Project Stakeholders
Management
Eng.Mukhlis Mirghani
Project Stakeholders Management
It includes the processes required to identify the people, groups, or
organizations that could impact or be impacted by the project.
Analyze stakeholder expectations and their impact on the project,
Develop appropriate management strategies for effectively engaging
stakeholders in project decisions and execution.
Eng.Mukhlis Mirghani
13.1 Identify Stakeholders
Eng.Mukhlis Mirghani
.1 Project
charter
.2 Procurement 1 Stakeholder
analysis .1 Stakeholder
documents
.2 Expert register
.3 EEFs
.4 OPAs judgment
.3 Meetings
Eng.Mukhlis Mirghani
Inputs
.1 Project Charter
oprovide information about internal and external parties
related with the project and affected by the result or
the execution of the project
o.2 Procurement Documents
• the parties in that contract are key project stakeholders,
e.g. suppliers.
Eng.Mukhlis Mirghani
Tools and techniques
.1 Stakeholder analysis (steps)
1. Identify all potential project stakeholders and relevant information,
2. Analyze the impact or support each stakeholder could generate, and classify
them so as to define an approach strategy,
3. Assess how key stakeholders are likely to react or respond in various situations,
in order to plan how to influence them to enhance their support and mitigate
potential negative impacts.
• There are multiple classification models used for stakeholders analysis, such as:
• Power/interest grid
• Power/influence grid
Eng.Mukhlis Mirghani
Power/Interest Grid with Stakeholders
Eng.Mukhlis Mirghani
Outputs
1 Stakeholder Register
• Identification information
Name, organizational position, location, contact information;
• Assessment information
Major requirements, main expectations, potential influence
• Stakeholder classification
Internal/external, supporter/neutral/resistor
Eng.Mukhlis Mirghani
13.2 Plan Stakeholders Management
Eng.Mukhlis Mirghani
.1 Stakeholder mgt
.1 Expert
plan
.1 Project mgt Plan judgment
.2 Project
.2 SHs Register .2 Meetings
documents
.3 EEFs .3 Analytical
updates
.4 OPAs techniques
Eng.Mukhlis Mirghani
Inputs
.2 Stakeholders register
• provides the information needed to plan appropriate ways to
engage project stakeholders.
3 EEFs
• Because the management of stakeholders should be adapted to
the project environment (e.g. organizational culture, political
climate)
4 OPA
• lessons learned database and historical information
Eng.Mukhlis Mirghani
Tools and techniques
.3 Analytical Techniques
• The engagement level of the stakeholders can be classified as
follows:
Unaware. Unaware of project and potential impacts.
Resistant. Aware of project and potential impacts and resistant to
change.
Neutral. Aware of project yet neither supportive nor resistant.
Supportive. Aware of project and potential impacts and supportive
to change.
Leading. Aware of project and potential impacts and actively
engaged in ensuring the project is a success.
Eng.Mukhlis Mirghani
Stakeholders Engagement Assessment Matrix
Eng.Mukhlis Mirghani
Outputs
.1 Stakeholder Management Plan
• Desired and current engagement levels of key stakeholders;
• Scope and impact of change to stakeholders; Identified interrelationships and
potential overlap between stakeholders;
• Information to be distributed to stakeholders, including language, format,
content;
• Reason for the distribution of that information
• Time frame and frequency for the distribution of required information;
• Method for updating and refining the stakeholder management plan as the
project progresses and develops.
Eng.Mukhlis Mirghani
13.3 Manage Stakeholder
Engagement
Eng.Mukhlis Mirghani
.1 Stakeholder mgt .1 Issue log
plan .1 Communication .2 Change requests
.2 Communications methods .3 Project mgt plan
mgt plan .2 Interpersonal skills updates
.3 Change log .3 Management skills .4 Project documents
.4 OPA updates
.5 OPA updates
Eng.Mukhlis Mirghani
Inputs
1 Stakeholders mgt plan
• helps define a strategy for identifying and managing stakeholders
throughout the project
.2 Communications mgt plan
.3 change log
• is used to document changes that occur during a project.
• These changes—and their impact on the project in terms of time,
cost, and risk—are communicated to the appropriate stakeholders.
Eng.Mukhlis Mirghani
Tools and techniques
.1 Communications methods
• identified in the communications mgt plan are utilized during stakeholder
engagement management.
.2 Interpersonal Skills
• Building trust,
• Resolving conflict,
• Overcoming resistance to change
.3 Management Skills
• Influence people to support the project,
• Negotiate agreements to satisfy the project needs.
Eng.Mukhlis Mirghani
Outputs
.1 Issue log
• Managing stakeholder engagement may result in the development of an issue log.
.2 Change Requests
Managing stakeholder engagement may result in a change request to the product or the
project
.3 Project Management Plan Updates
• an ineffective communication method may be replaced by another one,
• or a new communication requirement may be identified
.4 Project Documents Updates
• new stakeholders are identified ,
• or if registered stakeholders are no longer involved in or impacted by the project
Eng.Mukhlis Mirghani
13.4 Control Stakeholder
Engagement
Eng.Mukhlis Mirghani
.1 Project management .1 Work performance
.1 Information information
plan
management .2 Change requests
.2 Issue log
systems .3 Project mgt plan
.3 Work performance
.2 Expert judgment updates
data
.3 Meetings .4 Project documents
.4 Project documents
updates
.5 OPA updates
Eng.Mukhlis Mirghani
Inputs
.1 Project mgt plan
Needs and techniques for communication among stakeholders.
.2 Issue log
.3 Work Performance Data
• include reported percentage of work completed,
• technical performance measures,
• start and finish dates of schedule activities,
• actual costs, actual durations etc.
.4 Project Documents Eng.Mukhlis Mirghani
Tools and Techniques
Eng.Mukhlis Mirghani