assumed no impact on meterology and climate

surface water

- barrage
- construction: build in dry season and ensure that construction materials
and materials removed are kept away from the Mekong river and other streams to
prevent contamination
- operation: maintenance of minimum flow of 5k m3/sec and should be monitored
by "well-trained" technicial/engineer and appropriate instrumentation

- powerhouse
- construction: prevent material contamination
- operation: no mitigation

- tranmission line
- construction: prevent material contamination
- operation: no mitigation

- access road
- construction: prevent material contamination and ensure there is something
for storm water drainage
- operation: no mitigation

surface water quality

- barrage
- construction: keep camps 50m away, stockpiles and construction materials
away from river and natural watercourses, prohibit garbage disposal and
equipment/machinery cleaning near watercourses, regular weekly check-up and
maintenace of equipment, restore the bank/embankment to stable conditions
immediately after construction, control soil erosion at site, provide adequate
toilets and oil and grease traps with the carrying capacity of wastewater receiving
pond, wastewater must be treated to standard, sedimentation and possibly
neutralization ponds need to be constructed for runoff from concrete prep sites, no
cleaning near or in the water or anywhere that flows into the river, prevent oil
contamination, have a detailed plan for monitoring effects of surface water runoff
from construction areas which include where, frequency, and methods which are in
accordance with internationally recognized standards, with the standards, there
will be no pollution of waterways by meeting internationally recognized limits for
TSS, BOD and PO3/PO4 for rural sites in similar tropical areas, contractor submits
monthly data reports within 4 days of month end, report any abnormal and/or
dangerous concentrations that could cause harm to ppl/env within 48 hours,
monitoring program should also monitor potable water quality supplied to
construction people and nearby
- operation: prevent oil contamination from boats and continuously make
weekly checkups and maintenance of the project operation system

- powerhouse
- construction: prohibit garbage disposal and equipment/machinery cleaning
near watercourses, provide adequate toilets and oil and grease traps with the
carrying capacity of wastewater receiving pond, regular weekly check-up and
maintenace of equipment
- operation: prevent oil contamination from maintenance and continuously make
weekly checkups and maintenance of the project operation system

- transmission line
- construction: avoid open area nearby water but open only one working area
at time in a successive manner (poor grammar what?), prohibit to dispose garbages
and clean equipment/machines in watercourses
- operation: continuous check up and maintenance (how often?)

- access roads
- construction: concentrate in dry season with minimun period of time as
possible to alleviate SS into waterway, avoid open area nearby water but open only
one working area at time in a successive manner (poor grammar what?), 50m away
camps, 10m away stockpiles and mats, prohibit garbage disposal and
equipment/machinery cleaning near watercourses, prohibit garbage disposal and
equipment/machinery cleaning near watercourses, provide adequate toilets and oil
and grease traps with the carrying capacity of wastewater receiving pond, (what
about water treatment?)

ecological resources

fish biodiversity in area is low,

very vague descriptions of compensation, almost no monetary values present, under


human use values

listed mitigation measures then put it in a chart again