulations made in addition to these Acts which
may be applicable (for example, for hazardous materials).
Environmental impact assessments (EIAs)
There is an EIA Notification of 2004 under which all projects
above certain minimum criteria must obtain a "no objection" from
the concerned environmental authorities. Various additional
conditions are imposed by the environment authorities while
granting a "no objection" decision, such as a proper Environment
Management Plan, afforestation, protection and preservation of
flora and fauna in the area.
Therefore, in a construction project, the environment authorities
check the safety and advisability of the project from an
environmental stand point. Issues also arise about the use of
forest land for the project or for disposing of waste. The
environmental approval also deals with measures to minimise
environment pollution or hazard (including minimising cutting of
trees or compensatory afforestation). However, many of these
environment approvals are required to be taken by the employer,
while those relating to the actual work are to be taken by the
contractor.
Sustainable development
Environmental approval also considers sustainable development
and, as a result, conditions are often imposed in this regard by the
environmental authorities. This is currently on a case-by-case
basis but there are plans to standardise the process. The courts
have also considered environmental issues from time to time,
particularly relating to sustainable development and the right of
the landowners whose lands have been acquired. A number of
hydroelectric projects have been postponed in view of lack of
proper environmental studies relating to sustainable development.
Bankruptcy/insolvency
28. What rights do the client and funder have on the
contractor's bankruptcy or insolvency?
Typically, most contracts allow the employer to terminate the
contract upon bankruptcy or insolvency of the contractor and
similarly that of the employer. Insolvency law in India is governed
by the Sick Industrial Companies Act 1985, in which a company
which has eroded its net worth is must go before the Board of
Industrial and Financial Reconstruction (BIFR). There is a winding
up procedure provided under the Companies Act 2013 which
normally goes to the High Court.
PPPs
29. Are public private partnerships (PPPs) common in
local construction projects? If so, which sectors
commonly use PPPs?
PPP projects are quite common, specifically in larger projects.
PPPs are also becoming more common in smaller projects and
there are many cases of PPPs in road and bus stop projects. In
larger projects, including airports, these are very common and
becoming more popular. However, there are many issues which
need to be resolved for PPPs to be successful.
back to top
By definition there is always a public component to a PPP. The form that this component takes
will depend on the country and the project and can range from financial support, to indirect or
contingent support, to in kind support (such as provision of land or equipment), to broader
financial mechanisms that can support the country’s PPP program or encourage the financial
markets to lend into projects.
This section considers:
Funded products
Contingent Products
Financial Intermediaries
Project Development Funds
European Union Funds
Funded products
The government may decide to provide direct support for the project for example through
subsidies/grants, equity investment and/or debt. These mechanisms are particularly useful where
the project does not in its own merit achieve bankability, financial viability or is otherwise
subject to specific risks that the private investors or lenders are not well placed to manage. In
developing countries where private finance is most needed, these constraints may necessitate
more government support than would be required in more developed countries. Funded support
involves the government committing financial support to a project, such as:
direct support – in cash or in-kind (e.g. to defray construction costs, to procure land, to
provide assets, to compensate for bid costs or to support major maintenance);
waiving fees, costs and other payments which would otherwise have to be paid by the
project company to a public sector entity (e.g. authorising tax holidays or a waiver of tax
liability);
providing financing for the project in the form of loans (including mezzanine debt) or
equity investment (or in the form of viability gap funding); and
funding shadow tariffs for roads and topping up tariffs to be paid by some or all
consumers (in particular, those least able to pay) say in water and electricity projects to
reduce the demand risk borne by the project company[1].
Few PPP projects are viable without some form of government technical or financial support.
Efficient financing of PPP projects can involve the use of government support, to ensure that the
government bears risks which it can manage better than private investors and to supplement
projects which are economically but not financially viable.
back to top
Contingent Products
The government may choose to provide contingent mechanisms, i.e. where the government is not
providing funding, but is instead taking on certain contingent liabilities, for example providing:
guarantees, including guarantees of debt, exchange rates, convertibility of local currency,
offtake purchaser obligations, tariff collection, the level of tariffs permitted, the level of
demand for services, termination compensation, etc.;
indemnities, e.g. against non-payment by state entities, for revenue shortfall, or cost
overruns;
insurance;
hedging of project risk, e.g. adverse weather, currency exchange rates, interest rates or
commodity pricing; or
contingent debt, such as take-out financing (where the project can only obtain short tenor
debt, the government promises to make debt available at a given interest rate at a certain
date in the future) or revenue support (where the government promises to lend money to
the project company to make up for revenue short-falls, enough to satisfy debt-service
obligations).
For example, on the Zagreb-Macelj toll road , the government provided in-kind support in the
form of land and contingent debt drawn down whenever revenues were insufficient to cover debt
service. Thus, lenders were protected, but the risk remained with the equity holders.
The government will want to manage the provision of government support, and in particular any
contingent liabilities created through such support mechanisms. Governments seek a balance
between supporting private infrastructure investment and fiscal prudence.[2] Striking this
balance right will help the government make careful decisions about when to provide public-
money support and manage the government liabilities that arise from such public-money support,
while still being aggressive in encouraging infrastructure investment. Government assessment of
projects receiving such support is doubly important given the tendency of lenders to e less
vigilant in their due diligence when government support is available, since this reduces lender
risk and exposure.
Governments actively managing fiscal risk exposure face challenges associated with gathering
information, creating opportunities for dialogue, analyzing the available information, setting
government policy and creating and enforcing appropriate incentives for those involved. Given
the complexity of these tasks, it is becoming more popular for governments, and in particular
ministries of finance, to create specialist teams to manage fiscal risk arising from contingent
liabilities, in particular those associated with PPP. This is often achieved through debt
management departments, which are already responsible for risk analysis and management. The
government may also consider creating a separate fund to provide guarantees, allowing the
government to regulate better this function and ring fence the associated government liabilities.
For more, see Management of Government Risk.
back to top
Financial Intermediaries
The government may wish to use its support to mobilize private financing (in particular from
local financial markets), where that financing would not otherwise be available for infrastructure
projects. The government may want to mobilize local financial capacity for infrastructure
investment, to mitigate foreign exchange risk (where debt is denominated in a currency different
than revenues), to replace retreating or expensive foreign investment (for example, in the event
of a financial crisis) and/or to provide new opportunities in local financial markets. But local
financial markets may not have the experience, or risk management functions, needed to lend to
some sub-sovereign entities or to private companies on a limited recourse basis.
To overcome these constraints, the government may want to consider the intermediation of debt
from commercial financial markets, creating an intermediary sufficiently skilled and resourced to
mitigate the risks that the financial markets associate with lending to infrastructure projects. To
achieve this, the government may want to use a separate mechanism (the “intermediary”) to
support such activities without creating undue risk for the local financial market, for example,
by:
using the intermediary’s good credit rating to borrow from the private debt market (e.g.
providing a vehicle for institutional investors who could not invest directly in projects)
then lend these funds to individual entities or projects as local currency private financing
of the right tenor, terms and price for the development of creditworthy, strategic
infrastructure projects;
providing financial products and services to enhance the credit of the project and thereby
mobilize additional private financing, for example by providing the riskiest tranche of
debt, providing specialist expertise needed to act as lead financier on complex or
structured lending, syndication, credit enhancement, and specialist advisory functions;
and/or
providing support to finance or reduce the cost or improve the terms of private finance
for key utilities. These entities may need first to learn gradually the ways of the private
financial markets, and the financial markets may need to get comfortable with lending to
infrastructure operators. This mechanism can help slowly graduate such sub-national
entities or state owned enterprises from reliance on public finance to interaction with the
private financial markets.
Current best practice indicates that such intermediaries should be private financial institutions
with commercially oriented private sector governance. Intermediaries meant to create space in an
existing financial market must have commercial incentives aligned to this goal, with
appropriately skilled and experienced staff, and a credit position sufficiently strong to mobilize
financing from the market. Existing private financial institutions with appropriate skills and
capacity can help to perform this function. However, private entities often suffer from conflicts
of interest (e.g. holding positions in the market such that their interests are not aligned with the
role of intermediary) or would be constrained from taking positions in the market due to its role
as intermediary (crowding out vital market capacity). The government may therefore want to
create a new private entity to play this role.
Examples of financial intermediaries developed by Governments are:
India:
India’s Infrastructure Development Finance Company (IDFC)
IDFC was set up in 1997 by the Government of India along with various Indian banks and
financial institutions and IFIs. IDFC’s task was to connect projects and financial institutions to
financial markets and by so doing develop and nurture the creation of a long-term debt market. It
offered loans, equity/quasi equity, advisory, asset management and syndication services and
earned fee based income from advisory services, loan syndication, and asset management
capitalize on its established knowledge base and credibility in the market. IDFC also developed a
project development arm, taking early positions in some project vehicles. By bringing projects
through feasibility, structuring, and presentation to bidders, it generated success/development
fees from the winning bidders.
The agency invested significant efforts in its early years in policy and regulatory framework
changes to facilitate private investment in infrastructure. More bankable infrastructure projects
subsequently emerged. IDFC has successfully leveraged the fact that the Government holds an
equity stake – without compromising on its commercial orientation.
IDFC began operations with a strong capital base of approx US$400 million. Growth was
initially slower than expected. After 6 years of operations, IDFC had a loan portfolio of around
US$550 million and growth accelerated. After 8 years, an IPO in July 2005 introduced new
equity and allowed early investors to realize their gains. An additional US$525 million equity
was raised through an institutional placement in 2007, by which time, the Indian government’s
stake had fallen to 22 %. Other major shareholders now include Khazanah, Barclays and various
Indian institutions.
IIFCL – India Infrastructure Finance Company Limited
India Infrastructure Finance Company Limited (IIFCL) was incorporated on January 5, 2006
under the Companies Act 1956 as a wholly Government owned Company. IIFCL is a dedicated
institution purported to assume an apex role for financing and development of infrastructure
projects in the country. The authorized capital of the Company is Rs. 2,000 crore of which, paid
up capital, at present, is Rs. 2,000 crore. Besides, the resource-raising programme of the
Company would have sovereign support, wherever required.
The Company renders financial assistance through:
Direct lending to eligible projects
Refinance to banks and FIs for loans with tenor of five years or more
Any other method approved by Government of India
back to top
India
Project Development Fund of IL&FS
India Project Development Fund (IPDF) was introduced by IL&FS towards funding project
development expenses of large infrastructure projects, primarily in surface transport, ports, water
and power infrastructure. IPDF meets all project development costs and takes on the
development risk upto financial closure.
IPDF is the first private equity fund in India for project development funding covering:
Project Design & Techno-Financial Feasibility
Environmental, Social & Market Studies
Establishing Contractual Framework